A PRELIMINARIES/GENERAL CONDITIONS
A40 Contractor's general cost items: Management
and staff
Site administrative staff
Provide general site supervision/administration
a Project Manager 10.00 week 378.80 3,788.00
A42 Contractor's general cost items: Services and
facilities
Provide the following services and facilities
Rubbish disposal
b Skips item 233.97 233.97
A44 Contractor's general cost items: Temporary
works
Scaffolding up to 10m high
Independent scaffolding
c Erect and subsequently dismantle 42.91 m2 15.32 657.38
Temporary screens
50 x 75mm sawn softwood weatherproof screens
(two uses) covered with roofing felt and lined with
d 13mm insulation board 10.02 m2 21.99 220.34
A45 Contractor's general cost items; Associated
with the works
e Defects after completion Item 167.12 167.12
f Delivery costs for slate cladding & paving Item 334.24 334.24
Page 1 / 1
This content is of Estimating Service 2015. PRELIMINARIES / GENERAL CONDITIONS
Collection
Page 1 / 2
This content is of Estimating Service 2015. EXISTING SITE / BUILDINGS / SERVICES
C EXISTING SITE/BUILDINGS/SERVICES
C20 Demolition
Pulling down - including removal of debris
Demolish external brickwork walls in cement
mortar; disposal of debris off-site
a 2 x 102.5 mm thick skins forming cavity wall 3.46 m2 42.50 147.05
Pulling down with care - including removal of debris
Existing structures by hand
b Conservatory; dispose of debris off-site item 1001.47 1,001.47
c Porch; set aside for client item 155.98 155.98
Demolishing parts of timber structures
Softwood rails
d 25 x 150 mm 32.61 m 0.73 23.81
C90 Alterations - spot items
Removing fittings and fixtures
Doors including frame; dispose of debris off-site or
set
aside for re-use
e single door 2.00 nr 13.07 26.14
Windows; dispose of debris off-site or set aside for
re-use
f casement window 7.08 m2 19.89 140.82
Remove finishings
Walls, without backing
g plaster 3.46 m2 20.83 72.07
Page 1 / 3
This content is of Estimating Service 2015. EXISTING SITE / BUILDINGS / SERVICES
Collection
Page 1 / 4
This content is of Estimating Service 2015. GROUNDWORK
D GROUNDWORK
D20 Excavating and filling
Excavating by machine
To reduce levels, maximum depth not exceeding
a 0.25 m 50.33 m3 29.56 1,487.75
Trenches, width over 0.30 m, maximum depth not
exceeding
b 2.00 m 9.11 m3 35.53 323.68
Excavating by hand
To reduce levels, maximum depth not exceeding
c 0.25 m; avaerage depth 0.15m 0.68 m3 23.40 15.91
Pits, maximum depth not exceeding
d 1.00 m 3.62 m3 26.80 97.02
Breaking out
Existing materials
e coated macadam or asphalt 4.18 m3 62.62 261.75
Existing hard pavings
f pavers or slabs and sub base up to 250 mm thick 30.82 m2 18.14 559.07
Disposal
Off site to tip average 15 km from site
loaded by grab wagon from spoil heaps; bulking
g factor 1.25 84.91 m3 22.11 1,877.36
On site by hand
in spoil heaps; distance no greater than 50 m
h from excavation 28.59 m3 5.27 150.67
Filling to make up levels
Imported MOT Type 1 material
i not exceeding 0.25 m 27.19 m3 64.04 1,741.25
Imported sand
j not exceeding 0.25 m 2.77 m3 52.54 145.54
Surface treatments
Compacting
k surface of filling 217.58 m2 0.51 110.97
l bottom of excavation 27.25 m2 0.51 13.90
Geotextiles
Membranes
m laid over ground 132.20 m2 1.62 214.16
Page 1 / 5
This content is of Estimating Service 2015. GROUNDWORK
Collection
Page 1 / 6
This content is of Estimating Service 2015. IN SITU CONCRETE / LARGE PRECAST CONCRETE
Page 1 / 7
This content is of Estimating Service 2015. IN SITU CONCRETE / LARGE PRECAST CONCRETE
Collection
Page 1 / 8
This content is of Estimating Service 2015. MASONRY
F MASONRY
F10 Brick/Block walling
Class B engineering bricks in cement mortar 1:3
Walls
a 102.5 mm 4.14 m2 84.69 350.62
Precast concrete dense aggregate blocks to BS 6073
Walls, facework one side
100 mm solid; in gauged mortar 1:3; below DPC
b level 31.79 m2 36.04 1,145.71
100 mm solid; in gauged mortar 1:4; above DPC
c level 19.28 m2 35.29 680.39
Precast concrete lightweight aerated loadbearing
blocks to BS 6073
Walls, facework one side
d 100 mm 7N; above DPC level 16.44 m2 34.99 575.24
Forming cavities
50 - 100 mm cavities in hollow walls with 225 mm
wall-ties at 5 per
m2 using
e 3 mm vertical-twist ties 35.87 m2 1.95 69.95
Closing cavities
Thermabate cavity closers
f 150 mm cavity 4.80 m 9.84 47.23
Damp proof courses
Pitch polymer
g horizontal not exceeding 225 mm 2.93 m2 8.13 23.82
Cavity trays
Type W Cavity weep ventilator
h wall weep vent 32.00 nr 1.48 47.36
Polythene
i horizontal exceeding 225 mm 12.43 m2 11.72 145.68
Joint reinforcement
Mesh reinforcement in walls
j 64 mm 79.86 m 2.04 162.91
Proprietary items
Wall extension profiles, single flange, plugging and
screwing
k 100mm 11.36 m 10.13 115.08
Page 1 / 9
This content is of Estimating Service 2015. MASONRY
Page 1 / 10
This content is of Estimating Service 2015. MASONRY
Collection
Page 1 / 11
This content is of Estimating Service 2015. STRUCTURAL / CARCASSING METAL / TIMBER
G STRUCTURAL/CARCASSING METAL/TIMBER
G10 Structural steel framing
Framing, fabrication
Fabricated steelwork
a columns less than 40 kg/m SHS 0.05 tonne 2168.52 108.43
b beams less than 40 kg/m 0.21 tonne 1859.13 390.42
Connections
c general steel connections 2.00 nr 63.34 126.68
Erection on site
d permanent erection 0.26 tonne 524.48 136.36
Surface treatments at fabrication workshop
e shot blasting & priming 8.51 m2 8.63 73.44
f 30 minute intumescent fire paint 8.51 m2 14.53 123.65
G20 Carpentry/Timber framing/First fixing
Impregnated sawn softwood - SC3 Grade
Floor members; sub-floor framing to decking
g 50 x 150mm 110.27 m 6.10 672.65
Wall or partition members
h 50 x 75mm 23.60 m 4.72 111.39
100 x 100mm; support posts to decking
i sub-frame 67.00 m 10.95 733.65
Flat roof members
j 50 x 50mm 18.00 m 3.18 57.24
k 50 x 100mm 15.00 m 6.07 91.05
l 50 x 200mm 129.26 m 7.37 952.65
m 50 x 225mm 36.02 m 7.82 281.68
n 50 x 50mm angle fillets 16.00 m 3.09 49.44
o sawn softwood firrings 28.34 m 9.18 260.16
Eaves and verge boarding
WBP plywood
p 12mm Oak plywood - 75mm wide 15.00 m 7.21 108.15
q 12mm Oak plywood - 150mm wide 15.00 m 9.65 144.75
r 12mm Oak plywood - 600mm wide 15.00 m 20.76 311.40
s 24mm Softwood WBP plywood - 300mm wide 10.23 m 12.52 128.08
t 24mm Softwood WBP plywood - 400mm wide 15.00 m 14.04 210.60
Wrought Oak
u 150mm wide 3.56 m 16.80 59.81
v 300mm wide 6.13 m 26.35 161.53
Page 1 / 12
This content is of Estimating Service 2015. STRUCTURAL / CARCASSING METAL / TIMBER
Page 1 / 13
This content is of Estimating Service 2015. STRUCTURAL / CARCASSING METAL / TIMBER
Collection
Page 1 / 14
This content is of Estimating Service 2015. CLADDING / COVERING
H CLADDING/COVERING
H22 Composite decking
Ultra Shield Eco decking
a width exceeding 300 mm 40.79 m2 63.00 2,569.77
b width not exceeding 300 mm 32.74 m 19.47 637.45
H31 Metal profiled/flat sheet
cladding/covering/siding
RAL Aluminium cladding trims
RAL Aluminium cladding trims fixed to
timber/masonry/steel background
c fascia cladding, girth not exceeding 375mm 25.23 m 53.21 1,342.49
reveal cladding, girth not exceeding 180mm; bent
d three times; to patio door reveals 13.32 m 35.55 473.53
e external angles for reveal cladding 2.00 nr 34.16 68.32
H71 Lead sheet coverings/flashings
Flashings, aprons
Code 4 lead, horizontal, 150 mm lapped joints,
fixing with lead clips and wedges
f 300 mm girth 13.80 m 22.93 316.43
Page 1 / 15
This content is of Estimating Service 2015. CLADDING / COVERING
Collection
Page 1 / 16
This content is of Estimating Service 2015. WATERPROOFING
J WATERPROOFING
J40 Flexible sheet tanking/ damp proof
membranes
Tanking and damp proofing
Building paper underlay lapped 150 mm at joints
a horizontally 21.33 m2 2.57 54.82
Polythene medium weight sheet underlay lapped
150 mm at joints
b horizontally 26.06 m2 1.82 47.43
J42 Single layer Polymeric roof coverings
Sedum Landscape Roofing
to timber or metal decking; pitch not exceeding 5
c degrees 28.04 m2 152.81 4,284.79
d kerb detail to Sedum roofing 9.20 m 36.37 334.60
e eaves detail to Sedum roofing 17.89 m 60.27 1,078.23
Sarnafil Waterproof Membrane
to timber or metal decking; pitch not exceeding 5
f degrees 5.80 m2 35.54 206.13
g eaves detail to Sarnafil Waterproof Membrane 9.69 m 29.97 290.41
h Sarnafil rainwater outlet 3.00 nr 100.13 300.39
Tapered Insulation Board Underlays
i tapered PIR board; mechanically fastened 29.54 m2 69.12 2,041.80
Page 1 / 17
This content is of Estimating Service 2015. WATERPROOFING
Collection
Page 1 / 18
This content is of Estimating Service 2015. LININGS / SHEATHING / DRY PARTITIONING
K LININGS/SHEATHING/DRY PARTITIONING
K20 Timber board
flooring/sheathing/linings/casings
Roof decking
WBP plywood
a 12mm WBP plywood exceeding 300 mm wide 10.89 m2 14.89 162.15
b 24mm WBP plywood exceeding 300 mm wide 29.54 m2 20.04 591.98
Page 1 / 19
This content is of Estimating Service 2015. LININGS / SHEATHING / DRY PARTITIONING
Collection
Page 1 / 20
This content is of Estimating Service 2015. WINDOWS / DOORS / STAIRS
L WINDOWS/DOORS/STAIRS
L10 Windows/rooflights/screens/louvres
uPVC Windows
1 section windows - Anthracite Grey
a 400 x 790 mm fixed light window with cill 2.00 nr 171.25 342.50
b 1300 x 2280 mm fixed light window with cill 1.00 nr 596.92 596.92
3 section windows - Anthracite Grey
2470 x 2280 mm 3 section fixed light window with
c toughened glazing 1.00 nr 1075.52 1,075.52
4 section windows - Anthracite Grey
2330 x 790 mm 4 section window with 2 side
d hung opening lights and 2 fixed lights 1.00 nr 586.16 586.16
Roof Lights
Astroglaze flat fixed roof lights on timber kerb
(taken elsewhere)
2760 x 1360mm roof light providing 2600 x
e 1200mm clear opening 1.00 nr 2442.17 2,442.17
L20 Doors/shutters/hatches
uPVC Doors
Fully glazed doors - Anthracite Grey
1300 x 2280 mm fully glazed door with fully
f glazed sidelight 1.00 nr 738.39 738.39
g 980 x 2100 mm fully glazed door 1.00 nr 520.38 520.38
Aluminium Doors
Sliding patio doors - RAL colour finish
h 3160 x 2400 mm 2 pane sliding door 1.00 nr 2489.47 2,489.47
i 5159 x 2400 mm 3 pane sliding door 1.00 nr 3848.59 3,848.59
Page 1 / 21
This content is of Estimating Service 2015. WINDOWS / DOORS / STAIRS
Collection
Page 1 / 22
This content is of Estimating Service 2015. SURFACE FINISHES
M SURFACE FINISHES
M10 Cement sand/Concrete screeds/toppings
Cement and sand 1:3, work to floors
Screeded beds, level and to falls not exceeding 15
degrees from horizontal, over 300 mm wide
a 75 mm 21.33 m2 18.13 386.71
M20 Plastered/Rendered/Roughcast coatings
Gypsum plasterboard to BS 1230
Fixing with plaster dabs to masonry backgrounds
b 12.5 mm Plain Wallboard over 300 mm wide 18.19 m2 10.69 194.45
12.5 mm Plain Wallboard not exceeding 300 mm
c wide 27.48 m 5.09 139.87
Fixing with screws to timber or steel stud framing
d 12.5 mm Plain Wallboard over 300 mm wide 5.09 m2 10.17 51.77
Fixing with screws to ceilings
e 12.5 mm Plain Wallboard over 300 mm wide 24.10 m2 11.01 265.34
Retarded hemihydrate gypsum ("Thistle") plasters to
BS 1191, Class B
3 mm board finish on walls or ceilings including
scrimming
joints
f over 300 mm wide 47.38 m2 8.31 393.73
g not exceeding 300 mm wide 27.48 m 4.20 115.42
Plastering sundries
Galvanised plaster beads
h thin coat angle bead 42.19 m 1.93 81.43
M40 Stone/Concrete/Quarry/Ceramic tiling/Mosaic
Slate cladding
Fixing with adhesive
30 mm thick slate cladding to walls; fix only;
i supply of cladding taken elsewhere 20.01 m2 40.89 818.21
j supply of cladding item 4367.38 4,367.38
Floor Tiles
Fixing with adhesive
k over 300 mm wide 3.06 m2 79.72 243.94
M42 Engineered wooden flooring
Laminated flooring 10mm thick
laminated wooden flooring, over 300 mm wide;
l supply of materials taken in PC Sums 22.83 m2 14.04 320.53
Page 1 / 23
This content is of Estimating Service 2015. SURFACE FINISHES
Page 1 / 24
This content is of Estimating Service 2015. SURFACE FINISHES
Collection
Page 1 / 25
This content is of Estimating Service 2015. BUILDING FABRIC SUNDRIES
Page 1 / 26
This content is of Estimating Service 2015. BUILDING FABRIC SUNDRIES
Collection
Page 1 / 27
This content is of Estimating Service 2015. PAVING / PLANTING / FENCING / SITE FURNITURE
Q PAVING/PLANTING/FENCING/SITE FURNITURE
Q10 Kerbs/Edgings/Channels/paving accessories
kerbs, edgings and channels
Brickwork edging, bedding & pointing in cement
mortar (1:3); bedding and haunching in concrete
(1:2:4) - 20mm
100 x 215mm brick edging - curved - 300 x
a 150mm concrete bed 8.27 m 24.84 205.43
Q22 Coated macadam/Asphalt roads/pavings
Laying on prepared bases (taken elsewhere) and
rolling with an appropriate roller
b 60 mm thick binder course 108.72 m2 14.08 1,530.78
Q23 Gravel/Hoggin/Woodchip roads/pavings
Resin Bound Pavings
Permeable fully mixed decorative aggregate paving;
laid to macadam base course (taken elsewhere);
18 mm thick with 6 mm aggregate
c total area 100-300 m2 132.20 m2 57.93 7,658.35
Q25 Slab/Brick/Sett/Cobble pavings
Slate paving
30 mm thick slate, 50 mm sand base, bedding in
cement mortar (1:3), level and to falls only, slate
size,
d 600 x 400mm 1.20 m2 10.27 12.32
e 800 x 400mm 4.80 m2 12.80 61.44
f 1200 x 400mm 2.88 m2 20.00 57.60
g supply of paving item 4010.86 4,010.86
Slate edgings
30 mm thick slate held in place with sawn softwood
stacks
h 890 x 150mm 45.00 nr 5.60 252.00
i supply of edgings item 2005.43 2,005.43
Q30 Seeding/Turfing
Artifical Grass
To prepared hardcore and sand blinded bases by
others
"As Good As Grass" artifical turf including timber
j sub-frame 88.96 m2 44.57 3,964.95
Page 1 / 28
This content is of Estimating Service 2015. PAVING / PLANTING / FENCING / SITE FURNITURE
Page 1 / 29
This content is of Estimating Service 2015. PAVING / PLANTING / FENCING / SITE FURNITURE
Collection
Page 1 / 30
This content is of Estimating Service 2015. DISPOSAL SYSTEMS
R DISPOSAL SYSTEMS
R10 Rainwater pipework/gutters
Lindab rainwater system
Rainwater pipes
a 75mm steel downpipe 5.48 m 16.74 91.74
Fittings for rainwater pipes
Gutters
b 136mm square gutter 27.69 m 17.61 487.62
Fittings for rainwater gutters
c 136mm square gutter 90 degree external angle 4.00 nr 68.94 275.76
d 136mm square gutter outlet 2.00 nr 27.91 55.82
e 136mm square gutter stop end 4.00 nr 12.59 50.36
R12 Drainage below ground
Manholes
Manhole Covers
f 750 x 600 x 100 mm recessed manhole cover 1.00 nr 145.04 145.04
Page 1 / 31
This content is of Estimating Service 2015. DISPOSAL SYSTEMS
Collection
Page 1 / 32
This content is of Estimating Service 2015. MECHANICAL HEATING / COOLING / REFRIGERATION
T MECHANICAL HEATING/COOLING/REFRIGERATION
SYSTEMS
T32 Low temperature hot water heating (small
scale)
Central heating points
Copper pipework and fittings; includes chasing out
background, cutting mortices and making good
finishes; radiators, towel rails and TVR's taken
elsewhere
a central heating service point 1.00 nr 428.91 428.91
T33 Under floor heating
Under floor heating; flow and return pipewwork at
300mm centres; pipe fixings; flow and return
manifolds and zone actuators; wiring block; includes
fixing in position, secondary pumps, mixing valves
and thermostats
b Screeded floors up to 50 m2 22.83 m2 59.73 1,363.64
Page 1 / 33
This content is of Estimating Service 2015. MECHANICAL HEATING / COOLING / REFRIGERATION
Collection
Page 1 / 34
This content is of Estimating Service 2015. ELECTRICAL SUPPLY / POWER / LIGHTING SYSTEMS
Page 1 / 35
This content is of Estimating Service 2015. ELECTRICAL SUPPLY / POWER / LIGHTING SYSTEMS
Collection
Page 1 / 36
This content is of Estimating Service 2015. PC SUMS
Z PC SUMS
PC Sums associated with the project
forming steps to frontage; requirements to be
a discussed with client item 310.92 310.92
b Underground storm water drainage item 414.56 414.56
c supply of laminated wooden flooring and underlay 23.00 m2 19.43 446.89