QA/QC Inspection Checklist: Design Coordinates, Inc. CP No. - Vector Three

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 1

QA/QC Inspection Checklist

design coordinates, inc. CP No. __________________


VECTOR THREE
Northgate, Cyberzone, Filinvest Corporate City,
Alabang, Muntinlupa City

Building Element/System: D20 Plumbing Systems


Category: D2010 Plumbing Fixtures
Items to be Inspected: Slop Sink
Date Inspected:
Supplier:
Location:

Non - Not Remarks / Due


ITEM / REQUIREMENT Conform.
Conform. Avail.
N/A
Corrective Actions Date
Open Close

A SUBMITTALS:
A.1 Materials:
1. Type :
2. Brand:
4. Origin:
A.2 Shopdrawings

B INSTALLATIONS:

B.1 Leveled
B.2 Location as per drawing
Height of roughing-in of
B.3 supply pipe and p-trap as
required
B.4 Rigidly fixed and supported
Sealant between fixture and
B.5
wall
B.6 Escutchon properly fitted
Free from cracks and
B.7
scratches
B.8 Free from imperfections
B.9 Hose bib or faucet provision
B.10 Water pressure
B.11 Drain strainer as per spec
C TESTING:
C.1 Water Pressure
a. Cold Water Supply
b. Hot Water Supply

General Notes, Comments and Recommendations:

Inspected by : Noted by : Concurred by :


________________________________ ___________________________________ ________________________________
Construction Project Engineer / Architect Construction Project Manager Supplier

Distribution:
Supplier Customer/ Developer DCI File

Note: A separate Notice to Comply (DCI-NTC) can be issued to the supplier/contractor if the non-conforming
item may take time to rectify and complete.
DCI-QIC rev. 01 Page 1 of 1