Professional Documents
Culture Documents
Checklist Preliminary Meeting of Piling Works
Checklist Preliminary Meeting of Piling Works
Construction
Site Name
( )
Date Year Month Day (Day of the Week) Start Time Termination Time
Attendance (hand-writing)
Manager Supervisor
Member Member
Relevant Department Name
Department
AIS
Preventive Measure for Same
Type of Accidents Consider how to prevent recurrence of Similar Accidents with Data from Anzen
Check
when
Carry
Out
Organization
1.
Outline of the Plan General Method of Piling, Version of Piling, Number of
2.
3.
Confirming Affiliated Site Organization Chart
1
Documents submitted by Subcontractors
Confirmation of Qualification
4.
Preliminary Survey
1. ( Presence or Absence )
Aerial Wire etc.
Protection ( High-tension Wire, Low-tension
2.
Neighborhood Agreement Written Agreement ( Presence or Absence )
Days when works are not permitted (Sunday, Holiday)
Available Hour ( )
3.
Hauling Route Rule Applied to Heavy Vehicle / Trailer (Traffic
Permission)
Place to Wait (Machine, Pile, Concrete Mixer Truck)
4.
Safety Measures for Third Security Guard
Person
5.
Soil Disposal Place, License
6.
Vibration & Noise Measures for Reducing Vibration & Noise
Measures
7.
Buried Structure Investigation & Measure
8.
2
9.
Boring Histogram Condition of the Ground, Underground Water
1.
Plan for Erection / Use of Safety Belt when High-place Work
Disassembling Pile Driver
& Plant Nomination of Supervisor
Inspection when Assembling
Construction Planning
1.
Construction Process of Clear Indication of Flowchart & Schematic Drawing
Piling Work
2.
Scheme Drawing of Piling
Work (Main Machines) Pile Driver, Plant, Stockyard, Processing Yard, Pit for
Liquid Waste
3.
Allocation of Piling Driver & Scheme Drawing of Piling Work
Casting Order
4.
Power, Water, Light & Heat Generator
Equipment for Electricity / Water Supply & Drainage
Equipment for lighting
5.
6.
Plant Planning Nomination of Person in Charge of Plant
7.
Consideration of Special Under-ground Piled Column (Reverse Drive Method)
Construction Method
Excavation Plan
3
1.
Fall Accident Measures Fall Accident Measures when Pile-driving
Fall Accident Measures after Pile-driving
Fall Accident Measures when Ascending or
Fall Accident Measures when Ascending or
Descending Plant
Handrails on the Top of Plant
2.
Tumble Measures Ground Bearing Capacity
Excavated Ground ( Presence or Absence )
Necessity of Soil Stabilization
22
Iron Plate
Ground Bearing Capacity where Backfilled
3.
Measures to Prevent No Entry Measures for Movement of Heavy
Machinery
Measures for Preventing Contact of Heavy
Machineries
4.
Others Method of Signal
Measurement of Poisonous Gas / Oxygen
Concentration
Daily Inspection of Pile Driver etc.
Specified Self-inspections
4
Basic Prohibition against the Use for Other than Main
Purpose
Inspection of Arc Welder etc.
Safety Measures when Relocating Machines
Others
be considered in terms of
be done.
Notes
5
6