Professional Documents
Culture Documents
F16 Midterm Solutions
F16 Midterm Solutions
F16 Midterm Solutions
Crashing activities in project management is based on two criteria (1) the cost
2) T F of crashing an activity and (2) whether or not the activity is on a critical path.
Among these criteria the first always takes precedence.
Forecasts for group of items tend to be less accurate than forecasts for
5) T F
individual items.
The order qualifiers for a company are those characteristics that cause
6) T F
consumers to actually purchase the product or service.
If the average throughput (flow) rate of a process increases but the average
9) T F
inventory remains constant, the average throughput (flow) time will increase.
The cost of the project is the sum of the costs of the activities on the critical
10) T F
path.
1
1) To increase the responsiveness of forecasts computed based on the moving average
technique, the number of data points should be:
a) Increased
b) Decreased
c) Multiplied by a larger alpha
d) Multiplied by a smaller alpha
e) None of the above
2) In project management, a critical path activity
a) moving averages
b) single exponential smoothing
c) double exponential smoothing
d) None of the above
4) When are the conventional NPV and the Real Options Value exactly identical?
I. When the investment decision can be deferred.
II. When the volatility per period is zero.
III. When the investment decision cannot be deferred further.
IV. When the volatility per period is high.
V. None of the above.
a) I only
b) III only
c) II and III only
d) I and II only
e) V
5) Suppose that the most recent actual data for demand is observed in February 2010.
Using the double exponential smoothing technique, the forecast for August 2010 is equal
to
a) FJan.15+ 7Tjan.15
b) FFeb15+ 6*TFeb15
c) FFeb.15+ 7*TFeb15
d) FFeb15+ 5*TFeb15
e) FMarch15+ 5*Tmarch15
2
6) Given COGS = 1200 M$, and Inventory=100 M$, then what is the number of inventory
turns per month?
a) 12
b) 10
c) 5
d) 2
e) 1
7) Which of the following would not affect B in the Black-Scholes Options Formula?
a) Cumulative volatility
b) A change in the risk-free rate of return
c) Time difference between the start of 1st and 2nd stages
d) Volatility per period
e) Ability to predict the revenue of the 2nd stage
8) Bank of Montreal employs three loan officers, each working eight hours per day. Each
officer processes an average of five loans per day. The banks payroll cost for each officer
is $35 per hour, and there is a daily overhead expense of $500. Which of the following is
the multifactor productivity of loan process in terms of loans/$?
a) 0.011
b) 0.017
c) 0.025
d) 0.019
9) After crashing a project by one week by spending $500 for crashing, any further crashing
by another week (if possible) will cost:
(a) I only
(b) II only
(c) III only
(d) I or III
(e) None of the above
3
Question 2
ABC Kokia recently started producing kPhones model ultimate, and the company strategy team
derived its competitive strategy based on price, quality, and the best effort customer care
named Hey, We serve you the best. ABC Kokia priced an aggressive $300 per unit for its
kPhone ultimate models, in an effort to compete with its top rival company Kapple. The weekly
output rate of kPhone ultimate models has been variable, and the accounting department has
provided the following information about the process for the past two weeks:
Week 1 Week 2
MFP(Week 1) = 269*300/(11942+30654+10194)=1.5287
MFP(Week 2) = 323*300/(12603+36434+10736)=1.6211
b) After reengineering the manufacturing process, Mrs. Ville-Mary estimated that the average
cost of each unit of kPhone ultimate is $180 per unit (labor: $40/unit; materials: $110/unit;
and overhead: $30/unit). The selling price remained the same $300 per unit. Therefore, the
unitless multifactor productivity (considering labor + material + overhead) reaches 1.6667.
How much overhead cost per unit should be reduced in order to increase the multifactor productivity
level of 1.6667 by 5%, while keeping other costs unchanged?
Comment: Some students add 5% to 1.67 and get x=24.4. In that case, give them full points.
4
Question 3 (Forecasting):
(a) MA, Weighted MA, and Simple Exponential smoothing are right methods since it is
stated that the demand is stable.
Comment: If they answer any of them without double exponential, give them full points.
If they answer double exponential only, take off 2pt. If they answer double EX together
with other, take off 1pt.
(b)
Demand 0.5
Oct 36 36
Nov 40 36
Dec 35 38
Jan 39 36.5
Feb 42 37.75
Mar 39.875
April 39.875
(c)
Demand F T FIT
Oct 36 36 4
Nov 40 40 4 40
Dec 35 40.4 3.28 44
Jan 39 41.808 2.9056 43.68
Feb 42 43.62816 2.688512 44.7136
Mar 46.31667
April 49.00518
(d)
5
Question 4 (Process Management)
Maxs Motor Shop (MMS) is a family-run auto dealership selling both new and used vehicles. In
an average month, MMS sells a total of 160 vehicles. New vehicles represent 60% of sales, and
used vehicles represent 40% of sales. Inventory financing is a significant expense for MMS, and
so Max tries to keep inventory turns as high as possible.
a. Examining the dealerships performance over recent years, Max discovered that MMS had
been turning its inventory (including both new and used vehicles) at a rate of 8 times per
year. What is MMSs average level of inventory (including both new and used vehicles)? (3
points)
b. Max has also determined that the dealerships new and used businesses appear to behave
differently. Specifically, turns of new vehicles are 7.2 per year, while turns of used vehicles
are 9.6 per year. Holding a new vehicle in inventory for a month costs MMS roughly $175.
Holding the average used vehicle in inventory for a month costs roughly $145. What is
MMSs average monthly financing (inventory) cost per vehicle (averaged over both types)?
(5 points)
c. A consulting firm has suggested that MMS subscribe to its monthly market analysis service.
They claim that their program will allow MMS to maintain its current sales rate of new cars
while reducing the amount of time a new car sits in inventory before being sold by 20%.
Assuming the consulting firms claim is true, how much maximum should Max be willing to
pay for the service? (3 points)
Solution:
a.
ITtotal = 1/Ttotal so Ttotal = 1/8 years = 1.5 months
Itotal = RtotalTtotal = 160 vehicles/month * 1.5 months = 240 vehicles, which is the answer.
b.
Similar to part a, we have Tnew = 1/7.2 years = 1.667 months and Tused = 1/9.6 years = 1.25
months.
Total monthly financing costs then 160*$175 + 80*$145 = 28,000 + 11,600 = $39,600/month.
6
Cost per vehicle are then $39,600/month (160+80) = $165 per vehicle per month, which is the
answer.
c.
From Littles Law, cutting time 20% while holding R unchanged will reduce inventory by 20%.
From part b, average monthly financing costs for new vehicles is 160*$175 = $28,000/month. A
20% drop gives $5,600 per month, which is the answer.
7
Question 5 (Project Management)
(a)
Skipped.
(b)
The project has the following six paths and their durations:
ABDHI, Duration = 22
ABEHI, Duration = 23
ABEGI, Duration = 23
ACEHI, Duration = 22
ACEGI, Duration = 22
ACFGI, Duration=19
(c)
The normal cost of the project (sum of the costs of all activities) is $5,400.
(d)
Activity Predecessor Activity duration Activity cost ($) Crash Max Crash
(weeks) Cost/Week (weeks)
Normal Expedited Normal Expedited
A - 4 3 800 1,200 400 1
B A 3 2 1,000 1,200 200 1
C A 2 1 400 560 160 1
D B 5 3 800 1,200 200 2
E B, C 6 5 500 600 100 1
F C 3 2 200 400 200 1
G E, F 4 3 400 580 180 1
H D, E 4 3 300 310 10 1
I G, H 6 5 1000 2400 1400 1
2 500-190=310
G&H by 1 week $ 190
3 500-200=300
B by 1 week $ 200
Crash activities E, G, H, and B by 1 week each. Crashing cost of the project by 3 weeks= $490
8
(e)
Net profit= $1500- $480 = $1010. Total completion cost = 5400+490 = 5890.
(f)
a) In-house:
a. Break even occurs when (99 71) Q = 7000, at Q = 250 units.
b. Break even occurs when (99 67) Q = 12000, at Q = 375 units.
Outsource: The only breakeven point: Q = 0.
So outsourcing is better for Q between [0 280] and in-house is better for Q between
[280 - 300].
So Outsourcing better for Q in range [300 432] and in-house better for Q in range [432
600].
c) At Q = 300, In-house profit = 28*300 7000 => 1400, same profit is achieved when
At Q = 600, In-house profit = 32*600 12000 => 7200, same profit is achieved when
To make outsourcing always a better choice, they should charge 96 dollars / unit.
9
Question 7
a)
Alternative 1:
Discount
Year Investment Revenue Net Income ($m) PV ($m)
Factors
0 1 5 0 (5.00) (5.00)
NPV 6.42
Alternative 2:
Discount
Year Investment Revenue Net Income ($m) PV ($m)
Factors
0 1 5 0 (5.00) (5.00)
NPV 6.14
10
Note that NPV (Alternative 1) > NPV (Alternative 2). So, Montreal-Toronto is better than Toronto-
Montreal.
b) Based on Real Options analysis, calculate the total value of each alternative and decide
whether Alternative 1 or 2 is better for the company.
(round to the closest value, if the exact match of A or B is not found in the table)
Alternative 1:
S 14.92
X 12.35
B (T=3) 0.69
A 1.21
Alternative 2:
S 11.19
X 8.03
B (T=4) 0.8
A 1.39
11
Options Value of Montreal
Phase 4.68
Note that Total Real Options Value (Alternative 1) > Total Real Options Value (Alternative 2). Hence,
based on Real Options criterion, Alternative 1 is better than Alternative 2.
Alternative 3: The Company can delay the introduction of services in both Montreal and
Toronto by one year and will decide whether or not to start the project in year 1. If it decides to
start the project, The Company will introduce the service in Montreal and Toronto
simultaneously. The cash flows for Alternative 3 are as follows:
d) Based on real options analysis, calculate the total value of Alternative 3. Based on real
options value, compare Alternative 3 to Alternatives 1 and 2 and determine which one is
the best. (4 points)
In Alt.3, there is only one discretionary phase (without any phase to be decided at t=0);
so, the total value is equal to the real option vale of the discretionary phase.
S 29.41
X 22.91
B (T=1) 0.4
12
A 1.28
13