PROYEK PEMBANGUNAN
PLTU TANJUNG AWAR-AWAR
TUBAN JAWA TIMUR UNIT 2
KAPASITAS 1 x 350 MW
= PROJECT DEFINITION =
TY
DENIS RISMANTO
DWI JOKO
FAJAR ARISMUNANDAR
GAYATRI INERSIA S
Document Ref :1
PMO-PMM TI PLN 01 PMM - INI
PT. PLN (Persero)
Version : 1.0
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
= TABLE OF CONTENT =
= TABLE OF CONTENT = 2
= DOCUMENT CONTROL = 3
= GENERAL INFO = 4
F. Area Impacted 6
G. Technology 7
H. Project Description 7
J. Risk 8
K. Constraints 8
L. Assumptions 8
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
= DOCUMENT CONTROL =
Revision History
20/01/201
1.0 PROJECT DEFINITION
7 KELOMPOK 5
Reviewers
Distribution
Note To Holders:
If you receive an electronic copy of this document and print it out, please write your
name on the equivalent of the cover page, for document control purposes.
If you receive a hard copy of this document, please write your name on the front
cover, for document control purposes.
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
= GENERAL INFO =
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
Dependency Map : Peraturan Pemerintah
Provide a brief concise description of the business problem and business challenges.
Business Problem :
- Bertambahnya perindustrian di Indonesia menyebabkan meningkatnya kebutuhan listrik. Untuk
mengatasi hal tersebut, pemerintah melaksanakan kegiatan percepatan pembangunan
pembangkit listrik. Dan memilih PLTU (Pembangkit Listrik Tenaga Uap) karena merupakan
pembangkit yang memiliki efisiensi yang tinggi dibanding pembangkit lainnya, untuk itu
dibangunlahh PLTU Tanjung Awar-Awar unit II
- Surplus listrik di daerah Jawa Timur sebelum unit 2 PLTU Tanjung Awar Awar dioperasikan
sebesar 2000 MW, setelah unit 2 dioperasikan, surplus daerah Jawa Timur meningkat menjadi
2600 2700 MW
Business Challenges :
- PLTU Tanjung Awar Awar mengacu pada proyek 35.000 MW
- Digunakan untuk persiapan pertumbuhan ekonomi rakyat Indonesia, khususnya Jawa yang
membutuhkan suplai listrik yang tinggi.
- Menaikkan UMR daerah Tuban dan sekitarnya
- Meningkatkan mutu pelayanan pasokan listrik
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
B. Product or Services Description
Is the project consistent with the state organization Business Plan.? If Yes
not, why not?
Is the project identified in the state organization IT strategic plan? If not, Yes
why not?
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
2. Meningkatkan citra PLN
3. Meningkatkan mutu pelayanan PLN
4. Meningkatkan jumlah pelanggan
SAVINGS PLAN
CATEGORY
ONE TIME RECURRING
2 Reduces Turnover
Subtotal
Subtotal
Subtotal
Subtotal
Subtotal
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
SAVINGS PLAN
CATEGORY
ONE TIME RECURRING
1 Increase Sales
3 Reduced Penalties
Subtotal
TOTAL SAVINGS
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
F. Area Impacted
Business Operation
Business Process
Material Management Finance & Accounting Regulatory
Management Accounting
Controlling and Human Resources Regulatory and
Assurance Management External Affairs
Performance and Process
Risk Management Central Procurement
Management
Partner Management Scheduling Management Energy Trading
Energy Fulfillment Energy Operation, Asset, Facilities,
Management Administration and Equipment
Automation Maintenance
Billing and Collection Engineering, Load Balancing
Procurement and Management and
Construction Automation
Location Management Customer Management Marketing
AM/FM/GIS
Sales
G. Technology
Identify technology areas that might apply to this project. Check all appropriate categories:
Application Architecture Category
Corporate Mgt Automation Operations
Engineering, Design & Customer Service Trading
Construction
H. Project Description
Provide high-level project description such as goal, objectives, deliverables & milestones, estimate
schedule, cost, resources requirement.
Project Goal and Objective
a. Goal
Terelealisasinya proyek pembangunan PLTU Tanjung Awar-Awar unit dengan kapasitas 1 x
350 MW untuk meningkatkan dan memenuhi kebutuhan listrik di daerah Jawa Timur dan
Bali serta merealisasikan program pemerintah 35000MW.
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
b. Objectives
1. Menjamin kebutuhan distribusi listrik di wilayah Jawa Timur dan Bali
2. Mendukung PLTU Tanjung Awar-Awar unit 3 meningkatkan kapasitas dan kebutuhan
tenaga listrik di wilayah Jawa Timur dan Bali
3. Pemanfaatan SDA dan SDM di lokasi sekitar Proyek
4. Meningkatkan rasio elektrifikasi Indonesia
5. Meningkatkan produktivitas listrik dan mendukung program 35000 MW
Deliverables
Topography Result Y
Installed System Y
Trained User Y
Installed System Y
Trained User Y
Preproduction System Y
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
Quality Control Document Y
Maintanance Document Y
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
Schedule and Milestones
Schedule
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
Milestones
D. Test Pre-Commiss
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
Cost Estimate
Rp
1 Civil Work
1,648,479,040,895.00
Rp
2 Electrical
114,449,499,494.00
Rp
3 Mechanical
301,029,394,394.00
Rp
4 Lain-lain
294,948,840.00
Rp
PPN (10%)
206,425,288,362.30
Rp
Total
2,270,678,171,985.30
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
Kebutuhan Pegawai
I Pengawas
1 Rekayasa Sipil 40
3 Rekayasa Listrik 75
5 Bagian Turbin 50
6 Commissioning 15
II Pekerja
4 Konstruksi Boiler 80
5 Instrumentasi 45
7 Logging Worker 35
8 Pengendali Material 20
9 Mill Wight 75
10 Tukang Cat 80
11 Pemasamng Pipa 90
12 Perlengkapan 120
14 Pengelas 150
16 Perlengkapan 110
Total 2340
Kebutuhan Material
A Material Alam
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
No. Nama Material Satuan Volume Keterangan
B Material Industri
1 Multipleks 12 mm Lembar 23.000 Dari wilayah Pati dan sekitar PLTU
2 Besi beton Ton 12.500 Pre-stressed concrete spun piles,
3 Tiang pancang 500 mm concrete sheet piles dari Jakarta,
m3 55.000
Bekasi and
4 Tiang pancang 600 mm m3 55.000
6 Baja struktur Ton 3.500 Karawang (Jawa barat). Beton ready
mix
Semen Portland cement dari pabrik
semen di Tuban (Jawa Timur),
5 Semen PC Zak 170.000
Gresik (Jawa Timur)
1 Bulldozer 5
2 Backhoe 5
3 Motor Grader 3
4 Vibratory Roller 2
5 Watertank Truck 2
6 Dump Truck 40
A high-level planning information should be provided with this project statement if any sizable
effort of business analysis needs to be completed. If not, this section may be omitted.
Please provide a list of activities to complete the Initiation and Planning phases. There should be
approximately 2 to 10 tasks.
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
Activity Activity Description No. of Estimated Milestone
No. Days Cost
J. Risk
a. Force Majeur, apabila terjadi force mayor akan mengakibatkan perubahan jadwal
dan terjadi kenaikan biaya proyek sehingga mitigasi sesuai rencana
d. Demo dan Pungutan Liar, Protes dari LSM yang menghambat pelaksanaan
proyek menyebabkan penambahan biaya.
K. Constraints
Biaya, Proyek harus dikerjakan dengan biaya yang tidak melebihi anggaran.
Waktu, Proyek harus dikerjakan dengan waktu sesuai dengan jadwal pelaksanaan
proyek (schedule).
Mutu, Mutu produk atau disebut sebagai kinerja (performance), harus memenuhi
spesifikasi.
SDM, SDM pada kompetensi yang sudah tersertifikasi sesuai ruang lingkup pekerjaan.
L. Assumptions
Anggaran yang dikeluarkan sesuai dengan rancangan anggaran yang telah ditetapkan.
Struktur Organisasi
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
M. Other Related Information
Lihat lampiran dan dokumen-dokumen berikut sebagai referensi dari proyek ini :
Kontak
TOR
KKO-KKF
KAJIAN RISIKO
AMDAL
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04