Professional Documents
Culture Documents
The Arup Journal 2014 Issue 1
The Arup Journal 2014 Issue 1
1.
Personal Rapid Transit:
implementing the ULTra Heathrow system
Location Authors
Heathrow Airport, London Tony Kerr Martin Lowson Austin Smith
2.
Requirements5, 6 Delivered
Available on demand Average wait time: ~10 seconds
Goes anywhere Can go to any point on the network
Non-stop No stops
Environmentally sustainable >50% reduction in energy and emissions
Low cost Less than half the cost of other modes
Safe and secure Very reliable, fully monitored
Integrates with other modes Complementary to conventional transport
Initial system requirements, and Arup was involved from the outset, the
prototype design firms Bristol office having been contacted
The ULTra system design concept originated by Advanced Transport Systems Ltd (the
in 1995 at the University of Bristol, UK. original name for ULTra Global PRT) to join
The original objective was to identify an in designing the infrastructure for such a
ideal system better than the car system. These requirements were considered
for urban transport in the 21st century. in depth when, in its initial involvement,
Requirements analysis showed that the Arup designed the structure for a prototype
optimum system should offer the features in test track. The team undertook stated
the first column of Table 1 (anticipating later preference evaluation of a PRT system for
discussion, the second column shows how Cardiff City Council, and partly as a result
these have been met at Heathrow). of this, the c800m test track, including a
three-span bridge, was built at Cardiff in
Recognising the integrated nature of PRT 20012002 (Fig 7).
systems is fundamental to their successful
delivery, and analysis suggested that Early guideway designs used parameters
inadequate consideration of this factor was developed from road, rail, and footbridge
the root cause of the failure of some earlier codes, and these generated heavy structures
PRT concepts. Infrastructure issues are a and resulting high costs. The overall loading
core consideration, with budget reviews from a PRT system based on first principles
showing infrastructure to comprise and actual applied loading from vehicles is
50%60% of the total cost. about 2000N/m2, compared with the 7.
5000N/m2 loading required in footbridge
design to cover passenger crush loads.
Designs which exploit this lower loading for 6. Pods in service bay at Heathrow.
PRT are significantly lighter and lower cost, 7. Cardiff test track.
and those used at Cardiff proved entirely 8. The Heathrow PRT layout.
satisfactory. This approach was therefore
used in the design for Heathrow.
0 200m Condition 3
9. The running surface is formed Passenger comfort The running surface pairs of finely
from pairs of finely engineered The issue of a passenger comfort standard engineered precast concrete planks gives
precast concrete planks.
was paramount, and parameters developed traction to the vehicles rubber tyres for
10. The structure in its crowded
urban setting.
with the guideway design were based on steering, acceleration and braking, and is
ASCE APM standards10 and experiments on wide enough to accommodate variations in
the test track. Relationships between speed vehicle positioning (Fig 9). Experience at the
and alignment radius were established, based test track had shown that small surface
on moving vehicle mechanics, a limiting irregularities transferred to the vehicle and
Design standards
lateral acceleration of 2.5m/sec, and an discomforted passengers, so at Heathrow
Design code angular velocity limit of 0.5rad/sec. vehicle suspension was introduced to
As this was the worlds first application of mitigate this. Against this was the need for
PRT as a public transport service, no specific This in turn translated into the lengths of the lasers to retain their ability to sense the
design code existed. Experience from the transition curves at entry to and exit from wall, making a firm suspension necessary.
prototype system at the Cardiff test track circular curves. Standards were specified for
informed the initial specification of design surface regularity and steps at adjoining In operation this firmer suspension was
requirements, and as the guideway design running planks, relating to a jerk standard found to increase passenger confidence.
progressed, the decisions taken informed a and the transmission of irregularities through The design and fabrication specifications
design code that ULTra and Arup developed the vehicle suspension system to the also included very tight control of tolerances,
in parallel with the design itself. passengers. One early design decision was to and measures to avoid cumulative effects.
avoid canting (super-elevating) the running
The aim was to capture these decisions and surface, and so minimise complexity and Constraints
the reasons for them, and thus establish an cost. This influenced the speed of travel At Heathrow the overall vertical and
authoritative basis whereby future checkers around turning radii. horizontal alignments had to be carefully
and reviewers could avoid taking questions threaded between fixed points, while still
back to first principles to be satisfied that the The internal vehicle configuration includes respecting ride comfort. Constraints to be
solutions offered would deliver a safe, two forward-facing fixed seats and two worked around included existing and
reliable and appropriate guideway. rear-facing seats. Early trials showed that planned structures, particularly roads serving
a direct forward view over and down an the terminal and its car parks, boundaries
Where relevant, the code refers to existing incline is discomforting for some passengers, between airside and landside (the alignment
UK or USA codes or standards, in particular so the forward view needed to be partly is largely landside within Heathrow Airport
concerning the expected properties of steel, obscured. This was provided in the car body Ltd property), clearances over roads, and the
concrete, and corrosion protection, and for design and by limiting gradients to 6.25%. virtual surface (obstacle limitation surface)
foundation and structural design parameters. radiating from the north runway (Fig 10).
Guardrail
Cable tray
250 Condition 3
450 450
Cross-beam
Cross-head Long-span
deep beam
Construction considerations Evaluation from the test track showed this The foundation construction was
Background form to be simple and easy to construct; significantly affected by the T5 building
The basic structural form for the elevated a standard 18m span was efficient in its programme, and access to carry out the
PRT guideway had been developed at the use of materials, and provided the very piling was taken when it became available.
Cardiff test track as a one-way route shallow profile and cross-section, with low As a result the foundations were in place
comprising a pair of side beams with visual impact, suitable for constrained urban long before the columns and superstructure
cross-members at regular 2m intervals. areas. The 18m length can be transported in were added, imposing a no change
Different forms of construction were one piece and will span over a typical UK discipline to the alignment design once
considered, including fabricated trusses, urban road at right angles. This basic foundation work had commenced. Airport
precast and in situ concrete, and composites. concept for the elevated structure was restrictions required the use of low profile
applied at Heathrow. The single columns that piling rigs in areas of height restriction, but
Steelwork fabrication data indicated that the support it are a constant 500mm in diameter. otherwise industry standards applied.
cost of cutting and welding for a fully
prefabricated structure would double the Simply-supported beam performance is
total cost compared with basic steel supply. affected by the wall thickness of the rolled
For its part, concrete lacks flexibility where hollow section (RHS) that forms each side
a variety of radii are used and has high beam a consequence of bringing together
mould set-up costs. On this basis the least load, design life, fatigue, and welding
costly option was to construct from steel considerations in the overall structural
using as little fabrication as possible. analysis. Adopting simply-supported spans
resting on bearings at each end avoids
The cross-members support the running on-site connections for a continuous
surface, cable tray, and drainage channels. structure, and is efficient in its use of a
The side beams form simply-supported foundation and column crosshead to support
spanning elements, as well as being the the ends of adjacent spans.
upstands to contain errant vehicles and
provide navigational direction. The side Foundations
beams also support the guardrail, and control The location of foundations influenced the
and safety equipment. As previously noted, superstructure alignment due to the need to
pairs of 300mm wide precast concrete planks avoid existing features in particular roads, as
form the running surface. (Fig 11). well as planned but not-yet-constructed
buildings and other infrastructure elements.
The PRT systems low loading results in a 12.
small footprint to support the structure,
generally a pile cap with four continuous
flight augured (CFA) piles (Fig 12). 11. Structural cross-sections:
(a) standard; (b) long-span;
By adjusting the pile cap shape or providing all dimensions in mm.
ducts, it proved possible to avoid diverting
12. Low loading results in a small
any buried services a major benefit of footprint to support the structure.
this transport system. 13. Typical columns and spans.
14. PRT between highway structures.
The long spans were prefabricated off site in The 18m standard module has the weight
manageable lengths, and joined using bolted characteristics set out in Table 4, which
splice connections prior to being lifted onto shows that the concrete running surface
the column heads. planks form a significant component of the
total weight. These may be added after 15.
Fabrication steelwork erection, so contractors have the
Off-site factory fabrication brought the option to assemble on the ground and lift as
benefits of production in a controlled one assembly or to order a lighter lift and
environment with access to lifting, rolling, place the planks once the guideway structure
and automated welding facilities. It was is in place.
found that the steel supplied complied
reliably with UK codes and standards and At Heathrow it was not possible to use
little straightening of supplied beams was cranes below an already constructed
needed to meet the design requirements. highway ramp, and this particular lifting
problem was solved by the use of a
The combination of fabrication tolerances transporter (Fig 16) to raise guideway
and rolling tolerances establish the range of elements into position. A further issue was
likely outcomes for the constructed that of airport operations, which limited the 16.
guideway. This combination of tolerances time available for installation to a four-hour
was a critical issue in establishing a period at night. Despite this very limited
comfortable ride, and was partly countered time window, 1000m of guideway was
by specifying the three dimensional location erected in one week. Once it was in place,
of points for each beam element at each all further construction and commissioning
column cross-head, and managing the was carried out from within the confines of
cumulative effect of construction and the guideway, avoiding any more
component tolerances working together. interference with ground-level activities.
Bath Renaissance PRT design competition In 2009 ULTra (then still operating as Advanced
Transport Systems Ltd) held an open competition for
designs to provide solutions for the integration of PRT
into the city centre of Bath in Somerset, south-west
England, and a UNESCO World Heritage Site.
Arup took forward the initial concept of a city centre
loop as part of a wider future network, including
connections to park-and-ride sites and major
employment areas on the urban fringe. The concept
alignment took account of constraints including the
citys historic buildings, the River Avon, the Bristol to
Bath Canal, various highways, and the Great Western
22. rail line. The firms urbanism and landscape team,
inspired by the citys Victorian railway bridges,
developed a vision using contemporary lightweight
mesh technology to produce an effortless flowing
structure designed to provide a unique, Bath-specific
solution (Figs 2122).
The Arup entry was awarded first place in the
competition, based on the judgment of an independent
review panel consisting of local politicians and
designers. Though not implemented, it serves as an
example of how a PRT guideway can be configured to
21. its environment.
1.
c) Arup also led the procurement of the The CGB had few access points, which
topographical survey and ground resulted in a linear approach to construction,
investigation for the entire 26km route, with 15m long precast concrete ladder beams
and this was followed by preparation of the laid on foundations at 7.5m centres using a
technical content and specification of the bespoke gantry running on the previously
Contract Documents, as well as the Works placed guideway. This limited the rate of
Information for the guideway. progress on site due to the output of the
single gantry. LDB, by contrast, was planned
The scheme went to tender as a design-and- to have numerous access points, and it was
build project. It was intended that Arup be decided at the tender stage to keep the
novated to the successful design-and-build precast beams as short as possible and, in
contractor, but at the best-and-final-offer particular, not to use bespoke placing
d) stage, negotiations led to a design joint equipment that would inhibit progress.
venture (DJV) being formed with
2. Parsons Brinckerhoff (PB).
Kings Houghton
Middle School
3. 4.
Parkside
HOUGHTON
REGIS
Guide face
A B C
PLAN
Guide face
5. 6.
railway used to pass over existing highways To create the busway route horizontal
in Luton town centre. Here, the route was curves, the beams were cast with the faces
cleared to street level by demolishing the of their upstands slightly concave in the
bridges and removing embankments. horizontal plane, the depth of the curve
This not only changed the street scene but corresponding to the radius of curve of
also freed-up peoples mobility. that particular section of the route (Fig 6).
The outer faces of these beams, however,
The design scope of work for the LDB was were still cast straight. To facilitate
distributed differently from the CGB, with construction, beams were delivered to the
Arup being responsible for design of the guideway site on standard flatbed trucks and
main bus alignment, the junctions, the offloaded into position by a Hiab loader
guideway structure, Luton railway station crane. Keeping the beam weight to no more
bus interchange, and all of the projects than 4.5 tonnes ensured easy and safe
environmental works. handling within standard equipment 7.
compatibility (Fig 7).
Guideway design
In the 7.4km guided section, the buses use a The design speed for the guided section is
2.6m transverse gauge corridor formed from 85kph, which reduces to 50kph near
6m long precast concrete beams. Standard junctions and pedestrian crossings to allow
buses, fitted with two small guide wheels to safe passage through the entry and exit
their front axles (Fig 5), can join and leave flares. Junctions are signal-controlled and
the track, and travel on it in both directions the buses are fitted with transmitters to
smoothly and safely. There is no need for trigger traffic light priority to the busway
specialised vehicles, and the modified buses as they approach (Fig 8).
can also drive on normal public highways.
The alignment design parameters were set Traditional highway transition curves were
out in the contract documents provided by eliminated, as it would not have been
Luton Council, with further guidance from practicable or cost-effective to make the
highway design standards in TD 9/934 and precast concrete beams fit to curves that
changed proportionally to their length, ie a 8.
the Guided Busway Design Handbook.
clothoid. Special series of beams could have
The beams and foundation pads were all been constructed for individual transition 5. Standard buses are fitted with a
cast on site in a temporary precast concrete curves, but this would have had a major pair of guide wheels.
factory, so as to minimise the environmental impact on the cost, programme, and 6. Plan and sections of typical beam
impact and also keep production of the key working tolerances. used in curved part of the guideway
(dimensions exaggerated for clarity).
components in house using direct labour.
To compensate for the lack of transition, 7. Beams delivered by standard
flatbed trucks.
To ensure cost-effective beam production, a series of larger radii curves was placed
8. Buses are fitted with triggers to
the number of horizontal alignment radii was before and after curves that would in theory control junction lights.
limited, and the design was rationalised to require a transition. The larger radii curves
four (550m1880m); as the terrain was assist passenger comfort by smoothing the
suitable, there was no need to consider entry and exit and gradually introducing the
vertical curvatures of running surface beams. lateral force exerted to the vehicle.
Guided section Central reserve Guided section First, the horizontal alignment was designed
using a combination of the standard radii
Horizontal and vertical selected. As the beams were a uniform 6m
control point
long, all elements of the alignment needed to
A
Fall Fall
A A
Fall Fall
A be multiples of 6. They also needed to fit
between the land boundaries, and to conform
to the requirements of the Guided Busway
Note: elevation of point A is equal to vertical control point elevation Design Handbook.
9.
The horizontal and vertical control point of
the alignment was at the midpoint of the
R1, length 6.009m central reserve at the guideway running
surface level. However, the setting-out
information for the individual beams was
provided at the beam edges at the top of
R2, length 6.001m
the pad foundation level, 0.34m below
point A (Fig 9).
neighbouring houses) had grown to line it, To guide how the construction was to be
and invasive plant species such as Japanese undertaken in respect of the environmental
knotweed had become established. resource and then how the wildlife and
This naturalised rail corridor now formed landscape would be managed post-
a primary habitat corridor connecting construction, two documents were produced,
otherwise discrete areas of chalk grassland. both informed by the Route Biodiversity
Action Plan and the Landscape and Design
The challenge facing the Arup team was to Strategy. BAM Nuttall devised a
ensure that this diverse ecological and Construction Environmental Management
landscape resource identified in the Plan while Arup produced the supporting
Environmental Statement was fully Landscape and Ecological Management
considered in the schemes design and Plan. To ensure that day-to-day management
delivery. BAM Nuttall was responsible for was in line with the guidance in these over
19. ensuring that the construction works, and the two years of construction, the contractor
their maintenance and monitoring, complied appointed an environmental manager from
fully with all existing UK and EU legislation Arup and an environmental clerk of works.
concerning environmental protection.
The Landscape and Ecological Management
This demanded a carefully co-ordinated Plan guided the project for both construction
approach which protected notable flora and and operation, being developed to be
fauna as well as the surrounding landscape relevant for five years beyond completion.
features during construction. The approach It set out the basis for all ecological
also had to incorporate appropriate wildlife mitigation needed to compensate for partial
mitigation and compensation to ensure that loss of land and ecological resources from
there was no net loss, and preferably the railway corridor, and was supported by
introduced gains, to biodiversity. extensive pre-construction surveys of the
route corridor and surrounding habitats.
Prior to the design-and-build phase of works,
three documents served as the golden
thread that would guide the approach taken: 17. Telford Way.
the Route Biodiversity Action Plan, the Code 18. Upgraded railway corridor
of Construction Practice, and the Landscape and cycle route.
and Design Strategy. 19. Around 400 slow worms
(Anguis fragilis) were relocated.
This golden thread effectively extended 20. Area of chalk grassland near
the planning requirement for protecting and M1 bridge.
mitigating, or otherwise compensating,
biodiversity impacts from the construction.
It required input from Arup landscape
architects and Arup ecologists throughout
design development and construction.
20.
Authors
Kim Blackmore is an Associate in the UK Midlands
Campus, and was guideway alignment and junction
design team leader for the Luton Dunstable Busway.
21.
Alan Dennis is a senior engineer in the UK Bristol
office, and was lead guideway structure designer for the
Environmental aims and achievements thorough eradication of Japanese knotweed Luton Dunstable Busway.
The key aims for the five-year post- Steve Fancourt is an Associate in the UK Midlands
enhancement of nearly 4ha of semi- Campus, and was environment team leader for the
construction period were to:
improved chalk grassland at the Hay Luton Dunstable Busway.
Meadows, involving translocating several Oliver Nicholas is a senior engineer in the UK
protect existing and retained habitats along
hundred square metres of species-rich Midlands Campus, and was lead engineer junctions and
the guideway route site representative for the Luton Dunstable Busway.
grassland turfs known to support common
provide ecological mitigation and and pyramidal orchids Kulvinder Rayat is an Associate Director in the UK
enhancement measures targeting specific Midlands Campus, and was Project Manager for the
enhancement of reptile habitats at the Luton Dunstable Busway.
sites, habitats and specific species,
eastern extent of the scheme
especially protected species Project credits
installation of a network of bat boxes to Project owner: Luton Borough Council Client and
incorporate and record the design proposals
boost local populations contractor: BAM Nuttall Ltd Joint venture partner and
for the landscape and ecology mitigation bridge designer: Parsons Brinckerhoff Civil and
areas created design of badger-friendly exclusion fencing structural engineer, and environmental consultant:
along the length of the scheme Arup Rahul Bagchi, Yiannis Baltagiannis,
ensure that replacement and compensation Oliver Barnett, Jess Batchelor, Joseph Bearne,
areas contain appropriate species and wildlife tunnels from side to side beneath Chris Bellingham, Simon Birkbeck, Kim Blackmore,
habitats to replace lost resources in the the guideway to maintain permeability of Andy Boyle, Phil Brand, Grainne Breen, James Brock,
long term the infrastructure to wildlife, including Austin Brown, Carol Brownridge, Rory Buckley,
Andrew Clarke, Tony Clifton, Ian Davis, Alan Dennis,
reptiles and small mammals
set out management and monitoring tasks Ajminder Dhani, Jenny Dunwoody, Michael Evans,
and targets. a materials management strategy where Steve Fancourt, Ian Fiddes, John Griffiths,
James Hargreaves, Kate Harrington, Rob Harrison,
topsoil was re-used. Neil Harwood, Stephen Haynes, Darren Hickmott,
Local people travelling the busway today Rachel Hotston, Pat Howard, David Hurton,
now enjoy a green corridor that passes Opening Phil James, Thomas Johnson, Jim Keyte, Areeb Khan,
sensitively through the unique chalkland The Luton-Dunstable busway was opened Joe Kingston, Simon Lacey, Yi Jin Lee, Kieran Littley,
to the public on September 25, 2013, by the Angus Low, Neil Mackay, Jamie MacSkimming,
landscape of Dunstable Downs. Oliver Nicholas, Rachel Oates, Declan OShea,
Environmental successes less obvious to UK Transport Secretary, the Rt Hon Norman Allen Paul, Ellen Pickett, Ben Price, Richard Price,
passengers, but nonetheless part of this Baker MP (Fig 21). He noted that the Oliver Pye, Kulvinder Rayat, Henrietta Ridgeon,
projects sustainability credentials, include: busway would be beneficial to Luton, Jake Sidwell, Andy Turner, Gary Walker,
environmentally and economically, and Natalie Walker.
the translocation and safeguarding of went on to state that this new dedicated Image credits
around 400 slow worms (Fig 19) transport corridor provides a quick and 1, 45, 8, 12, 15, 1718, 2122 Ian Cooper 2a-d James
replanting with native tree and hedgerow efficient way for passengers to travel Prestage 3, 16 Nigel Whale 6, 9 Rahul Bagchi/Nigel
between two main town centres, and makes Whale 7 Oliver Nicholas 10 Kim Blackmore/Nigel
species to reinforce and reinstate the Whale 11, 1314 Alan Dennis 19 Natalie Walker
Busway as a green corridor, including good use of the disused Luton-Dunstable
20 Oliver Barnett.
continuous grass strips along the length of railway corridor. The busway now stands as
the guideway the second longest in the world and the
longest in an urban environment. 21. Opening ceremony at the Luton
station interchange.
22. White Lion retail park stop.
operation
between the running rails at pavement fixed-system vendor. The implications of introduces a fleet-dependent element to
level. The contact rail is segmented and committing to a single-source supplier the total cost equation.
only those segments fully under the LR must be considered when procuring such
Introduction vehicle are energised. Switching can be a system; questions of system Interoperability with wired sections
Two broad categories of technologies either by active control of line-side obsolescence and vendors business No wire-free technology is inherently
switchgear or by a means inherent in the continuity through the networks incompatible with conventional wired
exist for wire-free operation: those using
contact rail design. lifetime must be considered. sections; systems based on on-board
on-board energy storage, and those that
energy storage can readily use normal
transfer energy to the LRVs without
Contactless (inductive) Marginal cost factors and pantograph equipment to draw power
OLE. The latter further divide into those power transmission from a wire or conductor rail to recharge
using ground-level electrical contact, scaling factors
At least one system, now only on a Generally, the investment in on-board the on-board stores. Controls will be
and those that transfer the energy demonstration track, has the energy required to ensure that the pantograph is
inductively without the need for energy storage directly relates to fleet
inductively coupled to the LRVs from size. However, while a wire-free section lowered and raised appropriately to
electrical contacts. coils in the track bed. Such a system can avoid entanglement or the unintended
by definition will not require investment
have continuous energy transfer, in overhead wire, charging points at operation of automatic lowering devices
On-board storage technologies although the more likely configuration designed to mitigate dewirements.
stations and other locations will still be
Those with potential application for would be to provide charging at stops The pantographs also need to be suitable
needed. As noted below, the load factor
LR include: and high power requirement areas, for frequent raising and lowering.
may have to be dealt with; the
electrochemical: various established and rely on on-board energy storage for parameters of the charging points will be
and emerging battery chemistries running between the charging points. Stray current
a function of several factors, including
Modern materials and techniques to
electrostatic: double-layer capacitor traffic density. Conversely, the cost of a
Open vs proprietary architectures insulate rails in street running systems
(supercapacitor or ultracapacitor) segmented third-rail system will largely
On-board storage systems that use have significantly reduced stray current.
scale with the track length that includes
flywheel conventional pantographs to recharge For on-board storage and inductive
it. While vehicle-mounted equipment is
from overhead lines when in wired areas coupling systems, the DC traction
compressed air. required, it is not anticipated to form a
are essentially open architecture. system electrolysis risk is further
As well as facilitating wire-free In these, vehicles can be mixed and large portion of the total vehicle cost. reduced to zero. These systems do not
operation, on-board storage can also matched from multiple vendors, whereas For an inductively-coupled system, use the running rails for traction return
improve energy efficiency through systems relying on segmented third-rail significant costs are likely on both sides. in wire-free areas, and should be able to
effective recovery of regenerative or inductive coupling are generally Clearly, major investment is required for operate with the rails earthed and
braking energy. proprietary single-vendor solutions. the fixed infrastructure scaling with insulated from the traction return.
reliability and reduce OLE maintenance. ground but may not contact the return rails resistance, this can have a very significant
The author is not aware of such strategies and thus not provide the low-resistance fault impact on energy store size. It should be
being deployed, and the incident risks needed to initiate fast disconnection of noted that gradient and speed of ascent are
associated with lowering and raising power by the protection equipment. less significant than change in elevation.
pantographs (the apparatus on LRV roofs to
draw power from the OLE) at the correct Broken wire incidents may stem from Even if the vehicle is not moving, the HVAC
points would also have to be factored into causes within the rail system, such as spark (heating, ventilating and air-conditioning)
any such decision. erosion of the wire at points of poor system will still be running, and the energy
geometry, or from external triggers like for it must also come from the on-board
Special events overheight road vehicles and falling tree store. Accordingly, local climatic conditions
Where part of a proposed LR route might branches. Adopting a wire-free system can and the amount of HVAC required for
accommodate a regular if infrequent event effectively eliminate public safety risk from acceptable passenger comfort must be
like an annual parade or a motor sport street fallen OLE conductors. factored into sizing the energy store, which
circuit, going wire-free might mitigate the has to be for the worst design case, not the
complications of such an event. System parameters to consider average. For a system with shared street
On-board energy storage running, the potential to be held up between
Safety: fallen conductor risk charging points by traffic congestion must
The amount of energy that must be stored,
Direct current (DC) electric railways often also be allowed for.
and so the viability of this approach, will be
operate with little margin between maximum
significantly influenced by the parameters of
load current and minimum fault current.
the particular system. First, large height Service frequency considerations
This makes detecting a fallen conductor Infrastructure-intensive solutions will be
differences along the alignment will require
quite challenging, particularly if it doesnt more affordable on sections with high
more energy, as the amount needed to climb
land on the running rails that provide the service frequency and thus high asset use.
an incline is directly proportional to its
traction return. While the catenary systems Conversely, if service frequency is low,
height. While it will likely be possible to
generally used by heavy rail may continue to on-board energy storage is more likely to
recover some of the energy through
support a broken contact wire above ground, be economic.
regenerative braking in descent, there must
a broken trolley wire will always fall to the
still be enough in the store to complete the
climb. As LRVs have a relatively low rolling
2. 3.
equipment offered. Both batteries and DLCs
are usually supplied as modules and so
vehicle down-time for the replacement
would be relatively modest.
Authors
Jim Bell Samantha Birchall David Clixby
Ian Drabble Eoghan Given Richard Greer
Neil Hooton Susie Horsefield Lee Kirby
Helen Marsh Ben Watkins
Overview
The 60M first direct arena in Leeds is the
most sustainable project of its kind in the
UK. With its fan-shaped seating bowl
terraced into a sloping site, the world-class
13 500-capacity venue optimises sight lines
by focusing every seat on centre-stage to
bring the public closer to the action (Fig 1).
It caters for a wide variety of shows,
from concerts to boxing, and comedy to
basketball, but whatever the event the
arenas inherent flexibility enables
unforgettable experiences for audiences.
University Lane
e
re
of Leeds
St
Leeds General
W
first direct
oo
ett
Infermary
ay
d
ck
arena
economy. However, its proximity to noise-
ho
Cl
Be
A58(M)
us
e
nt St
Leeds City
ne
St treet
erp
station
Pe
S
Welling
ter
to n Street Le
lc
na
s
l ed
a
sr
a ilw
ay To the north and east, the site is bounded by
ire
the Inner Ring Road (IRR), 5m down in a
A
v
Ri
er
1. Elton John in performance at The site itself is small for a venue of this
the first direct arenas official scale, and slopes by 6m north to south.
opening night, 4 September, 2013.
2. The arenas close proximity to The adjacent student residential
other buildings in Leeds city accommodation led to stringent
centre led to design challenges. planning restrictions on noise breakout,
3. Location plan. thus making acoustics the key driver of
the engineering design.
It was to be the most sustainable venue
in the UK.
Project creation
Introduction
Leeds had long been targeting the
development of an arena to strengthen its
cultural resources and planned social and
economic growth; indeed, the local public
and private sectors tried three times in the
1990s but failed. Making the arena finally
happen, through the worst economic
recession in living memory, took clear
5.
vision from LCC, strong management, and
innovation at every stage of the project.
Arup, initially focused through its venue 4. The arena under construction,
showing key site constraints.
consulting offer and then its building
engineering practice, is proud to have been 5. The daytime appearance of the
arenas unique faade.
central to that innovation throughout the
project, which sets not only a new paradigm
in arena design and event-goer experience,
but also in the planning, finance and delivery
strategy for such a venue.
Secure the minimum public sector gap This was to ensure that the selected operator
funding needed to bridge the difference could be introduced to the shortlisted
between the arenas cost and the funding developers, to test and ensure that the
otherwise available through borrowing operator could be contracted with the
against the operator rental, borrowing developer selected.
against other incomes such as car parking
and, for example, cross-funding from Both competitions were launched in June
8.
enabling development on the selected site. 2007. Interest in the operator competition
The level of gap funding was demonstrated was very high, and competition between
to be entirely justified by the scale of the major global venue operators continued
arenas economic stimulus, eg spending by through short-listing to the final stage of
people coming into Leeds for events there. the process.
Arups long experience with performing arts In May 2008, SMG Europe was announced
projects highlighted the importance of as the preferred bidder and was temporarily
designing the venue from the inside out, contracted to LCC to guarantee fulfilling the
based on needs in terms of target audience terms of its successful bid until SMG could
and performers. The Leeds arena be contracted on the same or better terms to
implementation plan innovated the way to the selected developer.
this next stage, effectively procuring the
venue from the inside out. In addition to its guaranteed rental, SMGs
successful bid was differentiated by a range
9.
Delivering the implementation plan: of innovations. These included the
the operator requirement for a fan-shaped auditorium to
Under the contract established, LCC provide the best possible experience for
6. Early 3-D model showing the commissioned IPW Ltd (then PMP Ltd) event-goers with all seats facing to a clear
overall massing of the building. supported by Arup and DTZ to deliver the view of the stage (Figs 79), a high level of
7. The fan shape gives a clear view approved implementation plan. Arup was front-of-house food and beverage offering
of the stage from all seats. technical advisor throughout this phase. both for events and at other times, and clear
8. Architects graphic. facility requirements to deliver these
9. Audience enjoying the Bruce This team developed the procurement innovative components at a fundable cost.
Springsteen concert. documentation which LCC issued as two
competitive tenders under OJEU procedures, For SMG, this project was an opportunity to
with the developer process intentionally meet its long-held objective to set a new
planned to lag a few months behind that paradigm in new-build arenas.
for the operator.
10.
3 4
Public realm
In n
er
Rin
2
gR
1 5
oad
2 7
n e 3
it La 4
5
yP
Cla
6
6
1
1 Public entry 5 Service yard
6
2 Concourse 6 Performers entry
3 Auditorium 7 Access road 0 100m
4 Stage
13. 14
The structural design Initially, the access road was placed well recessed plant well, 54m x 15m, to conceal
Overall concept clear of the IRR to avoid overloading the six large air-handling units behind an
To provide an arena on this tight, sloping site large retaining structures. But this resulted in acoustic wall (Fig 14).
required the UKs first fan-shaped bowl, the upper levels of the bowl significantly
overhanging the road, creating dynamic It was tempting to have a radial roof grid to
overlooking a stage set into the slope.
issues with the structure and uplift on the mimic the scallop shell, bringing the roof
This innovation allowed the desired capacity
foundations, and making the turning access trusses together to a point above the stage.
to be achieved impossible with a
into the service yard excessively tight for However, this would have placed excessive
conventional in-the-round configuration
large articulated vehicles. load on a single element the proscenium
and thereby unlocked the commercial
arch (PA) truss, spanning 54m clear across
potential of this central location to host a
Greater efficiency could be achieved by the stage and the non-parallel trusses also
large venue, cementing LCCs belief in a
moving the road closer to the IRR. Detailed presented a buildability challenge.
city-centre location for the arena as a
structural investigation and back-analysis of Instead, 13 trusses up to 72m in length span
catalyst for growth and development.
the IRR structure enabled the access road to north-south at 9m centres, limiting the load
The arena then grew around the move adjacent to the wall, with a limited on the PA truss to a third of the total, better
auditorium: concourses to the north-west, strengthening of just its top 2m. spreading the load across the foundations
service yard to the south-east, performers and greatly simplifying the two-layer roof
Internally, the challenge to create an intimate construction. This also dramatically
entry from the south-west, and the access
auditorium with world-class acoustics and simplified the integration of services, rigging
road to the east creating a building
energy performance required a minimum- and gantries within the roof structure.
resembling a scallop shell in plan (Fig 13).
volume space, without interruption to
All areas were kept to a functional sightlines, while accommodating extensive Stability for the roof is separate from that for
minimum, and the building was rigging structures some 20m above the event the concourses to the north, enabling the
metaphorically shrink-wrapped by the floor, integrated with the ventilation system, cranked trusses to spread under load without
roof and the faade to minimise its volume. gantries and lighting. The solution was a impacting the overall structural efficiency.
This strategy, however, created many folded roof, falling towards the stage to The concourses themselves are steel-framed,
challenges for the structural design. reflect the profile of the site and the stabilised with concrete stair cores and
sightlines, and creating above the stage a shear walls.
Acoustic cavity
350
16.
19.
Acoustic cavity
msA -1
20. Testing an air-handling unit.
1.0
21. The performers-eye view
0.9
reveals the careful co-ordination of
0.8
structure, ductwork and gantries.
0.7
22. BIM with the supply chain:
0.6
the Arup models brought together
0.5
with Creaghs precast, Fishers
0.4 steelwork and Rotarys MEP
0.3 installation models.
a) b) 0.2 23. CFD profiles for:
0.1 (ab) air movement/velocity;
0 (cd) temperature profile.
C
28.0
27.0
26.0
25.0
24.0
23.0
22.0
21.0
c) d) 20.0
19.0
18.0
23.
sound pressure levels at the adjacent The controlled level of reverberance was
residential receptors (Fig 29). This approach achieved through the use of an acoustically
allowed the attenuation performance of the absorptive roof liner and acoustic treatment
faade and roof to be optimised, which also around the stage area and around the side
included value engineering of these elements and rear walls, all within the constrained
in an acoustic testing laboratory. materials budget.
29.
Achieving the cost-effective roof build-up Upholstered seats were installed to enhance
previously described on page 43, was key, 27. The complex geometry of the the user experience and also to provide a
and the Arup team provided the series of faade structure. suitable level of reverberance, irrespective of
costed-out acoustic and structural options for 28. One of the many colour- the level of occupancy.
differing double skin roof constructions to change faade lighting effects.
meet the criteria. The study recommended 29. Sound mapping in the locality
introducing the mixed concrete and around the arena.
31.
48 The Arup Journal 1/2014
Lighting and faade panels, perforated mesh sections and
coloured glazed elements, stitched together
reflecting the energy of the stage bursting
outwards to the city. The undulating
with protruding tracery lines snaking across, illuminated tracery lines tie all these varied
The arenas fan shape creates a highly and acting to break down the vast faade. elements together and create continuity
prominent faade that looks west out over Arup proposed a layered lighting approach across the building.
the city. As the first interface between venue to enhance the varied faade elements, and
and visitor, it was vital that this primary provide a flexible treatment that could be Throughout the development of the faade
faade communicated the aspirations of the tailored to the arenas operating mode. lighting concept, adaptability was a key
arena and formed a strong part of the overall theme. The fully dynamic colour-changing
event experience. Arups lighting team in the Tall lighting masts frame the primary faade treatment would visually represent
Sheffield office developed an external entrance, illuminating the public realm and the arena being tailored to the event taking
lighting design concept, including the feature providing focused illumination of the solid place. RGB LED lighting was proposed for
lighting of the primary faade. coloured acrylic hexagonal panels of the the backlit mesh and tracery lines to
faade. Functional lighting from within the transform the faade to complement and
The concept was essentially to complement arena emanates out through the coloured promote the on-going event. This bold and
the architectural design with a dynamic and glass, giving views of activity within. Arup vibrant faade treatment creates a vast and
eye-catching frontage. The design presents a proposed a back-lit solution to the mesh ever-changing colour billboard that
kaleidoscope of materials, colours and panels to emphasise the texture and give transforms the building and makes each visit
textures, a combination of solid acrylic depth to the faade, with light from within unique and dazzling (Figs 3235).
35.
The Arup Journal 1/2014 49
Civil engineering The foundation design was driven by Beside its other roles, Arup was BREEAM
An initial enabling works package was CDM (construction design and management) assessor for this landmark project. The scale
needed to remove of an area of Japanese and by buildability. The founding stratum and building end-use meant that several
knotweed from directly behind the IRR wall, was too shallow for cost-effective piling, complex BREEAM requirements formed
and divert an existing sewer outside the but too deep to work in the excavations for part of the assessment, including acoustic,
building footprint. Drainage connections on spread footings. Mass concrete infill was thermal and lighting issues. Integrating these
the site had to be split into three for surface therefore used to bring excavations from on such a major project with a very tight
water and two foul sewers to match the rockhead to the working level, and the programme was highly challenging, and was
limited discharge at existing connection reinforced cages for the pads were then only achieved with proactive support from
points. A separate attenuated system was placed safely above (Fig 36). the whole design team.
provided for the adopted highway drainage
to one of the connections, and a further Utility and building services penetrations Conclusion
system of sustainable drainage was were concentrated adjacent to the access Delivering the first direct arena overcame
provided beneath the public realm in front road. The installation sequence was critical technical and commercial challenges, gave
of the main entrance. and so each one was modelled and co- the client a highly sustainable, world-class
ordinated in the BIM workflows. venue, and provided a huge catalyst for
To connect to one of the existing sewers, growth and employment in the city of Leeds.
the main attenuation system, taking well Sustainability The end result is an iconic building that met
over half of the main roof, was constructed To achieve the record BREEAM score for the requirements of the operator, and to a
above ground within a raised loading dock this kind of arena in the UK, the materials demanding programme in a difficult
inside the internal service yard. The yard is selection resorted to recycled products and economic environment.
limited to a small triangular area, so an sustainable materials. BREEAM credits
extensive analysis of turning manoeuvres were obtained for the precast structural Complex constraints and requirements were
was undertaken to design the loading bays at slabs, in addition to the use of recycled used to develop a unique response, with
just the correct angle to enable all possible cement replacement products and recycled innovative solutions at all stages of the
forward and reversing manoeuvres. glass sand for paving and external works. project, from the positioning of the arena on
Cut-and-fill was carefully balanced to the site to the creative use of concrete for
As previously noted, the arena access road dramatically reduce the export and import of acoustic containment on the roof.
was pushed tight against the existing material, and sustainable drainage systems Using state-of-the-art modelling and
retaining wall above a dual carriageway, were applied to the new public plaza to the collaboration between all designers and
providing turning access to the service yard front of the arena. Rainwater is also members of the supply chain, an integrated
and minimising the overhang of the seating harvested and used for toilet flushing. solution was delivered that minimised
bowl over the road. To assess the impact of problems and waste during construction.
the arena on the IRR retaining wall, the team BREEAM is the worlds most widely used
made a detailed investigation and analysis of environmental assessment method for Chris Coulson, executive officer at Leeds
the existing structure, enabling strengthening buildings. It sets the standard for best City Council Asset Management department,
works to be limited to just its top 2m. practice in sustainable design and has commented: Arups multidisciplinary team
The access road was designed to adoptable become the de facto measure used to and their ability to combine innovative
standards that included vehicle restraint describe environmental performance. engineering solutions have contributed
systems to prevent errant vehicles falling The interim BREEAM score for the first significantly to the success of this exciting
onto the IRR over 5m below. direct arena was 60.99% (Very Good). world-class venue. These services have been
delivered consistently to a high standard
and to the City Councils satisfaction.
The Council would be pleased to recommend
Arup to other clients on similar projects.
36.
36. Excavation and foundation
construction in progress.
37. Bruce Springsteen in
performance, with the house lights
on so he could see the audience.
References Eoghan Given is a senior engineer in the Leeds office, Andrew Dickinson, Ian Drabble, Cathy Edy,
(1) www.leeds.gov.uk/docs/Planning%20 and led the fire engineering design of the arena. Keith Emmett, Mike Fletcher, Nigel Foster, Chris Gibbs,
Performance%20Agreements%20Protocol.pdf Richard Greer is a Director in the Leeds office, and led Chris Gauntlett, Eoghan Given, Alastair Gordon,
(2) http://tinyurl.com/kanbjuv the planning advice team and the venue consulting input David Green, Richard Greer, Llew Hancock,
for the arena. Jim Harbord, Nicole Harrison, Steven Hazlehurst,
(3) http://yorkshiretimes.co.uk/article/Rod-Stewart-At- Andy Heath, Adrian Hides, Peter Holt, Neil Hooton,
Leeds-Arena Neil Hooton is an Associate in the Leeds office, and the Susie Horsefield, Ray Houghton, Will House,
multidisciplinary Project Manager for the arena. Justin Howell, Richard Hunt, Paul Irwin, Robert Issott,
Awards Susie Horsefield is a senior engineer in the Sheffield Richard Jackson, Phil Jagger, Matt Johnson,
Institution of Structural Engineers Structural Awards: office, and was a member of the structural engineering Laurence Kearsey, Rory Kenneally, Lee Kirby,
Winner design team and BREEAM assessor for the arena. Ian Knowles, Mike Kong, Angus Law, John Linnell,
Institution of Structural Engineers Yorkshire Structural Lee Kirby is a senior consultant in the Leeds office, and Dan Lister, Matt Lovell, Laura Marchant, Stu Marley,
Excellence Awards: Winner led the acoustic design for the arena. Helen Marsh, William Martin, Sandra Murray,
Yorkshire Property Industry Awards, Development of Robert Nash, Darren Parker, Chris Parsons,
Helen Marsh is a designer in the Sheffield office, and Owen Phillips, Gavin Poyntz, Alan Rowe, Judith Ruttle,
the Year & Design Excellence Awards: winner was a member of the lighting design team for the arena. Gary Smith, Hannah Smith, Jim Smith, Neale Smith,
YorHub Constructing Excellence Awards, BIM project Ben Watkins is an Associate in the Sheffield office, and Adam Smout, Martin Stanley, Ryan Taylor,
of the year: Winner led the structural engineering design for the arena. Pete Thompson, Nick Troth, Dave Twiss, Dave Wade,
YorHub Constructing Excellence Awards, Project of the Ben Watkins, Paul Wheatley, Gary White, Laura Wilson
year: Winner Project credits Architect: Populous Project manager: Davis Langdon
Institution of Civil Engineers Award First Direct Promoter: City of Leeds Clients: City of Leeds; PMP LLP Steelwork subcontractor: Fisher Engineering Ltd
Arena (shortlisted) Ltd (now IPW Ltd); BAM Construction Ltd; Yorkshire Concrete subcontractor: Creagh Concrete Ltd
Forward (due diligence review); SMG Europe Ltd Faade subcontractor: Lakesmere.
Authors (fitout) JV consortium partner: Donaldsons
Jim Bell is a Director and leader of the Sheffield office, Planning agent, technical adviser, civil and SMEP Image credits
and was Project Director for the detailed design of the engineer, acoustics, fire, lighting and BREEAM 12, 5, 7, 11, 16, 21, 28, 3235 Giles Rocholl
first direct arena. assessment services consultant: Arup Iain Adcock, Photography; 3, 13 Nigel Whale;
Gareth Ainley, Stuart Allinson, Pete Allison, Ben Aston, 4, 17 BAM Construction Ltd; 6, 8, 10, 12, 1415, 20,
Samantha Birchall is business development Mohd Bahardin, Susanna Bathe, Jim Bell, 2225, 27, 29, 31, 3637 Arup; 9, 26 Populous;
co-ordinator in the Sheffield office, and for the arena. Andrew Bradshaw, Ryan Brate, Adam Brown, 1819, 30 Arup/Nigel Whale.
David Clixby is an Associate Director in the Sheffield Jonathan Burton, Neal Butterworth, Rachel Capstick,
office, and led the MEP team for the arena. Lee Carl, Andrew Carter, Judith Chan, Josh Childs,
Ian Drabble is an Associate Director in the Sheffield David Clixby, Robert Collett, Anna Coppel, Ben Cox,
office, and led the civil engineering design of the arena. Richard Crabtree, Paul Davies, Derek Devereaux,
1.
New
Fulton Center
Dey Street
concourse
The Corbin 135 William Street
Building Headhouse
2.
11.
The original structure internal floors and roof. Wrought iron beams
With a hybrid structure of loadbearing frame between the columns and perimeter
masonry and an ironwork gravity frame, walls and support the Guastavino tile arch
Corbin is wedge-shaped on plan, 40ft floors. The large projecting bay windows in
(12.2m) wide at the east end but only 20ft the south and west faades were formed as
(6.1m) wide at the west elevation self-supporting decorative cast iron
overlooking Broadway. Its overall length is structures. For all lateral stability the
152ft (46.3m), and it has two basement building relies on the masonry elements
8. levels, double-height retail space at street acting as shear walls.
level, and seven full levels of office space
above. The building ends were once crowned While the exterior was found to be more or
8. Elaborately decorated staircase. with fairytale towers but lost their peaked less intact (albeit suffering from its long
roofs in the early 20th century. neglect), the building interiors had been
9. Uday Durg, MTACC Program
Executive, examining decorative extensively redecorated and remodelled.
detail on Corbin. The faade is predominantly self-supporting But the grand ornate staircase still connected
10. The Corbin Building signature. masonry. Cast iron columns were used levels 2 through 8, and some elements of the
11. Detail of brass and copper-plated internally and are also embedded within the original Otis elevator remained.
cast iron balustrade. perimeter masonry walls as support for the
Cast iron faade repairs Faced with this, the team recommended a likely excessive cost of site containment and
The original design called for wholesale change of approach. While the multiple blast media collection. Although Vacu-Blast
removal of cast iron elements in the faade, small decorative elements fixed onto the face performed well in the shop, it did not
so that individual pieces could be of the windows would still be removed and translate effectively to the field due to the
documented, cleaned down to bare metal, either cleaned off-site or replicated if too quantity of decoration on the existing
and repainted. Damaged pieces were to be damaged, the cast iron windows and frames metalwork forming a high relief and
replicated. This approach was based on the would be left in place and repaired there. preventing a good seal between equipment
assumption that the cast iron was erected and working face.
bottom-up after the main masonry faade, This gave the team new challenges: to clean
as was common in many similar buildings and repaint the cast iron in situ, repair Fortunately the needle-gun (a drill-like
of this period. non-structural cracking in infill panels and device with multiple metal needles driven
window sills, and the in situ structural percussively by pneumatic action) proved
Work commenced with the careful removal repairs to load-bearing armatures. effective in cleaning but still avoiding
of the decorative cast iron leaf-shaped damage to the base metal decoration.
tracery elements that stood proud of the Solutions had to be rapidly developed while
window framing (Fig 15). Unfortunately, as engaging the contractor to perform necessary Meanwhile, PACA examined the paint on the
removal of the internal wood window field testing and mock-ups to ensure that existing ironwork and came to a startling
framing began, it was discovered that the both designer and client were happy with conclusion: it had not always been black as
original cast iron armatures were built into the final solutions. originally thought, but rather a bright red
and behind the decorative terracotta window color (somewhat ironically named shy
surrounds. It would be impossible to remove Cleaning and repainting cast iron in situ cherry). This was further backed up when
these elements without wholesale damage to The team conducted shop and field testing of PACA found a contemporary citation to
the terracotta, and extending the project several cleaning options, including Vacu- Corbin as the red building.
schedule by several months. Fortunately the Blast and needle-guns, to determine which
back side of the cast iron windows was would be most effective. Traditional blasting
found to be generally in excellent condition. was considered but dismissed, due to the
Clay shrinks about 10% in firing, and the The team looked for alternatives.
implications were significant. Instead of Trials using the wet Prosoco alkali-based
being formed from original pieces from the cleaning agent were carried out (Fig 26),
23. building, new moulds exactly 10% larger with different dwell times and various
than the proposed finished article had to be degrees of agitation, until an acceptable
made. This is no mean feat of artistic skill, result was achieved. This had some
as the sculptor creates the clay master advantages in that a similar system had been
working by eye from an original piece specified for nearby areas of stone cleaning,
(Fig 23). Even when the moulds were so the contractor could readily adapt his
formed, the inability to press out any kind of means and methods of protection to extend
re-entrant detail required that the individual this approach.
pieces be hand-finished and stippled/marked
to match the originals prior to placing and
firing in the kiln (Fig 24). Given the level of
artisan skill needed, the typical price was
around $500/piece, uninstalled.
24.
28.
BROADWAY
already expected: Corbins iron frame was Escalator
designed as a gravity-only structure fairly wellway
void
typical for the time and it clearly relied
on the various masonry elements of the Lateral
faade for lateral stability. The plan (Fig 29) 29.
instability
New lateral
shows the main stiffnesses of the lateral bracing frame
JOHN
STREE
system to be along the length of the extreme T
north perimeter wall and in and around the
main building core at the wider east end.
References In addition, the Corbin Building restoration was Patty Nordhausen, Elizabeth Perez, Clare Phillips,
(1) KOSTURA, Z, et al. The Fulton Center: the main contributing factor in MTA being given a Ricardo Pittella, Samantha Plourde, Lana Potapova,
design of the cable net. The Arup Journal, 48(2), special Stewardship Award in the 2013 New York Marie Reedy, Tom Rice, Robb Risani, Justin Rodriguez,
pp74-83, 2/2013. Landmarks Conservancy Lucy G Moses Preservation Arkady Rubinstein, Yet Sang, David Sivin, Nick Watkins,
(2) http://en.wikipedia.org/wiki/Francis_H._Kimball Awards, for the management and care of its many Chelsea Zdawczyk Architect: PACA (Page Ayres
historic properties. Cowley Architects) General contractor:
(3) http://en.wikipedia.org/wiki/Guastavino_tile Judlau Contracting Specialist sub-contractors:
(4) APPLEBY, J, et al. Fulton Street transit center Authors Brisk Waterproofing, Western Facades Group,
foundation design and construction in a dense urban Ian Buckley is an Associate in the New York office, and Boston Valley Terra Cotta Foundations contractor:
environment. Presented at the 2011 Pan-Am CGS was Project Manager and structural design team leader Skanska Construction.
Geotechnical Conference, Toronto, October 2011. throughout construction for the Corbin restoration.
(5) BUCKLEY, I, et al. Cast-iron columns and brackets: Craig Covil is a Principal in the New York office, and Image credits
an historic and contemporary study. To be presented at was Project Director for the Fulton Center and the 1, 1115, 2728, 40, 48, 54 MTA/Patrick Cashin;
APTI (Association for Preservation Technology Corbin restoration. 2 Anthony Cortez; 3, 6, 46b New York City Library;
International) Qubec, October 2014. Back cover, 4, 17, 19, 2224, 26, 30, 36, 38, 45, 47,
Ricardo Pittella is a Principal now in the So Paulo 4951, 53 Ian Buckley; 5 Boston Public Library;
office. He was the Structural Engineer of Record for the 7 Peter Aaslestad/Frazier Associates; 8 Geoffrey Gross;
Awards Corbin restoration while he was based in New York.
American Institute of Architects (AIA) New York 910, 25 PACA/Carlos Carrera; 16, 29, 37, 39ac, 42,
State Design Awards: Adaptive Reuse/Historic 52 Nigel Whale; 18, 21 Brisk/James Norberg;
Project credits 20 Brisk/Mike Radigan; 3132, Yet Sang and Ho-Yan
Preservation: Award of Merit 2013 Client: MTA Capital Construction Lead consultant Cheung; 3334 Lana Potopova; 35, 43 Joe Appleby;
American Council of Engineering Companies of New and multidisciplinary engineering design: Arup 39d Yet Sang; 41, 44 Skanska Construction;
York (ACEC NY): Diamond Award for Engineering Joseph Appleby, Leo Argiris, Liam Basilio, 46a Mark Nelson.
Rehabilitation 2014 John Batchelor, Gillian Blake, Mark Brand,
American Council of Engineering Companies Ian Buckley, Alison Caldwell, Bob Cather,
(ACEC): National Recognition Award 2014 Foram Chaliawala, Ann Chamley, Ho-Yan Cheung,
Anthony Cortez, Fiona Cousins, Craig Covil,
New York Historic Districts Council Design Awards: Casey Curbow, Carmen Danescu, Star Davis,
Honorable Mention 2014 Michael Deutscher, Nicola Dobbs, Jonathan Drescher,
AIA New York State, Excelsior Award 2014 Alex Engelman, Adam Friedberg, Bethel Gebre,
Structural Engineers Association of New York Tom Grimard, Gregory Hodkinson, David Jacoby,
(SEAoNY) Excellence in Engineering Awards 2014: Igor Kitagorsky, Tanya Kokorina, Marina Kremer,
Engineers Choice Award Steve Lasser, Deborah Lazarus, Adrian Lee,
Hillary Lobo, Andrew Marchesin, Cecy Martinez,
New York State Society of Professional Engineers Cliff McMillan, Kristina Moores, Mark Nelson,
(NYSSPE) Central New York Chapter 2014 Project of
the Year Award (for the complete Fulton Center).
1.
5.
Base building Effectiveness of design strategies Table 3. Estimated cooling load and breakdown
New buildings in Hong Kong are becoming The energy simulations predicted the for the CIC ZCB.
more efficient, partially due to the mandatory effectiveness of passive and active energy Components Cooling load
2012 building energy code (BEC)9, which saving strategies in Hong Kong (Fig 7),
Fabric load 64.4kW
provides best practice design guidelines for the design considerations and performance
all new developments there. In addition, of which can be summarised as follows: Equipment load 18.4kW
BEC regulates the design of overall thermal Lighting load 6.0kW
transmittance values (OTTV)10 of the Faade thermal performance People load 20.2kW
building fabric and the minimum The envelope loads must be minimised to Fresh air load 53.4kW
requirements for major building services reduce heat build-up. The ZCBs peak
Total peak cooling load 162.4kW
systems, eg air-conditioning (AC), electrical, cooling load was calculated as approaching
lighting, escalators, etc. 163W/m2, with the general average being
around 80W/m2. Table 3 shows the cooling
BEC thus supplies the baseline and design load breakdown of this building if it were 6. Results of energy simulation
targets for practitioners. To achieve its constructed to BEC standards. Note that on the energy use of various
objective of ultra-low energy use, the ZCB fabric loads comprise the major portion, building systems.
was designed to substantially surpass such as the building has a high envelope-to- 7. Summary of energy simulation
baseline performance. floor area ratio. results for different design strategies.
9.
10.
Optimising microclimate and Because the floors are radiantly cooled, the 13. Building massing and orientation
natural ventilation air temperature can be higher to achieve the optimising natural ventilation.
As previously noted, enhanced natural same level of comfort, and higher air 14. Wind catcher.
ventilation reduces the CIC ZCB energy temperatures also result in lower heat losses 15. CCHP biodiesel generator.
loads, as air moves through naturally for to the outdoors. And radiant cooling systems 16. Absorption chiller.
30%40% of the year (helped by ceiling are silent, enhancing occupant comfort.
fans). The building is oriented to receive
the sites prevailing south-easterly wind, so A limiting factor for the panel temperature
as to optimise natural air flow availability and the cooling capacity is the dew-point
(Fig 13). A thermal dynamic study showed temperature in the space. Standards
that in natural ventilation operation, cool recommend a limit of 60% or 70% relative
fresh air is brought in through orifices, humidity, which at an air temperature of
warmed by the internal loads, and exhausted. 26C corresponds to a dew point between
17C20C, ie lower than the floor
The internal temperature to be maintained is temperature (typically 21C).
25.5C, and for this level of internal gain
natural ventilation can function below The CIC ZCB radiant system is sized to
external temperatures of 20C, taking into deliver 50W/m2, accounting for 30%50%
account increased air movement due to of the total heat load. Energy savings occur
ceiling fans. This delivers a minimum of six through the reduction in fan-power (by
air changes/hour under typical conditions. 30%50%), though are slightly offset by an
increase in pump power additional energy
Radiant cooling for the chilled water circuit.
The radiant cooling systems rely primarily
on radiation heat transfer. Typically, chilled Given the risk of condensation, the radiant
water is circulated through ceiling panels or panels are located away from the perimeter,
beams to maintain comfort by collecting and with appropriate control methods outlined
removing heat from the space. Also, radiant below. The panels are provided with higher
systems are more energy-efficient than water temperature compared to conventional
air-based systems, requiring less parasitic fan coils, leading to higher coefficient of
(pump and fan) energy to deliver cooling, performance (COP) at the chillers.
and higher operating temperatures mean that The cooling energy savings are around
a chiller can operate more efficiently if it is 6%12%, with the corresponding overall 14.
not required to serve other, cooler, areas. energy reduction approximately 1%3%.
Energy grading highlights interesting issues, 0 compared to the local standard, and the
like the inherent inefficiency of many -2000
energy cascade concept was introduced to
conventional systems that consume high- maximise the thermal efficiency of the
-4000
grade energy and deliver only low-grade biodiesel CCHP system. Overall this is 80%,
energy to building users. It shows that the -6000 a significant performance that helps to lower
high energy penalties of chilled water -8000 the buildings carbon footprint. The total
production can be supplied by waste heat -10 000
life-cycle carbon emission is offset by
rather than conventional grid electricity; on-site renewable energy generated by PV
-12 000
an annual energy balance can be achieved and biodiesel CCHP systems.
between consumption and renewable -14 000
generation (Fig 17). -16 000 Commissioning the building tested the
J F M A M J J A S O N D
performance of the CCHP system;
Applying the general carbon conversion 18.
generator output power, absorption chiller
factor of 0.7kgCO2-e/kWh in Hong Kong14 cooling capacity, and supply and return
shows the carbon trade-off for the whole 120
CCHP power output chilled water temperatures were all logged
CCHP power generation
year (Fig 18); it can be seen that carbon 100 and investigated. Several rounds of
emissions in the cool season (November 80 condensing water temperature calibrations
March) can be fully offset in summer showed that the system delivers the design
(kWe)
60
(JuneSeptember). 40 cooling capacity and chilled water
20 temperatures. Further comprehensive
Commissioning 0 analysis is anticipated when more testing
.20 .20 .20 .20 .20 .20 .20
The CCHP was installed and commissioned 00 07 09 11 13 15 17 data are available.
to test the system performance. The results Absorption chiller cooling power
80
showed (Fig 19) that at the design power Since the CIC ZCB opened, a campaign of
Absorption chiller cooling
70
generation (100kWe), the absorption chiller 60 regular guided tours for both professionals
can deliver a cooling capacity of 70kW. 50
and the public has enabled visitors to
(kW)
40
The COP is at 1.1 with overall thermal 30 experience the ZC built environment.
efficiency of 80%. The chilled water 20 This has raised the level of discussion about
10
temperature can achieve the design 0 and awareness of climate change, ZC
conditions, ie supply temperature of 9C and 00
.20
07
.20
09
.20
11
.20
13
.20
15
.20
17
.20 technologies, and behavioural change, etc.
return temperature of 12C. More testing Absorption chiller chilled water temperature
25
results are expected in the future after a The building was awarded the Grand
Chilled water temperature
longer period of occupancy of the building. 20 Award in the Hong Kong Green Building
15 Awards 2012.
(C)
10
1.
Introduction The two-storey, 24 000ft2 (2230m2) OTC, the resulting patterns controlling the amount
Located in the heart of Greenfield in named after the long-serving Massachusetts of heat entering the interior in summer and
north-west Massachusetts, the new John W congressman John W Olver, is the first winter (Figs 12).
Olver Transit Center (OTC) is an intermodal zero-net energy (ZNE) building of its type in
depot for all of the areas fixed-route bus the United States. Embedded in its design The OTC is part of an ongoing effort by the
lines and private inter-city, taxi and are numerous strategies for energy Commonwealth of Massachusetts to foster
paratransit (community transport) services. conservation and generation. projects that use renewable energy systems,
and it is one of a handful of ZNE buildings
It also houses the offices of the Franklin One example is the textured brick cladding in the state.
Regional Transit Authority (FRTA) on the western side: a respectful nod to
the public transportation provider for this Greenfields past, but with green as its Working closely with Charles Rose
part of Massachusetts and client for the OTC main purpose a high-tech strategy for Architects (CRA), Arup provided a range of
and the Franklin Regional Council of managing the buildings exposure to services including mechanical, electrical,
Governments, the successor organisation to afternoon sun. In parts, the brick dissolves plumbing and lighting design, and
the Franklin County government. and the faade becomes a kind of screen, sustainability advice.
What is zero-net?
To design the building and meet the project
goals, the team needed a clear understanding
of what a ZNE building is. Wikipedia1 has
an extensive series of definitions, while the
National Renewal Energy Laboratory in
20062 formulated as follows: In concept, a
net ZEB is a building with greatly reduced
energy needs through efficiency gains such
that the balance of the energy needs can be 2.
supplied by renewable technologies.
Supply
Reheat coil (from
ground source system)
Return Supply
Heating coil
(from biomass boiler) Return 3. Biomass boiler (left) and PV
Cooling coil (from array (right).
ground source system)
4. Building cross-section
showing air-side
5. conservation strategies.
5. Water-side
conservation elements.
ROW
worked with the client to select equipment
Meeting
that balanced the OTCs technological and
BANK
room
energy conservation requirements.
Lobby
The site
When designing a ZNE building one of
Electrical
the first design decisions to make is its
Mechanical
orientation, which can impact heating, Transit waiting area
lighting and cooling costs. For example,
maximising southern exposure takes Parking
optimal advantage of the sun for daylight Solar wall
and passive solar heating. Cooling costs will
be lowered by minimising western
exposures, where it is most difficult to Biomass
boiler
provide shade from the sun.
Geothermal
The OTC site is close to the centre of 6. wells
Bio-retention
downtown Greenfield on the corner of Bank garden
Row and Olive Street, and the building
orientation was fixed by the size of the site
and the requirements for the bus driveway Bus
(Fig 6). This resulted in a long northsouth loop
axis and a short eastwest axis. Arup worked
with CRA to relocate elements such as 0 50ft
Railway PV array
storage, plantrooms and bathrooms to the (15.24m)
west side of the building, which insulated the
offices on the east from solar gain. For this
faade Arup and the architect developed a
perforated copper screen that reduces glare
in the office space (Fig 7).
Reduced loads
Envelope
In the initial design, Arup worked closely
with the architect to improve the envelope
performance beyond code minimum
requirements (Table 3). By reducing the
amount of heat gains and losses through the
building envelope, the team was able to
reduce the overall mechanical plant required.
Lighting
Lighting is a key component in the design of
low-energy buildings, and there are two
primary ways that it can influence energy
use in a space:
Glare control Active strategies and as a heat source in winter for chilled and
While one aspect of daylighting design is to hot water. The heat pumps are coupled with
Chilled beams
achieve appropriate minimum light levels, a geothermal well field and ground loop.
Compared to traditional all-air systems,
it is also important to ensure that measures
active chilled beams (ACBs) typically save
are taken to reduce daylight glare. The OTC has 22 closed loop geothermal
money on operating costs. These systems
Glare from direct sunlight or high sky wells, each over 400ft (122m) deep.
combine water-based sensible cooling at
brightness can not only be distracting, Arup worked closely with the geotechnical
the room level with latent cooling via the
but also increase energy use by encouraging sub-consultants to co-ordinate building
air-handling unit (AHU) system. As a result
users to close shades or blinds, which in loads and service connections between the
less conditioned air needs to be moved
turn requires electric lighting to compensate indoor heat pumps and the geothermal well
through the building.
for the reduced daylight. field. Geothermal heat pump systems
ACBs include a sensible cooling coil and typically use less energy than conventional
Each faade had different conditions, so a HVAC systems, are less obtrusive, and
high-velocity nozzles. As conditioned air is
different approach was taken on the north reduce water consumption by not requiring
supplied through the beam, the nozzles
faade compared to the east and south. a cooling tower.
create a pressure differential that induces or
The north faade is glazed, without
pulls room air into the beam. As it flows
additional shading, due to the minimal Transpired solar collector (solar wall)
through the beam the room air passes
level of direct sunlight striking it. Almost all the south-facing opaque faade
through the sensible cooling coil and mixes
forms (Fig 10) a transpired solar collector,
with primary supply air.
The east and south faades, on the other used to preheat ventilation air in the winter.
hand, have glazing protected by custom- As the collector absorbs solar radiation,
The central system is designed to circulate
designed copper screens with roughly 50% perforations in it allow fans to draw
only the amount of air needed for ventilation
openness (Fig 10). These reduce the daylight ventilation air into the cavity between it and
and dehumidification, with the ACBs
entering the spaces but maintain enough for the faade itself. This preheated ventilation
providing the remaining sensible cooling
internal illumination, and protect against air is then ducted to the central AHU for
through the induced room air and sensible
glare by reducing the average sky brightness further conditioning and distribution.
cooling coil. Fan energy is one of the largest
seen through the screen. They also reduce building energy uses, and ACB systems
thermal loads. As well as the winter energy savings, the
require less energy since they move less air
added cladding to the south faade reduces
throughout the building.
There is also automated shading on the west the summer cooling demand by shading
and south faades; this is controlled based direct sunlight. In the summer months the
Ground source heat pumps
on the time of day and exterior daylight transpired collector is bypassed so as not to
Primary cooling and auxiliary heating are
conditions, with an override capability for overheat the incoming air.
provided through ground source heat pumps,
local users.
which use the earth as a heat sink in summer
Authors
Julian Astbury is an Associate Principal in the Boston
office and was Project Manager for the OTC.
Matt Franks is an Associate in the New York office and
was a member of the electrical engineering team.
Geoff Gunn is a senior engineer in the Boston office and
led the BIM design.
Michael Hovanec is an Associate in the Boston office
and led the mechanical engineering design.
Leroy Le-Lacheur is an Associate in the Boston office
and led the plumbing and fire protection design..
Charles Rose is Principal of Charles Rose Architects,
Somerville, MA, which designed the OTC.
Project credits
Client: Franklin Regional Transit Authority
Architect: Charles Rose Architects Inc
Building services engineer and sustainability consultant:
Arup Julian Astbury, Fiona Cousins, Matt Franks,
Geoff Gunn, Michael Hovanec, Beth Iacono,
Carey Jones, Kevin Kresser, Leroy Le-Lacheur,
Nora McCawley, Anna Murray, Sasha Velic,
Mark Walsh-Cooke, Craig Webster Civil engineer:
McMahon Associates Geotechnical engineer:
McPhail Associates Structural engineer: Richmond So
Engineers Cost consultant: Faithful & Gold
Code consultant: RW Sullivan.
13.
Image credits
1, 78, 11, 14 Charles Rose Architects;
23, 10, 1213 Peter Vanderwarker Photography;
Conclusion Arup is currently conducting a post- 45 Rebecca Hatchadorian; 6 Nigel Whale; 9 Arup.
The John W Olver Transit Center opened occupancy energy survey of the building to
on May 4, 2012, in a dedication ceremony confirm that the design goals have been met.
with Massachusetts Governor Deval Patrick, This is planned to be completed in 2014, 11. Daylight enters the second
Lieutenant Governor Timothy Murray, to confirm that the team achieved the goal floor office space through
and other state officials present. At the of designing a high performance building overhead skylights.
time of ground-breaking in April 2009, with energy consumption reduced by 50% 12. The PV array.
the construction budget was $12.8M, but the compared to a typical code-compliant 13. Eastern elevation with second
building came in $2.4M under budget, with office building. floor perforated screens.
all its numerous sustainable and ZNE 14. Transit waiting area.
features intact and operating.
A30:
Autoroute 30 Montral
Southern By-pass
Location Authors
Montral, Qubec, Canada Douglas Balmer Matt Carter Tim Hackett
Alan Phear Nick Sartain Derya Thompson
540 N
Notre-Dame-de-Ile-Perrot Chteauguay
Northern
Interchange
Chteauguay
River
30 30
20 Chamberry Lake Saint-Louis
stream A540
Bridges
over railway A20
es Canal
Soulang Toll plaza 30
al
tr
Beauharnois on
t o M ay
on ilw
St Lawrence River 30 Tor ra
Section 1
A20/A30/A540
Section 2 Northern
l
na
Section 3 Interchange
Ca
Section 4
ip
St Louis A20
Sh
30 le de Salaberry Section 5
River
is
r no
0 5km
ha
A30
au
Be
2.
Given the design teams geographical document but in a read-only format without Project correspondence also included
spread, regular data management protocols making changes to the master version. letters to and from the client, CJV. All these
would have been inefficient and risky, with This reduced the complications of documents were also stored on Projectwise.
large volumes of data and drawings being individuals updating different versions of
exchanged between servers in each office, the same document, and the changes having Both systems were made possible by the
duplicating storage, and bringing the danger to be consolidated at a later date. Arup also quality of the data network connections that
of working from out-of-date information. enabled its subconsultants to have access to Arup has in place between all its offices,
To overcome these potential problems, Projectwise, which helped the team to share a factor that was planned into the project
Arup adopted two key systems. and control data. infrastructure and links from the outset.
The main data management tool used was Email now being the default means of
Bentley Systems Projectwise, which communicating data and information on
enabled all the data to be stored in one projects, the second key application used by
location, accessible to all the design teams. Arup on the A30 was Mail Manager, an
Sensitive information was handled by setting add-on to Microsoft Outlook developed
up user permissions that could control read/ by Oasys, Arups internal software
write privileges allocated to users or, if development team. This simplified filing and
necessary, deny access. Approved users searching for emails with over 180 000
checked out documents or drawings to work generated on the project, the ability to store
on, and check them back in once any edits and recover any one within a few seconds
were made. Other users could open the same was a real asset.
5.
4. The Northern Interchange in use The St Lawrence River bridge accelerations are substantial and the forces
in October 2012, prior to the from ice in the river during winter are very
official opening. Design constraints
Several constraints influenced the design of large. Permanent disturbance to the riverbed,
5. The toll plaza, between the south however, had to be minimised, due to
end of the Soulanges Canal tunnel the St Lawrence River bridge (now named
and the north end of the the Serge Marcil Bridge after the prominent environmental restraints.
St Lawrence Bridge. Qubec educator, administrator and
6. The St Lawrence Bridge, Last but not least, the CJV client sought a
politician who was tragically killed in the
December 2012. fast track design to start building temporary
2010 Haiti earthquake). They included, first,
works in the first construction season. As the
the low-level profile: this would require
river level was controlled by hydroelectric
short piers which, given the minimum
dams both upstream and downstream of the
practical dimensions needed for robustness,
A30 alignment, the design of the bunds and
would be relatively stiff.
cofferdams required close co-ordination with
Secondly, the rock in the riverbed, along the the construction team and early completion
bridge alignment, is at shallow depth with of the bathymetry and hydraulic studies and
little soil overburden, while seismic ground preliminary substructure design.
9.
7.
17.
Reinforced concrete 31
Launching sequence 26 27 28 pier head 29 30 32
The temporary forces during the launching During the bridge launch, snow loading on improve productivity, quality and safety
dominated the design of the steel section and the deck was a dominant design factor, as by maximising off-site construction.
to reduce these forces, the maximum launch over the course of a winter the weight of Though precast segmental piers have been
cantilever was reduced to 130m by snow could potentially exceed the decks used on other projects, care was still needed
supporting the bridge at two points on a self-weight. Close co-ordination between the to ensure that seismic performance and
concrete hammerhead at the top of each contractor and the designer was needed to durability would not be compromised.
main pier. Hydraulically-linked jacks ensure that appropriate measures were in
ensured that the reaction load was evenly place to clear snow from the deck and The seismic performance was ensured by
distributed between the two lines of support. confirm that the residual snow loading in the using in situ construction for the plastic
design was consistent with these measures. hinge zone at the base of the pier.
The tendon prestress that holds the segments
When the launch was complete, the deck together is anchored on internal blisters
19. Eastern approach under was made monolithic at both piers and an above this zone. The segment joints
construction. additional haunch segment was erected to themselves were designed as capacity-
20. Construction sequence of increase the girders structural depth at its protected elements to ensure that ductile
navigation span.
supports (Fig 20). This strengthening was yielding in the in situ base takes place before
needed to resist in-service loading. the joints reach their ultimate capacity.
23.
0.6
Proposed design
spectrum
on white noise), it preserves the non-
GSC 2500-year To cope with these irregularities and stationarity of the original seed record and
0.5 spectrum x 1.35
non-linear elements, time history analyses does not add unrealistic energy content to
0.4 were carried out using LS-DYNA. the entire duration of the history.
0.3 The bridges were modelled in their entirety
0.2 and soil elements explicitly modelled. RSPMatch2005 can closely match a target
0.1
This allowed the input ground motion to be spectrum across a wide range of periods, but
consistently applied at bedrock level and for is most effective when the original seed
0
0 1 2 3 4 5 6 site response to be analysed directly, as record response spectrum has a reasonably
Period, T (sec) opposed to estimated from the CHBDC site close match to the target spectrum before
coefficients. Non-linear soil column models spectral matching. This ensures that the
were developed and analysed in isolation program can successfully converge, and that
24. with the results compared against Arups the modifications to the record are as small
in-house site response analysis software as possible. Seed spectra were obtained from
SIREN, so as to optimise the finite element UC Berkeleys PEER NGA database3 which
soil mesh density and validate the behaviour. contains over 3000 records, predominantly
from the western USA, but also some
international records.
27.
Ground engineering alongside the CJV team during the Several construction challenges were
Overview construction phase. The detailed inherent in the soils encountered on the site.
The ground engineering for the A30 project geotechnical design was carried out by Arup They included the Champlain Clay being
included embankments on soft ground, two teams in the UK and USA, as well as by sensitive soft clay, fairly typical of eastern
deep cuttings, the foundations for the two Aecom in its Montral office acting as a Canadian and Scandinavian glacial soft
major bridges as well as the many other design sub-consultant to Arup, and co- clays. When disturbed, either naturally
smaller bridges, and a cut-and-cover tunnel ordinated by the Montral Arup team. (river erosion or earthquakes) or by human
under an old but working ship canal4. activities like construction or excavation,
Geology and ground conditions the soft sensitive clay has the potential to
Also, the design solutions needed to be
The area through which the A30 passes is lose much of its strength, resulting in a
constructed by the CJV using a self-
relatively flat and predominantly rural. danger of retrogressive landslides.
certification procurement approach.
The ground conditions under the route
As with other aspects of the project, generally comprise deep Champlain Clay In addition, the very cold winters in this part
Arup drew on its expertise in soft ground deposits, overlying granular glacial till of Eastern Canada meant that earthworks
engineering, heavy foundations, seismic which in turn overlies bedrock. and other construction were generally only
engineering and highway earthworks to possible during the summer months as the
The Champlain Clay is marine clay and upper 2m3m of clay would freeze,
meet the short design schedule and project
comprises a stiffer weathered surface crust essentially forming a rock type material.
complexities. In addition, outside experts
of brown clay, typically about 3m thick,
with particular experience of constructing in
over unweathered softer, compressible and
the local Champlain Clay were identified and
sensitive grey clay. Bedrock is typically
brought into the team. Several experienced
strong or very strong quartzitic sandstone
Arup geotechnical engineers were brought
with beds of dolomitic sandstone.
into the Montral project office to work
Embankments
Most of the main line of the A30 is on
low-height embankments, typically 2m3m
high. As already noted, higher ones were
required at interchanges (Figs 2829) and for
side roads on the approaches to bridges over
the A30. The highest embankments, (up to
11m) are at the Northern Interchange, where
the A30 joins the existing A20 and A540
autoroutes. This coincided with the greatest
thickness (up to 20m) of Champlain Clay
along the route.
29.
The CJV judged this foundation solution to Micropiles were installed efficiently with a In addition, two load tests were done on
be expensive, so suggested spread footings relatively small drilling rig, making them sacrificial, heavily-instrumented 1.18m
founded directly on the shallow rock as a far more economical than drilled shafts, diameter test drilled shafts using Osterberg
more economical alternative. The CJV even when many are used. A substantial load cells10. The results of the pile load test
additionally sought to avoid expensive reduction in the size of the footings and programme not only proved the method
over-excavation to recess the foundations reinforced tremie plugs was possible this of pile installation, but enabled the final
into sound rock to resist sliding way, achieving the CJVs goal of cost- design of the driven steel pile and drilled
a standard MTQ foundation detail. effective foundations while avoiding shaft foundations to be optimised and
environmental consequences. value engineered.
Despite the reduction in seismic overturning
moments realised by using FP bearings, the Beauharnois Canal bridge foundations The design of the piled foundations in the
horizontal forces and overturning moments river involved conflicting criteria. The piles
Overview
due to design ice and wind forces would still could not be too large in diameter or they
The Beauharnois Canal bridge twin
have required very large spread footings. would attract significant pressures due to
decks have single abutments at each end.
Early estimates found that the area of static ice forces. On the other hand they had
Each span is supported by single columns,
riverbed disturbed this way could be much to be strong enough to resist seismic loads
with pairs of adjacent columns tied together
higher than considered in the environmental without being so stiff as to increase the
at the waterline to form a single foundation
study, triggering the need for an updated loading. This led to heavy reinforcement
element (Fig 34).
environmental study with associated time cages within the piles near the
delay and the possibility of permit refusal. The 44 foundation elements for the bridge maximum allowable.
include: pad footings bearing directly on
The solution to reducing the size of the A significant enhancement in design strength
rock (in eight locations); piers supported on
spread footings and avoiding over- was achieved by successfully demonstrating
groups of 96 concrete-filled driven steel tube
excavation into rock was to stabilise them that strength reduction factors for drilled
piles (at 16 locations); and piers supported
against lateral forces by using micropiles, shafts should only be applied to the concrete
by groups of 1.85m diameter drilled shafts
150mm in diameter with 65mm diameter while the reinforcement itself should be
socketed a minimum of 4m into rock (at 20
high strength bar cores. The micropiles were considered to have its full design strength.
locations, with a total of 138 drilled shafts)9.
principally designed to act in tension in the
event of lateral movement of a foundation Testing and design
and they also contribute to controlling A comprehensive pile load test programme
overturning. The maximum tension load in was carried out to validate the foundation
the micropiles from the overturning design parameters for the bridge. Full-scale
moments was chosen to limit the elongation static compression and uplift tests were
of the bars to less than 10mm, and the performed on instrumented driven steel tube
embedment length of 7m was controlled by piles (subsequently filled with concrete).
grout-to-rock bond strength.
Section 3: on le de Salaberry
(six bridges):
35.
side roads Chemin du Canal) and
Other bridges Monte Pilon over A30
The bridges in Sections 1 and 3 are one for each carriageway of A530
characterised by high curvatures and skews, over Boul Pie XII
generally because the interchanges had to fit
R201 at interchange with A530
into small land areas (interesting for a
country with one of the highest amounts of two links over A30 at southern
undeveloped land in the world). The Arup interchange with A30
team had to develop its own methodology
for the seismic design of walls and Section 5: from the Beauharnois
abutments backfilled by lightweight fill. Canal to Chteauguay (11 bridges):
36.
side-road Boul St Jean Baptiste over
The Section 3 bridges were generally the A30
conventional, mostly square and straight,
while those in Section 5 formed a mix of side-road Boul St Joseph over A30
types. Generally these were also A30 over Chteauguay River
geometrically simple, but in terms of
structural type embraced decks of post- side-road Montee Bellevue over A30
tensioned in situ concrete, prestressed R205 over A30 at interchange
precast concrete, prefabricated steel girders,
and a steel truss pedestrian crossing. Most cycle track over A30
37.
had lightweight backfill and piled supports. side road Chemin St Louis over A30
The choice of foundations was determined one for each A30 carriageway over St
primarily by the thickness of the Champlain Louis River
Clay at each location and most are in R236 over A30
areas where it is relatively thick.
R236 over St Louis River.
Following local practice, these bridges were
designed with 320mm diameter steel tubular
piles driven closed ended, either vertically or
raked to resist horizontal forces.
Typically the piles were driven either to the 35. Looking east along the A30
bedrock or, where the glacial till was thick, across the Chteauguay River bridge.
38.
terminated in the till. The team undertook a 3637. Road bridges at the
programme of preliminary pile drives and Northern Interchange.
testing, and subsequent optimisation of the 38. Installing lightweight fill
transition to bridge over the
foundation design11. Toronto-Montral railway at the
Northern Interchange, early 2010.
As part of the A30 project, an 80m long, from the passage of canal ships without The requirement to reconstruct the canal
four-lane tunnel was constructed beneath the restriction. Finally, all of the works, embankments without inducing excessive
canal using a concrete cut-and-cover box including the cut-and-cover tunnel under the differential settlement was achieved by
structure founded in the Champlain Clay, canal, had to be designed to resist the intense incorporating expanded polystyrene
which (as previously noted) is normally freezing inherent in Qubec climate. lightweight fill within the embankments
consolidated, compressible and sensitive. immediately adjacent to the sides of the
A floating foundation solution was Watertight temporary bunds were first tunnel. To ensure watertightness of the new
developed by balancing the weight of the constructed to dam the canal on each side of canal water-confining side embankments, a
structure with the excavation of a significant the tunnel, the length of canal in between combination of mineral liner, geocomposite,
thickness of clay. was drained, and the water-confining side and high-density polyethylene (HDPE)
embankments removed. Then a cutting was liner was used.
The challenge consisted of temporarily formed to construct the tunnel section, and
cutting a section of the canal without the tunnel box structure was built in two
flooding the surrounding area, building high stages between temporary sheet pile walls 39. Construction of the Soulanges
retaining walls at the tunnel portals to make Canal tunnel, October 2010.
(Fig 39). The tunnel was backfilled, the
way for the walkway and for Route 338 water-confining side embankments were 40. High embankments contain the
alongside the canal, and tying the new canal Soulanges Canal above the tunnel.
replaced, and the canal was then reinstated
lining to the clay dikes of the 100+ year-old above the tunnel.
Soulanges Canal. In addition, the design had
to accommodate the design effects resulting
41.
About Arup
Arup is a global organisation of designers, Arups core values drive a strong culture Printed by Pureprint Group using
engineers, planners, and business of sharing and collaboration. their
environmental print
technology. The printing inks are
consultants, founded in 1946 by Sir Ove made from vegetable based oils and
Arup (1895-1988). It has a constantly All this results in: no harmful industrial alcohol is used
evolving skills base, and works with local a dynamic working environment that
in the printing process with 98% of
and international clients around the world. any dry waste associated with this
inspires creativity and innovation production diverted from landfill.
Pureprint Group is a CarbonNeutral
Arup is owned by Trusts established for the a commitment to the environment and the company and is certificated to
benefit of its staff and for charitable communities where we work that defines Environmental Management
purposes, with no external shareholders. our approach to work, to clients and System ISO 14001 and registered
This ownership structure, together with the collaborators, and to our own members to EMAS, the Eco Management
and Audit Scheme.
core values set down by Sir Ove Arup, robust professional and personal networks
are fundamental to the way the firm is that are reinforced by positive policies on
organised and operates. The Arup Journal
equality, fairness, staff mobility, and Vol49 No1 (1/2014)
knowledge sharing Editor: David J Brown
Independence enables Arup to: Designer: Nigel Whale
the ability to grow organically by attracting Editorial: Tel: +1 617 349 9291
shape its own direction and take a long- and retaining the best and brightest email: arup.journal@arup.com
term view, unhampered by short-term individuals from around the world and Published by Global Marketing
pressures from external shareholders from a broad range of cultures who share and Communications,
distribute its profits through reinvestment those core values and beliefs in social Arup, 13 Fitzroy Street,
London W1T 4BQ, UK.
in learning, research and development, to usefulness, sustainable development, and Tel: +44 (0)20 7636 1531
staff through a global profit-sharing excellence in the quality of our work. Fax: +44 (0)20 7580 3924
scheme, and by donation to charitable All articles Arup 2014
organisations. With this combination of global reach and a
collaborative approach that is values-driven,
Front cover: St Lawrence Bridge
Arup is uniquely positioned to fulfil its aim
Back cover: Corbin Building.
to shape a better world.
We shape a better world | www.arup.com