Seeping of Sewage Water at Men's Toilet Room:-

Background.

We all know that In March 2014, an over-pressurisation within the Unit 3 boiler rendered the unit inoperable. The
over-pressurisation resulted in substantial damage to the boiler itself including the surrounding associated
structural components. It has been determined that the existing boiler and associated damaged infrastructure is
to be demolished and replaced accordingly by the Main Boiler Contractor.

The project recovery team appointed to handle all works associated with the re-instatement of Duvha Unit 3 has
designated working spaces for the Main Boiler Contractor and their subsequent activities. Area D has been
designated as a storage region for all demolished metals from the boiler.

Cause.

At Mens Toilet room continuously sewage smell was coming out which was even feel during sitting in the
Boardrooms meeting and at & near by the floor was observed wet. It was mainly during early morning hours.
After a thorough investigation understand that a leak Kitchen Area. So self had putting defect notifications with
other defect notification (Annexure 1 Subject) without wasting time. Self had informed to SHE Rap for putting
defect notification as it was not hygienic and it might create bad impression if any board members visited for
meeting or audits.

Annexure -3, attachment mail regarding defect Notifications. Also for quick response self had given a call to
Mrs. Thembka Z for confirming the mail had been acknowledged from her side. Following to that - next day self
had given a call to Mrs. Thembka find whether defect notifications had been raised and feedback from the
respective maintenance dept. for their representative to attend the defect at the earliest.

Feedback.

Dated on 27th Feb 2017, respective Maintenance Dept. personnel had visited the Recovery office for the
inspection. Self was assigned by Mrs. Thembka to show the defect. Self accompany them and shown the defect
and they understand the proper reason behind the same. They told that will get back to us within a day.

Conclusion.

The Personnel from Maintenance Dept. had arrived to site and rectify the defect within two hours with proper
PPE and safe working acts. For satisfactorily performance, self-had went thorough and a quick check to know
the defect had been closed or not.

Moral:

Prevention is better than Cure, this is a famous proverb, but sometimes systems and equipments fail due to
many issues, so Quick reaction with effective action will sometimes manage to control the damage beyond the
intensive manner.