Download as pdf or txt
Download as pdf or txt
You are on page 1of 28

482 LLOYDS LAW REPORTS [2011] Vol 1

PART 9 Borealis v Geogas Trading [QBD (Comm Ct)

QUEENS BENCH DIVISION (b) In order to break the chain of causation, the
conduct of the claimant had to constitute an event of
(COMMERCIAL COURT) such impact that it obliterated the wrongdoing of
the defendant. The true cause of the loss had to be
19, 2122, 2629 April, 46, 10, 1718 May; the conduct of the claimant rather than the breach of
9 November 2010 contract on the part of the defendant. If the breach of
contract by the defendant and the claimants sub-
sequent conduct were concurrent causes, it was
unlikely that the chain of causation would be bro-
BOREALIS AB ken. In circumstances where the defendants breach
v of contract remained an effective cause of the loss,
GEOGAS TRADING SA at least ordinarily, the chain of causation would not
be broken.
(c) Anything less than unreasonable conduct on
[2010] EWHC 2789 (Comm) the part of the claimant was unlikely to be capable of
breaking the chain of causation. However, mere
Before Lord Justice GROSS unreasonable conduct on a claimants part would not
necessarily do so, eg where the defendants breach
remained an effective cause of the loss, albeit in
Sale of goods Damages Causation Sale of combination with the claimants failure to take rea-
butane to be used as feedstock in buyers olefin plant sonable precautions in its own interest. Reckless
Butane contaminated with fluorides producing conduct by the claimant would ordinarily break the
harmful acids Acids causing physical damage to chain of causation.
buyers plant Seller contending that loss and
damage would have been avoided had buyer (d) The claimants state of knowledge at the time
responded appropriately to acid alarm at plant of and following the defendants breach of contract
Whether chain of causation broken Relevant was likely to be a factor of very great significance.
principles. For the chain of causation to be broken, the claimant
need not have knowledge of the legal niceties of the
By a contract made on 22 August 2003 the defendant breach of contract; nor would the chain of causation
(Geogas) agreed to sell to the claimant (Borealis) 5,200 only be broken if the claimant had actual knowledge
mt of butane as a feedstock for Borealiss integrated that a breach of contract had occurred otherwise
olefin plant situated at Stenungsund, Sweden. there would be a premium on ignorance. However,
Borealis alleged that, in breach of contract, Geogas the more the claimant had actual knowledge of the
supplied butane heavily contaminated with fluorides breach, of the dangerousness of the situation which
that cracked under normal processing conditions to had thus arisen and of the need to take appropriate
produce hydrofluoric acid which, in turn, caused seri- remedial measures, the greater the likelihood that
ous and extensive physical damage to the plant, with the chain of causation would be broken. Conversely,
consequential interruption to Borealiss business. Bore- the less the claimant knew the more likely it was that
alis claimed damages under various different heads, only recklessness would suffice to break the chain of
including loss of profits. causation.
It was common ground that the butane was contami- (e) Ultimately, the question of whether there had
nated with fluorides, and Geogas admitted that it was in been a break in the chain of causation was fact
breach of an implied term of the contract that the sensitive, involving a practical inquiry into the cir-
butane would be of satisfactory quality. However, Geo- cumstances of the defendants breach of contract
gas denied that it was liable for all the losses claimed and the claimants subsequent conduct. It was
by Borealis, raising arguments on causation, remote- always a question of degree at what point the dam-
ness of damage, mitigation and quantum. age claimed for ceased to flow naturally and directly
from the breach:
As to causation, Geogas contended that Borealis
failed to react appropriately to a pH alarm. Had Bore- County Ltd v Girozentrale Securities
alis reacted appropriately, the physical damage to the [1996] 3 All ER 834, Compania Naviera Maropan
plant would have been reduced by 22/58ths, and the SA v Bowaters Lloyd Pulp and Paper Mills Ltd (The
claimed loss of production would have been avoided. Stork) [1955] 1 Lloyds Rep 349; [1955] 2 QB 68,
Accordingly, Geogas should not be liable for more than Kristiandsands Tankrederei AS v Standard Tankers
22/58ths of the physical damage, and should not be (Bahamas) Ltd (The Polyglory) [1977] 2 Lloyds
liable at all for the lost production. Rep 353, The Spontaneity [1962] 1 Lloyds Rep 460,
Lambert v Lewis [1982] AC 225, Schering Agro-
Held by QBD (Comm Ct) (GROSS LJ) that: chemicals Ltd v Resibel NV SA 26 November 1992,
(1) The principles applicable to breaking the chain of unreported; CA Transcript No 1298 of 1992 and
causation were as follows (see paras 42 to 47). Barings plc v Coopers & Lybrand [2003] Lloyds
(a) Although an evidential burden rested on the Rep IR 566 considered.
defendant insofar as it contended that there was a (2) Although Borealiss reaction left considerable
break in the chain of causation, the legal burden of room for improvement, and fell well short of best
proof rested throughout on the claimant to prove that practice, it was not unreasonable. There was no break
the defendants breach of contract caused its loss. in the chain of causation. Even if Borealiss reaction
[2011] Vol 1 LLOYDS LAW REPORTS 483

QBD (Comm Ct)] Borealis v Geogas Trading [GROSS LJ

was unreasonable, the chain of causation would not Sylvia Shipping Co Ltd v Progress Bulk Carriers
have been broken. There was no suggestion that Bor- Ltd (The Sylvia) [2010] EWHC 542 (Comm);
ealiss reaction was reckless, as distinct from unreason- [2010] 2 Lloyds Rep 81;
able. Any failure on the part of Borealis did not
obliterate or destroy the causative potency of the Transfield Shipping Inc v Mercator Shipping Inc
anterior Geogas breach of contract. Although Borealis (The Achilleas) (HL) [2008] UKHL 48; [2008] 2
knew or ought to have known of the presence of an acid Lloyds Rep 275; [2009] 1 AC 61;
in the system, it remained in the grip of an unknown West Wales, The (1932) 43 Ll L Rep 504; [1932]
breach giving rise to an unknown danger. In any event, P 165.
the steps proposed by Geogas would not have success-
fully avoided the loss (see paras 93 to 119).

This was the trial of the action brought by the


claimant buyers, Borealis AB, against the defendant
The following cases were referred to in the sellers, Geogas Trading SA, for damages for breach
judgment: of contract arising out of the sale of butane for use
4 Eng Ltd v Harper [2008] EWHC 915 (Ch); in the buyers integrated olefin plant in Sweden.
[2009] Ch 91; Veronique Buehrlen QC and Henry King,
Aerospace Publishing Ltd v Thames Water Utilities instructed by Clyde & Co, for Borealis; Michael
Ltd (CA) [2007] EWCA Civ 3; [2007] Bus LR Ashcroft, instructed by Thomas Cooper, for
726; Geogas.
Al Rawas v Pegasus Energy Ltd [2008] EWHC 617 The further facts are stated in the judgment of
(QB); [2009] 1 All ER 346; Gross LJ.
Banco de Portugal v Waterlow & Sons Ltd (HL) Judgment was reserved.
[1932] AC 452;
Tuesday, 9 November 2010
Barings plc v Coopers & Lybrand [2003] EWHC
1319 (Ch); [2003] Lloyds Rep IR 566;
C Czarnikow Ltd v Koufos (The Heron II) (HL)
[1967] 2 Lloyds Rep 457; [1969] 1 AC 350; JUDGMENT
Compania Naviera Maropan SA v Bowaters Lloyd
Pulp and Paper Mills Ltd (The Stork) (CA) Lord Justice GROSS:
[1955] 1 Lloyds Rep 349; [1955] 2 QB 68; Introduction
County Ltd v Girozentrale Securities (CA) [1996] 3 1. The claimant (Borealis) claims damages
All ER 834; from the defendant (Geogas), arising out of the
Elpidoforos Shipping Corporation v Furness Withy supply by Geogas to Borealis of some 5,200 mt of
(Australia) Pty Ltd (The Oinoussian Friendship) butane as feedstock for Borealiss integrated olefin
[1987] 1 Lloyds Rep 258; plant situated at Stenungsund, Sweden, in Septem-
ber 2003 (the plant). It is Borealiss case that, in
Hadley v Baxendale (1854) 9 Exch 341; breach of contract, Geogas supplied butane (the
Hart v Lancashire and Yorkshire Railway Co goods) heavily contaminated with fluorides that
(1869) 21 LT 261; cracked under normal processing conditions to pro-
Islamic Republic of Iran Shipping Lines v Ierax duce, amongst other substances, hydrofluoric acid
Shipping Co of Panama (The Forum Craftsman) (HF) which, in turn, caused serious and extensive
[1991] 1 Lloyds Rep 81; physical damage to the plant and equipment,
together with consequential interruption to Bor-
Kristiandsands Tankrederei AS v Standard Tankers ealiss business.
(Bahamas) Ltd (The Polyglory) [1977] 2 Lloyds 2. It is common ground that the goods were
Rep 353; contaminated with fluorides. It is further admitted
Lambert v Lewis (HL) [1982] AC 225; by Geogas that it was in breach of contract in
Lodge Holes Colliery Co v Wednesbury Corpora- that the contamination of the goods (by 2 methyl 2
tion (HL) [1908] AC 323; fluoropropane, 2M2F) placed Geogas in breach
of an implied term of the contract to the effect that
Schering Agrochemicals Ltd v Resibel NV SA (CA)
the goods must be of satisfactory quality. Geogas
26 November 1992, unreported; CA Transcript does not, however, concede that it was in breach of
No 1298 of 1992; contract in other respects alleged by Borealis.
Sotiros Shipping Inc v Sameiet Solholt (The Solholt) 3. Against this background, the trial was essen-
(CA) [1983] 1 Lloyds Rep 605; tially about causation, remoteness, mitigation and
Spontaneity, The [1962] 1 Lloyds Rep 460; quantum.
484 LLOYDS LAW REPORTS [2011] Vol 1

GROSS LJ] Borealis v Geogas Trading [QBD (Comm Ct)

4. Much of the factual history is common ground copper corr 1 max


and can largely be taken from the relevant section
of the most helpful list of issues, prepared by origin: us east coast
counsel.
quantity: 5,200 mt 5 pct molso
Parties
cif one safe port/berth
5. Borealis is a well-known producer of polyeth- delivery: stenungsund during period
ylene and polypropylene (plastics) for use in vari- 712th september 2003
ous applications with production sites all over the
world. The plant includes an ethylene cracker com- price: usd 259.50 mt
plex that processes hydrocarbon feedstocks (such as
butane and propane) to produce ethylene and vessel: gt henning maersk . . .
propylene.
at loadport to be inspected by
6. Geogas is a well-known trader in, inter alia,
independent inspector to be
liquefied petroleum gas (LPG), including appointed and paid for by sell-
butane. inspection: er. At discharge port cargo to
be inspected by independent
The contract inspector to be appointed and
7. By an oral agreement, evidenced in and/or paid for by buyer.
subsequently reduced into writing, entered into
between Borealis and Geogas on 22 August 2003, 11. As is common ground, there were implied
Geogas agreed to sell and Borealis agreed to buy terms of the contract:
5,200 mt (5 per cent more or less at Geogass (i) that the goods would correspond with their
option) of butane (ie, the goods), at a price of contractual description;
US$259.50 pmt (the contract). (ii) that the goods would be of satisfactory
8. A firm called Norenergy Oilbrokers AS (Nor- quality.
energy) acted as the parties broker. The docu-
ments evidencing the contract include Norenergys Delivery
email sent to the parties at 18.11 on 22 August 2003 12. The goods (in the event, 5,455.662 mt of
confirming the transaction (the 22 August email) butane) were sourced by Geogas from petrochem-
and a further email sent to the parties at 11.53 on 25 ical facilities owned by Sunoco Inc (Sunoco),
August 2003 (the 25 August email), setting out situated at Marcus Hook, Pennsylvania. The goods
the detailed terms. were loaded onto the carrying vessel, Henning
9. The 22 August email stated: quality: field Maersk (the vessel), on 27 and 28 August 2003
grade as per specs in separate email. and the vessel arrived at Stenungsund on 12
10. The 25 August email confirmed the sale of September 2003.
5,200 mt of commercial butane to be delivered 13. Discharge from the vessel into one of the
colder than zero deg c on, inter alia, the following plants underground caverns, number UC-731 (the
express terms: cavern), commenced at about 13.20 the same day
and was completed at about 00.58 on 13 September.
field grade with specs as fol- At the time of discharge, the cavern already con-
Quality:
lows: tained some 25,276 mt of butane/propane feedstock
mixture. As discharge took place, so fluids from the
c3 and lighter less than 1pct
cavern were simultaneously fed to the plant (to
nc4 80pct
the cracking furnaces) as is usual.

ic4 14pct The contamination


14. As already noted, the goods were contami-
butenes 3pct nated with a compound subsequently identified
c5 plus less than 2pct as 2M2F.

sulphur less than 50ppm The incident


15. At about 20.00 on 13 September 2003, a gas
oxygenates nil
alarm in the disengaging basin (indicating contami-
water nil nated seawater cooling medium returning to the
sea) signalled the presence of hydrocarbon gas
[2011] Vol 1 LLOYDS LAW REPORTS 485

QBD (Comm Ct)] Borealis v Geogas Trading [GROSS LJ

indicative of leaks in the cracker plants overhead patented polyethylene products, primarily for pipe,
heat exchangers. Subsequent investigations wire and cable applications.
revealed that numerous tubes in the crackers pri- 19. The raw materials are delivered by ship
mary and secondary heat exchangers sustained an directly to Borealiss harbour in Stenungsund and
extensive and severe corrosion attack in the hours are stored in four underground caverns and one
leading up to the triggering of the gas alarm on 13 overground ethylene tank.
September so much so that several of the tubes
became perforated allowing (inter alia) ethylene to 20. Butane is stored in cavern UC-731 (ie, the
escape into the atmosphere. cavern), along with a proportion of propane (75:25
butane/propane) to create an LPG feed.
Further matters not in dispute 21. The cracker alone is a large plant consisting
of approximately 950 km of pipes, 20 distillation
16. A number of further matters were not in towers, reactors, some 400 pumps and 20,000
dispute: valves.
(i) HF can be extremely destructive. 22. A process flow diagram of the relevant part
(ii) Cargo containing 2M2F would not be fit of the plant for present purposes is attached here-
for use in the plant. with as Annexe I. [Editors note: diagram omitted
from this Report.]
(iii) Borealis did not specifically warn Geogas
about the danger of a fluoride compound being 23. In essence, naphtha, ethane, propane and
present in the goods. butane/propane (the LPG mix) in various quantities
(iv) Borealis did not test the goods for fluoride are fed from the caverns (and the overground eth-
compounds prior to discharge. For that matter, ane tank) to nine cracking furnaces (F-1601 A-G, V
nor did Geogass inspector when inspecting the and X), where the feeds are mixed with steam, in a
goods at the loadport. ratio of 70:30 hydrocarbonteam, and heated to 850
to 870C. (It may be noted though it does not
(v) Representatives of Borealis noted that the effect this description that on the date of the
smell and appearance of the first set of samples incident, seven or eight furnaces were operating.)
taken from the vessel on 12 September 2003 The effect is to break up long chains of hydro-
(prior to discharge) were unusual. carbon molecules into shorter ones. The individual
(vi) A pH meter (at the plant) indicated that pH product streams from the furnaces are then cooled
in the discharge from the distillate drum (quenched) individually, by heat exchangers (not
(D-1681) dropped from its target level of the subject of these proceedings), before being
between pH 5 to 7, to a range of about pH 3.5 to mixed into a single product stream. That product
3.7, shortly after discharge of the goods into the stream is then transported through an overhead
cavern had commenced. transfer line to the T-1651 primary fractionator
(vii) After the gas alarm went off at 20.00 on tower. This is the plants first stage distillation
13 September (as described above), Borealis tower where heavier components in the product
(inter alia) brought heat exchangers E and G on stream are separated out from the lighter ones. The
line to continue production while it shut down lighter components, consisting primarily of ethyl-
heat exchangers B, D, F and H in order to inves- ene and steam, are taken from the top of T-1651
tigate the problem. through overhead pipelines (the T-1651 overhead
line) to a set of primary and secondary heat
(viii) All production of ethylene using feed-
exchangers: E-1651 and E-1656.
stock from the cavern was halted by Borealis at
about 21.40 on 16 September 2003.
The E-1651 and E-1656 heat exchangers
The workings of the plant 24. E-1651 and E-1656 are made up of 16 heat
General exchangers E-1651 A to H and E-1656 A to H.
They operate in pairs, each consisting of a primary
17. I must next and in very simple terms, based exchanger sitting above a secondary exchanger: so,
on the excellent agreed note prepared by counsel, eg, E-1651 A and E-1656 A. Further, they are
describe the working of the plant. divided into a north bank and a south bank, each
18. The Stenungsund site comprises a cracker bank consisting of four exchanger pairs. The south
complex, three polyethylene plants and an innova- bank is made up of units A, C, E and G. The north
tion centre. The plant uses naphtha, ethane, propane bank is made up of units B, D, F and H.
and butane as feedstock to produce ethylene and 25. The heat exchanger shells are made of carbon
propylene which are in turn used to produce high- steel. The shells house heat exchanger tube bundles,
density polyethylene, low-density polyethylene and consisting (in the case of the primary exchangers)
486 LLOYDS LAW REPORTS [2011] Vol 1

GROSS LJ] Borealis v Geogas Trading [QBD (Comm Ct)

of some 1,445 titanium tubes (ie, ~ 8.8 km of 12 September 2003


tubes). Cooling seawater flows through the titanium u 04.00 to 08.45: taking of samples from the
tubes whilst the product stream flows around the vessel and complaint as to cargo quality.
outside (ie, the shell) of the tubes. Cooling water u 13.20: commencement of discharge.
used in the plant as a whole is returned to the sea
through two effluent pipes, known as the northern u 15.20: pH falls below 5, triggering pH
header and the southern header, which then merge alarm.
before entering the disengaging basin (D-1101). 13 September 2003
The cooling water from the E-1651 and E-1656 u 00.58: completion of discharge.
heat exchangers passes through the northern header. u 20.00 and 20.30: gas alarms go off in the
Alarms exist to detect the presence of hydrocarbons disengaging basin. Laboratory tests confirm
in the cooling water returning to the sea in both hydrocarbon leak into seawater.
headers and in the disengaging basin. 14 September 2003
26. The product stream from the T-1651 over- u 01.30: gas alarm goes off in northern
head line passes first into the primary E-1651 heat header, indicating that leak is coming from
exchangers where it is cooled from about 110C to E-1651 and E-1656 heat exchangers. By 06.00
58C and then on into the secondary E-1656 heat this is traced to the D unit. Decision taken by
exchangers (sitting, as already described, below the Borealis to maintain production by bringing
primary exchangers). In the secondary heat (south) heat exchangers E-1651 and E-1656 E
exchangers, the product stream is further cooled to and G into service, before isolating the north
approximately 35C. The cooled product stream bank heat exchangers.
then flows downstream into a distillate drum u 12.30: furnace C (cracking naphtha) taken
(D-1681), where the hydrocarbon gas, hydrocarbon offline.
liquid and water are further separated from each
u 23.45: furnace F (one of two furnaces
other.
cracking LPG from the cavern at the time of
27. The pH of the water stream leaving D-1681 the incident) taken offline; time now elapsed,
(sour water) is measured by an online meter (the pH from the triggering of the pH alarm on 12
meter) and also, three times a week, by the cracker September, approximately 56 hours.
laboratory. The measurements are recorded and, if 15 September 2003
the online pH meter readings drop below 5 (or
u 03.00: south bank heat exchangers
increase above 7), a visible and audible alarm dis-
(including units E and G) brought online.
play in the cracker control room activates by means
of a flashing white button which the operator u 10.00: lab tests show pH reading of 6.
acknowledges by pressing the button. u 20.45: north bank heat exchangers
28. The feedstocks can contain compounds such isolated.
as oxygenates that once cracked and dissolved in 16 September 2003
water create weak acids, eg, carbonic acid. Over u 21.40: furnace B (the other furnace crack-
time, these acids can corrode carbon steel. ing LPG from the cavern at the time of the
29. The plant is fitted with a system that provides incident) taken offline; all production of ethyl-
for the manual injection of a neutralising agent, ene using feedstock from the cavern now
here ammonia, into the T-1651 overhead line. The halted.
original design purpose of the ammonia injection
system was disputed between the parties; Geogass Principal issues
case was that it was intended to neutralise any 31. To begin with, a word needs to be said as to
acids, without discrimination, that might be present the significant narrowing of the issues in the course
in the system; Borealiss case was that it was to of the trial.
neutralise weak acids that form naturally in the 32. I have already indicated the broad outline of
system from the feedstocks used, including car- the Borealis case; namely, that, in breach of the
bonic acid resulting from the presence of oxygen- contract, Geogas supplied heavily contaminated
ates in the feedstocks. goods which caused serious and extensive physical
damage to the plant and equipment, together with a
Chronology variety of consequential losses.
33. Initially, amongst these consequential losses,
30. The unfolding of the incident can be seen the Borealis claim included the amount of
having regard to a number of significant times 4,838,238 (some 38 per cent of the total claim), in
which it is now convenient to bring together here respect of alleged loss of profits in November 2003,
(albeit that some have already been referred to): said to have resulted from the damage to the heat
[2011] Vol 1 LLOYDS LAW REPORTS 487

QBD (Comm Ct)] Borealis v Geogas Trading [GROSS LJ

exchangers in September 2003. Realistically, if I ealiss claim for loss of profits in September 2004
may say so, Ms Buehrlen QC, for Borealis, did not and the second to the unavailability of the cavern.
ultimately pursue this head of claim, recognising Thirdly and (effectively or largely) in the alter-
the difficulties in establishing the requisite causa- native to the second of its remoteness arguments,
tive link. Geogas submitted that the cavern was unavailable
34. At the start of the trial, Geogas relied on an for too long; in that regard, Borealis had failed to
extensive assortment of defences, including the mitigate its loss and, to the extent that it had so
following. failed, Geogas denied liability. Fourthly, Geogas
(i) The Geogas primary case alleged failure continued to maintain a miscellany of arguments as
or unreasonable failure on the part of Borealis to to the quantum of damage.
test for fluorides in the goods. 38. It follows that the principal issues which
(ii) The Geogas tertiary case alleged a fail- remained at the end of the trial and with which I
ure to react appropriately to the gas alarms must deal, concerned causation, remoteness, mit-
(which, as will be recollected, sounded from igation and quantum. These may be summarised as
20.00 on 13 September). follows:
(iii) Geogas further raised an erosion-corro- (i) Issue (I): the Geogas secondary case.
sion defence, asserting that the flow rate of the (ii) Issue (II): remoteness of damage.
product through the exchangers was excessive (iii) Issue (III): mitigation.
and unreasonable. (iv) Issue (IV): quantum.
(iv) A point was taken on the currency of loss I shall deal with these issues in turn but, before
and exchange rates. doing so, I must complete my survey of what may
(v) It was alleged that in selling the LPG mix be termed preliminaries and should say something
from the cavern to Statoil, as it did, Borealis had as to the legal framework concerning issues (I)
failed to mitigate its loss; other avenues and to (III).
prospective purchasers could and should have 39. This narrowing of the issues had certain con-
been explored. sequences. First, on any view, Borealis was entitled
(vi) A host of detailed points as to quantum to a substantial sum by way of damages. In the
were raised. circumstances, the Borealis application at the con-
35. Realistically, with respect, Mr Ashcroft, for clusion of closing submissions for an interim pay-
Geogas, jettisoned these defences over the course ment was irresistible in principle: in the exercise of
of the trial, recognising the legal and factual diffi- my discretion, I duly made an order for such a
culties they variously faced and, in at least one payment in the amount of 2.75 million. This judg-
instance (the currency point) taking a simple prag- ment therefore deals with the balance of the sums
matic view. in dispute.
36. As already recorded, Geogas conceded 40. Secondly, Borealis called a large number of
before the trial that it was in breach of an implied factual witnesses and Geogas two such witnesses.
term of the contract that the goods must be of Both parties called or relied upon a number of
satisfactory quality. By the conclusion of the trial, expert witnesses. It is unnecessary to list these
both counsel were sensibly agreed that the question witnesses here. Suffice to say that in the light of the
of whether there were further breaches of contract narrowing of the issues, a not insignificant part of
on the part of Geogas was academic. the evidence had ceased to be of practical relevance
37. In the event, by the time of closing submis- by the end of the trial. Such comments as I have on
sions, Geogass case was, in a nutshell, as follows. particular witnesses are best deferred until later and
First and foremost, Geogas relied on its secondary in the context of the issues which remain.
case (as it was known by way of shorthand 41. It is convenient at this stage, to express my
throughout the trial); namely, the allegation that thanks to both Ms Buehrlen and Mr Ashcroft, not
Borealis had failed to react appropriately, or at all, only for their realism in narrowing the issues in
to the pH alarm (which sounded at 15.20 on 12 dispute but also for the quality of their written and
September). Conceptually, this case was advanced oral submissions those thanks extending to the
both in terms of causation and mitigation. Bor- assistance given by Mr King, Ms Buehrlens junior,
ealiss acts or omissions following the sounding of in the area of quantum.
the pH alarm had broken the chain of causation and
Geogas denied liability for the resulting inflated The legal framework
losses, especially in respect of consequential loss; Causation
alternatively Geogas was not liable for avoidable
losses flowing from a failure to mitigate. Secondly, 42. I start with causation, extensively debated by
Geogas raised two discrete arguments involving counsel when addressing the Geogas secondary
remoteness of damage. The first related to Bor- case (issue (I)). The specific focus was the test for
488 LLOYDS LAW REPORTS [2011] Vol 1

GROSS LJ] Borealis v Geogas Trading [QBD (Comm Ct)

breaking the chain of causation. My approach, dis- take reasonable precautions in its own interest: see,
tilled from the submissions of counsel and the for example, County Ltd v Girozentrale Securities,
authorities cited, is summarised in the paragraphs per Beldam LJ (loc cit). By its nature, reckless
which follow. conduct by the claimant would or would ordinarily
43. First, although an evidential burden rests on break the chain of causation, though there is no rule
the defendant insofar as it contends that there was a of law that only recklessness on the part of the
break in the chain of causation, the legal burden of claimant will do so: Lambert v Lewis [1982] AC
proof rests throughout on the claimant to prove that 225, per Roskill LJ (as he then was) in the Court of
the defendants breach of contract caused its loss. Appeal, at page 252; County Ltd v Girozentrale
(supra), per Hobhouse LJ at page 857, more con-
44. Secondly, in order to comprise a novus actus
veniently discussed below, when dealing with the
interveniens, so breaking the chain of causation, the
claimants knowledge or lack of it.
conduct of the claimant must constitute an event of
such impact that it obliterates the wrongdoing . . . 46. Fourthly, the claimants state of knowledge at
of the defendant: Clerk and Lindsell on Torts, the time of and following the defendants breach of
19th Edition, at para 2-78. The same test applies in contract is likely to be a factor of very great sig-
contract. For there to be a break in the chain of nificance. For the chain of causation to be broken,
causation, the true cause of the loss must be the the claimant need not have knowledge of the legal
conduct of the claimant rather than the breach of niceties of the breach of contract; nor, as it seems to
contract on the part of the defendant; if the breach me, will the chain of causation only be broken if the
of contract by the defendant and the claimants claimant has actual knowledge that a breach of
subsequent conduct are concurrent causes, it must contract has occurred otherwise there would be
be unlikely that the chain of causation will be a premium on ignorance. However, the more the
broken. In circumstances where the defendants claimant has actual knowledge of the breach, of the
breach of contract remains an effective cause of the dangerousness of the situation which has thus
loss, at least ordinarily, the chain of causation will arisen and of the need to take appropriate remedial
not be broken: County Ltd v Girozentrale Securities measures, the greater the likelihood that the chain
[1996] 3 All ER 834, at page 849b to c, per Beldam of causation will be broken. Conversely, the less the
LJ and at pages 857f to g and 858b to c, per claimant knows the more likely it is that only reck-
Hobhouse LJ (as he then was). Other examples can lessness will suffice to break the chain of causation.
be found in the area of shipping law. Where, in Ready illustrations are furnished by the
breach of charterparty, charterers order a vessel to authorities:
proceed to an unsafe port, the conduct of the ves- (i) In the sad case of Lambert v Lewis (supra),
sels master in obeying the order (placed as he well the farmer could no longer rely on the dealers
may be, on the horns of a dilemma) will be judged warranty in the factual circumstances graphically
sympathetically, in context and will not lightly be outlined by Lord Diplock (at pages 276 and
treated as unreasonable: Compania Naviera Mar- 277):
opan SA v Bowaters Lloyd Pulp and Paper Mills . . . I would accept that in the case of the
Ltd (The Stork) [1955] 2 QB 68. But even negligent coupling the warranty was still continuing up
navigation following the charterers order to pro- to the date, some three to six months before
ceed to an unsafe port will not necessarily break the the accident, when it first became known to the
chain of causation: see, for example, Kristiand- farmer that the handle of the locking mecha-
sands Tankrederei AS v Standard Tankers (Baha- nism was missing. Up to that time the farmer
mas) Ltd (The Polyglory) [1977] 2 Lloyds Rep would have had a right to rely upon the dealers
353, at page 366. Conversely, where the negligence warranty as excusing him from making his
of vessel X caused vessel Y to run aground, vessel own examination of the coupling to see if it
X was not liable for such damages as were attribut- were safe . . . After it had become apparent to
able to the subsequent, clearly separate and negli- the farmer that the locking mechanism of the
gent re-floating of vessel Y: The Spontaneity [1962] coupling was broken, and consequently that it
1 Lloyds Rep 460; the negligence of vessel X had was no longer in the same state as when it was
ceased to be operative. delivered, the only implied warranty which
45. Thirdly, it is difficult to conceive that any- could justify his failure to take the precaution
thing less than unreasonable conduct on the part of either to get it mended or at least to find out
the claimant would be capable of breaking the chain whether it was safe to continue to use it in that
of causation. It is, however, also plain that mere condition, would be a warranty that the cou-
unreasonable conduct on a claimants part will not pling could continue to be safely used to tow a
necessarily do so for example where the defen- trailer on a public highway notwithstanding
dants breach remains an effective cause of the loss, that it was in an obviously damaged state. My
albeit in combination with the claimants failure to Lords, any implication of a warranty in these
[2011] Vol 1 LLOYDS LAW REPORTS 489

QBD (Comm Ct)] Borealis v Geogas Trading [GROSS LJ

terms needs only to be stated, to be rejected though the warning on 8 September had been
. . . In the state in which the farmer knew the purely fortuitous (Nolan LJ, at page 16 of the
coupling to be at the time of the accident, there Schering transcript), the defendants were entitled
was no longer any warranty by the dealers of to pray it in aid.
its continued safety in use on which the farmer (iii) By contrast with Lambert v Lewis and
was entitled to rely. Schering, the plaintiff in County Ltd v Girozen-
. . . The farmers liability arose, not from the trale Securities (supra) did not know of the
defective design of the coupling but from his defendants breach of contract. This case con-
own negligence in failing, when he knew that cerned a share issue. The plaintiff bank agreed to
the coupling was damaged, to have it repaired underwrite a placement of the shares; the defen-
or to ascertain if it was still safe to use. The dant brokers made representations to potential
issue of causation, therefore, on which the investors outside and in breach of the terms of
farmers claim against the dealers depended, the engagement letter; for its part, the bank failed
was whether his negligence resulted directly to check on the status of indicative commitments
and naturally, in the ordinary course of events, obtained by the chairman of the company. In the
from the dealers breach of warranty. Mani- event, a significant number of shares were not
festly it did not. taken up, leaving the bank with a loss. The Court
(ii) In the unreported case of Schering Agro- of Appeal held that the bank was entitled to
chemicals Ltd v Resibel NV SA (CA) 26 Novem- recover its loss from the brokers. In so doing, the
ber 1992, unreported; CA Transcript No 1298 of Court of Appeal reversed the decision of the trial
1992, the defendants were employed by the judge who had held, inter alia, that the brokers
plaintiffs to provide safety devices to guard representations were not of equal efficacy with
against the known risk of fire. The safety devices the banks decision to accept the quality of the
were defectively designed and did not provide indicative commitments . . . without making
that protection. The result, on 30 September proper inquiries (see, the headnote, at page
1987, was a serious fire. However, on 8 Sep- 834). Against this background, Hobhouse LJ said
tember, so some three weeks earlier, there had this (at page 857b to d):
been very small fire, which disclosed to the Where a plaintiff does not know of a
plaintiffs that the safety device did not work. defendants breach of contract and where he is
Both the eminent judge at first instance (Hob- entitled to rely upon the defendant having per-
house J, as he then was) and the Court of Appeal formed his contract, it will only be in the most
(Purchas LJ and Nolan and Scott LJJ, as they exceptional circumstances that conduct of the
then were) held that the defendants were not plaintiff suffices to break the causal relation-
liable in respect of the loss occasioned by the 30 ship between the defendants breach and the
September fire. Their reasons for doing so dif- plaintiffs loss.
fered, spanning a break in the chain of causation,
a failure to mitigate and remoteness of damage. It The plaintiffs conduct was not voluntary in
is unnecessary to explore those differences of the sense of being undertaken with a knowl-
reasoning here. The striking feature of Schering edge of its significance. Conduct which is
was that the 8 September incident was sufficient undertaken without an appreciation of the
to disclose to the plaintiffs that a breach of con- existence of the earlier causal factor will nor-
tract had occurred and made it reasonable to mally only suffice to break the causal relation-
expect the plaintiffs to take appropriate steps to ship if the conduct was reckless. It is the
minimise the consequences. A highly dangerous character of reckless conduct that it makes the
situation had been revealed; the production line actual state of knowledge of that party imma-
ought to have been stopped so that a proper terial . . .
investigation could take place. It may further be For completeness, I do not, with respect, read
noted that, as in Lambert v Lewis (supra), the these observations of Hobhouse LJ as furnishing
plaintiffs knowledge of the breach and the need support for any rule of law that only reckless con-
to address it took place some period of time duct will serve to break the chain of causation.
before the later incident in respect of which the Instead, these observations are authority for a more
(bulk of) the damages were claimed. On the facts limited proposition: namely, that in circumstances
of the case, viewed as a matter of causation, the where the claimant is unaware of the defendants
plaintiffs failure to do what was reasonable . . . breach of contract normally (ie, not invariably)
destroyed the further causative potency of the only recklessness will suffice. As such the good
pre-existing breach of contract . . . : Hobhouse sense of the rule is difficult to gainsay and its
LJ, explaining Schering, in County Ltd v Gir- compatibility with rules governing mitigation of
ozentrale Securities (supra), at page 858. Even damage is apparent.
490 LLOYDS LAW REPORTS [2011] Vol 1

GROSS LJ] Borealis v Geogas Trading [QBD (Comm Ct)

47. Fifthly and ultimately, the question of bility for that type of loss), the orthodox approach
whether there has been a break in the chain of continues to apply in the great majority of cases
causation is fact sensitive, involving as it does a as Lord Hoffmanns and Lord Hopes observa-
practical inquiry into the circumstances of the tions themselves make clear: see, The Achilleas, at
defendants breach of contract and the claimants paras 9, 11 and 36; see too, the valuable discussion
subsequent conduct. As Roskill LJ observed, in to be found in Hamblen Js judgment in The Sylvia
Lambert v Lewis (loc cit), it is always a question of (supra), at paras 20 to 51. There are, in my judg-
degree at what point the damage claimed for ceases ment, no exceptional circumstances in the present
to flow naturally and directly from the breach. For case calling for specific consideration of the
my part, I respectfully agree with the observations assumption of responsibility test. Fourthly,
of Evans-Lombe J, in Barings plc v Coopers & because, looking ahead, I cannot see that the appli-
Lybrand [2003] Lloyds Rep IR 566, at para 838, cation of Lord Hoffmanns test (whether a party
where he expressed an unwillingness to accept any would reasonably be regarded as having assumed
all-embracing test for what may constitute the responsibility for the type of losses in question) to
breaking of the chain of causation: the issues in dispute here would realistically pro-
. . . It seems to me that what will constitute duce a different outcome to that flowing from the
such conduct is so fact-sensitive to the facts of application of the orthodox approach. For present
any case where the issue arises that it is almost purposes, it is therefore unnecessary to say more as
impossible to generalise. If one must do so, I to the law on remoteness.
would say that it must be some unreasonable
conduct, not necessarily unforeseeable . . . , a Mitigation
new cause coming in and disturbing the sequence
of events . . . , not necessarily reckless . . . , 49. Mitigation was relevant both to the Geogas
which may result from an accumulation of events secondary case and to the discrete point as to the
which in sum have the effect of removing the unavailability of the cavern. As it is so well settled
negligence sued on as a cause . . . , which and was not in dispute before me, the law here can
accumulation of events may take place over likewise be taken very shortly. A convenient start-
time . . . ing point is to be found in the judgment of Sir John
Donaldson MR in Sotiros Shipping Inc v Sameiet
I would add too that while the authorities of
Solholt (The Solholt) [1983] 1 Lloyds Rep 605, at
course provide guidance, they are not to be read as
page 608:
statutes.
A plaintiff is under no duty to mitigate his
Remoteness loss, despite the habitual use by the lawyers of
the phrase duty to mitigate. He is completely
48. This topic can be taken very shortly indeed. free to act as he judges to be in his best interests.
First, because as already underlined it is raised by On the other hand, a defendant is not liable for all
Geogas only in respect of two discrete areas of loss suffered by the plaintiff in consequence of
dispute. Secondly, because the orthodox his so acting. A defendant is only liable for such
approach (Hamblen J in Sylvia Shipping Co Ltd v part of the plaintiffs loss as is properly to be
Progress Bulk Carriers Ltd (The Sylvia) [2010] 2 regarded as caused by the defendants breach of
Lloyds Rep 81; at para 20 et seq) based upon duty. As Viscount Haldane LC put it in British
Hadley v Baxendale (1854) 9 Exch 341 and C Westinghouse Electric and Manufacturing Co
Czarnikow Ltd v Koufos (The Heron II) [1969] 1 Ltd v Underground Electric Railways Co of
AC 350 has been settled for so long. As succinctly London Ltd [1912] AC 673 at p689:
formulated by Lord Reid in The Heron II, at pages
382 and 383, was the loss of a kind which the The fundamental basis is thus compensa-
defendant at the time of the contract ought to have tion for pecuniary loss naturally flowing from
realised was not unlikely to result from the the breach; but this first principle is qualified
breach meaning a degree of probability con- by a second, which imposes on a plaintiff the
siderably less than an even chance but nevertheless duty of taking all reasonable steps to mitigate
not very unusual and easily foreseeable? Thirdly, the loss consequent on the breach, and debars
because if and to the extent that, with respect, the him from claiming any part of the damage
speeches of Lords Hoffmann and Hope in Trans- which is due to his neglect to take such
field Shipping Inc v Mercator Shipping Inc (The steps.
Achilleas) [2009] 1 AC 61 have added assumption ...
of responsibility as an additional requirement of Whether a loss is avoidable by reasonable
the remoteness rule in some cases (so that a loss action on the part of the plaintiff is a question of
even if not unlikely to result might still be too fact not law. This was decided in Payzu Ltd v
remote if the defendant had not assumed responsi- Saunders [1919] 2 KB 581.
[2011] Vol 1 LLOYDS LAW REPORTS 491

QBD (Comm Ct)] Borealis v Geogas Trading [GROSS LJ

50. For present purposes, it is only necessary to used. Accepting that the physical damage sustained
add the following. First, the onus of proof on the by the plant was substantially suffered in the first 58
issue of mitigation is on the defendant: McGregor hours following discharge, Geogas should not be
on Damages, 18th Edition, at para 7-019. Secondly, liable for more than 22/58ths of that physical dam-
the conduct of the innocent party should not be age, or at any rate, Geogass liability for physical
weighed in nice scales at the instance of the party damage should be substantially reduced reflecting
whose breach of contract has occasioned the diffi- the time by when the feed should have been
culty: per Lord Macmillan in Banco de Portugal v changed. Even if that were wrong and by the
Waterlow & Sons Ltd [1932] AC 452, at page 506. conclusion of his submissions Mr Ashcroft realis-
Immediately thereafter (ibid), Lord Macmillan said tically accepted that the meat of the Geogas sec-
this: ondary case lay in reducing or eliminating its
It is often easy after an emergency has passed liability for consequential loss had the feedstock
to criticise the steps which have been taken to been changed in a timely manner, the titanium tubes
meet it, but such criticism does not come well would not have been holed and the very sizeable
from those who have themselves created the claim for lost production in September 2003 would
emergency. The law is satisfied if the party have been avoided.
placed in a difficult situation by reason of the 52. Ms Buehrlens response for Borealis was
breach of a duty owed to him has acted reason- forthright. There had been no unreasonable conduct
ably in the adoption of remedial measures, and on the part of Borealis; even if there had been, it
he will not be held disentitled to recover the cost was not such as to break the chain of causation, nor
of such measures merely because the party in had there been a failure to mitigate; in any event,
breach can suggest that other measures less the Geogas secondary case (if reasoned through)
burdensome to him might have been taken. would not have avoided any loss, physical or con-
sequential. Borealis did not know and had no rea-
Issue (I): the Geogas secondary case son to suspect that the goods had been
contaminated with fluorides. The Geogas focus on
(1) The rival contentions the pH alarm failed to take into account the purpose
51. As already introduced, the Geogas secondary of that alarm and Borealiss operational experience.
case is that Borealis failed to react appropriately, or Having regard to the context, it would not have
at all, to the pH alarm which sounded at 15.20 on 12 been unreasonable for the operators to wait until
September some two hours after discharge of the Monday 15 September for the next scheduled labo-
goods had commenced. Borealiss conduct broke ratory samples but of course by then, any con-
the chain of causation between the admitted Geogas cerns as to the pH alarm had been overtaken by
breach of contract and the loss and damage claimed events. There was moreover no or insufficient rea-
by Borealis; alternatively, Borealis had failed to son to suppose that, if steps had been taken in
mitigate its loss. In broad outline and as presented accordance with the Geogas secondary case, plant
in his closing submissions, Mr Ashcroft argued that management would have concluded that the LPG
the operators failure to take prompt action in feed from the cavern should be stopped. Even if the
response to the pH alarm was unreasonable. The pH ammonia injection though incapable of prevent-
trend should have been monitored; such monitoring ing damage to the primary heat exchangers did
would have revealed a severe and unusual fall. The not mask the damage being done by the HF in the
reliability of the pH meter should have been con- contaminated feed, the more likely conclusion
firmed, ammonia should have been injected and would have been that the drop in pH was attributa-
laboratory samples obtained; that it was a Friday ble to the high level of oxygenates in the goods. In
night was neither here nor there the plant oper- any event, the timeline contemplated by the Geogas
ated on a 24/7 basis. On the footing that, contrary to secondary case was artificial and unrealistic. On the
expectations, the injection of ammonia did not evidence, it would have required at least 12 hours to
result in any significant increase in the pH level, take the relevant furnaces offline so as to change the
plant management should have been involved. feed; as it was known that titanium tubes had perfo-
Once the matter had been properly considered, the rated by 20.00 on 13 September the time when
linkage between the contamination and the goods, the gas alarm sounded the Geogas secondary
now forming part of the feedstock from the cavern, case went nowhere unless all the relevant decisions
would have become clear. Urgent steps should then and conclusions had been reached by 08.00 on 13
have been taken to stop using the LPG mix from the September at the latest. Further, on the undisputed
cavern; these should have been accomplished evidence that the titanium tubes needed to be
within 22 hours of the alarm sounding, so by replaced if 20 per cent damaged, it could not be said
13.20 on 13 September the contaminated feed- that physical damage would have been avoided,
stock from the cavern should no longer have been even if the contaminated feed had been stopped as
492 LLOYDS LAW REPORTS [2011] Vol 1

GROSS LJ] Borealis v Geogas Trading [QBD (Comm Ct)

contended for by Geogas; there was not and could unit. On the evidence of a number of witnesses
not be any assumption that damage was linear. Still called by Borealis (Messrs Andersson, Petersen,
further and as to consequential loss, the reasoning Eerola and Harris) I further find that:
of the Geogas secondary case did not make good (i) Borealis was not aware that the goods were
the case that the September 2003 production would contaminated with fluorides;
not have been lost; had Borealis suspected the pres-
ence of an unusual and corrosive acid in the system, (ii) Borealis was not aware of the risk that
it was unlikely that full production would have field grade butane sourced from a refinery
gone ahead, regardless. might be heavily contaminated with fluorides;
(iii) contrary to some suggestions from Mr
(2) The Geogas breach of contract Lumley, an expert witness called by Geogas (of
whom more presently), Borealis could not rea-
53. With a view to placing the Borealis reaction sonably have been expected to be aware of the
to the Geogas breach of contract in context it is risk that field grade butane sourced from a
appropriate first to focus on the breach of contract refinery might be heavily contaminated with
itself albeit that the breach has been conceded. fluorides.
That concession, welcome, forensically wise and 57. Borealis was further unaware that although
perhaps inevitable though it was, should not be the contract had provided for a water content of
allowed to deflect attention from the position in nil, the goods had in fact contained some 10 mt of
which Borealis found itself by reason of the water at the load port. I find, with regret but no
breach. hesitation, that Mr Gudefin the Geogas trader
54. The reality is that Geogas supplied goods whose trade this was and who gave oral evidence at
which were heavily contaminated with fluorides. In trial perhaps with others at Geogas, went to
accordance with the figures contended for by Bore- some lengths to conceal this fact from Borealis.
alis Geogas advanced no positive case to the Instead of claiming from Sunoco, the supplier to
contrary I find that the average level of con- Geogas in respect of this water content, Geogas
tamination was 265 to 295 ppm fluoride compounds arranged for the removal of much of the water and
(wtt), corresponding to 1,060 to 1,180 ppm of the went to the lengths of procuring the issue of new
actual contaminant, 2M2F. bills of lading for a reduced cargo quantity. It subse-
55. Samples of the contents of the cavern follow- quently transpired, to my mind, revealingly, that the
ing discharge of the goods from the vessel showed water had a pH of 2 to 2.2 Of this, Borealis was at
levels of fluoride contamination up to 83 ppm (wtt) all material times unaware but the evidence does
and averaging 55 ppm corresponding to 220 ppm not permit any conclusion as to whether Borealiss
(wtt) of 2M2F. Prior to discharge of the goods into actions would have been different had it known.
the cavern, the contents of the cavern contained 58. Borealis was aware of the levels of oxygen-
levels of fluorides of 1ppm or less, ie, at most trace ates in the goods, a matter of some significance and
levels. considered further below. The vessels tanks con-
56. The contract provided, expressly, that Geogas tained 225 ppm, 135 ppm, 200 ppm and 130 ppm
would supply Borealis with field grade butane. respectively. The average oxygenates content of the
The evidence at trial differed as to whether field goods overall was some 172.5ppm against a con-
grade meant butane that had come directly from a tractual specification of nil and Borealiss internal
field (so that field grade related to the source of specification limit of 200 ppm. In the event,
the goods) or that it had the same quality or purity Borealis accepted the goods.
characteristics as butane sourced from a field (so 59. Queries as to the goods met with unhelpful
that field grade related to the quality of the goods) responses from Geogas. So, on 12 September 2003
ie, a high quality cargo free of contaminants. For (the morning of discharge), when Borealis
present purposes it matters not which definition of expressed some concern as to the quality of the
field grade is adopted. Butane sourced from a goods, Geogas replied, reassuringly, that the two
field would not be contaminated with fluorides. previous cargoes on the vessel had been field grade
Field grade butane sourced from a refinery products. An internal Geogas communication of the
plainly ought not to have been contaminated with same day remarked: Luckily water was no[t]
fluorides. In any event, butane sourced from a refin- reported. Subsequently, on 24 September, after
ery could only be contaminated with fluorides if the Geogas had reserved its rights, Mr Gudefin
refinery was using an HF alkylation unit. On the responded, inter alia, that Geogass suppliers con-
evidence, of the 31 cargoes of butane sourced by firmed that nothing abnormal that could have con-
Borealis from refineries in the period January to taminated the cargo happened during loading
September 2003, only one (the Stanlow cargo) operations. He remained, in my judgment and
was sourced from a refinery using an HF alkylation despite the answer he gave in cross-examination,
[2011] Vol 1 LLOYDS LAW REPORTS 493

QBD (Comm Ct)] Borealis v Geogas Trading [GROSS LJ

most anxious to conceal the fact that there had been expected the operator to make a particular request
an unusual quantity of water in the cargo when first for an additional manual sample on Sunday 14
loaded. September; he surmised that no such request had
60. Pulling the threads together, as at 12 Sep- been made because it was overtaken by events. The
tember 2003, Borealis was wholly unaware that the ammonia injection system had been designed for
goods with which it had been supplied were con- weak acids. Having regard to those acids, low pH
taminated with fluorides. Nor was there any reason was not seen as a problem:
why Borealis ought to have been aware that the Based on the experience, I mean, we have
goods might have been so contaminated. To my operated this plant since 1970 and low pH has
mind, this is an important factual consideration never been a problem until September 2003. So
when addressing the Geogas secondary case. based on the knowledge we had [in] 2003 I
would say that the operators did not see low pH
(3) The pH alarm as a problem.
61. Though there was some resistance from Geo- 64. Mr Andersson was a control room shift
gas, there was overwhelming evidence that the supervisor at Borealis, from 1989 to 2007; he was
essential purpose of the pH alarm was to protect not on duty on 12 September when the pH alarm
downstream carbon steel plant and equipment from was triggered (but came on duty subsequently). The
corroding weak acids (eg, carbonic acid) naturally tenor of Mr Anderssons evidence here was clear.
occurring in the product stream. This alarm system The purposes of the pH alarm was to alert the
was not designed or intended to deal with an unex- operator to the pH being lower (and though he did
pected contaminant in the feed such as HF. not say it, higher) than recommended. However, a
62. Mr Harris is a Sales Director of Shaw Energy low pH was not harmful for the equipment and so
& Chemicals Group, a leading engineering and was not a big deal for Borealis. They had oper-
design contractor and the designer of the plant. Mr ated with a low pH for a long time previously; in his
Harris is also the Borealis account manager. Mr view, there was no need to react promptly to the pH
Harris accepted in cross-examination that the pH alarm sounding. In response to the suggestion that a
alarm would detect the presence of any acid in the strong acid had come into the system, he said
system and that the injection of ammonia the this:
anticipated response to a fall in pH below desirable In our knowledge there was no strong acid.
levels would (no doubt depending on quantities, We didnt know anything about that. We only
proportions and the like) neutralise acids generally. knew . . . that the system is constructed for a
As I understood his evidence, he did not, however, slow build-up of acid in the process. This is a low
depart from the following observations in his wit- capacity ammonia system. It has no big capacity
ness statement: to take care of anything larger than that.
The pH control system in process systems The pH alarm system was there to control the pH
such as that existing at the . . . plant, is designed for the carbon steel system. The pH alarms were
to counter organic acids that may form in the in any event unreliable so there was a general
furnace outlet stream during normal operating practice to wait for the regular testing undertaken
conditions . . . The pH control systems are not by the laboratory on Mondays, Wednesdays and
designed to counteract hydrofluoric acid as this is Fridays.
not an acid that one would expect to encounter in 65. Professor Davies was called by Borealis to
an ethylene plant . . . give expert evidence in the discipline of chemical
63. Mr Hedvall was, in 2003, the Production engineering. He had visited the plant. He pointed
Manager of the plant. His evidence was that the pH out that a fall in the pH level, even a rapid drop,
alarms were unreliable and, based on the informa- while indicating the presence of an acid in the
tion available to Borealis in 2003, there was no system would not tell the operator what type of acid
need for immediate action when the pH alarm it was. It was his opinion:
sounded. As he put it: . . . that the pH system . . . was designed
. . . this is a slow system so that there is no and the introduction of ammonia was designed to
high priority on this alarm. . . . we know from neutralise acids that have formed from oxygen-
experience that we can operate this system for a ates that appear in the feed . . .
long period with low pH so there is no need for Carbonic acid is a weak acid. So we are deal-
immediate response . . . ing with a system that has been principally
Mr Hedvall said in a witness statement that designed to remove CO2 in the form of its weak
though, ordinarily, manual laboratory samples were acid in aqueous solution . . .
not undertaken over the weekend, where pH So we have a system designed to remove weak
remained low for hours (as here), he would have acids . . .
494 LLOYDS LAW REPORTS [2011] Vol 1

GROSS LJ] Borealis v Geogas Trading [QBD (Comm Ct)

. . . downstream of the heat exchangers and But I think it needs to be kept in perspective a
before the compressors . . . carbon steel is used perspective provided by the context already out-
and is attacked by weak acids. The reason why lined. The provision in the Handbook does not, for
the ammonia system is there in the first place is instance, say anything as to the necessary speed of
to protect the downstream plant, it is as simple response, should the pH level move outside the
as that. relevant parameters, or as to the prioritisation of the
. . . the corrosion rate of . . . [these] . . . weak pH alarm. It is additionally of note that this provi-
acids is very low. So there is no real urgency in sion cautions both against pH levels above and
adjusting the pH . . . below the recommended levels; a matter to which I
66. Pulling the threads together, on the shall briefly return later.
evidence: 70. For my part, therefore, I remain very much of
(i) The pH alarm was a low priority (a white the view that the purpose of the pH alarm and the
not a red) alarm; these alarms had been notori- operating experience of those at the plant are sig-
ously unreliable. nificant and material factors when considering the
Geogas secondary case and its criticisms of
(ii) The weak acids typically encountered by Borealiss conduct.
the plant and with which the pH alarm and
ammonia system were designed to deal, took a
long time to do damage to the carbon steel so (4) The sounding of the pH alarm
suggesting that a prompt let alone immediate 71. Against the background already outlined, I
response to the pH alarm was not thus come to the sounding of the pH alarm at 15.20 on
necessary. the afternoon of 12 September.
(iii) In some 40 years of operating experience,
72. The pH levels are a good place to start. It will
low pH had not been seen as a problem.
be recollected that discharge of the goods com-
(iv) Low pH indicated the presence of an acid menced at 13.20 on 12 September. Between 12.00
in the system but not the type of acid; those at the and 14.00, the pH levels were a little above 6.
plant did not contemplate encountering HF and However, between 15.00 and 20.00, the pH levels
had no reason to do so. dropped considerably.
(v) Laboratory sampling was routinely under-
taken on Mondays, Wednesdays and Fridays but, 15.00 5.3
ordinarily, not on weekends.
67. Mention has already been made of Mr Lum- 16.00 4.2
ley, an expert called by Geogas. Significantly, in 17.00 3.8
cross-examination, he accepted a good deal of this
evidence. As fairly summarised by Ms Buehrlen: 18.00 3.7
The purpose of the pH system, . . . the fact
that the pH system was itself a low priority 19.00 3.6
alarm, the fact that it was not designed to deal
with contaminants in the feeds such as fluorides, 20.00 3.6
. . . the experience of how the plant operates
were all accepted by Mr Lumley as relevant Thereafter, the pH levels remained in the high 3s
factors when considering Borealis response to until 13.00 on 14 September when they rose to a
the pH alarm and drop in pH . . . little over 4 and rose further to more than 5 at about
01.45 on 15 September.
68. Mr Lumley did, however, place much empha-
sis on the following provision found in the Borealis 73. Surprisingly, in my view, Borealis did not
Operations Handbook (the Handbook): call either of the operators who had been on duty
when the pH alarm was triggered (or, for that mat-
The pH value must be maintained at 5.56.5. ter, the supervisors then on duty). The best explana-
At a higher pH value emulsion problems may tion was that neither of the operators any longer
arise in D-1681, and at low PHs corrosive worked for Borealis. Even that explanation does not
attacks on the material increase. altogether satisfy concerns in this regard, in partic-
In the absence of other written procedures for the ular as to the reason why no witness statements
plant this provision was to be followed; it was not were available. Mr Ashcroft criticised Borealis with
for the operators to go off-piste and ignore the pH regard to the absence of the operators, in my judg-
alarm. The plant was to be operated within strict ment, rightly. He submitted, again rightly, that I
guidelines; it was dangerous to do otherwise. should be cautious as to the explanations from
69. With respect, I appreciate the force of Mr others as to what was or might have been done or
Lumleys reasoning on this part of his evidence. left undone by the operators; I agree. As canvassed
[2011] Vol 1 LLOYDS LAW REPORTS 495

QBD (Comm Ct)] Borealis v Geogas Trading [GROSS LJ

at the trial, it also seems right to me not to speculate A pH alarm is present with the LLA set at
as to what the operators might have said, had they 5.0. No actions were taken. There was no knowl-
given evidence. I must proceed on the evidence edge at production department or among opera-
available. tors about the potentially damaging effects of
74. All this said, the lacuna left by the absence of hydrofluoric acid on titanium. The alarm was
the operators and supervisors (or any witness state- later tested and found to be working.
ments from them) is at least in good measure filled The low pH condition persisted for approx-
by the extremely helpful Root Cause Failure Anal- imately 59 hours.
ysis Report, an internal Borealis document, pre- The Executive Summary recommended that:
pared after the incident and in its final form dated
Understanding about the potential corrosive
18 December, 2003 (the Report). The frankness
effects of low pH, and the need to react to low
of the Report in criticising various of Borealiss
pH alarm, have to be communicated to all
own procedures is commendable and adds to its
operators.
weight such frankness doubtless aiding the man-
ifest objective of the Report, namely, to avoid a 77. In the section of the Report entitled Events
recurrence. Furthermore, the Borealis lead inves- and Conditions, the drop in pH from 5.5 to a range
tigator into the incident and (with a team of others) of 3.5 to 3.7 was considered. Laboratory samples
responsible for the preparation of the Report, was a taken before and after the incident indicated that the
Mr Arvidsson. He did attend to give evidence. As pH meter was relatively accurate. While there was
both his evidence and the Report made clear, in the no alarm log for the pH alarm system, this passage
course of preparing the Report interviews were con- of the Report was able to say the following:
ducted, including of the operators. It follows that, in No actions were taken to increase the pH (eg,
part, at least, the Report reflects what the operators increase NH3). Causal Factor 4
were saying at the time. u Historically the unit has run without NH3
75. Before turning to the substance of the Report, with a pH of ~ 4 for extended periods without
I should mention two preliminary matters: damage.
(i) Ms Buehrlen very properly invited me to u In earlier years, the pH meter was unreli-
read the Report with these observations of Bram- able and more emphasis was put on lab sam-
well B, in Hart v Lancashire and Yorkshire Rail- pling of pH.
way Co (1869) 21 LT 261 in mind: u Lab samples are not routinely taken dur-
. . . people do not furnish evidence against ing the weekend.
themselves simply by adopting a new plan in u ...
order to prevent the recurrence of an accident.
u There has been no experience to show that
I think that a proposition to the contrary would
low pH is harmful to titanium. Causal Factor
be barbarous.
5
Although, as Mr Ashcroft submitted, there can
As Geogas sought to pray it in aid (discussed
be no rule of law to this effect, I think, with
below), I should record the entry for 13.00 on 18
respect, that these observations of Bramwell B
September. A request had been made by the inves-
are germane and helpful in maintaining a sense
tigation team and:
of perspective.
pH trend was noted for the first time.
(ii) The Report speaks of the Direct Cause of
the damage to the titanium tubes (the contami- 78. Under the heading Observations and Con-
nants in the goods cracking in the cracking fur- clusions, the Report has this to say:
nace allowing the formation of HF and an . . . pH is controlled by manually adjusting
aggressive corrosive attack on the tubes) and NH3 injection rates to the tower overhead. The
various Causal Factors. Two of those Causal target range for pH is 5.0 and 7.0. Historically
Factors concern pH. However, the methodology the primary purpose for pH control has been to
of the Report is such that I do not think the mere reduce corrosion of carbon steel in the tower
inclusion of pH matters amongst the Causal overhead, piping and heat exchanger shells.
Factors assists the argument before me. Under normal operating conditions the primary
76. Coming to the substance of the Report but corroding species is carbonic acid formed from a
confining myself to matters relevant to the Geogas combination of steam condensate and CO2.
secondary case, the Executive Summary records Since the bundle metallurgy was changed to
that approximately 1 hour 20 minutes after dis- titanium there have been a number of incidents
charging commenced, the pH of sour water in when NH3 injection has been interrupted and pH
D-1681 dropped rapidly from 5.5 to a range of levels have been allowed to fall without neutral-
3.5 to 3.7. The Executive Summary continued: ization, in at least one case for a period of 23
496 LLOYDS LAW REPORTS [2011] Vol 1

GROSS LJ] Borealis v Geogas Trading [QBD (Comm Ct)

weeks. The resulting overhead pH levels have ing experience with pH, lack of knowledge and
typically fallen to around 4.6. It was determined understanding of the potential damaging effects
that the corrosion rate of carbon steel under these of low pH, or simple failure to follow reasonable
conditions is relatively low and, during routine standard operating procedures.
inspections, no visual indication of titanium has The Report indicated that the findings from these
been observed as a consequence of intermittent interviews had been set out in the Events and
operation below a pH of 5.0. Nevertheless, long Conditions section already recorded above.
term exposure of carbon steel to lower levels of
pH has been deemed to be inadvisable. Until this 81. The Reports own conclusions in this regard
incident, there have been no pH excursions were as follows:
below 5.0 during the past two years. . . . operating experience for the past 20
pH is monitored with an online pH meter years suggested that pH was a relatively unim-
located in the sour water distillate drum portant operating parameter. It was certainly true
(D-1681). When the online pH meter was origi- that essentially no one in the production depart-
nally installed it was relatively unreliable. Labo- ment was aware of the potentially damaging
ratory samples are taken three times a week to effects of hydrofluoric and/or hydrochloric acid
verify pH meter readings. Comparison of recent on titanium or even for the potential for HC1 in
laboratory measures of pH with the on-line meter the primary fractionator tower overhead.
has shown that the meter currently tracks pH This said, it is apparent that the low pH alarm
reliably. However, appreciation of this improve- was functional, yet no additional samples were
ment in reliability is not shared by all operators sent to the lab to confirm that the low readings
who are responsible for monitoring pH. were real. Also, no adjustments were made to
79. Later in the Report, there were these observa- NH3 injections which may have mitigated the
tions, linking the corrosive attack to the contami- effects of the HC1.
nated goods: 82. Finally, the Report dealt with Causal Factors
The drop in pH . . . began approximately 1 4 and 5 as follows:
hour after . . . [unloading began] . . . of a Root cause category 2a) Lack of knowledge
shipment of N-butane from the Henning Maersk and skills
into the UC731 storage cavern. The cavern inlet Historical experience and lack of familiarity of
from the dock is in close proximity to the unit the impact of low pH on the corrosion of tita-
feed pump suction line. Past experience has nium, resulted in little or no attention to pH
shown that the effects of new feed are typically levels below the alarm level.
observed in the unit in approximately 1 hour
from the time that unloading begins. This obser- 83. To my mind, on the evidence before the
vation is viewed as further confirmation that cor- court, no action had been taken in respect of the pH
rosion of the E-1651 and E-1656 is related to alarm prior to the gas alarm sounding essentially for
contaminants in the butane that was shipped on the reasons set out in the Report and noted above.
the Henning Maersk. (Understandably, after the gas alarms sounded,
other concerns predominated.) Those reasons
80. As already highlighted, two Causal Factors related to the experience of the plant and the pur-
are here relevant and are related. These were: pose of the pH alarm. It is unsurprising that with an
4. No action was taken in response to drop- eye to the future whatever the outcome of this
ping pH. litigation the authors of the Report should rec-
5. Experience has never indicated that low pH ommend improved understanding of low pH, its
is potentially damaging to Ti. possible consequences and the need to react to the
The Report noted the online measure of pH had low pH alarm.
fallen below the low level alarm of 5.0 and 84. For completeness, in the light of the Reports
remained there for over 40 hours. After 30 hours at conclusions, I accept that the low level pH alarm
a pH of approximately 3.6, the first (gas) leak from was in working order on 12 September. In his
the E-1651 exchangers was detected. The Report witness statement, Mr Andersson described what
remarked that there was no evidence that any happens when the alarm is triggered:
attention was paid to this parameter (ie, the low The low level pH alarm sounds when the pH
level pH alarm). The Report went on to say: in the D1681 distillate drum falls below pH5.
The investigative team interviewed a number When the alarm sounds the alarm indicator light
of operators and other members of the production on the panel above the process computer begins
staff to gain a better understanding of this over- to flash. The operator acknowledges the alarm by
sight. Our objective was to determine the extent pressing the flashing light button. Once acknowl-
to which this could be explained by past operat- edged the alarm sound and flashing light will
[2011] Vol 1 LLOYDS LAW REPORTS 497

QBD (Comm Ct)] Borealis v Geogas Trading [GROSS LJ

stop. However, the indicator light will stay lit itored to check the effect of the additional
until the pH returns above 5. supply
If only to stop the sound and flashing light, the 3. A further allowance of 6 hours [01.20 on 13
probabilities are that an operator acknowledged September] is made for Borealis to confirm the
the alarm by pressing the flashing light button. On source of the acidity. Time is also required for
the available evidence, the operator did no more discussions with the supervisor and management
than that, for the reasons already discussed. Against to obtain approval to change the feed. I regard
this background, I am unable, with respect, to this allowance as generous to Borealis, because
attach to the 13.00 entry in the Report, under . . . the operators, supervisors and management
Events and Conditions, the significance for which should quickly have appreciated that the HM
Mr Ashcroft contends. Even assuming that the par- cargo was the cause of the drop in pH.
ticular entry is not simply referring to the work of 4. A further 12 hours is required [13.20 on 13
the investigators, I do not think that any failure to September] to stop LPG and change over to
note the pH trend advances the argument it is alternative feed safely.
no more than part of the overall picture already
5. Continue to operate the plant on alternative
outlined.
feed from 13.20 hours 13th September . . . at
full capacity, not 15th September . . .
(5) The high point of the Geogas secondary case Therefore, I estimate, the contaminated feed
85. The high point of the Geogas secondary case through the heat exchangers should have ceased
may be seen as the level of similarity in the evi- within 22 hours of the triggering of the pH
dence of Mr Harris, Mr Lumley and Professor alarm.
Davies as to the reactions they would have expected (Times in italics in square brackets are added.)
from the Borealis operators and management to the It may be noted that in taking 12 hours as the
drop in pH levels on the afternoon of 12 September. time to stop the LPG and change to an alternative
On the basis of this evidence in particular, Geogas feed (step 4), Mr Lumley relied on Mr Hedvalls
pressed its secondary case; the Borealis reaction to evidence to this effect, rather than Mr Anderssons
the drop in pH levels was indefensible; it was 16 hours.
unreasonable; it broke the chain of causation; had 88. Turning to Professor Davies, he accepted that
the reaction been as contemplated by these wit- he did not know what Borealiss procedures were
nesses, physical damage and consequential loss and was surprised that (as he put it) he had not got
would have been very substantially reduced. to the bottom of the reasons why the operators had
86. Mr Harris (to whom reference has already not acted in response to the pH alarm. He also said
been made) said that the sudden drop in pH levels that one wouldnt be running . . . to the lab every
was an indication that something was wrong. On time it went down below 5. Subject to the caveat,
the assumption that there was nothing wrong with twice underlined in the course of his cross-exam-
the measuring instrument, in his view, the sudden ination, that the scenario was artificial, Pro-
drop indicated to the operator that there was a fessor Daviess evidence as to timings and related
strong acid in the system. If there was a strong acid matters on the 12 and 13 September was along the
in the system, then that called for an immediate following lines:
laboratory analysis on the water in the system. (i) Within two hours of the pH alarm being
87. As I understood Mr Lumleys evidence, in its triggered [so, by 17.20], the operators should
final form on this part of the case, his views may be have looked at the pH trend, decided it was real
summarised by reference to a passage in one of his and added ammonia. Throughout his evidence,
reports. Once the pH alarm had been triggered (at Professor Davies made it clear that additions of
15.20 on 12 September) the timeline should have ammonia should be incremental; he disagreed
been as follows: with Mr Lumleys suggestion of increasing the
1. The first step should have been to increase ammonia flow to maximum in one fell swoop.
the ammonia flow to the maximum. This would (ii) Within a further four hours [by 21.20], the
have been a safe procedure with no negative operators should have checked with the labo-
consequences. ratory that the pH readings were accurate.
2. Within 4 hours [so, 19.20], the pH signal (iii) By 21.20, the ammonia flow (on this sce-
could have been confirmed after drawing a sam- nario) would have been increased incrementally
ple from the plant, checking with pH indicator up to the maximum. If there was then no discern-
paper and confirming with the laboratory. Within ible improvement in pH levels the operator
this period as the ammonia had been increased to ought to say this is unusual and lets get some
the maximum, the pH record should be mon- advice.
498 LLOYDS LAW REPORTS [2011] Vol 1

GROSS LJ] Borealis v Geogas Trading [QBD (Comm Ct)

(iv) If the readings were accurate and if there attack included the suggestion that in part he had set
was by this stage [21.20] no discernible change out to mislead the court, I should at once and in
in the pH level and if a supervisor had been fairness to Mr Lumley make it clear that I reject it.
consulted, that indicated acid in the system I do not at all think that Mr Lumley was a dishonest
though Professor Davies was adamantly opposed witness. Nor was his evidence without a number of
to any suggestion that it was strong acid; for that points of considerable force (one of which has
matter he was of the opinion (a debate which it is already been mentioned). There were, however, a
unnecessary to explore) that HF was not a strong number of features of his evidence which do
acid. The inquiry then was [now about or post- prompt very considerable caution when that evi-
21.20]: where did the acid come from? As the dence comes to be weighed; these features include
plant used a number of feedstocks, there would the following:
be a question (for a supervisor rather than an (i) Although he gave his Specialist Field as
operator) as to whether the acid could be linked Chemical and process plant design and opera-
with one of them. tion in the manufacture of organic chemicals, he
(v) Professor Davies was to some degree is in fact a mechanical engineer. He had never
equivocal about making the linkage between the worked in an ethylene cracker or on a project
unusual situation and the feedstock from the cav- concerned with an ethylene cracker; he had never
ern. If, however, such linkage had been made, a been involved in the design, operation or man-
deduction that would have been entirely in agement of a cracker; he has never visited the
keeping was that the low pH level was due to plant. Mr Ashcroft retorted, fairly, that Professor
the contaminated goods, on account of the oxy- Davies had himself never worked in an ethylene
genates in the goods being well . . . above the cracker or been involved in the design, operation
normal levels. If so, it was at least implicit in or management of a cracker. That is fair as far as
Professor Daviess evidence that the anxiety it goes and is indeed a matter I shall take into
would, for the time being at least, have been account when considering Professor Daviess
allayed. evidence. Mr Ashcroft further submitted that
(vi) If it was possible to identify which feed- what was required was general knowledge of
stock was causing the problem and if oxygenates proper plant operations and procedures and that
in the goods did not furnish the perceived cause, Mr Lumley had a great deal of experience in
then it would be reasonable to take urgent action relation to plant design and operation. That too is
to stop using that feedstock while investigations fair and does serve to weaken the force of the
were made. On this footing, he accepted that it Borealis criticism going to Mr Lumleys lack of
would be more than prudent to take steps relevant expertise or experience. Even so, I am
immediately to stop using the LPG mix from the left with something of a question mark as to Mr
cavern. Lumleys expertise. An example directly rele-
vant to the Geogas secondary case was Mr
(6) Discussion: Starting point Lumleys suggestion in his timeline evidence (set
out above) that a sample could have been drawn
89. I start with the evidence characterised as the from the line and checked with litmus paper
high point of the Geogas secondary case. before the pH was confirmed by the laboratory.
90. With respect, I am not sure that that part of Without belabouring the point, the operation of
Mr Harriss evidence relied upon by Geogas took the plant made any such suggestion absurd;
the matter significantly further. I have no doubt that proper procedure required taking a sample with a
Mr Harris was doing his best to assist the court. It specialised pressurised container for testing,
would, moreover, be difficult to quibble with his using proper pH metering equipment not
view that the sudden drop in pH levels gave an litmus paper.
indication that something was wrong. But I am (ii) This concern as to Mr Lumleys expertise
unable to accept his further answer that (assuming and a tendency to stray beyond it is magnified
there was nothing wrong with the measuring instru- rather than assuaged when regard is had to Mr
ment) the sudden drop in pH levels indicated that Lumleys evidence overall. An example is appar-
there was a strong acid in the system and hence ent in the context of the later abandoned Geogas
the need for an immediate laboratory analysis. I allegation that, in its re-sale of the goods, Bore-
accept in this regard the evidence of Professor alis had failed to mitigate its loss. Mr Lumley
Davies that a drop in pH levels (assuming no instru- purported to express an opinion as to how long it
ment fault) indicated acid in the system but not would have taken to identify the contaminant in
what type of acid. the goods (2M2F), find a suitable buyer and
91. I turn to Mr Lumley. His evidence came arrange delivery. Inevitably, in cross-examina-
under severe attack from Borealis. Insofar as that tion, he accepted that he was not in a position to
[2011] Vol 1 LLOYDS LAW REPORTS 499

QBD (Comm Ct)] Borealis v Geogas Trading [GROSS LJ

give expert evidence of this nature. In the same civil case and a jury in a criminal case) to decide
vein, Mr Lumley in his report strayed into the the case on the whole of the evidence.
debate as to whether butane with a particular
level of contamination could be used for cooking Unreasonable?
or heating in India or Africa. Although Mr Lum-
ley sought to justify his evidence in this regard 95. Having regard to the evidence of Professor
(as a crossover between the technical and trading Davies, all the more so, when considered in con-
features of the case), in my judgment, comments junction with the Report, I am readily satisfied that
of this nature were outside his expertise the Borealis reaction to the sudden and substantial
indeed plainly so and should never have drop in pH levels on the afternoon of 12 September
featured in his evidence. left considerable room for improvement. On any
(iii) In his reports, Mr Lumley spoke of his view, this reaction fell well short of best practice.
primary case, secondary case and tertiary The recommendations in the Report were undoubt-
case. During the trial, I observed that parties had edly apposite.
cases but experts did not. This language was 96. But was the Borealis reaction unreasonable?
unhelpful and troubling, in that the court relies I confess that I did not find this an easy question to
on expert witnesses being non-partisan. That resolve. But, on balance, on the whole of the
said, I am not minded to make too much of this evidence and notwithstanding Mr Ashcrofts advo-
criticism because the error may well have been cacy, I do not think it was.
no more than semantic. 97. In my judgment, it is essential to keep upper-
(iv) There was, with respect, bizarre confusion most in mind my earlier conclusion: namely, that
between the body of Mr Lumleys original report Borealis did not know and could not reasonably
and one of his appendices as to the length of time have been expected to know of the kind of acid
to be allowed from the triggering of the alarm for introduced into the system by the Geogas breach of
the LPG feeds to be closed down and the fur- contract and the nature of the threat it posed. Again,
naces transferred to alternative feeds. While I do as already concluded, the pH system was not
not think that anything more sinister than chaotic designed or intended to deal with acids of such a
preparation was to blame for this disconnect nature. It is correct that the sudden and considerable
(as Ms Buehrlen termed it), it did nothing to drop in pH and the triggering of the pH alarm
enhance any feeling of confidence in Mr Lum- indicated an acid in the system; but, strikingly, had
leys evidence. it been an acid of the kind typically encountered by
the plant, nothing untoward would have resulted
92. Against the background of these criticisms, from the operators waiting until the routine samples
Mr Lumleys evidence, had it stood alone, would were taken on the Monday (15 September). In the
have furnished a weak foundation for the Geogas light of the experience of those at the plant, this
secondary case. In reality, the force of the Geogas would not have been a problem. That the operators
secondary case lay in the evidence of Professor could have done better, as indeed they did when pH
Davies, upon which Geogas placed understandable dropped significantly after discharge of the Stanlow
reliance. cargo (a cargo mentioned above), is one thing
93. Professor Davies was a witness of manifest and as already underlined amply justifies the con-
independence and, within his discipline (chemical clusions in the Report. But, against this back-
or process engineering) undoubted expertise. To my ground, to characterise as unreasonable the
mind, it was his evidence which gave the Geogas operators failure to achieve best practice, seems to
secondary case such credibility as it had. me a step too far. It should also be noted that
94. Even, however, in connection with an expert operators and supervisors (including Mr Anders-
of the calibre of Professor Davies, it is necessary to son) on the shift/s subsequent to that when the pH
bear in mind the following: levels first fell, reacted in the same manner as those
on the initial shift. It might be said that the focus
(i) Professor Davies did not have experience as must then move (away from the initial operators
a plant operator. Although he had visited the and supervisors) to the training given to operators
plant, as he himself said, he did not know what and others in the production department in the
Borealiss procedures were. plant. If so, however, the same conclusion is
(ii) As already underlined, Professor Davies reached: until the occurrence of this incident and in
himself described the time line scenario, as to the light of experience hitherto, Borealis had no
which he was cross-examined, as artificial. reason to anticipate that low pH would or could
(iii) While an expert is there to provide a court have consequences of this nature.
with the benefit of his expertise on part of the 98. For my part, I conclude that it was not unrea-
case, it is for the tribunal of fact (a judge in a sonable of those at the plant not to take the steps on
500 LLOYDS LAW REPORTS [2011] Vol 1

GROSS LJ] Borealis v Geogas Trading [QBD (Comm Ct)

Friday 12 September or Saturday 13 September, there was actual knowledge of the danger to which
canvassed in the evidence of Mr Lumley and Pro- the defective heat sealer gave rise. Nor are the facts
fessor Davies when dealing with timelines. I am here close to those of The Spontaneity (supra),
fortified in that conclusion and in preferring the where the negligent re-floating was clearly sepa-
evidence of those with practical experience of the rate, both in time and in terms of seamanship, from
plant, by Professor Daviess own concerns under- the earlier grounding. While Borealis did know of
lined by his description of the timelines scenario the rapid and substantial fall in pH, the facts here
as artificial. In my judgment, it would not have are closer to those of County Ltd v Girozentrale
been unreasonable to wait for routine sampling on Securities (supra); on 12 September, Borealis was
Monday 15 September, or, given Mr Hedvalls evi- entitled to start from the premise that it had been
dence (recounted earlier), at least Sunday 14 Sep- supplied with a high quality cargo free of con-
tember. I take no more time over the difference taminants, whereas the reality, unknown to Bore-
between 14 and 15 September, as, in my view, it is alis, was very different.
academic; in any event, by 14 September, such 104. Thirdly, the answer ultimately lies not
questions as to sampling had been overtaken by in authority but in a fact-sensitive inquiry.
events. Approached as a question of fact and degree, I
99. This conclusion is sufficient to dispose of the cannot begin to say that any failure/s on the part of
Geogas secondary case whether advanced in terms Borealis, obliterated or destroyed the causative
of a break in the chain of causation or as a failure potency of the anterior Geogas breach of contract.
to mitigate. It seems plain to me that the Geogas breach of
100. With specific regard to the question of mit- contract remained, at the least, an effective cause of
igation, the linkage between the knowledge of a the Borealis loss and damage, regardless of any
claimant and the reasonableness (or otherwise) of failure/s on the part of Borealis. Though Borealis
its conduct is plain. As illustrated by the judgment knew or ought to have known of the presence of an
of Nolan LJ in Schering (supra), at page 16, the acid in the system, it remained in the grip of
conclusion that there had in that case been a failure an unknown breach giving rise to an unknown
to mitigate was premised on the plaintiffs: danger.
. . . actual knowledge of the danger to which
the defective heat sealer gave rise. Would any loss have been avoided?
There was no such knowledge in this case, aris-
ing from the drop in pH on the afternoon of 12 105. The conclusion that the chain of causation
September nor, in fairness to Borealis, ought was not broken is itself sufficient to dispose of the
there to have been. Geogas secondary case. In any event, however, I
would have been unable to accept the Geogas sec-
If unreasonable, was the chain of causation ondary case because, reasoned through, I do not
broken? think the steps it advocated would have avoided any
loss, physical or consequential. I proceed by way of
101. In case I am wrong and in any event out of an examination of those steps, as they broadly
deference to the arguments advanced, I go on to appear from the evidence of Mr Lumley and
consider whether the Borealis reaction to the drop Professor Davies.
in pH levels and the triggering of the pH alarm, if 106. I consider, first, the adding of ammonia. I
unreasonable, broke the chain of causation. Here, have no hesitation in preferring the evidence of
without hesitation, I conclude it did not. Professor Davies to Mr Lumley; there was, simply,
102. First, I did not understand the Geogas sec- no or no proper basis for immediately increasing
ondary case to be advanced on the basis that the the flow of ammonia to the maximum; any addi-
Borealis reaction was reckless (as distinct from tions would or would likely have been incremental.
unreasonable). For the avoidance of doubt, any The fact that a pH of more than 7 was a concern
such case would have been hopeless. The absence would also have told against an immediate increase
of recklessness is itself a significant conclusion, of the flow to the maximum. Thereafter, the point is
favourable to Borealis, even if (as discussed above) to a degree double edged, for both parties. The
it is not by itself sufficient to dispose of the Geogas more the addition of ammonia increased the pH,
secondary case. the more likely it would be that to some extent,
103. Secondly, on the facts already found, while the addition of ammonia masked the presence of the
this is not a horns of a dilemma case, as in The contaminants in the system. The less it did so, while
Stork (supra), it is also far removed from the facts underlining that the addition of ammonia by itself
of Lambert v Lewis (supra) where the defect in would not have achieved significant results, the
the coupling was, so to speak, staring the farmer in more it would have prompted further consideration
the face and the facts of Schering (supra), where of the situation.
[2011] Vol 1 LLOYDS LAW REPORTS 501

QBD (Comm Ct)] Borealis v Geogas Trading [GROSS LJ

107. In my judgment, the addition of ammonia improvement in pH levels. The conclusion would
would not have had any significant effect in reduc- have been that there was an acid in the system and,
ing the damage suffered especially where the logically, the inquiry would have been as to the
damage most mattered, in the area of the primary source of the acid. I am not sure that the connection
heat exchangers. Having regard to the evidence of to the goods (and hence the feedstock to the cavern)
Dr Brisdon (an expert called by Borealis in the field would have been quite so straightforward and quick
of chemistry) and Professor Davies, the relevant as argued by Geogas; nor for that matter do I think
reaction depicting the addition of ammonia to it would have been as complex as suggested by
hydrogen fluoride, producing ammonium fluoride, Borealis, in the light of the observations in the
is: HF + NH3 = NH4F; however, this reaction Report (set out above) as to the typical timescale for
cannot take place at temperatures above 100C as observing the effects of new feed.
ammonium fluoride disassociates at such tempera- 111. If, however, a connection had been made
tures. Accordingly, no additional amount of ammo- between the low pH readings and the goods, then,
nia could have protected the primary heat in agreement with Ms Buehrlen, I do think that
exchangers (where the temperature of the water considerable time would have been taken thereafter,
entering the exchangers under pressure is about while the acidity was attributed to the level of
105C) from the corrosive effect of the HF. As oxygenates in the goods. It is to be remembered that
Professor Davies put it: the weak acids normally present in the feeds and
. . . the HF cannot be neutralised at the which the pH system is designed to detect are a
entrance to the [primary] exchanger. consequence of the presence of oxygenates in the
It doesnt matter how much ammonia you put feeds. Both Professor Davies and Mr Lumley stated
in because it is not going to work if it is or agreed in cross-examination that it would have
unstable. been reasonable for Borealis to have linked the drop
in pH with the high oxygenates content of the
If that is the case you must always have the
goods. As already foreshadowed, Professor Davies
risk of corrosion at the entrance to the [primary]
would have reached that conclusion himself. In
exchangers . . . if HF is present.
re-examination Mr Lumley, reminded that the aver-
In passing, it may be thought that this difficulty, age oxygenates content of the four tanks of the
by itself, serves to illustrate the fact that the pH vessel was less than the Borealis 200 ppm accep-
alarm system was not designed for dealing with the tance criterion and that therefore the cargo had
problems posed by the introduction of an acid such been approved for unloading retreated somewhat
as HF into the system. from his answers in cross-examination.
108. If an addition of ammonia had neutralised 112. A clear perspective is necessary. In my
HF it would have done so in the area of the secon- view, Geogas was right to insist that the average
dary exchangers (where the temperature range was level of oxygenates in the goods was within the
some 58 to 35C), producing some reduction in Borealis acceptance parameters (not more than 200
damage but also increasing to some extent the ppm) otherwise discharge of the goods would
pH and, in so doing, masking the corrosive attack in likely not have taken place. That said, Borealis was
the areas of the highest temperatures. That said, right to underline that the oxygenates level was
though the matter is to an extent speculative, on all high in that it was significantly above the norm
the evidence, my inclination is that an increase in of cargoes for feedstock deliveries received by
ammonia would not have significantly increased Borealis at the plant over the period 14 January to
the pH level. 12 September 2003. A study of the cargoes deliv-
109. Pulling these threads together, while the ered over that period shows that the goods con-
addition of ammonia would have been an entirely tained the second highest average level of
understandable step to take in response to a fall in oxygenates, exceeded only by the Stanlow cargo
pH, I conclude that it would not on its own have (referred to above). The Stanlow cargo had oxygen-
averted the physical damage suffered at the plant. ates ranging from 200 to 229 ppm; the range for the
Its contribution to the Geogas secondary case must goods was 130 to 225 ppm; the average of all
be assessed on effectively the converse assumption; deliveries over this period was 59 ppm (including
namely, that the addition of ammonia would not the Stanlow cargo and the goods) and 31 ppm for
have had a significant effect in raising pH and so the remaining 39 deliveries if the Stanlow cargo
would have prompted further consideration as to and the vessels cargo are excluded. Moreover, as
the nature of the problem. canvassed earlier, the presence of these oxygenates
110. I turn next, therefore, to the position reached in the goods disclosed a breach of contract.
when it was ascertained that the pH readings were 113. I do not overlook Mr Ashcrofts submission,
accurate and that despite the addition of ammonia based on the reaction of witnesses from the plant
up to the maximum there was no discernible (Messrs Hedvall and Andersson) that, as the
502 LLOYDS LAW REPORTS [2011] Vol 1

GROSS LJ] Borealis v Geogas Trading [QBD (Comm Ct)

drop in pH was not explicable by reference to Against this background, Mr Ashcroft was, in my
normal operating conditions, it was unrealistic to judgment, realistic when he accepted in his closing
postulate oxygenates as the likely explanation for oral submissions that:
the fall in pH. Nor do I overlook the data put . . . the meat of this secondary case . . . as
forward by Mr Ashcroft as suggesting that the pH the evidence has turned out, is not so much in
fall compared to other deliveries could not be relation to the costs of the physical repairs . . .
ascribed to oxygenates; in this regard, however, Mr
Ashcroft both accepted that he had not put this data 116. The real meat of the Geogas secondary
to Professor Davies and, by way of a qualification, case, Mr Ashcroft went on to contend, related to the
that the data he relied upon could not be simplist- substantial loss of profit claim for September 2003.
ically interpreted. I take all this into account. Hav- I shall deal with that in a moment but I must first
ing done so and stripping the matter of all deal with the Borealis case as to E and G units
hindsight, I am of the view that if the problem had which sustained (very limited) damage, having
been escalated up the Borealis hierarchy (as the come online at about 03.00 on 15 September. Here,
Geogas secondary case assumes), so the question of Mr Ashcroft submitted that if there was force in the
oxygenates would indeed have loomed large. The Geogas secondary case other than in his timeline
presence of HF would not have occurred to anyone. argument, then such loss as related to these units
They would instead have begun their consideration would have been avoided; they ought not to have
by reference to the available analyses. On those been exposed to contaminated feed at all. For the
analyses, the presence of oxygenates would have reasons already given, if I am right about Borealiss
been conspicuous. Suffice it is to say that some conduct not being unreasonable and not breaking
considerable time would likely have elapsed and, to the chain of causation, this submission too must
my mind, quite properly, while this topic was can- fail. But in any event, as it seems to me, if the
vassed. No doubt in time, the conclusion would matter is only to be considered once the gas alarm
have been reached that the explanation could not lie had sounded, it is unrealistic to castigate as unrea-
with oxygenates but time is critical for the Geo- sonable the steps taken by those at the plant after
gas secondary case to have any practical impact. 20.00 on 13 September. No such case was devel-
114. It only needs to be kept in mind that for the oped on the evidence and, understandably, at that
feedstock to be changed decisions needed to be time, attention had shifted to other matters.
taken that the drop in pH was alarming; that the pH 117. I come finally in this chapter to the submis-
readings were accurate; that the reason for the drop sion that the September 2003 loss of profit claim
in pH, which additions of ammonia had failed to should reasonably have been avoided. This argu-
reverse, was an acid in the system; that the acid was ment was advanced by Mr Ashcroft in these
linked to the goods; that the explanation did not or terms:
could not be assumed to lie in oxygenates. All this
would have involved the matter moving from the . . . there is no reason to conclude that there
operators to the supervisors, via a special request to were any holes in the heat exchanger tubes any
the laboratory and then further up the organisation significant time before the gas alarm was trig-
chain to plant management. The decision to change gered. If the feeds had been changed before there
feedstock was not one to be taken lightly. were holes in the tubes, the probability . . . is
that production would have continued using
115. For my part, I regard the notion that within perfectly acceptable uncontaminated feeds which
10 hours (or anything like it) of the pH alarm being would cause no further damage to the tubes
triggered a decision would have been taken to for the balance of September . . .
change the feed as arbitrary and artificial in like
measure. Bearing in mind that the titanium tubes ...
needed replacing once 20 per cent damaged, it can If they were not leaking . . . there would have
readily be seen that the Geogas secondary case been no reason to stop.
(even if otherwise well-founded) was unlikely to Developing this submission, Mr Ashcroft con-
avoid any or significant physical damage. Moreo- tended that the entire September 2003 loss of profit
ver, as perforations were present in the tubes by or claim could have been avoided if he was right as to
at 20.00 on 13 September hence the sounding of a change of feed within 22 hours of the triggering of
the gas alarm and as the minimum time for the pH alarm (ie, by 13.20 on 13 September). Even
changing the feedstock was 12 hours, it seems to if I was against him on that but concluded that there
me that the Geogas secondary case could not have should have been a change of feed by (say) 18.00
avoided physical damage to the plant unless a final on 13 September, then he submitted that the same
decision to change the feedstock had been taken by conclusion should be reached. It could not be
08.00 on 13 September. But that timescale, for assumed that the tubes were significantly holed
the reasons already given, I regard as unrealistic. before 20.00 on 13 September otherwise the gas
[2011] Vol 1 LLOYDS LAW REPORTS 503

QBD (Comm Ct)] Borealis v Geogas Trading [GROSS LJ

alarm would have sounded earlier. Once the feed (ii) Secondly, it was said that losses due to the
had been switched, there was, he said, no reason to non-availability of the cavern were too remote:
suppose that the tubes would have been perforated Such losses are too remote in law to be
at 20.00 on 13 September, or at all. recoverable. No losses were suffered until
118. With respect, I am unable to accept this 2004. It was not within the reasonable con-
submission. First, for reasons already fully dis- templation of G that the cavern was likely (or
cussed, I am not persuaded that there was unreaso- not unlikely) to remain unusable into 2004,
nableness, still less unreasonableness breaking the nor that any inability to use the cavern would
chain of causation, prior to 20.00 on 13 September. be likely (or not unlikely) to result in a loss of
Secondly, I think the case is speculative as to profits. It is not suggested that G had any
whether the perforations would have been avoided knowledge of Bs practice of stockpiling
if there had been a change of feed close to 20.00 on cheap butane in the autumn and winter
13 September. Thirdly and in any event, Ms Buehr- months nor of the complicated manner in
lens succinct response was as follows: which B juggled different feedstocks to maxi-
To suggest that the probable consequence of mise revenue. Further, the losses in fact suf-
discovering that your plant has been subjected to fered were due to a particular combination of
a strong acid for 22 plus hours and to then con- the movements in relative market prices of
tinue at full production ignoring that fact, not different feedstocks, customer requirements
even looking at your equipment to discover the relating to the end product and the relative
level of damage . . . we say cannot possibly be yields of different feedstocks . . . Such losses
the probable consequence of ceasing to use the were entirely unpredictable and unquantifi-
LPG shortly before the perforations occur. able. They are not a type or kind of loss that
One could imagine the scenario in which would follow ordinarily, in the great multitude
Borealis were to conduct itself like that and what of cases. They are not a type or kind of loss for
would be said if two weeks later there was sud- which G can reasonably be taken to have
denly a major incident arising out of the fact that assumed responsibility.
these pipes have simply been allowed to stay in 122. By way of explanation as to the September
situ with nobody doing anything about it. 2004 loss of profits, this head of argument relates to
Suffice to say that I entirely agree; notably, this the reinstalling of heat exchanger units E and G. It
case was not explored with the Borealis witnesses will be recollected that these units were brought
in cross-examination. online from 03.00 on 15 September 2003. As a
119. It follows that I am unable to accept that the result of the incident, they were disconnected in
steps proposed in the Geogas secondary case would March 2004 for inspection and were reinstalled
have successfully avoided loss, whether physical or put neutrally at a time when other works were
consequential. I accordingly dismiss the Geogas done in September 2004. The argument here is
secondary case. It follows that Borealis is entitled purely one of remoteness; submissions that this loss
to recover the September 2003 loss of profit, agreed is not recoverable by virtue of the Geogas secon-
at 2,902,237. dary case have already failed; submissions that this
loss is not recoverable because other works were in
Issue (II): remoteness of damage any event undertaken in September 2004 will be
dealt with below. The amount in question is rela-
120. In the event, this is an issue falling within a tively small, some 72,000.
narrow compass and which can be taken very 123. As to losses due to the non-availability of
briefly indeed. the cavern, these relate to two distinct, if not unre-
121. As ultimately put by Mr Ashcroft in his lated, heads of claim, amounting in total to
written closing submissions, the Geogas case on 938,000 (agreed as a figure). The first, concerns
remoteness was as follows: the loss of use of the 32,000 mt-odd of butane stock
(i) First, it was contended that the September that was in the cavern. The second, arises out of the
2004 loss of profit was too remote: inability to buy and crack butane after the existing
Any loss of profits occurring almost a full butane stock had been used up, because of dealing
year after the incident and many months after with the heel of the contaminated product. The
all repairs had been completed would be too focus here is on remoteness only. The Geogas sub-
remote in law to be recoverable. It is not a type missions as to a failure by Borealis to mitigate are
or kind of loss that would follow ordinarily, in dealt with below.
the great multitude of cases. It is not a type or 124. With great respect to Mr Ashcroft, these
kind of loss for which G can reasonably be valiant submissions lacked substance. As to the lost
taken to have assumed responsibility. profits in September 2004, it was perfectly likely,
504 LLOYDS LAW REPORTS [2011] Vol 1

GROSS LJ] Borealis v Geogas Trading [QBD (Comm Ct)

as Ms Buehrlen submitted, that if a contaminant that challenge was later abandoned. The loading of
was introduced into the plant that the equipment the cargo pursuant to this contract was not ulti-
would need to be inspected and that production mately completed until 21 January 2004. One day
would be lost when taking such equipment offline before that, on 20 January 2004, Borealis concluded
and bringing it back online. Whichever test of a contract for the import of 3,300 mt of butane (+/
remoteness of damage is applicable (see above), 5 per cent), at a price of US$327 pmt. This ship-
Geogas seems to me to be plainly on the wrong side ment was delivered on 29 January 2004 (3,266 mt
of the line. Moreover, as a question of remoteness, to which 871 mt of propane were added). Under-
it cannot matter whether the E and G heat standably, Borealis was concerned that the cavern
exchanger units were reinstalled in March or Sep- contents (ie, the heel after the disposal to Statoil) as
tember 2004. diluted by this shipment were safe for cracking;
125. Turning to the losses due to the non-availa- vessel and cavern samples were accordingly taken
bility of the cavern, again, with respect, this does and analysed (externally) by Saybolt. On 10 Feb-
not seem to give rise to a question of remoteness at ruary 2004 Borealis decided that at least another
all whichever test is applied. The introduction of 4,000 mt should be imported to further dilute the
goods heavily contaminated with fluorides was contents of the cavern before cracking. Some 14
obviously likely to result in contamination of and days followed before, on 24 February 2004, Bore-
damage to the pre-existing contents of the cavern. alis concluded two contracts. The first, a contract
Insofar as Mr Ashcroft suggested that this loss with BP, at US$315 pmt, produced a delivery on 2
arose from Borealiss inability to buy in replace- March of 5,018 mt (to which 1,896 mt of propane
ment butane in September 2003 without loss, it were added); vessel and cavern samples were again
seems to me that the point becomes no stronger; the analysed. The second, a contract with Shell, at
type of loss was plainly likely; there is no require- US$317 pmt, was for delivery of 20,600 mt during
ment that liability depends on Geogas foreseeing or the period 14 to 18 March. On 9 March, satisfied
taking responsibility for its precise manifestation. with tests of the fluoride content, Borealis proposed
Equally, in my judgment, the introduction of heav- to start cracking but with one LPG furnace only; the
ily contaminated goods was likely to result in the use of one furnace was a matter of prudence but
loss of use of the cavern while the contamination entailed a loss of profit as the best choice would
was dealt with. Even assuming in Mr Ashcrofts have been to use two LPG furnaces. Independent
favour that, as he put it, the extent of the loss
advice at the time remained cautious and con-
involved a complex equation, that is neither here
cerned. On 12 March Borealis did proceed and
nor there. For completeness, I do not think that, to
which Mr Ashcroft referred, advanced the re-started cracking, albeit using one LPG furnace
argument. only. On 20 and 21 March Borealis started using
two furnaces, so bringing this chapter to an end.
126. No further elaboration is required. The
remoteness defence fails. 129. To my mind, working through this chronol-
ogy is invaluable. First, even if the notion that
Borealis should have bought in one single cargo
Issue (III): mitigation sufficient by itself to dilute the heel appropriately
127. In broad terms, Mr Ashcrofts attractively- had practical merit without the benefit of hind-
presented argument was that Borealis had unrea- sight it was in no sense unreasonable not to have
sonably delayed replenishing the cavern and that done so. On any view, such a purchasing strategy
Geogas should not be liable for losses resulting would have involved buying in a larger quantity of
from such errors or failings on the part of Borealis. butane (whether 20,000 mt plus or about 11,000 mt
The Geogas case was that the cavern should have of butane, depending on which variant of the Geo-
been ready for use by 1 February 2004, or such gas case is under consideration) at a winter seasonal
intermediate date as the court thought appropriate, high a matter evidenced even by the difference
whereas it was in fact only ready on 21 March between the January and February purchase prices
2004. The amount in dispute was some 238,000 at of the cargoes bought in. Such a strategy would
most and less if it should be held that there had have risked increasing the overall loss. Secondly,
been a failure to mitigate but with reference to a Borealis had been seared by the experience of the
date later than 1 February 2004. contaminated goods. If its subsequent approach dis-
128. In considering this criticism of Borealis it is closed caution, that was eminently understandable.
necessary to keep well in mind what Borealis did Thirdly, against this background, I can see no
do. The contents of the cavern were sold to Statoil proper ground whether commercial or technical
on 5 January 2004. Originally, this disposal was one for criticising the Borealis approach of replen-
of the main planks of the Geogas case that Borealis ishing the cavern in stages, having samples inde-
had failed to mitigate its loss; but, as foreshadowed, pendently analysed as it proceeded. Fourthly, I can
[2011] Vol 1 LLOYDS LAW REPORTS 505

QBD (Comm Ct)] Borealis v Geogas Trading [GROSS LJ

see nothing wrong with the timing of the first pur- ondly, despite the field in which she was called to
chase, that contract having been entered into even give expert evidence, it transpired that Ms Jago had
before conclusion of the loading of the Statoil never traded LPG or butane. This lack of experi-
cargo. It follows that the Geogas submission that ence did not inhibit Ms Jago from expressing her
the cavern ought to have been available by 1 Feb- opinion on a variety of issues which called for such
ruary is, with respect, entirely unrealistic. The mit- experience. In the light of these reservations, even
igation argument, if it is to prevail at all, can only though Ms Jago may well have had some experi-
be for a significantly lesser period than that con- ence in dealing with heels and blending, I confess
tended for. that I would in any event have been unable to place
130. Pausing there, I am not sure that these any serious weight on her evidence, at least unless
conclusions involve a rejection of Ms Jagos evi- it was agreed or uncontradicted. In the event, for the
dence but, for reasons to which I shall come in reasons given earlier, I do not think that Ms Jagos
a moment, if they do then I am not at all deterred. evidence takes the present issue any further.
The key passage in Ms Jagos evidence seemed to 132. What remains of the Geogas case really
me to be the following: comes down to two points: (1) a criticism that
. . . during the early part of January, they Borealis waited until 10 February before taking a
should have been looking at availabilities of decision to purchase additional cargo; (2) a failure
butane to blend with what they could be fairly thereafter to conclude any purchase contracts until
certain was going to be some heel left there. So 24 February.
by the time they were getting close to completion 133. Pausing here and as foreshadowed, it may
of lifting of the cargo to Statoil, they should have be noted that this claim is necessarily restricted to a
been close to purchasing a cargo of butane to small sum only. The maximum period in issue
blend in with what would have been left in the would have been some three weeks the 10 to
cavern . . . 12-day period between discharging the first incom-
ing cargo and determining to order more, coupled
...
with the fortnights wait before concluding the sec-
. . . they would have to wait until they knew ond purchase contract (followed, it is to be remem-
what the heel was before they could finally make bered, by prompt delivery). I am, in any event,
the purchase, but they could still be determining inclined to think that those two periods could not
what cargoes were available prior to that . . . have been added together simplistically. It follows
With respect, given the timing of the first pur- that on no view could Geogas realistically have
chase of butane (the day before completion of the expected the cavern to be ready before 1 March
loading of the Statoil cargo), these observations 2004 and any successful claim for mitigation would
hardly advance the Geogas case that Borealis failed have been for some reduced period, between a date
in its duty to mitigate. They would only go some- later than 1 March and 21 March.
where if allied to other criticisms of the Borealis 134. It is next pertinent to inquire as to the
purchasing strategy which I have already rejected. evidential basis for the Geogas case of a failure to
131. There are, however, with regret, other reser- mitigate bearing in mind that, on this issue,
vations I have as to Ms Jagos evidence. Ms Jago Geogas bears the burden of proof. Nothing in Ms
was called by Geogas as an expert in the fields of Jagos evidence assists on these points. So far as
LPG trading or broking and as a market analyst. My concerns Mr Lumley, he was asked in cross-exam-
first reservation goes to some (in fairness to Ms ination about Borealis taking until 12 March to
Jago, by no means all) of her promotional material re-start cracking; to this, he answered:
and other material in the case, which materially . . . they were slow, they could have been
misstated her qualifications. So, Ms Jago was in quicker.
places described as Dr Jago; but although Ms Asked next if he was saying that Borealis had
Jago had been a doctoral student, she had not sub- been unreasonable, he gave this reply:
mitted her thesis and was not entitled to the title No, I wouldnt say it was unreasonable.
Dr. Furthermore, she was also described as Dr
Jago LLB but she did not have the LLB qual- Plainly, that evidence provides no assistance to
ification either; she had a postgraduate diploma in the Geogas case.
law. Having regard to Mr Ashcrofts submissions, I 135. In fairness to Geogas and Mr Lumley, it
am prepared to accept that these errors came about might be said that this area, in part at least, was
through lax oversight rather than that she had delib- outside his field of expertise. But be that as it may,
erately set out to misrepresent her qualifications. In it follows that the Geogas case is left somewhat
the field of expert evidence, however, this remains bereft of evidential support.
a matter of grave concern and Ms Jago must be in 136. The reality is that the Geogas case depends
no doubt that there should be no recurrence. Sec- on gaps in or inferences to be drawn from the
506 LLOYDS LAW REPORTS [2011] Vol 1

GROSS LJ] Borealis v Geogas Trading [QBD (Comm Ct)

evidence called by Borealis. Mr Eerola was the Issue (IV): quantum


senior feedstock trader at Borealis. As to the wait
138. Although the parties undertook a consider-
until 10 February before deciding to purchase addi- able amount of work to narrow the disputes as to
tional cargo, his somewhat speculative answer was quantum, a number of issues remain. These are
that it was linked to the progress made with the first addressed here.
incoming shipment. As to the time taken until 24
February to conclude the next purchase contract, he
(1) Supplier repair costs
frankly accepted that he could not remember but
nonetheless maintained that the second cargo was 139. Borealis claims 1,332,451 in this regard.
ordered and received within the three-week period 140. Mr Ashcroft invited me to deal with this
ordinarily allowed by Borealis for sourcing head of claim on a rough and ready basis and
feedstock. argued for a 30 per cent deduction or such other
137. Somewhat on balance, I am not persuaded figure as the court thought appropriate. First, Bore-
by the Geogas case of a failure to mitigate. I do not alis had been over-inclusive in its allocation of
think that the evidence makes good a case that costs to these repairs; there was a lack of underlying
Borealis acted unreasonably; the facts that there are documentation to support this claim. Moreover,
do not speak for themselves; the inferences to be there was reason to be sceptical, having regard to
drawn from the gaps in the evidence do not point the very large claim advanced by Borealis for lost
sufficiently cogently to unreasonable delay on the profits in November 2003 and subsequently aban-
part of Borealis. It would not be right to be unduly doned. Secondly, he relied on Mr Lumleys evi-
dence for the proposition that Borealis had
precise in assessing every step taken by Borealis in
(unreasonably) failed to negotiate a 5 to 10 per cent
dealing with the contaminated cavern and bringing
discount.
it back into use. I keep in mind in addition to the
authority cited earlier the trenchant observations 141. I think that there is much practical good
of Lord Loreburn LC in Lodge Holes Colliery Co v sense in Mr Ashcrofts call for a rough and ready
Wednesbury Corporation [1908] AC 323, at approach to be adopted. Whether it entitles Geogas
to anything like the deduction for which he con-
page 325:
tended, may be another matter.
Now I think a Court of Justice ought to be 142. To begin with, I am wholly unable to accept
very slow in countenancing any attempt by a Mr Lumleys evidence that Borealis had unreason-
wrong-doer to make captious objections to the ably failed to negotiate a 5 to 10 per cent discount.
methods by which those whom he has injured Mr Lumley had said that Borealis was not to be
have sought to repair the injury. When a road is given a blank cheque. It should have nibbled at the
let down or land let down, those entitled to have prices quoted by suppliers. From his experience, a
it repaired find themselves saddled with a busi- discount of the order of 5 to 10 per cent should have
ness which they did not seek, and for which they been negotiated. To my mind, Mr Lumleys evi-
are not to blame. Errors of judgment may be dence simply failed to grapple with the following
committed in this as in other affairs of life. It considerations:
would be intolerable if persons so situated could (i) Borealis was seeking to effect repairs under
be called to account by the wrong-doer in a pressure of time. The daily cost to Borealis of
minute scrutiny of the expense, as though they having the plant out of action was put at several
were his agents, for any mistake or miscalcula- hundred thousand euros per day.
tion, provided they act honestly and reasonably. (ii) The Borealis predicament was known to
In judging whether they have acted reasonably, I relevant suppliers. Moreover and as Mr Lumley
think a Court should be very indulgent and accepted in cross-examination, he was in no
always bear in mind who was to blame. position to challenge the undisputed evidence of
I further keep in mind that Borealis had no Mr Hermansson (of Borealis) that at the time of
motive for not getting on with restoring the cavern Borealiss 2003 turnaround similar maintenance
into service; tellingly, the events in question took projects were also being carried out by other
place in 2004; any recovery from Geogas will not industries in the vicinity so that the number of
be received until 2010. I think on this issue, Mr available contractors was limited.
Lumleys opinion captures the essence of the mat- (iii) In any event, some of the supplies were
ter: the Borealis reaction was slow; it could have called down under a long-term framework agree-
been quicker but it was not unreasonable. That is an ment which left no room for item-by-item
end of the Geogas case of a failure on the part of haggling.
Borealis to mitigate its losses in connection with the With respect to Mr Lumley, I think his evidence
cavern. in this regard was without substance.
[2011] Vol 1 LLOYDS LAW REPORTS 507

QBD (Comm Ct)] Borealis v Geogas Trading [GROSS LJ

143. I turn to the question of allocation. In gen- time dealing with the heat exchanger damage, they
eral, I accept the accuracy of the Borealis account- would have been engaged on revenue-earning
ing system, under which costs were allocated to activities.
particular work orders. To my mind, the detailed 147. It was common ground that the relevant
material contained in the Scott Schedule, in its final principles appear from the following passage in
form and as attached to the Borealis closing sub- Aerospace Publishing Ltd v Thames Water Utilities
missions (the Scott Schedule), was of consider- Ltd [2007] Bus LR 726, per Wilson LJ at para
able assistance in this regard. Accordingly, I can see 86:
no basis for any significant discount. That said, I do
have regard to the abandoned claim for November I consider that the authorities establish the
2003 profits. I also have in mind that in the course following propositions. (a) The fact and, if so,
of her closing submissions, Ms Buehrlen very prop- the extent of the diversion of staff time have to be
erly conceded that she could not support some properly established and, if in that regard evi-
55,000 of the claim. In works of this scale and dence which it would have been reasonable for
nature it is very difficult to guard against any inac- the claimant to adduce is not adduced, he is at
curacies creeping in. I see no unfairness to Borealis risk of a finding that they have not been estab-
if I make some limited allowance in this regard. lished. (b) The claimant also has to establish that
Adopting Mr Ashcrofts rough and ready approach, the diversion caused significant disruption to its
I think that an award of 1,250,000 under this head business. (c) Even though it may well be that
of claim does justice to both parties. strictly the claim should be cast in terms of a loss
of revenue attributable to the diversion of staff
(2) Personnel costs time, nevertheless in the ordinary case, and
unless the defendant can establish the contrary, it
144. Borealis claims 135,748 under this head of is reasonable for the court to infer from the dis-
claim. It relates essentially to amounts paid to its ruption that, had their time not been thus
own employees and managers in respect of the diverted, staff would have applied to activities
inspection of and repairs to the heat exchangers. which would, directly or indirectly, have gen-
This claim includes an amount of basic rate time erated revenue for the claimant in an amount at
where wages would have had to be paid to employ- least equal to the costs of employing them during
ees in any event but as they were diverted from that time.
their ordinary duties, additional costs were incurred
by way of payments to sub-contractors who ful- See too, Al Rawas v Pegasus Energy [2009] 1 All
filled their duties. The claim has been restricted to ER 346, especially at paras 22 and 23; and 4 Eng
the employees basic rate time given the difficulties Ltd v Harper [2009] Ch 91, especially at para 40.
of quantifying the increased costs relating to sub- 148. Insofar as Geogas denies this claim in its
contractors and given that sub-contractors time entirely, it seems to me that its approach is, with
is more costly than the time of the employees in respect, unrealistic. I am satisfied on the totality of
question. The sum claimed here also includes a the evidence helpfully summarised in both the
round sum in respect of management time. Borealis opening and closing written submissions
145. As appears from the Scott Schedule, Geogas (and which need not be set out here), that there was
disputes this amount on the following grounds: significant and major business disruption flowing
from the Geogas breach of contract. Such disrup-
(i) Salaries would have been incurred in any
tion inescapably consumed staff and management
event.
time which was thus lost. I think that any Geogas
(ii) There was no proven linkage to the heat insistence on further detail risks a disproportionate
exchanger damage. approach to proof of damage. As Jack J observed in
(iii) There is no proof of increased sub-con- Al Rawas v Pegasus Energy Ltd (supra), at para 23,
tractors costs. in this area, the application of common sense
(iv) There is no proof that staff or management may fill a gap in the evidence. I am also unable to
were diverted from revenue-generating accept Mr Ashcrofts submission that the inference,
activities. referred to by Wilson LJ under (c) in the passage of
146. Developing these grounds orally, Mr Ash- his judgment in Aerospace (supra) cited above, is
croft emphasised two matters in particular. First, he negated because of the focus on the turnaround; that
submitted that a significant part of the claim was for is to take altogether too narrow a view of revenue-
unproven sub-contractors costs, dressed up as a generating activities.
claim for personnel costs. Secondly, he contended 149. However, it is also the case that there is a
that as the plant was focused on the planned Octo- good deal of the broad brush in this Borealis claim
ber turnaround, no inference could be drawn that if as Borealis in effect itself avers. There are diffi-
management and staff had not had to spend more culties of proof relating to the correlation of the
508 LLOYDS LAW REPORTS [2011] Vol 1

GROSS LJ] Borealis v Geogas Trading [QBD (Comm Ct)

expense on sub-contractors and the additional work expenditure and loss. It may not be actual money
done by staff. There must be recognition of the fact paid out to any particular person, but these
that wages would have been incurred in any event. expensive appliances cannot be utilised without
As Borealis itself acknowledges, the figure for some loss.
management time is a round figure. Doing the best 153. Mr Ashcroft submitted that there was no
I can on the evidence, I am satisfied that Borealis evidential basis for a finding here that the use of the
suffered a loss in this regard of at least 75,000 and Borealis equipment could not take place without
it is that sum I propose to award under this head. pecuniary expenditure and loss. I disagree. The
logic of Bateson Js reasoning is, with respect,
(3) Own equipment used to effect repairs inherently attractive, practical and, to my mind,
applicable here at least in the absence of evi-
150. Here, Borealis claims 18,630. The basis of dence or a compelling inference to the contrary.
the claim lies in Borealiss use of its own equip- The use of the equipment carries a cost. However,
ment for 12 hours a day on 14 days to repair the Mr Ashcroft is plainly right in submitting that Bore-
heat exchangers. Borealis contends that this use alis cannot recover for the daily rate it would have
gives rise to a recoverable loss, quantified as the paid had it hired the equipment; that is simply not a
same amount that an outside contractor would have loss it suffered. Borealis is accordingly restricted to
charged by way of a daily rate for the equipment in the operating cost of the equipment in question; that
question. cost cannot be equated with the cost of hiring the
151. Geogas resists this claim, submitting that equipment it must necessarily be significantly
Borealis has not proved that costs were incurred or less. Doing the best I can, I assess the operating cost
loss suffered. In any event and though the of the equipment as 6,000.
amount of the claim is agreed as a reasonable figure
for the hire of such equipment the claim could
only lie (if at all) for the cost of operating the (4) Warehousing cost of corroded titanium tubes:
equipment not the (notional) hire cost. 19,066
152. Both parties relied on the decision in The 154. I confess to some regret that the parties did
West Wales [1932] P 165. That case concerned the not find it possible to reach agreement on an item
battleship HMS Nelson; she had been damaged in a such as this. I take it summarily. Borealis was
collision and was put into a naval drydock for entitled to store these tubes while the litigation was
repairs. In assessing damages, the Registrar allowed pending; it is anything but fanciful to suppose that
nothing in respect of the use of the dock and cranes, a point may have been taken by Geogas had Bore-
on the ground that the Admiralty had suffered no alis not done so. I think this (external) cost is
pecuniary expenses or loss. Bateson J remitted the allowable. Geogas submitted that a deduction
case to the Registrar for reassessment, holding that should be made for the scrap value of the tubes.
the ship had occupied the dock and used the cranes, There does come a time when common sense must
to the exclusion of other vessels and some allow- prevail. I decline to investigate or to require the
ance was therefore to be made to the Admiralty in parties to investigate the scrap value of these tubes.
respect of these items. Bateson J said this, at I allow the claim in the full amount of 19,066 on
page 168: terms that, on payment of this claim, Geogas shall
The learned registrar has allowed nothing for be at liberty, if it so desires, to take delivery of the
either of these items. I think it is clear that some- tubes and to dispose of them as it sees fit. In the
thing must be allowed. What the figure may be is order, a fallback provision should be made for
a matter for him to decide, but I do not think it Borealis to dispose of the tubes within a given
can be right to say that the Admiralty have suf- period of time, should Geogas choose not to take
fered no loss by giving up their dry dock and by delivery of the tubes.
using their cranes in doing these repairs. The
Nelson occupied the dock to the exclusion of (5) Spare parts: 19,420
other ships, and made use of the cranes and so on
for the purpose of docking and cleaning and 155. This is a claim for consumables such as
coating the bottom, which would be necessary in breathing masks, batteries, gloves, goggles, packing
connection with these repairs. Docks and cranes materials and so on. Geogas resists this claim on the
cannot be used without expense, and there must basis that the cost of these items is not referable to
be some damage to the Admiralty from these its breach of contract. I adopt the same approach as
matters. The learned registrar says that in respect I did in connection with the allocation question
of these there was not a pecuniary expenditure or more generally. I think there is sufficient evidence
loss and, therefore, these items are not allowable. of a linkage to justify the claim generally but
I think that is wrong. I think there was pecuniary that some allowance should be made for inevitable
[2011] Vol 1 LLOYDS LAW REPORTS 509

QBD (Comm Ct)] Borealis v Geogas Trading [GROSS LJ

errors in allocation. I allow this claim but only in undertake those other works at that particular
the amount of 15,000. time.
159. These circumstances are such that guidance
(6) Loss of profit September 2004 may usefully be obtained from a number of Admi-
ralty (and commercial) cases, most simply sum-
156. The hard-fought and already much dis- marised as follows. Let it be assumed that a ship is
cussed issue which arises under this heading con- damaged in a collision. She is not immediately
cerns a relatively small sum of money, 72,202, rendered unseaworthy but the repairs need to be
agreed as a figure, concerning loss of profit incurred undertaken at some convenient time. At the time
in September 2004 when reinstalling heat exchang- when the collision repairs are undertaken, the
ers E and G. As will be recollected, these heat owner takes the opportunity of undertaking other
exchangers were disconnected in March 2004 as a works, not immediately necessary. As I understand
result of the incident. The issue arises because, over the authorities, the tortfeasor will be liable for the
the same period in September 2004, Borealis entire period of detention and the owner will not be
effected repairs to other equipment at the plant. obliged to give credit for the time required by the
157. Geogas contends that no loss of profit is unrelated repairs. The position would be different if
recoverable in respect of this period, as, given the it was necessary to undertake the unrelated repairs
other works done to the acetylene reactor (uncon- at that time. See the very helpful summary in
nected with Geogass breach of contract), there McGregor on Damages, 18th Edition, at para
would have been a similar loss of production 32-037, together with the authorities there cited; see
regardless of the reinstallation of the heat exchang- too, Elpidoforos Shipping Corporation v Furness
ers. Borealis contends that, as a matter of law, it is Withy (Australia) Pty Ltd (The Oinoussian Friend-
entitled to the entire period of lost production; that ship) [1987] 1 Lloyds Rep 258, especially at
it did other works is neither here nor there. How- pages 263 to 265.
ever, as a pragmatic matter, it is content to attribute 160. In my judgment, the key to this issue is that
the lost production over the three-day period in whenever the heat exchangers were reinstalled
question equally between the heat exchangers and there would, in all probability, be a loss of produc-
the acetylene reactor. tion. On the face of it, therefore, Borealis ought to
be entitled to recover for the loss suffered when the
158. In cross-examination, Mr Eerola explained
reinstallation took place. No doubt if it had been
the position as to the various works as follows:
necessary to do other works at the same time, then
. . . we had two parallel maintenance works Geogas would have had a good answer to any such
going on at the site . . . both would have resulted claim. But that was not this case; the evidence does
. . . [in] . . . a production loss alone but since not show that the other works Borealis undertook in
they were carried out in parallel the production September 2004 had to be done then. On that foot-
loss that resulted was clearly less than in the case ing, Borealis is in principle entitled to recover for
they would have been done at a different time the lost production in September 2004. As, how-
individually. ever, pragmatically (and attractively) Borealis has
As it seems to me, on such evidence as there was: indicated that it is content to claim for only half the
(1) Borealis needed to reinstall the exchangers at time in question, I shall allow the claim to such
some time and whenever it did so, production extent only, namely in the amount of 36,101.
was likely to be lost; (2) the other works undertaken 161. I shall be grateful for the assistance of
in September 2004 were conveniently undertaken counsel in drawing up an appropriate order and as
then but it was not necessary for Borealis to to all questions of costs.

You might also like