KPI-Primavera Test1 PDF
KPI-Primavera Test1 PDF
com/1046009/student
KPI-Primavera test
Welcome to KPI Primavera test! Please read quesitons and following
answers carefully. You are given 30 minutes to complete the test.
Question #1 (1 point)
In P6, the data element At Completion Total Cost is calculated as
Actual Total Cost + Remaining Total Cost
Question #2 (1 point)
Set of codes to organize the project in the EPS in groups according
to specific categories.
Activity codes
WBS
Project codes
Filter
Question #3 (1 point)
You are updating a planned activity with physical % complete type
and duration type "Fixed Duration and Units/time". The activity has
an assigned resource with budgeted units of 168 and budgeted cost
of $9,240. You record the Actual Start Date and enter 70% Physical
% complete. What is the actual cost reflected in P6 for this activity?
$0
$9,240
$6,468
$2,772
Question #4 (1 point)
At any given time, the user can choose which of the following
options to update actual costs in P6
1 of 7 23-Feb-17 3:22 PM
KPI-Primavera test https://testmozusercontent.com/1046009/student
When updating Actual Costs in P6, the user can choose to subtract actual
cost from At Completion Cost
When updating Actual Costs in P6, the user can choose to add Actual Cost
to Remaining Cost
Either a or b
Both a and b
Question #5 (1 point)
How many levels of WBS can be defined in a project
10
20
40
50
Question #6 (1 point)
Cost Variance is calculated as______.
Earned Value Cost - Actual Cost
Question #7 (1 point)
Identify the two required components of the
calculation to determine Resource costs.
(select two)
By predefined contracts
Question #8 (1 point)
The finish of the successor activity depends on the finish of the
predecessor activity is referred to as
finish to finish
2 of 7 23-Feb-17 3:22 PM
KPI-Primavera test https://testmozusercontent.com/1046009/student
start to finish
finish to start
start to start
Question #9 (1 point)
To apply constraints, select an activity and select the
Activity tab
Relatonship tab
Status tab
Codes tab
Baseline
Status
Relationship
E. P. S.
Resource list
W. B. S
3 of 7 23-Feb-17 3:22 PM
KPI-Primavera test https://testmozusercontent.com/1046009/student
Role
Project codes
None of them
The user must check the box "calculate cost from units" for that resource
Activities
Baselines
Expenses
Resources
4 of 7 23-Feb-17 3:22 PM
KPI-Primavera test https://testmozusercontent.com/1046009/student
Budget Log
Resources or Expenses
Spending Plan
Modify the Planned Start Date for the project and reschedule
Modify the Must Finish By Date for the project and reschedule
The Actual Start Date has exceeded the Plan Start Date.
Units
Effort
Duration
5 of 7 23-Feb-17 3:22 PM
KPI-Primavera test https://testmozusercontent.com/1046009/student
False
False
Threshholds
Risk
6 of 7 23-Feb-17 3:22 PM
KPI-Primavera test https://testmozusercontent.com/1046009/student
10
7 of 7 23-Feb-17 3:22 PM