To make things more manageable in terms of the work needed finished the whole
project, it is going to be divided in several work packages. In this way, its going to be much easy
for the Project Manager to distribute workloads and track the remaining time. This project is
control, closeout) and each phase is also divided according to the works needed in each phase.
To be able to define each work packages easier the WBS Dictionary is used. The WBS
dictionary includes entries for each WBS component that briefly defines the scope or statement
of the work, defines deliverables, contains a list of associated activities, and provides a list of