Professional Documents
Culture Documents
Millennium ESU TIMBER RATTLESNAKE SUPPLEMENTAL REPORT
Millennium ESU TIMBER RATTLESNAKE SUPPLEMENTAL REPORT
Millennium ESU TIMBER RATTLESNAKE SUPPLEMENTAL REPORT
On July 29, 2016, Millennium Pipeline Company, L.L.C. (Millennium) filed with the
Federal Energy Regulatory Commission (Commission) in Docket No. CP16-486-000 an
Abbreviated Application for a Certificate of Public Convenience and Necessity (Application)
for its proposed Eastern System Upgrade Project (Project). 1 Millennium hereby submits
correspondence with the New York State Department of Environmental Conservations
(NYSDEC) in which it provided additional information requested by NYSDEC regarding the
state-listed threatened timber rattlesnake.
Public
Cover letter to NYSDEC
Timber Rattlesnake Impact Assessment and Mitigation Plan prepared for the Project
1
Millennium Pipeline Company, L.L.C., Abbreviated Application for a Certificate of Public Convenience and
Necessity, Docket No. CP16-486-000 (July 29, 2016).
www.millenniumpipeline.com
20170126-5194 FERC PDF (Unofficial) 1/26/2017 4:48:52 PM
Respectfully submitted,
Georgia Carter
Vice President and General Counsel
Millennium Pipeline Company, L.L.C.
Attachment
www.millenniumpipeline.com
2
20170126-5194 FERC PDF (Unofficial) 1/26/2017 4:48:52 PM
Millennium Pipeline Company, L.L.C. (Millennium) is providing this supplemental information to the New
York State Department of Environmental Conservations (NYSDEC) with respect to the proposed Eastern
System Upgrade (Project). The Project is currently under review by the Federal Energy Regulatory
Commission (FERC) under Docket No. CP16-486-000. On August 25, 2016, Millennium submitted a Joint
Permit Application (JPA) requesting a 401 Water Quality Certificate as well as NYSDEC review of the
Project under Articles 15 and 24 of the New York State Environmental Conservation Law (ECL).
Subsequent to the submittal of the JPA, NYSDEC and Millennium participated in a meeting on October
14, 2016 to discuss the Project and the application materials. At that meeting, NYSDEC requested
additional information on a number of topics including rare species, construction methodologies and
wetlands. These were summarized within a meeting summary provided by NYSDEC to Millennium on
October 24, 2016. With this correspondence Millennium is providing additional information requested by
NYSDEC at the October 2016 meeting regarding the state-listed threatened timber rattlesnake (crotalus
horridus). Millennium is currently preparing responses to the remaining topics covered in the October
meeting and anticipates submitting additional information and responses to those items in February 2017.
At the October 2016 meeting, NYSDEC requested the following information regarding the timber
rattlesnake: Additional details are needed in the review/assessment of all impacts to Timber rattlesnakes
for the three locations previously identified - Highland compressor station, West side of RT 209 on
Huguenot loop, and Ramapo metering station. These include impacts to foraging habitat and impacts to
20170126-5194 FERC PDF (Unofficial) 1/26/2017 4:48:52 PM
dens from construction/ rock removal, in addition to the discussed impacts to basking and denning areas.
The impact assessment should take the form of the outline for initial impact assessments in Article 11, Part
182 guidance (attached separately). In addition to looking at all the impacts, details on proposed take
avoidance measures and their implementation should also be provided. For example, no information on an
education and encounter plan, or the environmental monitors responsibilities, has been provided. Based
on the information and initial review, consideration should be given to enhancement of habitats or other
possible benefits to the species that could be accomplished (i.e. vegetation maintenance scheduling). BMPs
or take avoidance measures for ETS should be included in as a document that can be referenced by
contractors and construction personnel.
In response to this request, enclosed is a Timber Rattlesnake Impact Assessment and Mitigation Plan
prepared for the Project. The Plan includes an analysis of temporary and permanent impacts to timber
rattlesnake, take avoidance measures, and proposed habitat enhancement. As noted in the Plan, the
feasibility and exact locations for habitat enhancement at the Ramapo M&R is proposed to be developed in
coordination with NYSDEC, given the limited amount of temporary workspace available to create habitat
at the site and the proximity of several hiking trails.
Additionally, enclosed is an updated Timber Rattlesnake (Crotalus horridus) Habitat Occurrence and
Assessment for the Eastern System Upgrade (January 2017). The survey report has been updated to include
the Wagoner Interconnect and Pipe Yard 4, the maps of where photos were taken from, and clarifications
regarding the areas surveyed as requested by NYSDEC staff Lisa Masi during correspondence in December
2016.
On behalf of Millennium, TRC appreciates the opportunity to provide this additional information in support
of the Project. If you have any questions or need additional information to complete your review of the
Project pursuant to 6 NYCRR Part 182, please do not hesitate to contact me via phone at 978-697-0854 or
email at jzimmer@trcsolutions.com. Thank you for your continued consideration of this application.
Sincerely,
TRC Environmental Corporation
John Zimmer
Pipeline / LNG Market Director
Enclosures
Prepared for
Millennium Pipeline Company, L.L.C.
One Blue Hill Plaza
P.O. Box 1565
Pearl River, NY 10965
By
Kathy Michell
KT Wildlife, LLC
42 School Street
Narrowsburg, NY 12764
January 2017
20170126-5194 FERC PDF (Unofficial) 1/26/2017 4:48:52 PM
TABLE OF CONTENTS
Section Page
The Commission, as the lead agency in the review of the Project, is required to consult with the
United States Fish and Wildlife Service (USFWS) to determine whether federally listed species,
species proposed for listing, or their designated critical habitat may occur in the Project areas
and to determine the Projects potential effects on these species and critical habitats. However,
in accordance with Section 380.13(b) of FERCs regulations, the Project sponsor is designated as
FERCs non-federal representative for purposes of informal consultation with the USFWS.
The Project facilities have been specifically designed to provide for an additional 223,000
dekatherms per day of firm transportation, as well as to maintain adequate operating pressures
at intermediate delivery points following the construction of the Project, to continue to meet
customer demand on Millenniums system during the summer months, and to ensure continued
deliveries to interconnecting pipelines.
approximately 7.8 miles of new 30- and 36-inch diameter pipeline looping generally
overlapping with and adjacent to Millenniums existing pipeline right-of-way in Orange
County, New York;
construction and operation of a new 22,400 hp compressor station, Highland CS in
Sullivan County, New York;
construction and operation of an additional 22,400 hp at the existing Hancock CS in
Delaware County, New York;
modifications to the Ramapo M&R in Rockland County, New York;
modifications to the Wagoner Interconnect in Orange County, New York;
addition of pipeline appurtenant facilities, which includes pigging facilities, at the
Huguenot M&R and the Westtown M&R in Orange County, New York; and
addition of an alternate interconnect to the 16-inch Valley Lateral at milepost (MP) 7.6.
The auxiliary facilities will include the compressor building, and will be constructed of a rigid steel
frame with sheet metal roofs and walls. An auxiliary building will house station controls and
communications equipment as well as an emergency electrical power generator and compressed
air system. The proposed facilities will also include valves, filter-separators, an emergency
generator, a fuel gas heater, parking and access areas, and a fence enclosure. Utilities that will
be supplied from local utility companies are electric power and communications circuits. These
utilities will require minor construction to bring the services into the station property. No new
utility right-of-way is anticipated. The station site work will include a self-contained on-site water
well and sanitary sewer system.
2. Impact Analysis
The Millennium owned property at the Highland CS site consists of 80 acres of predominantly
upland forest, none of which is previously developed. Millennium has a 50-foot permanently
cleared easement that extends along the western border of the parcel. The proposed Project
will affect 27.88 acres of this land during the construction of the facilities. Following construction
and restoration of temporary workspaces, 15.73 acres will remain affected by the operation of
the facility. This 15.73 acres will be permanently lost as timber rattlesnake foraging habitat for
the rattlesnake population from the closest known den approximately one mile from the site.
The property boundary and Project footprint, including the temporary workspace, permanent
easement, and permanent access road are shown in Figure 1.
Timber rattlesnake habitat and presence/absence surveys were conducted by KT Wildlife in the
spring of 2016 on the entire 80-acre parcel. No critical timber rattlesnake habitats (i.e., den and
gestating areas) were found on the property. The impact associated with the Project will be
limited to the loss of upland habitat potentially used by timber rattlesnakes for seasonal foraging.
i. Limits of Grading
The temporary limits of grading are shown in Figure 1 as the workspaces, overlaid on the
forested habitat.
habitat for timber rattlesnakes since it supports a healthy rodent population. There will
be a temporary loss of 12.15 acres of foraging habitat.
During clearing and grading activities there will be noise and dust generated. The noise
levels are anticipated to be similar to noise at typical construction or road work sites. The
extent of rock that will require blasting is unknown until construction begins. Any blasting
will adhere to the New York State standards. Specifically, vibrations at the nearest
property line shall be a maximum of 2 inches per second which would not harm a timber
rattlesnake. Since the closest rattlesnake den to the Project workspace is approximately
one mile, hammering and/or blasting should have no adverse impact on the snakes or
their critical habitats.
Vegetation which is not being cleared for the Project will not be subject to any temporary
impacts during the construction of the Project.
3. Analysis of Alternatives
The Highland CS is an integral part of the Millennium Eastern System Upgrade and is necessary
to maintain adequate operating pressures at the intermediate delivery points in the
interconnecting pipelines. Hydraulic modeling results for optimum efficiency dictate that the
compressor station be located within approximately 0.25 mile of Millenniums existing mainline
and between approximate milepost 134 to 136, which led to the identification of two (2)
potential sites for the new station. Other considerations given to the siting of the station were
the remoteness from residences and avoidance of environmentally sensitive areas. Millennium
identified one alternative site (Alternate Site A) for the proposed new compressor station in its
Environmental Report filed with FERC for the Project. Alternate Site A is not being proposed due
to 1) impacts to the 100-foot adjacent area of a NYSDEC-regulated wetland system associated
with Halfway Brook, and 2) the presence of significantly more residential properties / noise
sensitive areas within 0.5 mile (i.e., affected landowners). The Environmental Report for the
Project is currently being reviewed by FERC.
The following measures are being taken to minimize and/or eliminate the risks to timber
rattlesnakes during the construction phase of the Project.
i. Construction Monitoring
Construction monitoring will be provided by a qualified rattlesnake biologist with the
necessary license to handle rattlesnakes as necessary based on the seasonal activities of
the rattlesnakes and the phase of the construction (i.e., move them outside the
workspace or to a nearby basking area). The responsibilities of the monitor shall include
the following:
iii. Education
Timber rattlesnake awareness training will be presented to all personnel working at the
Project site. This will be in the form of an initial PowerPoint presentation to supervisory
personnel, inspectors, and workers if possible (depending on the size of the training
facilities on site). All workers will receive a flyer with pictures of timber rattlesnakes taken
at actual construction sites to help them be aware of what they are looking for as they
operate machinery and vehicles during construction. All workers will also be given a card
with the phone number of the on-site monitor in the event they encounter a snake.
1. Provide all staff with a copy of this Encounter Plan and information regarding any other
NYSDEC required mitigation procedures, including reporting requirements.
3. Be alert and use caution when driving on the access roads and right-of-ways on the
property. This awareness should extend to public roadways in the area where
rattlesnakes have been observed crossing.
4. Provide staff with contact information for the monitor present on-site. Contact
information for a New York licensed rattlesnake rehabilitator should be provided in the
event of an injured rattlesnake or any other unusual circumstances.
a. If the snake is actively moving away from the work area and out of harms way,
allow it to continue, watching until it is a safe distance from the work area.
Alert the on-site monitor that a snake was encountered and provide location
and direction that it was moving.
b. If the snake is in the work area, contact the on-site monitor who will safely
capture the snake, placing it in a covered bucket and immediately releasing it
no more than a few hundred yards from the workspace. Watch the snake from
a distance of approximately 10 feet until the monitor arrives since they can
easily blend back into the vegetation. The monitor is knowledgeable in safe
capture techniques.
c. Any rattlesnakes which require relocation should be kept in a cool place, not
in the sun, until released which should be done as soon as possible.
d. The monitor will keep a log of the date, the location and approximate size and
color of any rattlesnakes which are encountered.
i. Habitat Enhancement
The Project site is surrounded by land that is predominantly forested. Although timber
rattlesnake denning and foraging activities are located in forested lands, it is essential for
the survival of the populations to have an open basking area in the vicinity of the den
which provide a gestation area for the gravid (pregnant) females and basking
opportunities for pre-shed snakes and those emerging from their dens in the spring. The
timber rattlesnake habitat impacted by the proposed Project has a limited number of
these basking areas. Most snakes from the closest den use the habitat which was created
by Millennium following the 2008 construction of the Millennium Pipeline.
iii. Reporting
An on-site log will be kept of all employee rattlesnake awareness training.
Included in the impact assessment for this portion of the Project is Pipe/Contractor Yard 4 located
a short distance northwest of the Huguenot M&R. This pipe/contractor yard is currently cleared
of all woody vegetation with only grasses and herbaceous plants remaining (see description and
photos in Timber Rattlesnake Habitat and Occurrence Assessment, Eastern System Upgrade
report, rev. January 2017). Figure 2 shows the temporary and permanent workspaces in both
the Huguenot M&R and Pipe/Contractor Yard 4.
2. Impact Analysis
This Huguenot M&R facility is located on the western side of Route 209 in Huguenot and is
situated on 0.40 acres. The proposed Project will be located inside the existing Huguenot M&R
site except for the extension of the 30-inch pipeline to the new Pig Launcher/Receiver which will
involve an additional 0.26 acres. This additional area will be a permanent easement. A
temporary workspace area extends from the back of the existing facility along the pipeline right-
of-way approximately 300 feet.
Timber rattlesnake habitat and presence/absence surveys were conducted by KT Wildlife in the
spring of 2016 on the entire 0.49 acre parcel of the Huguenot M&R Station. No critical timber
rattlesnake habitats (i.e., den and gestating areas) were found on the property. No suitable
timber rattlesnake foraging habitat was present, since this is a residential area. There were some
trees along the property line between the facility and several houses. There should be no impacts
to timber rattlesnakes from the construction and permanent changes to this facility.
Pipe/Contracor Yard 4 consists of 9.57 acres located northwest of the Huguenot Station on quarry
property. As described in the Assessment report, the property is open land which is subject to
vegetation maintenance, making it less suitable as foraging habitat than a wooded area. There
are residential streets on all sides of the proposed pipe/contractor yard which is approximately
0.8 miles from the closest known timber rattlesnake den. The only timber rattlesnake activity
that may occur here would be an occasional rattlesnake traveling through the area.
Pipe/Contractor Yard 4 will have no permanent impacts to timber rattlesnakes.
i. Limits of Grading
The temporary limits of grading are shown in Figure 2 as the workspaces, overlaid on the
existing Huguenot M&R facility.
3. Analysis of Alternatives
The Huguenot M&R Station is an existing facility with infrastructure. No alternatives were
considered. There is no impact to timber rattlesnakes at this site from the Project.
i. Construction Monitoring
Construction monitoring will be provided by a qualified rattlesnake biologist with the
necessary license to handle rattlesnakes as necessary based on the seasonal activities of
the rattlesnakes and the phase of the construction (i.e., move them outside the
workspace or to a nearby basking area). The responsibilities of the monitor shall include
the following:
ii. Education
Timber rattlesnake awareness training will be presented to all personnel working at the
Project site. This will be in the form of an initial PowerPoint presentation to supervisory
personnel, inspectors, and workers if possible (depending on the size of the training
facilities on site). All workers will receive a flyer with pictures of timber rattlesnakes taken
at actual construction sites to help them be aware of what they are looking for as they
operate machinery and vehicles during construction. All workers will also be given a card
with the phone number of the on-site monitor in the event they encounter a snake.
Millennium intends to use the permanent access road to the station for the period of
construction and for operation. Use of the existing 20-foot wide permanent access road for the
Project will require some tree clearing for maintenance of the existing road. Additionally,
Millennium proposes to widen the entrance of the access road from Sky Meadow Road. Tree
clearing and entrance improvements will be conducted as part of the Project and will not
commence until approvals are received. Millennium is also currently in the process of obtaining
a permanent easement from Orange County for placement of the new filter/separators and/or
other new equipment, including but not limited to new meters, heater, flow and pressure control
regulation.
2. Impact Analysis
The current Ramapo M&R Station occupies 1.93 acres. The existing permanent access road
occupies 1.09 acres. No additional workspace will be used for the access road during the Project.
The proposed Station workspace including both temporary and permanent spaces located
outside the boundaries of the Station totals 4.41 acres. Of this property 1.77 will be a permanent
easement on the southern and western sides of the Station. The temporary workspace, totaling
2.64 acres includes a narrow border on the northern boundary of the Station, approximately 400
feet of the existing pipeline right-of-way east of the Station, and an additional temporary
workspace located along the north side of Sky Meadow Road. This additional workspace area is
an open field on the pipeline right-of-way and has been used for vehicle parking during past
upgrades at the Station. Figure 3 is a map of the existing facility and the workspaces.
i. Limits of Grading
The temporary limits of grading are shown in Figure 3 as the workspaces, overlaid on the
habitat, some of which is forested.
brush piles, under a rock, etc.). These temporary potential impacts will be mitigated with
timing restrictions for clearing and/or construction monitoring by a qualified snake
biologist.
During clearing and grading activities there will be noise and dust generated. The noise
levels are anticipated to be similar to noise at typical construction or road work sites, and
similar to other upgrades which have been made to the Station in recent years.
Vegetation which is not being cleared for the Project will not be subject to any temporary
impacts during the construction of the Project.
3. Analysis of Alternatives
The Ramapo M&R Station is an existing facility servicing several pipelines. No alternative sites
for the station are being considered.
The following measures are being taken to minimize and/or eliminate the risks to timber
rattlesnakes during the construction phase of the Project.
i. Construction Monitoring
Construction monitoring will be provided by a qualified rattlesnake biologist with the
necessary license to handle rattlesnakes as necessary based on the seasonal activities of
the rattlesnakes and the phase of the construction (i.e., move them outside the
workspace or to a nearby basking area). The responsibilities of the monitor shall include
the following:
iii. Education
Timber rattlesnake awareness training will be presented to all personnel working at the
Project site. This will be in the form of an initial PowerPoint presentation to supervisory
personnel, inspectors, and workers if possible (depending on the size of the training
facilities on site). All workers will receive a flyer with pictures of timber rattlesnakes taken
at actual construction sites to help them be aware of what they are looking for as they
operate machinery and vehicles during construction. All workers will also be given a card
with the phone number of the on-site monitor in the event they encounter a snake.
i. Habitat Enhancement
The Project site is surrounded by land that is predominantly forested. Although timber
rattlesnake denning and foraging activities are located in forested lands, it is essential for
the survival of the populations to have an open basking area in the vicinity of the den
which provide a gestation area for the gravid (pregnant) females and basking
opportunities for pre-shed snakes and those emerging from their dens in the spring.
As part of the restoration of the temporary workspaces, rock basking habitat could be
added to enhance basking/gestating opportunities for timber rattlesnakes, particularly on
the north side of the Station. The feasibility and exact locations of these habitats would
need to be determined following the completion of the Project by surveying the
temporary workspaces for the appropriate conditions, such as slope, substrate, aspect
and accessibility for equipment to build the rock habitats. During the grading and
excavations, large rocks, a minimum of 3 X 3, particularly slab type rock approximately
8 to 12 thick, could be salvaged from the site and stockpiled. The number and type of
rock habitat would consist of multiple slab rocks placed in close proximity so that snakes
can shift from one to another and avoid human predation as well as animal predators.
Each habitat should be approximately 10 X 20.
There are several hiking trails in the area and the proximity to the trails as well as the
station facility will need to be considered when determining whether rock habitats should
be constructed and where they should be located. A site visit with NYSDEC would be
advisable to discuss this possibility.
In areas where on-site habitat enhancement is not feasible, conservation benefit to the
species could involve discussions with NYSDEC to provide habitat enhancement off-site at
a location where it is needed and feasible. Other options to benefit the species include
critical habitat land acquisition and funding for rattlesnake research, particularly on
methods for making linear utility construction safer for rattlesnakes and other
herpetofauna.
In addition, the education and awareness programs for operations staff will minimize and
offset the Projects potential impacts on timber rattlesnakes.
iii. Reporting
An on-site log will be kept of all employee rattlesnake awareness training.
Figure 1
Figure 2
Figure 3
CERTIFICATE OF SERVICE
C.F.R. 385.2010 (2016), I hereby certify that I have this day served the foregoing
document upon each person designated on the official service list compiled by the