MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Acknowledgement
We, the students are very grateful to many people who helped
and
supported us during the project. Our deepest thanks to our
guide
Prof. Vivek Garg (Asst. Professor) in Structure Engineering ,
Department of
Civil Engineering, MANIT, Bhopal for his valuable help,
guidance and
suggestions during project studies.
2012
We would like to thank our honorable HOD Dr. Vishnu Prasad
for his
faith in us and last but not the least we would like to thank our
Director of
Institute Dr. Appu Kuttan.
2
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
CERTIFICATE
3
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Prof.
Vishnu Prasad
(HOD Civil
Engg Department)
PREFACE
4
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
CONTENTS
1. INTRODUCTION
2. NEED FOR TIME ESTIMATE
3. PROPOSED DESIGN
4. OPERATIONAL PLAN
5. STEPS FOR TIME ESTIMATION
Excavation
PCC work foundation
RCC work foundation
Plinth Beam
Columns
Slab beam and slab
Finishing
Flooring and tiling
Wood work
Steel work
Services
6. GANTT CHART
5
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
7. SYNOPSIS
8. WHAT WE HAVE LEARNT
INTRODUCTION
Accurate time estimation is a crucial skill in civil construction.
Without it, you won't know how long your project will take to
complete and the various steps adopted to complete it.
6
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
2. CONSTRUCTION ACTIVITIES
Excavation
PCC work for foundation
RCC work for foundation
o ReinforcementTying
o Shuttering
o Concreting
Plinth
o Reinforcement Tying
o Shuttering
o Concreting
Columns
o Reinforcement Tying
o Shuttering
o Concreting
Slab beam and slab
o Reinforcement Tying
7
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
o Shuttering
o Concreting
Finishing
o Plastering
o White washing
o Painting
Flooring and tiling
Wood work
Steel work
Services
o Road work
o Sanitary installation
o Water supply
o Drainage
o Aluminum work
o Water proofing
o Wiring
o Fitting and accessories
o SDB and main board
o Earthing
8
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Scheduling of rates
Activity time
Event tie
CPM and PERT analysis
Representation by Gantt chart.
9
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
10
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
OPERATIONAL PLAN
11
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
PROJECT DEADLINE
EXCAVATION
It comprises of digging of trenches, holes, foundations,
extracting
material from the ground by digging.
Machines used:
a. 2 JCB Digger
b. 6 dumpers
Efficiency of digger:
8 m3 digging and loading per hour.
12
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
13
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
14
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Steps involved:
1) Laying reinforcement
2) Centering and shuttering
3) Laying of M-25
1) Laying of reinforcement.
Labours used
a) 4 Blacksmith
b) 4 Beldar
Efficiency of work
Can bend and lay 400kg/day.
Efficiency of work
4.8M2/Day per Beldar, Carpenter.
15
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
3) Laying M-25
Efficiency
45m3/hr.
16
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
17
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Steps involved:
1) Steel work
2) Shuttering
3) M-25
1) Laying of reinforcement.
Labours used
a) 8 Blacksmith
b) 8 Beldar
Efficiency of work
Can bend and lay 800kg/day.
Efficiency of work
19.2m2/day.
18
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
3) Laying M-25
Efficiency
45 m3/hr.
19
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
COLUMNS
Steps involved:
1) Steel work
2) Shuttering
3) M-25
1) Laying of reinforcement.
Labours used
a) 10 Blacksmith
b) 10 Beldar
Efficiency of work
Can bend and lay 1000kg/day.
Efficiency of work
4.8m2/day per Beldar per Carpenter.
20
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
3) Laying M-25
Efficiency
45 m3/hr.
21
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
SLABS
Steps involved:
1) Steel work
2) Shuttering
3) M-25
1) Laying of reinforcement.
Labours used
a) 16 Blacksmith
b) 16 Beldar
Efficiency of work
Can bend and lay 1600 kg/day.
Efficiency of work
2.4 m2/day per belder per carpenter.
3) Laying M-25
22
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
f) Batching Plants
g) Mixers
h) Concrete Pumps
i) Dumpers
j) Concrete Placers
Efficiency
45 m3/hr.
23
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
BRICK WORK
Erection of walls:
Types of wall:
200mm thick.
Labours used:
a. 3.5 mason.
b. 6.5 mazdoor
c. 0.75 bishti.
Efficiency of work
4.1 m3/day.
24
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
WHITE WASHING
Whitewash, or calcimine, kalsomine, or calsomine is a
very low cost type of paint made from slaked lime
(calcium hydroxide)
and chalk (whiting). Various other additives have also
been used. It is usually applied to exteriors - however
it is traditionally used internally in food preparation
areas - particularly rural dairies - for its mildly anti-
bacterial properties.
Labours used:
a. 2 whitewasher
b. 2 mazdoor.
Efficiency:
120 m2/day.
25
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
PAINTING
Painting involves coating the walls with distemper or
acrylic paint over the whitewash layer. It is intended
for aesthetic and hygienic purpose.
Labours used:
a. 12 painters
b. 8 mazdoor.
Efficiency:
40 m2/day.
26
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
FLOORING/TILING
This involves laying of the tiles on the floor slab for its
finishing and aesthetical importance.
Labour used:
3 tile layer
Efficiency
18 m2/day.
Total time required for tiling is 15.3 days.
27
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Labour used:
a. 4 carpenters.
b. 2 beldar.
Efficiency
2.06m2/day.
28
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
SANITARY INSTALLATIONS
This work includes installing water closets, wash
basins, other bathroom utilities in toilet and
bathrooms.
29
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
30
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
31
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
WATER SUPPLY
Proper water supply connections are a prerequisite for
any building construction. this work includes laying of
water supply network so as to meet various needs of
future inhabitants.
32
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
DRAINAGE
33
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
WATER PROOFING
34
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING