Work Breakdown Structure: Deliverables Milestones

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

Work Breakdown Structure

To make things more manageable in terms of the work needed finished the whole

project, it is going to be divided in several work packages. In this way, its going to be much easy

for the Project Manager to distribute workloads and track the remaining time. This project is

divided according to the 5 phases of Project Management (initiation, planning, execution,

control, closeout) and each phase is also divided according to the works needed in each phase.

(LAGAY MO DITO YUNG WBS)

To be able to define each work packages easier the WBS Dictionary is used. The WBS

dictionary includes entries for each WBS component that briefly defines the scope or statement

of the work, defines deliverables, contains a list of associated activities, and provides a list of

recognized milestones to gage progress.

(Dito nmn yung diction)


Level WBS Element Name Definition
Code
1 1 FFGo (Android Based All work to implement a Faculty Finder
Monitoring and Navigation Go (Android Based Monitoring and
System) Navigation System)
2 1.1 Initiation The work to initiate the project.
3 1.1.1 Research and Information The Project Team will do research and
Gathering gather information about the clients
environment
3 1.1.2 Evaluation and Project team will evaluate solution sets
Recommendation and make recommendations for the
project
3 1.1.3 The Project Team will make a Project
Make a Project Proposal
Proposal to be approved by the
Subject Professor.
3 1.1.4 The Project Team will submit the
Submit a Project Proposal
Project Proposal to be approved by the
Subject Professor.
3 1.1.5 Project Proposal Approved The Subject Professor approved the
Project Proposal which authorizes the
Project Manager to move to the
Planning Process.
2 1.2 Planning The work for the planning process for
the project.

3 1.2.1 Project Team will start to identify the


Identifying Constraints
Constraints that need to be fulfill at the
end of the Project.
4 1.2.1.1 Cost Estimation Project Team will identify the estimated
cost in doing the Project.

4 1.2.1.2 Time Estimation Project Team estimate the time in


doing each phases of the Project.

4 1.2.1.3 Project Team will identify and think


Project Scope
about the scope and features of the
system.
3 1.2.2 Project Manager will assign each
Role and Work Assignments
member of the team to their jobs and
roles.
3 1.2.3 Project Manager will set a meeting
Project Team Meeting together with the rest of the team.
3 1.2.4 The Project Team will develop a
Develop a Design Plan Design Plan.