Site:
Note
As part of this assessment, prior to working at height we need to query if the same results can be
achieved by the avoidance of working at height, if not the following hierarchy must be considered:-
The Work Activity
Where It Is
The Duration of the Work
Prevention of Falls
Migrate the Effects of Falling
Assessment and Selected Equipment
The Work Activity
Y N Possible (P)
Will it involve the need for additional work platforms
Will it be over or near other persons
Will it be over or near circulation routes
Will windy condition effect the activity
Will wet conditions effect the activity
Will mechanical plant be used
Will it involve manual handling by one person
Will it involve manual handling by multiple persons
Will the work involve strip out/demolition
Will the work involve soft strip activities
Will the work involve repair work
Will the work involve handling and fixing something
Will the work involve movement of items
Will the work involve stripping off and replacement of coverings
Will it require mechanical means of hoisting/lowering materials
Is it a simple task
Is it a complex task with high degree of familiarity
Is it a complex task with high degree of unfamiliar
Is it less than a complex task with a high degree of familiarity
Y N P
From a safe/suitable area with adequate methods to prevent falls
From a safe/suitable area having structural integrity
From a safe/suitable area but near by to openings/edges
Is there suitable safe access
On the façade of a building
On a flat roof area
On a sloping roof area
Over a staircase
Over/nearby a glazed roof/roof lights
Is it over/alongside fragile materials
Above recently excavated/back filled soil etc
Above a reasonably flat area/surface
Above obstructions/undulating surfaces
Alongside excavations
Working near water
Can persons fall from the proposed area/or access to it
Will separate access be required
If yes, describe what equipment might be suitable:-
Note
If none of the above reasonably describe the work position please do so
Comments:-
Duration of the work activity
Y N P
Will it involve more than one person
Will it take up to half an hour
Will it involve over half a day
Will it involve 5 days
Will it involve 10 days
Will it be repetitive periods of many times
Equipment
The following list of equipment has been selected for this project/work activity based on the
foregoing information:-
Assessor Date