Checklist for Preliminary Meeting of Piling Work (in International Department)

Construction

Site Name

( )
Date Year Month Day (Day of the Week) Start Time Termination Time

Attendance (hand-writing)

Site Office Project Safety

Manager Supervisor

Member Member


Relevant Department Name
Department

Subcontractor Trade Subcontractor Name

AIS
Preventive Measure for Same
Type of Accidents Consider how to prevent recurrence of Similar Accidents with Data from Anzen

Information System (AIS)

Heading Supplementary Explanation Check Meeting Record

Check

when

Carry

Out

Organization

1.
Outline of the Plan General Method of Piling, Version of Piling, Number of

Piles, Size of Piles, Work Schedule

2.

Confirmation of Documents by Affiliated Company

Safe Work Plans

3.
Confirming Affiliated Site Organization Chart

Companies & Workers


Subcontractor Organization Chart

1

Documents submitted by Subcontractors


Confirmation of Qualification

(e.g. Pile Driver, Crane, Vehicle-type Construction

Machine, Slinging, Welding)

4.

Emergency Contact Should be Written in Organization Chart

(Including Contact Address on Holidays & Nighttime)

Preliminary Survey

1. ( Presence or Absence )
Aerial Wire etc.
Protection ( High-tension Wire, Low-tension

distribution Line, Telephone Wire )

2.
Neighborhood Agreement Written Agreement ( Presence or Absence )


Days when works are not permitted (Sunday, Holiday)

Available Hour ( )

3.
Hauling Route Rule Applied to Heavy Vehicle / Trailer (Traffic

Permission)


Place to Wait (Machine, Pile, Concrete Mixer Truck)

4.
Safety Measures for Third Security Guard

Person

5.
Soil Disposal Place, License

6.
Vibration & Noise Measures for Reducing Vibration & Noise

Measures

7.
Buried Structure Investigation & Measure

8.

Investigation of Condition of Surrounding Area

Safety Measures for Third ( Presence or Absence )

Party such as Neighboring


Buildings How to Cure Outer Boundary of Site

2
9.
Boring Histogram Condition of the Ground, Underground Water

Erection / Disassembling Pile Driver etc.

1.

Assembly / Dismantling Sequences


Plan for Erection / Use of Safety Belt when High-place Work
Disassembling Pile Driver
& Plant Nomination of Supervisor


Inspection when Assembling

(Time to Replace Derricking Wire Rope)

Construction Planning

1.
Construction Process of Clear Indication of Flowchart & Schematic Drawing

Piling Work

2.
Scheme Drawing of Piling
Work (Main Machines) Pile Driver, Plant, Stockyard, Processing Yard, Pit for

Liquid Waste

(Take Account of Relocation)

3.
Allocation of Piling Driver & Scheme Drawing of Piling Work

Casting Order

4.
Power, Water, Light & Heat Generator


Equipment for Electricity / Water Supply & Drainage


Equipment for lighting

5.

Disposal of Surplus Soil & Muddy Water

Sewage Effluent Treatment


Sludge Treatment Planning Processing Plant, Export Route

6.
Plant Planning Nomination of Person in Charge of Plant

7.
Consideration of Special Under-ground Piled Column (Reverse Drive Method)

Construction Method

Excavation Plan

3
1.
Fall Accident Measures Fall Accident Measures when Pile-driving


Fall Accident Measures after Pile-driving


Fall Accident Measures when Ascending or

Descending Pile Driver


Fall Accident Measures when Ascending or

Descending Plant


Handrails on the Top of Plant

2.
Tumble Measures Ground Bearing Capacity


Excavated Ground ( Presence or Absence )


Necessity of Soil Stabilization

22
Iron Plate

(Quantity, Thickness should be more than 22mm)


Ground Bearing Capacity where Backfilled

( Post-hall of Piling Work )

3.
Measures to Prevent No Entry Measures for Movement of Heavy

Being Pinched by Heavy Machinery

Machinery
Measures for Preventing Contact of Heavy

Machineries

4.
Others Method of Signal


Measurement of Poisonous Gas / Oxygen

Concentration


Daily Inspection of Pile Driver etc.


Specified Self-inspections

(Pile Driver, Vehicle-type Construction Machine)

4

Basic Prohibition against the Use for Other than Main

Purpose

(Vehicle-type Construction Machine)


Inspection of Arc Welder etc.


Safety Measures when Relocating Machines

Others

Measures in the case that

other works which should

be considered in terms of

Risk Assessment have to

be done.

Notes