FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 1 of 24
OFF-SHORE
Approved Company
Rev. Date Description of revision Prepared by Verified by
by Approval
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 2 of 24
TABLE OF CONTENTS
1 GENERAL
7 EXCLUSIONS
8 TECHNICAL REQUIREMENTS
8.1 CHARACTERISTIC OF SYNCHRONOUS GENERATOR
8.1.1 GENERAL DESIGN
8.1.2 SHORT CIRCUIT CAPABILITY
8.1.3 OPERATIONAL REQUIREMENTS
8.1.4 SKID MOUNTING
8.1.5 COOLING
8.1.6 INSULATION
8.1.7 STATOR
8.1.8 ROTOR
8.1.9 COUPLINGS
8.1.10 EXCITATION
8.1.11 AUTOMATIC VOLTAGE REGULATOR (AVR)
8.1.12 BEARINGS
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 3 of 24
12 SPARE PARTS
13 GUARANTEES
13.1 MAKE-GOOD LIMIT
13.2 MECHANICAL GUARANTEES
14 FIELD ACCEPTANCE TESTING
14.1 PROVISIONAL ACCEPTANCE
14.2 FINAL ACCEPTANCE
15 TECHNICAL SUPPORT
17 PRESERVATION
19 CERTIFICATION
20 ATTACHMENTS
20.1 PROJECT GENERAL SPECIFICATIONS
20.2 DATA SHEET
20.3 INSPECTION DATA SHEET
20.4 REQUIRED DOCUMENTATION DATA SHEET
20.5 ELF/SNAMPROGETTI SPECIFICATIONS
20.6 ELECTRICAL DRAWINGS
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 4 of 24
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 5 of 24
1 GENERAL
This specification covers the minimum requirements for the design, manufacture, fabrication, testing,
inspection, packaging and supply of one (1) Diesel Generator Package, complete with components and
accessories, to be installed on ASPF2 Platform at ASHTART Oil Field located offshore TUNISIA.
The VENDOR and his sub-vendors shall comply with all requirements of these Specifications, Data Sheet,
and the last edition of all specifications, codes and standards referenced in the text.
The package shall be designed and guaranteed for service in the specified environmental SITE conditions
and with the specified parameters.
The included description is mainly intended to indicate the COMPANYs philosophy and minimum
requirements and does not relieve the VENDOR from full responsibility for the design, fabrication,
performance and safety for all the equipment being part of his supply.
SITE: Location of final installation of the Diesel Generation Package at Ashtart offshore oil field.
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 6 of 24
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 7 of 24
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 8 of 24
Probabilities of condensation, due to large temperature variations in a humid atmosphere, shall also be taken
into account.
4.2.3 EARTHQUAKE
Concerning earthquake Ashtart site is classified in zone 2 according to API RP 2A.
The structural design will be developed based on API RP 2A - WSD: Recommended Practice for Planning,
Designing and Constructing Fixed Offshore Platforms Working Stress Design (21st Edition).
4.3 UTILITIES
Utilities are specified in the attached General Specification for Site Data and Available Utilities SG 02A 13B
21 23703.
VENDOR shall identify at an early stage of his design any bottleneck in these utilities which need upgrade to
satisfy the packages utility requirements.
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 9 of 24
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 10 of 24
5 SCOPE OF SUPPLY
5.1 GENERAL
The diesel engine is used as an emergency power supply and a black start of the generation electric system,
it should be sized as such for both emergency loads to be insured and Load impact due to starting motor of
the heaviest gas turbine.
The Diesel Generator Package consists of a 400 V 50 Hz 1500 rpm diesel engine driven generator (to be
defined by VENDOR according to EDG load chart) at ISO condition power capacity, suitable for off-shore
installation, a diesel tank and all the piping and instrumentation necessary for normal operations.
- Diesel Engine.
- Starting systems (shall be equipped with two starting system: one pneumatic type and secondary
hydraulic type).
- A.C. air to air ventilated synchronous generator complete with brushless type excitation system and
automatic voltage regulator.
- Electrical interconnections inside package (power and auxiliaries cables) among generating set and
related ancillaries.
- Generator star point with necessary CTs.
- Diesel Generator instrumentation and control panel.
- Fuel system complete with Diesel Fuel Daily Tank, controls, on-skid pipework and all the connections
between the tank and the diesel generator skid.
- Shaft couplings and guards.
- Lubrication system, complete with pumps, filters, air cooled heat exchanger designed for 45C
ambient condition, piping, valves and controls.
- All necessary pipework and cabling, with terminal strips, between unit and junction boxes.
- Exhaust system, complete with silencer, expansion joint.
- Local gauge panel.
- Inlet air system combustion and ventilation complete with:
- Fire dampeners complete with pneumatic actuators for opening/closing and micro switches for status
indicator open/closed.
- Enclosure suitable for 85 dB(A) at 1 m and for required area classification.
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 11 of 24
5.2.2 MISCELLANEA
All Equipment Data Sheets and Instrument Data Sheets duly filled in.
All Performance data and Utilities Consumption.
All Drawings, Documentation and Operation and maintenance Manual Book numbered in
accordance with PURCHASER requirements and in Number of Copies and delivery date as
specified. Maintenance typical plan (different inspections required),
All drawings and documentation required by R.D.D.S. for the complete engineering and
installation of the package.
Inspection and Testing (including factory testing and SITE acceptance testing) in accordance
with IDS (Inspection Data Sheets) and applicable standards. requirements.
Spare parts for, Commissioning and Start-Up.
Spare parts for 2 years operations.
A complete set of Special Tools and Wrenches necessary for erection and maintenance as per
VENDOR recommendation.
Painting according to Elf specifications n STDI 0001.PRO.001.P.
Nameplates.
Preservation and Packing of all equipment.
Training Courses for Purchasers Staff.
FOB shipment.
First fill of chemicals and lubricants.
Supervision of installation.
Conduct the pre-commissioning, commissioning, and start-up of the Package up to hand over
to the PURCHASER following the SITE acceptance test.
Reporting to the PURCHASER as defined in the CONTRACT.
Planning, scheduling and progress reporting for the work.
Package Certification.
5.2.3 ENGINEERING
The VENDOR shall supply the engineering for the following items:
a) Basic and detailed design of the Diesel Generator Package, including diesel engine, generator,
Interconnecting process piping, instrumentation and all auxiliaries, on the basis of the
specified requirements and specification.
b) Detailed Engineering of Logic Sequence.
c) Valves operating sequence.
d) Static and dynamic loads and fixing details.
e) Process and detailed data for connecting all vents and drains.
f) Utility consumption list (including lube oil requirements).
g) Hardware connection to the ESD and the DCS.
h) Instrumentation detailed engineering in Purchasers standards and specifications.
i) Electrical and instrumentation interconnection and detailed engineering.
j) Data for the electrical and instrumentation sizing.
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 12 of 24
6 BATTERY LIMITS
The VENDOR is responsible for the supply of all equipment necessary for the normal and proper operation
of the unit within the below specified battery limits.
The battery limits, are as follows:
For diesel oil:
- Daily tank inlet flanges
- Drains and vent piping with flanged ends
For lube oil:
- Lube oil drain piping with flanged ends
- Oil fill points
Power and control section:
- Unit control panels
- The panels shall be internally wired and all external connections shall be grouped in one or more
terminal strips. VENDOR will group all electrical and instrument connections on generator set and daily
tank in junction boxes.
- All inside package interconnecting wiring, cabling, pipework and instrument tubing between junction
boxes and generator set shall be included in the supply.
Power supplies:
- generator terminal box
- junction boxes
7 EXCLUSIONS
The following Items are excluded from the Supply.
a) All Wiring connections from local Instrument Junction Box to the Control Room.
b) Power and control cables connection from the local junction boxes to control/electrical panel in
electrical substation and electrical/control room.
c) Direct current supply should be furnished by COMPANY, no battery / battery charger should be
within the scope
d) The Motor Control Centre is furnished by COMPANY, VENDOR should communicate the load list.
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 13 of 24
8 TECHNICAL REQUIREMENTS
8.1.5 COOLING
The generator shall be totally enclosed (IP55) and provided with a closed air type cooling system with air to
air heat exchanger.
8.1.6 INSULATION
The insulation shall be Class F. The temperature rise shall be limited to that of Class B.
8.1.7 STATOR
The stator frame shall be of fabricated rigid construction and the stator core shall be built up from silicon
steel laminations clamped together in a manner to minimize hysterisis and eddy current losses.
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 14 of 24
The stator winding shall have copper conductors and shall be star connected with each end of each phase
brought out to a suitable terminal.
Phase ends of the terminals shall be properly marked and printed respectively in their order of phase
sequence.
The final location of terminal box shall suit the layout of the complete diesel generator set and associated
cabling. The terminal box shall be suitable for the Zone 2, Gas Group IIB, Temperature Class T3.
The windings and winding overhang shall be effectively braced and blocked to withstand single phase or
three phase and line to neutral short circuit at the terminals.
Two earthing terminals or bolts shall be provided on the stator for earthing of generator casing.
Materials liable to shrink in the course of time and on heating shall not be used for packing and wedging and
the general construction of the stator and bracing of the windings shall be such as to provided adequate
cooling of the surface and avoidance of hot spots.
A minimum of six temperature resistance sensors shall be embedded in the stator slots and not directly
affected by cooling air stream.
Sensors shall be two per phase one for alarm level and one for shutdown level. Temperature sensors shall
be located so that a failure is quickly detected. The sensor wiring shall be brought out to a terminal box in an
accessible position.
The harmonic content of the line voltage shall be so that none of the instantaneous values of the line voltage
differs from the instantaneous value of the same phase of the fundamental wave by more than 5% of the
amplitude of the latter, when running at nominal speed and at open circuit.
8.1.8 ROTOR
The rotor shall be designed to withstand the mechanical forces due to possible overspeed. The insulation
wedging and bracing of the coils shall be designed to give an even temperature distribution and to eliminate
loosening and electrical breakdown of the winding.
The VENDOR shall advise on merits of rotor earth fault detection and alarm facilities and shall describe what
facilities should be provided if considered desirable.
The rotor, when completed, shall be dynamically balanced and shall be capable of withstanding an
overspeed test of 20% for 2 minutes.
The VENDOR shall perform, at least, the following analysis and calculations:
- a complete description of the method used in determining critical speeds
- a graphic display of critical speeds or operating speeds
- a graphic display of support stiffness and its effect on critical speeds
- a graphic display of rotor response to imbalanced weight
A torsional analysis including but not limited to the following:
- a complete description of the method used in the analysis
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 15 of 24
- a graphic display of the rotor system torsional frequencies or running frequencies showing
predominant forcing frequencies
- the torsional mode shape diagram of the rotor system
- a graphic display of the rotor system showing the stations used in the analysis, the torsional stiffness
constant and the criteria at each station.
8.1.9 COUPLINGS
Generator flange to match flange on prime mover shaft. Anti-vibration coupling shall be provided (Vulcan or
equivalent). Flange dimensions shall be worked out in cooperation with prime mover VENDOR and approved
by PURCHASER.
8.1.10EXCITATION
A permanent magnet type pilot exciter is preferable. However, for similar rated genset, the VENDOR can
suggest an alternative solution with the pilot exciter replaced by a self starting excitation ignition by the
remaining energy.
A main exciter and constant voltage pilot exciter directly coupled to the generator shaft shall be included.
System design to be of brushless type.
The main exciter shall be of the revolving armature type with rotating silicon diode full wave rectifiers directly
connected to the generator field. The continuous rating of the exciter shall be such that all generator loading
conditions shall be obtained without exceeding the exciter permissible temperatures.
Field suppression equipment shall be provided to ensure safe operation of the generator under all conditions.
The rating of the exciter and rotating rectifier shall be such that the exciter shall not be overheated due to
diode failure and that no further damage shall occur to the rectifier and the generator shall be able to
continue in service without damage. The Vendor shall advise on the capability of the generator to sustain
short circuit conditions on the stator terminals under conditions of diode failure.
The rated output of the exciter and rectifier assembly shall be 110% of the normal voltage and current. The
peak reverse voltage rating of each arm of the rectifier bridge shall be not less than three times the normal
field voltage.
The rectifier diodes shall be protected by easy accessible quick acting fuses. Facilities shall be provided for
protection and remote alarm indication in the event of a diode failure. This shall act on open circuited as well
as short circuited diodes.
The regulator equipment shall be free from voltage drifts, temperature errors and insensitive to frequency
changes between the limits of 10% of nominal frequency.
The automatic regulator shall be capable of maintaining the generator terminal voltage within +1% of the
controlled value for any deviation of output over the whole load range of the generator at rated power factor
for any constant load.
Manual voltage adjuster for installation in switchgear generator section to be included in generator
VENDORs supply, unless otherwise stated in the attached TDS.
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 16 of 24
8.1.12BEARINGS
The bearings shall be sleeve type. Nevertheless the generator manufacturers shall coordinate with the prime
mover Vendor to ensure that the optimum arrangement of bearings is provided for the combined unit.
The exciter and bearing of the generator shall be insulated from the base plate foundation to prevent the
circulation of any shaft currents.
Each bearing shall be provided with two temperature detectors wired with armoured cables to terminals in a
suitable terminal box located on the generator or bearing pedestal.
8.1.13ANTICONDENSATION HEATERS
Heating elements shall be located in lower part of the generator. The heaters shall be so designed that no
damage can be suffered by the winding if left switched on when the generator is on full load.
8.1.14VIBRATION
The vibration limits for generator during shop test are as follows:
Magnitude
- Antifriction bearings: velocity 5 mm/s
- Sleeve bearings: amplitude 50 m
Measuring methods
- Anti friction bearings: measured on bearing housing; filtered reading at the running speed.
- Sleeve bearings: measured on shaft adjacent to bearings; unfiltered signal and readings peak to
peak. (Including mechanical and electrical run out).
- Amplitude: measurement by proximity probes.
- Velocity signals: measurement by accelerometers.
-
8.1.15LUBRICATION
Sleeve bearings preferably to be arranged on separate pedestal outside of generator housing.
Local instruments shall be provided in the lube oil system. Components of the lube oil system requiring
service or attention during running shall be located on the outside of the baseplate/enclosure whenever
possible.
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 17 of 24
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 18 of 24
Exhaust pipe shall be lagged with a removable Aluminium cladding. Exhaust pipe outlet point shall be at
least 3 m above ground level.
All the exhaust system must be provided in stainless steel 316L.
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 19 of 24
The VENDOR shall provide free access to his work and that of SUBVENDORS for the authorized
representative of the COMPANY and the certifying authority (if required). All necessary certification of
materials, shop test data, etc. shall be made available to verify that the requirements of the CONTRACT are
being met.
The VENDOR shall inform the COMPANY a minimum of 3 working weeks in advance of any witnessed
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 20 of 24
testing. Such data shall be confirmed by the VENDOR 1 (one) week in advance of the date originally
foreseen.
The VENDOR shall perform inspection and test at his shop during fabrication and before shipment as per
attached Inspection Data Sheet (IDS No SP-02G-05A-25-25411) and in particular:
The following tests and checks which shall be carried out in the manufacturer's shops:
- All tests as required by the manufacturer's practice and by applicable standards during the
Manufacture stage.
- Performance tests on the assembled diesel generating set with enclosure (with Voltage regulator)
- Check of fuel consumption at different loads
- Hydrostatic pressure test on fuel tank (at 2 bars)
All necessary resistive loads shall be provided by the contractor at his own expense.
Acceptances of shop Tests shall not relieve the VENDOR to meet field tests under specified operating
condition, nor does the inspection relieve the VENDOR of his responsibility.
10 DOCUMENTATION
VENDOR shall supply, as a minimum, the documentation listed in the relevant RDDS attached. Any other
drawing and documentation necessary for the execution of this work, shall be identified and made available if
requested.
Comments on drawings and/or documents do not relieve the VENDOR of compliance with all the
requirements of the CONTRACT, nor must they be interpreted as an authorisation to change scope of work
specified in the CONTRACT.
Commissioning work force e.g. instrument technicians, electrical technicians, mechanical trades, foremen,
etc. shall be provided by the EPCI Contractor and the COMPANY.
Installation shall be carried out in accordance with the VENDOR supplied detailed installation procedure.
VENDOR shall verify that his installation procedure does not conflict with the design limitations or may be in
other ways harmful for the equipment or parts thereof.
The lube oil system shall undergo extensive hot-oil flushing prior to start-up as part of the pre-commissioning
activities.
VENDORs representative shall participate in all inspections and checks to be made at site prior to start-up.
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 21 of 24
VENDORs representative shall be responsible to provide any and all missing equipment information and
documentation required from VENDOR.
12 SPARE PARTS
The VENDOR shall provide all spare parts required for construction, pre-commissioning, commissioning,
start-up including first fill of chemicals and lubricants for the complete package.
The VENDOR shall provide quotation for Spare Parts of the various components of the supply according to
his experience as follow:
Capital spare.
Two Years of Operation.
Each part shall be separately quoted.
Spare parts definition shall include sectional drawings and/or exploded view to identify the listed parts on the
relevant Spare Parts Form.
13 GUARANTEES
The packages shall be guaranteed for satisfactory mechanical operation at start-up, shutdown, all
operations conditions specified on the data sheets.
The VENDOR has to guarantee the rated power at worst SITE conditions.
13.1 MAKE-GOOD LIMIT
If the diesel generator packages does not achieve performance guarantee, the VENDOR has to analyse the
cause of the failure and take the necessary actions in order to reach the guarantee values at his care and
cost.
13.2 MECHANICAL GUARANTEES
All equipment and component parts shall be guaranteed by the VENDOR against defective materials,
design and workmanship.
If any mal-performance or defect occurs during the guarantee period, the VENDOR shall make all necessary
alterations, repair and replacements free of charge.
The test shall include a test run at operating conditions at which the unit must not activate alarms or trips.
The purpose of the this test run is to demonstrate the integrity and reliability of the complete Diesel
Generator Package.
A complete set of data shall be taken during the test. In the event of a shutdown due to an external upset not
related to the unit, the test may be continued after restarting. In case of a trip caused by malfunctioning of
systems which are part of VENDORs work the 4 hour test run must be repeated completely.
Check the performance of the complete Diesel Generator Unit at the guaranteed conditions.
Record all pressures, flows, temperatures, and control valve positions.
Check all vibration levels, bearing temperatures at minimum and maximum load.
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 22 of 24
The Diesel Generator Package, including the control system, shall be provisional accepted when the
equipment is complete in every detail including successful 72 hour performance test, spares and
documentation, and the COMPANY is satisfied that the equipment has met the requirements of this
Technical Specification and the CONTRACT.
15 TECHNICAL SUPPORT
Technical support services during the installation, hook-up, commissioning, start-up and guarantee period,
shall be provided by the VENDOR to the COMPANY. These shall include but not limited to:
17 PRESERVATION
The extent of preservation to be applied shall be based on the assumption that a minimum 10 months will
pass before the equipment is ready for initial start-up. The VENDOR shall specify his recommendation for
the preservation for both indoor and outdoor storage.
VENDORs manual shall list all the conservation applied and all measures required for up-keeping the
conservation used. Also measurements to be taken if the construction period would be longer as expected.
VENDORs manual shall also describe measures for removal of conservation if this is necessary.
All equipment shall be adequately preserved, sealed to withstand any adverse condition evolving from the
appropriate mode of transportation. The preparation shall be suitable for a minimum of ten (10) month
storage period. A dedicated storage procedure must be defined by the VENDOR and incorporated into the
operating and maintenance manual.
The packing is of a marine type. They must be protected as follows and as a minimum:
Proof packing of all assemblies and sub assemblies (mainly for control panels) providing good
mechanical protection for ground and maritime transport.
All piping, equipment and steelwork shall be adequately protected against corrosion
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 23 of 24
All orifices and flanged opening must be blinded. All threaded opening shall be provided with steel
cap. Also, equipment need to be protected against sand and humidity.
All instruments, devices and piping that will be susceptible to damage during shipment shall be
removed, packaged separately, properly tagged and shipped together in appropriate export boxing.
Parts requiring special protection or cleaning before use must be indicated in the operating and
maintenance manual. Bearing need to be protected.
Internal and external corrosion proofing must be of a grade that requires no cleaning before
commissioning and be such that the equipment can be stored outside for minimum 10 months with
no deterioration.
19 CERTIFICATION
The Diesel Generator package shall be certified by a Third Party Certifying Agency such as DNV, BUREAU
VERITAS, LLOYD'S or any International certification organism approved by the COMPANY.
If the COMPANY decides to not include the package certification within the present CONTRACT, VENDOR
shall provide 2 copies of all documents necessary for the Diesel generator package certification.
It is to be noted that currently all existing platforms facilities are certified by BUREAU VERITAS.
346768963.doc
Saipem Energy International
Serept
FEASIBILITY STUDY AND ENGINEERING SERVICES FOR ASHTART REVAMPING PROJECT
Contract No. 2005003 FEED PHASE
Contractor Document No.: Company Document No.: Rev.: B1
539243-A-550-MAC-S-27028 SP-02G-05A-24-27028 Page 24 of 24
20 ATTACHMENTS