UPGRADING MUWAILAH-1 33/11KV PRIMARY SUBSTATION

Project FROM 2X6 MVA TO 2 X20MVA AT NORTH BATIHAH


GOVERNORATE .Ten. No146/2015
Date 10-11-016
Client
Report ref TLC-055-TR 11
Contract
Device 11KV SWGR
or

HIGH VOLTAGE TEST FOR 11KV SWGR

SWGR Details:

1. Make : JYOTI SOHAR SWGR LLC


2. Rated Voltage : 12 KV
3. Rated Current : 2000A

1. Testing Equipment Details

Equipment Name Make & Model Serial Number Calibration Validity


Hipot Test Set BAUR & PGK150/5H 1301338002 25/11/2016
Insulation Tester 5 kV Megger& MIT510 TL/IT/001 19/03/2017

2. Phasing and continuity: OK

3. Insulation Resistance:

Test Voltage (V) Duration Insulation Resistance-G-Ohms


Combination
(Min.) Before HV After HV
R-Ph to Earth (Y+B+E) 5000 1 51.4G 48.3G
Y-Ph to Earth (R+B+E) 5000 1 29.3G 28G
B-Ph to Earth (R+Y+E) 5000 1 39.4g 30.1G
R-Y 5000 1 88.3G 90.3G

Y-B 5000 1 34.8G 42.8G


B-R 5000 1 150G 133

4. Bus Bar Contact Resistance Test :

BUS SECTION R-R (m Y-Y(m) B-B(m)


BUS -A 61 62 63
BUS -B 74 80 68

TESTED BY WITNESSED/APPROVED BY

Sign Sign

Name Name

Date Date

Page 1 of 2
UPGRADING MUWAILAH-1 33/11KV PRIMARY SUBSTATION
Project FROM 2X6 MVA TO 2 X20MVA AT NORTH BATIHAH
GOVERNORATE .Ten. No146/2015
Date 10-11-016
Client
Report ref TLC-055-TR 11
Contract
Device 11KV SWGR
or

5. HV Pressure Test:

Test Voltage Duration Leakage Current Remarks


Combination AC (KV) (Min.) (mA)
R-Ph to Earth (Y+B+E) 19.0 1 28
Y-Ph to Earth (R+B+E) 19.0 1 29
B-Ph to Earth (R+Y+E) 19.0 1 27

6. Remarks / Observation: Tested the (SWGR) and test results found satisfactory.

TESTED BY WITNESSED/APPROVED BY

Sign Sign

Name Name

Date Date

Page 2 of 2