PT PLN (Persero)

PROYEK PEMBANGUNAN
PLTU TANJUNG AWAR-AWAR
TUBAN JAWA TIMUR UNIT 2
KAPASITAS 1 x 350 MW

= PROJECT DEFINITION =

TY

Author : ASYIATUL ALIYAH

BETTY NUR QAMARINA

DENIS RISMANTO

DWI JOKO

FAJAR ARISMUNANDAR

GAYATRI INERSIA S

Creation Date : 20/01/2017

Last Updated : 23/01/2017

Document Ref :1
PMO-PMM TI PLN 01 PMM - INI
PT. PLN (Persero)

Version : 1.0

All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
= TABLE OF CONTENT =

= TABLE OF CONTENT = 2

= DOCUMENT CONTROL = 3

= GENERAL INFO = 4

A. Business Problem and Business Challenges 5

B. Product or Services Description 5

C. Strategic and Background 5

D. Critical Success Factor 5

E. Expected Benefit and Key Performance Indicator 5

F. Area Impacted 6

G. Technology 7

H. Project Description 7

I. General Subsequent Planning Activities 7

J. Risk 8

K. Constraints 8

L. Assumptions 8

M. Other Related Information 8

All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
= DOCUMENT CONTROL =

Revision History

Date Author Version Reference

20/01/201
1.0 PROJECT DEFINITION
7 KELOMPOK 5

Reviewers

Name Title Signature

Denis Rismanto A.Md GM

Distribution

No Copy Name Location

001 PT. PLN TANJUNG AWAR-AWAR KABUPATEN TUBAN


PROVINSI JAWA TIMUR

Note To Holders:
If you receive an electronic copy of this document and print it out, please write your
name on the equivalent of the cover page, for document control purposes.
If you receive a hard copy of this document, please write your name on the front
cover, for document control purposes.

All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
= GENERAL INFO =

Project ID : 07 / PLTU / UIP VII / REGJBTB / 2017


Project Name : Proyek Pembangunan PLTU Tanjung
Awar-Awar Tuban Jawa Timur Unit 2
Kapasitas 1 x 350 MW
Project Owner : Denis Rismanto A.Md
Project Manager : DR. Ir. Asyiatul Afrika M.Eng BSCE
Project Dependency :

Main : Proyek Pembangunan Pembangkit 35000


MW
Sub : Proyek Pembangkitan Jawa Bagian
Timur & Bali
Predecessor : Proyek PLTU Tanjung awar-awar Unit 1
Kapasitas 350 MW
Successor : Sistem Pembangkitan Jawa Bagian Timur
dan Bali
Brief Description : Sistem PLTU Tanjung awar-awar 2
on Dependency
mendukung ketersediaan tenaga listrik
untuk wilayah Tanjung awar-awar dan
Sekitarnya Yang Terinterkoneksi Dengan
Unit 1

All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
Dependency Map : Peraturan Pemerintah

Proyek Pembangkitan Jawa


Bagian Timur & Bali II

Proyek Pembangunan PLTU Tanjung Awar-


Awar Tuban Jawa Timur Unit 2 Kapasitas 1
x 350 MW

Proyek PLTU Tanjung awar-awar


unit 3 Kapasitas 350 MW

Sistem Pembangkitan Jawa


Bagian Timur & Bali

A. Business Problem and Business Challenges

Provide a brief concise description of the business problem and business challenges.

Business Problem :
- Bertambahnya perindustrian di Indonesia menyebabkan meningkatnya kebutuhan listrik. Untuk
mengatasi hal tersebut, pemerintah melaksanakan kegiatan percepatan pembangunan
pembangkit listrik. Dan memilih PLTU (Pembangkit Listrik Tenaga Uap) karena merupakan
pembangkit yang memiliki efisiensi yang tinggi dibanding pembangkit lainnya, untuk itu
dibangunlahh PLTU Tanjung Awar-Awar unit II
- Surplus listrik di daerah Jawa Timur sebelum unit 2 PLTU Tanjung Awar Awar dioperasikan
sebesar 2000 MW, setelah unit 2 dioperasikan, surplus daerah Jawa Timur meningkat menjadi
2600 2700 MW

Business Challenges :
- PLTU Tanjung Awar Awar mengacu pada proyek 35.000 MW
- Digunakan untuk persiapan pertumbuhan ekonomi rakyat Indonesia, khususnya Jawa yang
membutuhkan suplai listrik yang tinggi.
- Menaikkan UMR daerah Tuban dan sekitarnya
- Meningkatkan mutu pelayanan pasokan listrik

All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
B. Product or Services Description

Provide a brief concise description of product or services.


PLTU Tanjung Awar-awar Ekstension ini akan memiliki kapasitas sebesar 350 MW, sehingga PLTU
Tanjung Awar-awar akan memiliki kapasitas sebesar 2x350 MW, pendistribusian listrik yang
dihasilkan PLTU Tanjung Awar-Awar masuk melalui gardu induk (GI) Tuban ditujukan untuk
memasok listrik di wilayah Gresik, Lamongan dan Bojonegoro. Selain itu, suplai juga masuk ke GI
Babat diteruskan ke Ngimbang dan masuk jaringan bertegangan 500 KV untuk mendukung
pasokan listrik di wilayah Jawa Tengah dan Jawa Barat.
Dengan penambahan kapasitas tersebut maka surplus listrik daerah Jawa Timur meningkat
sebesar 600-700 MW. Dengan adanya hal ini di harapkan tingkat kesejahteraan masyarakat juga
meningkat.
C. Strategic and Background

Please answer the following questions by marking Yes or No. Yes No

Is the project consistent with the state organization Business Plan.? If Yes
not, why not?
Is the project identified in the state organization IT strategic plan? If not, Yes
why not?

D. Critical Success Factor


Critical Success Factor proyek ini adalah :
- Komitmen stakeholder, manajemen, tim proyek dan user
- Kapabilitas tim proyek punya kompetensi yang baik
- Ketersediaan sumber daya manusia yang memadai.
- Optimalisasi dan Evaluasi kinerja proyek
- Jasa professional service yang akan diberikan (dukungan penuh pihak tim internal dan
eksternal atas proyek)

E. Expected Benefit and Key Performance Indicator

Short Term (12 - 24 bulan)


1. Meningkatkan rasio elektrifikasi.
2. Meningkatkan ketersediaan dan kehandalan tenaga listrik di wilayah Tuban.
3. Menambah jumlah lapangan kerja

Long Term (2-5 tahun)


1. Meningkatkan perekonomian masyarakat dan kesejahteraan khususnya di daerah Tuban dan di
area Jawa Timur.

All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
2. Meningkatkan citra PLN
3. Meningkatkan mutu pelayanan PLN
4. Meningkatkan jumlah pelanggan

Key Performance Indicator


1. Kinerja proyek & produksi berkualitas sesuai dengan dokumen kontrak
2. Rasio Elektrivitas meningkat.
3. PLTU berfungsi secara aman, andal dan akrab lingkungan

SAVINGS PLAN
CATEGORY
ONE TIME RECURRING

A. EMPLOYEE RELATED SAVINGS

1 Labor Cost Reduction / Avoidance

2 Reduces Turnover

Subtotal

B. EQUIPMENT RELATED SAVINGS

1 Elimination of Obsolete Equipment

Elimination of Maintenance Cost for Obsolete Equipment


2
(including labor and parts)

Reduced Cost for Existing Equipment Based on Higher


3
Utilization

Subtotal

C. SPACE RELATED SAVINGS

1 New Space Construction Avoidance

Subtotal

D. INVENTORY RELATED SAVINGS

1 Reduced Inventory Carrying Cost

2 Reduced Loss / Shrinkage

Subtotal

E. INFORMATION RELATED SAVINGS

1 Reduced IT Administration Support for Legacy Application

2 Resale of Existing Computer

3 Resale of Existing Computer

Subtotal

All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
SAVINGS PLAN
CATEGORY
ONE TIME RECURRING

F. CUSTOMER SERVICES RELATED

1 Increase Sales

2 Improve Customer Satisfaction

3 Reduced Penalties

Subtotal

TOTAL SAVINGS

All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
F. Area Impacted

Check all appropriate functions:

Business Operation

Holding Generation Transmission


Distribution MSO

Business Process
Material Management Finance & Accounting Regulatory
Management Accounting
Controlling and Human Resources Regulatory and
Assurance Management External Affairs
Performance and Process
Risk Management Central Procurement
Management
Partner Management Scheduling Management Energy Trading
Energy Fulfillment Energy Operation, Asset, Facilities,
Management Administration and Equipment
Automation Maintenance
Billing and Collection Engineering, Load Balancing
Procurement and Management and
Construction Automation
Location Management Customer Management Marketing
AM/FM/GIS
Sales

Other Business Functions:

G. Technology
Identify technology areas that might apply to this project. Check all appropriate categories:
Application Architecture Category
Corporate Mgt Automation Operations
Engineering, Design & Customer Service Trading
Construction

Other Technology Areas:


E-procurement

H. Project Description
Provide high-level project description such as goal, objectives, deliverables & milestones, estimate
schedule, cost, resources requirement.
Project Goal and Objective
a. Goal
Terelealisasinya proyek pembangunan PLTU Tanjung Awar-Awar unit dengan kapasitas 1 x
350 MW untuk meningkatkan dan memenuhi kebutuhan listrik di daerah Jawa Timur dan
Bali serta merealisasikan program pemerintah 35000MW.

All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
b. Objectives
1. Menjamin kebutuhan distribusi listrik di wilayah Jawa Timur dan Bali
2. Mendukung PLTU Tanjung Awar-Awar unit 3 meningkatkan kapasitas dan kebutuhan
tenaga listrik di wilayah Jawa Timur dan Bali
3. Pemanfaatan SDA dan SDM di lokasi sekitar Proyek
4. Meningkatkan rasio elektrifikasi Indonesia
5. Meningkatkan produktivitas listrik dan mendukung program 35000 MW

Deliverables

Project Phases Deliverables Submission Signed-


Schedule Off
Required

Project Initiation Project Definition Y

Project Planing Project Management Plan Y

Kick Off Meeting Y

Detail Desaign & Feasibility Study Y


Procurement of Additional
Land

Civil Works Hidrology Result Y

Topography Result Y

Soil Investigation Result Y

Detail Engineering Desaign Y


Foundation & Result

Detail Engineering Desaign Y


Structure Plan & Result

Mechanical Works Guide Book / User Manual Y

Installed System Y

Trained User Y

Electrical Works Guide Book / User Manual Y

Installed System Y

Trained User Y

Test / Commissioning Modul Test Script Y

Modul Test Plan & Result Y

Integration Test Plan & Result Y

Preproduction System Y

Project Controling & Laporan Progress Pekerjaan Y


Monitoring

Daily dan Weekly Meeting Y


Result

All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
Quality Control Document Y

Quantity Surveyor Result Y

Tracking & Monitoring Y


Performance Report

Project Closing Post Impelmentation Review Y


Document

Maintanance Document Y

All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
Schedule and Milestones

Schedule

Jadwal Pelaksanaan Konstruksi Unit #2 PLTU Awar-Awar

All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
Milestones

Jadwal Proyek Implementasi

I. TAHAP PREPARATION (150 Hari)


A. Fesibility Study
B. Perizinan Proyek
C. Pembebasan Lahan
D. Data Hidrologi
E. Data Topografi
F. Data Investigasi Tanah
G. Proses Pengadaan Alat dan Material Konstriksi
H. Proses pengadaan Mesin Pembangkit

II. TAHAP Eksekusi (960 Hari)


A. Civil Work (330 Hari)
1. Infrastruktur
2. Pile Foundation
3. Jetty
4. Bangunan PLTU

B. Mechanical Works (210)


1. Installation of main and auxilary boiler
2. Installation of steam turbines and support
3. Compressed air system
4. Condenser cooling system
5. Coal and limestone handling system
6. Means ash handling
7. Fuel oil tanks
8. Water supply systems and raw materials
9. Air pollution control system
10. Wastwater treatments palnts

C. Electrical Work (420 Hari)


1. Installation of the generator
2. Installation of transformer
3. Serendang Switch
4. Process control systems generating unit, lighting units,
communications and alarms

D. Test Pre-Commiss

All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
Cost Estimate

Tabel Estimasi Biaya


N
Deskripsi Biaya
o

Rp
1 Civil Work
1,648,479,040,895.00

Rp
2 Electrical
114,449,499,494.00

Rp
3 Mechanical
301,029,394,394.00

Rp
4 Lain-lain
294,948,840.00

Rp
PPN (10%)
206,425,288,362.30

Rp
Total
2,270,678,171,985.30

Resources Requirement Estimate

All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
Kebutuhan Pegawai

No. Jenis Pekerjaaan Jumlah Pekerja Keterangan

I Pengawas

1 Rekayasa Sipil 40

2 Rekayasa Mekanik 125

3 Rekayasa Listrik 75

4 Bagian Ketel Uap 35

5 Bagian Turbin 50

6 Commissioning 15

II Pekerja

1 Tekniksi Sipil 190

2 Tekniksi Mekanik 190

3 Teknisi Listrik 190

4 Konstruksi Boiler 80

5 Instrumentasi 45

6 Teknisi Insulator 100

7 Logging Worker 35

8 Pengendali Material 20

9 Mill Wight 75

10 Tukang Cat 80

11 Pemasamng Pipa 90

12 Perlengkapan 120

13 Operator Alat Pengangkat 25

14 Pengelas 150

15 Pekerjaan Umum 500

16 Perlengkapan 110

Total 2340

Kebutuhan Material

No. Nama Material Satuan Volume Keterangan

A Material Alam
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
No. Nama Material Satuan Volume Keterangan

1 Pasir urug m3 200.000 Didatangkan dari Merak ( 290 km


dari
2 Tanah urug m3 70.000
3 Sirtu m3 40.500 tapak proyek). Juga tersedia dari
4 Pasir beton m3 47.750 lereng merapi ( 94 km dari tapak
proyek))
5 Batu pecah m3 68.250
6 Batu kali m3 11.500
7 Batu bata Buah 2.900.00 Dari wilayah pati dan sekitar PLTU
8 Kayu kaso 0 3000

B Material Industri
1 Multipleks 12 mm Lembar 23.000 Dari wilayah Pati dan sekitar PLTU
2 Besi beton Ton 12.500 Pre-stressed concrete spun piles,
3 Tiang pancang 500 mm concrete sheet piles dari Jakarta,
m3 55.000
Bekasi and
4 Tiang pancang 600 mm m3 55.000
6 Baja struktur Ton 3.500 Karawang (Jawa barat). Beton ready
mix
Semen Portland cement dari pabrik
semen di Tuban (Jawa Timur),
5 Semen PC Zak 170.000
Gresik (Jawa Timur)

No Kebutuhan Alat Berat UNIT

1 Bulldozer 5

2 Backhoe 5

3 Motor Grader 3

4 Vibratory Roller 2

5 Watertank Truck 2

6 Dump Truck 40

7 Hydrolic Submersible Pump 6

8 Hydraulic Mechanical Jack 3

Kebutuhan Alat Berat

I. General Subsequent Planning Activities

A high-level planning information should be provided with this project statement if any sizable
effort of business analysis needs to be completed. If not, this section may be omitted.

Please provide a list of activities to complete the Initiation and Planning phases. There should be
approximately 2 to 10 tasks.

All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
Activity Activity Description No. of Estimated Milestone
No. Days Cost

1 Preparation 150 n.a

2 Pekerjaan Sipil 330 n.a

3 Pekerjaan Mechanical 210 n.a

4 Pekerjaan Electrical 420 n.a

5 Tes & komisioning 60 n.a

J. Risk

a. Force Majeur, apabila terjadi force mayor akan mengakibatkan perubahan jadwal
dan terjadi kenaikan biaya proyek sehingga mitigasi sesuai rencana

b. Perizinan, Terlambatnya izin pembebasan lahan proyek berpengaruh pada


pekerjaan konstruksi sehingga target tidak terpenuhi.

c. Alat dan Material, Keterlambatan pengadaan alat dan material menyebabkan


pemasangan peralatan menjadi terganggu.

d. Demo dan Pungutan Liar, Protes dari LSM yang menghambat pelaksanaan
proyek menyebabkan penambahan biaya.

K. Constraints

Biaya, Proyek harus dikerjakan dengan biaya yang tidak melebihi anggaran.

Waktu, Proyek harus dikerjakan dengan waktu sesuai dengan jadwal pelaksanaan
proyek (schedule).

Mutu, Mutu produk atau disebut sebagai kinerja (performance), harus memenuhi
spesifikasi.

SDM, SDM pada kompetensi yang sudah tersertifikasi sesuai ruang lingkup pekerjaan.

Peraturan Pemerintah yang masih berlaku saat berjalanya pelaksanaan proyek

Regulasi pemerintah terkait dengan RUPT

L. Assumptions

Anggaran yang dikeluarkan sesuai dengan rancangan anggaran yang telah ditetapkan.

Proyek selesai pada waktu yang telah ditetapkan.

Mutu produk atau kinerja (performance) memenuhi spesifikasi.

SDM memiliki kualitas kompetensi yang memadai.

Tidak ada perubahan schedule.

Struktur Organisasi
All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04
M. Other Related Information

Lihat lampiran dan dokumen-dokumen berikut sebagai referensi dari proyek ini :

Kontak

TOR

KKO-KKF

KAJIAN RISIKO

AMDAL

All Rights Reserved PT. Multipolar Corporation Tbk PMM-PLG-00-00-DOC - Released: 18/11/04