MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

TIME ESTIMATION OF A BUILDING

PROJECT ADVISORY
Prof. Vivek Garg
(Asst. Professor Civil Engg. dept.)

PROJECT TEAM

1. Avalanche Saini (081111006)


2. Abhishek Sharma (081111010)
3. Tathagat Barodh (081111014)
4. Pratik Vaishnav (081111018)
5. Siddharth Soni (081111043)

1
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

Acknowledgement

We, the students are very grateful to many people who helped
and
supported us during the project. Our deepest thanks to our
guide
Prof. Vivek Garg (Asst. Professor) in Structure Engineering ,
Department of
Civil Engineering, MANIT, Bhopal for his valuable help,
guidance and
suggestions during project studies.
2012
We would like to thank our honorable HOD Dr. Vishnu Prasad
for his
faith in us and last but not the least we would like to thank our
Director of
Institute Dr. Appu Kuttan.

2
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

CERTIFICATE

This is to certify that the project entitled DESIGN AND TIME


ESTIMATION OF A BUILDING submitted by afore mentioned
students to the Department of Civil Engineering towards partial
fulfillment of curriculum requirement for 7-8th semester is a
bonafide record of the work carried out by them under my
supervision. They have carried
out this project with utmost sincerity and hard work.

Prof. Vivek Garg


(project
guide)

3
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

Prof.
Vishnu Prasad
(HOD Civil
Engg Department)

PREFACE

Time estimation is a process of calculating the approximate


time required for the completion of the project given the dead
line and start
time of the project. Initially we focus on deadlines, cost comes
next. The
project database contains a lot of information, but at any given
time, you
only need a portion of it to get to information.

This information can be interpreted in form of Gantt chart or


programme evaluation review technique (PERT). The time
estimation of the project helps scheduling the activity. The
more accurate the time estimation more is the profit of
company.

In this project we are dealing with time estimation of a building.

We have used the basis as duration = work/resource effort.


Changing the resource effort we can change the duration of
completion
of activity.

4
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

The interdependency of activity plays a vital role in final


output. Some
activities are based on the relation start to finish, finish to
finish, finish
to start, start to start or overlapping dependency

CONTENTS
1. INTRODUCTION
2. NEED FOR TIME ESTIMATE
3. PROPOSED DESIGN
4. OPERATIONAL PLAN
5. STEPS FOR TIME ESTIMATION
Excavation
PCC work foundation
RCC work foundation
Plinth Beam
Columns
Slab beam and slab
Finishing
Flooring and tiling
Wood work
Steel work
Services

6. GANTT CHART

5
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

7. SYNOPSIS
8. WHAT WE HAVE LEARNT

INTRODUCTION
Accurate time estimation is a crucial skill in civil construction.
Without it, you won't know how long your project will take to
complete and the various steps adopted to complete it.

In current scenario everyone wants to have a perfect


construction with least investment and minimum time,
therefore time estimation before starting any project is a must.

By planning before hand we can know which activity will take


how much time, we can also check the delays in the project.

CPM (Critical Path Method) and PERT (Programme Evaluation


Review Technique) are project management techniques, which
have been created to plan, schedule and control complex
projects.

6
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

2. CONSTRUCTION ACTIVITIES

Excavation
PCC work for foundation
RCC work for foundation
o ReinforcementTying
o Shuttering
o Concreting
Plinth
o Reinforcement Tying
o Shuttering
o Concreting
Columns
o Reinforcement Tying
o Shuttering
o Concreting
Slab beam and slab
o Reinforcement Tying

7
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

o Shuttering
o Concreting
Finishing
o Plastering
o White washing
o Painting
Flooring and tiling
Wood work
Steel work
Services
o Road work
o Sanitary installation
o Water supply

o Drainage
o Aluminum work
o Water proofing
o Wiring
o Fitting and accessories
o SDB and main board
o Earthing

8
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

NEED FOR TIME ESTIMATION

For any major project proper time estimation prior to the


commencement of project is indispensible. It includes
scheduling of works, allotment of time duration for various
activities and marking of deadline.

Broadly speaking, time estimation comprises:

Scheduling of rates
Activity time
Event tie
CPM and PERT analysis
Representation by Gantt chart.

9
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

PROPOSED DESIGN (Plan)

10
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

OPERATIONAL PLAN

We have taken into account many factors, including task


dependencies,
constraints, and interruptions, such as holidays or vacation
days. Most
importantly we have scheduled each task using the formula.

Duration = Work/Resource effort, where:


1. Duration is the actual amount of time that passes before
the task is done.
2. Work is the effort required over a period of time to do the
task.
3. Resource effort is the amount of effort resources are
assigned to the task and their allocation.

For example, if:


Three painters work two days on a task, with an effort of 8
hours per day, the work for each resource is 16 hours: (2 days *
8 hours).

11
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

1. The total effort of the resources is 24 hours per day: (3


painters * 8 hours).
2. The total work for the task is 48 hours: (2 days * 8 hours *
3 painters).
3. The duration is 2 days: 48 hours / (3 painters * 8 hours).

So naturally if we increase resource effort then duration will


decrease.

PROJECT DEADLINE

WE HAVE ASSUMED THE PROJECT DEADLINE TO BE OF 5


MONTHS.

EXCAVATION
It comprises of digging of trenches, holes, foundations,
extracting
material from the ground by digging.

Machines used:
a. 2 JCB Digger
b. 6 dumpers
Efficiency of digger:
8 m3 digging and loading per hour.

Excavation per day:


64 m3 per day.

12
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

13
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

TOTAL TIME FOR EXCAVATION=10.96 DAYS.

14
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

RCC WORK FOUNDATION

It includes laying of reinforcement, centering and shuttering of


plain
area and laying of M-25.

Steps involved:
1) Laying reinforcement
2) Centering and shuttering
3) Laying of M-25

1) Laying of reinforcement.
Labours used
a) 4 Blacksmith
b) 4 Beldar

Efficiency of work
Can bend and lay 400kg/day.

Time for reinforcement of footing


The time for reinforcement of footing is 10.58days.

2) Centering and Shuttering.


Labours used:
a) 8 Beldar
b) 8 Carpenter.

Efficiency of work
4.8M2/Day per Beldar, Carpenter.

Time for shuttering of footing.


The time required for shuttering of footing is 11.28
days .

15
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

3) Laying M-25

Machinery and setup


a) Batching Plants
b) Mixers
c) Concrete Pumps
d) Dumpers
e) Concrete Placers

Efficiency
45m3/hr.

Time required for concreting of footing


The time required is 1 day.

16
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

17
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

PEDESTAL AND PLINTH BEAM

Steps involved:
1) Steel work
2) Shuttering
3) M-25

1) Laying of reinforcement.
Labours used
a) 8 Blacksmith
b) 8 Beldar

Efficiency of work
Can bend and lay 800kg/day.

Time for reinforcement of footing


The time for reinforcement of footing is 5.6 days.

2) Centering and Shuttering.


Labours used:
a) 16 Beldar
b)16 Carpenter.

Efficiency of work
19.2m2/day.

Time for shuttering of footing.


The time required for shuttering of footing is 12.18
days .

18
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

3) Laying M-25

Machinery and setup


a) Batching Plants
b) Mixers
c) Concrete Pumps
d) Dumpers
e) Concrete Placers

Efficiency
45 m3/hr.

Time requirement for concreting of plinth beam


The time required is 1 day.

19
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

COLUMNS

Steps involved:
1) Steel work
2) Shuttering
3) M-25

1) Laying of reinforcement.
Labours used
a) 10 Blacksmith
b) 10 Beldar

Efficiency of work
Can bend and lay 1000kg/day.

Time for reinforcement of footing


The time for reinforcement of footing is 9.1 days.

2) Centering and Shuttering.


Labours used:
a) 20 Beldar
b)20 Carpenter.

Efficiency of work
4.8m2/day per Beldar per Carpenter.

Time for shuttering of footing.


The time required for shuttering of footing is 12.41
days .

20
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

3) Laying M-25

Machinery and setup


a) Batching Plants
b) Mixers
c) Concrete Pumps
d) Dumpers
e) Concrete Placers

Efficiency
45 m3/hr.

Time required for concreting of column


the time required is 1 day.

21
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

SLABS

Steps involved:
1) Steel work
2) Shuttering
3) M-25

1) Laying of reinforcement.
Labours used
a) 16 Blacksmith
b) 16 Beldar

Efficiency of work
Can bend and lay 1600 kg/day.

Time for reinforcement of footing


The time for reinforcement of footing is 2.85 days.

2) Centering and Shuttering.


Labours used:
a) 16 Beldar
b)16 Carpenter.

Efficiency of work
2.4 m2/day per belder per carpenter.

Time for shuttering of footing


The time required for shuttering of footing is 12.28days .

3) Laying M-25

Machinery and setup

22
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

f) Batching Plants
g) Mixers
h) Concrete Pumps
i) Dumpers
j) Concrete Placers

Efficiency
45 m3/hr.

Total time required for concreting of slab


Time required is 1 day.

23
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

BRICK WORK
Erection of walls:
Types of wall:
200mm thick.
Labours used:
a. 3.5 mason.
b. 6.5 mazdoor
c. 0.75 bishti.

Efficiency of work
4.1 m3/day.

Time required for total brick work


Time required is 29.55 days.

24
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

WHITE WASHING
Whitewash, or calcimine, kalsomine, or calsomine is a
very low cost type of paint made from slaked lime
(calcium hydroxide)
and chalk (whiting). Various other additives have also
been used. It is usually applied to exteriors - however
it is traditionally used internally in food preparation
areas - particularly rural dairies - for its mildly anti-
bacterial properties.

Labours used:
a. 2 whitewasher
b. 2 mazdoor.

Efficiency:
120 m2/day.

Time required for white washing is 7.65 days.

25
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

PAINTING
Painting involves coating the walls with distemper or
acrylic paint over the whitewash layer. It is intended
for aesthetic and hygienic purpose.

Labours used:
a. 12 painters
b. 8 mazdoor.

Efficiency:
40 m2/day.

Total time required for painting is 14.3 days.

26
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

FLOORING/TILING
This involves laying of the tiles on the floor slab for its
finishing and aesthetical importance.

Labour used:
3 tile layer
Efficiency
18 m2/day.
Total time required for tiling is 15.3 days.

27
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

WOOD WORK (doors and windows)


Wood work includes installation of doors and
windows, sill and lintel frames, ventilators ,etc.

Labour used:
a. 4 carpenters.
b. 2 beldar.
Efficiency
2.06m2/day.

28
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

Time required for wood work is 25.86 days.

SANITARY INSTALLATIONS
This work includes installing water closets, wash
basins, other bathroom utilities in toilet and
bathrooms.

29
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

WIRING AND ELECTRICAL FITTINGS


This includes laying of the various electrical

30
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

networks within the building and installation of SDB,


main board and discrete
sockets.

31
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

WATER SUPPLY
Proper water supply connections are a prerequisite for
any building construction. this work includes laying of
water supply network so as to meet various needs of
future inhabitants.

32
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

DRAINAGE

Sewerage works, waste water outlets, manholes,


underground drains comes under this category.

33
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

WATER PROOFING

This is done to prevent seepage of underground


waters from seeping into the structure due to the pore
water pressure. This construction is done at plinth
level.

34
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING

REFERENCES

IS 456:2000 for limit state design of various rcc


components.
IS 1786:1985 for calculating mass per unit
length of various steel bars used.