HabshanTechnicalServicesSubDivision

PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
1. GENERAL General BiddernotedthatmanyoftheITBdrawingsprovidedby Availability of native files on case to case basis
companyareinPDFformat,notlegibleandcannotbe and consider preparation of drawings /
convertedtoelectronicfiletobeusedduringFEEDstage. documentswhereverunavailable.
The existing drawings, documents and
Bidderunderstandsthatexistingdocuments/drawingsfor calculationsifavailableshallberetrievedbythe
theconcernedareasrelatedtoprojectwillbeprovidedto successful bidder in whatever form available.
successfulbidderineditablenativeformattocarryout Existing asbuilt / available documents relevant
furtherdesignactivity. to the scope of work shall be collected by the
successful bidder, from the site design office in
COMPANYtoconfirm. the available format. Required site visits /
engineering shall be performed to obtain the
missingdata.Itshallbetheentireresponsibility
of the FEED consultant to verify the actual
conditionsatsiteinordertocompletethework
aspersite surveyandCOMPANYspecifications.
FEEDCONSULTANTshallresolveallthedetected
discrepancies/designissuesifany.
Incasedesigncalculationsanddrawingsarenot
available,Consultantshallperformsitesurveyto
collect all required information and shall carry
out all necessary calculations, develop required
deliverable, based on Companys current DGS
andAddendums.
Bidder shall confirm understanding and
adherence.

HTSPPF110 1|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery

1.1. General Bidderunderstandsthatupdatingofexistingdocumentsis Confirmed.
limitedtothescopeoftheprojectonly.
COMPANYtoconfirm.
1.2. General Allmeetings,workshopareconsideredatCONSULTANT/ Confirmed.
COMPANYAbuDhabioffices.
1.3. ScopeofWork a. Seebelowreply
a. Consultantshallconsiderfollowingstrategyin i. Early tiein (only) to Hab II
Doc.no.PE7172
preparingfollowingEPCpackages: header: prepare an MR for
SOW001Rev0
material and construction
i. EarlytieinsforHabshan2flare packageforexecution
a. Section6.3:EPC
headerduringTotalS/Din ii. EPC for implementation of
Implementation
February2018 allotherWorks
Strategy
b. optimum overall construction plan,
ii. EPCforRECOVERINGHABSHANIII guideline construction procedures and EPC

HYDROCARBONFLAREGAS contractors scope of work is required only
THROUGHEXISTINGRECOVERY forEPCpackage
b. Section9.3:
COMPRESSORINHABSHANII 3hardcopiesofEPCtenderpackageisrequired
Construction
planningservices
b. CONSULTANTshallproposeanoptimumoverall
Confirmed
constructionplan,guidelineconstructionprocedures
andEPCcontractorsscopeofworkforeachEPC
Package.

BidderunderstandthatCOMPANYrequestonlyone(01)
EPCtenderPackagefortheproject.

HTSPPF110 2|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery

CONSULTANTwillconsidertheearlytieinsduringplant
totalS/Dandalsoshallidentifyallearlysiteconstruction
works&activitieswhenpreparingtheexecution
methodologyandtheEPCschedule.

COMPANYtoconfirm.
1.4. General Biddertobeinformedthatbeinformedthatfor
Bidderunderstandsthatalltheengineeringwillbe H3FlarepiperackwedonothavePipingGA
developedusing2DAutoCAD.3DModellingisnot routingdrawings(civilGAisavailable)only3D
envisagedintheproject. modelisavailable.PortionswhereFGRprojectis
routed,therearepipingGAs.Biddertoextract
COMPANYtoConfirm. thepipingGADsforthesubjectprojectscope
fromtheavailable3DmodelfromHabshanplant
orextractitinHabshanplantdocumentation
officeanduseitfurtheractivities.
HoweverforEPCSOW,3Dmodeltobeincluded
forareathatalreadyhave3DPDSmodel.
1.5. AppendixI: TheCONSULTANTSquoteshallincludeanallinclusive Confirmed. The contract shall be as per TSSA
INSTRUCTIONSTO bid(lumpsum)whichshouldincludeallexpenses agreement.
CONSULTANT/ includingtravelexpenses,accommodationetc.
BIDDER AnypricingschedulehasbeenprovidedbyCOMPANY.

BidderunderstandthattheprojectisaLumpSumproject.

COMPANYtoConfirm.

HTSPPF110 3|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
1.6. ScopeofWorks BidderwouldliketohighlighttoCOMPANYthatschedule Expected duration for the FEED is maximum 6
PE7172SOW001 forcompletingtheFEEDisnotspecifiedinScopeofWorks months.
Rev.0 document.

ScheduleforFEED Bidder requests COMPANY to provide the expected
Study durationforthecompletionofFEED.
1.7. ScopeofWorks Bidderunderstandsthatthecostofthirdpartyservicesto Bidder understanding is not correct. All third
PE7172SOW001 be considered separately (under PROVISIONAL SUM) and party services shall covered under Lump sum
Rev.0 notincludedinlumpsumcostofthisFEED. costoftheFEED.

ThirdPartyServices
likeHAZID,ENVID,
HSEIA,HAZOP,SIL,
UltrasonicThickness
Testing
1.8. ScopeofWorks Bidder highlights that, Defining exact scope of relevant Geotechnical. Topographical & UG detection
PE7172SOW001 Topographical Survey and Geotechnical Survey works in SOW for the proposed equipments layout and
Rev.0 HabshanIIandHabshaanIIIplantareaswillbeextremely newPipealignmentrouteshallbepreparedand
difficultfromrelevantITTdata. executed. Bidder to consider these costs under
Section6.4 Lumpsum.
TopographicalSurvey, Bidder requests COMPANY to consider these survey
SoilInvestigationand activitiesunderPROVISIONALSUM.COMPANYtoconfirm
UltraSonicThickness andadviseaccordingly.
testing,SubContracts
1.9. ProjectSchedule COMPANY to kindly advise the expected overall schedule Seereplyunderitem7.
forthisproject.

HTSPPF110 4|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
1.10. Requirement fornew As per Pre FEED document, a new water seal drum for PreFEED document is integral part of the FEED
water seal drum for HabshanIII and its associated equipment are envisaged ScopeofWork,henceall items indicatedinthe
HabshanIII tobepartofthesolutiontorecovertheHabshanIIIflare PreFEEDreportarepartofFEEDScope.
gas.HoweverthesameisnotcoveredintheFEEDScope
of work document. CONTRACTOR understands that the
new water seal drum for HabshanIII and its associated
equipmentarepartofFEED.
COMPANYtokindlyconfirmBIDDERsunderstanding.

2. INSTRUMEN General SPIIntoolsnotconsideredforInstrumentDeliverablesand Confirmed
TATION& alldocumentsshallbeinExcel/WordasperCOMPANY
CONTROL format.COMPANYtoconfirm.
2.1. do General F&GMappingstudyisnotconsidered,existingF&G Confirmed.
philosophywillbefollowedfornewF&Gdetectorsasa
partofthisproject.
COMPANYtoconfirm.
2.2. General Itisassumedthatexistingareaiscoveredwithadequate
Telecomequipmenthence,Telecommunicationscopefor
CCTV,telephonesystem,PAGAsystem,accesscontrol&
Confirmed.
securitysystem,radiosystem,structuredcablingis
excluded.
COMPANYtoconfirm.
2.3. ScopeofWork FollowingI&Citemsareconsideredaslongleaditems,TBE
andMRenvisagedfortheseitems
Doc.no.PE7172SOW Confirmed.
1. Shutdownvalves
001Rev0
2. Controlvalve

HTSPPF110 5|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
Cl.no.6.2LongLead 3. BPRV
Items 4. PSV
Controlsystemisextensionofexistingsystem,henceTBE
forsameisexcluded.

Offersfromthree(03)vendorsshallbeconsideredforthe
evaluation.
COMPANYtoconfirm.
2.4. General Availabilityofsparespaceinexistingcontrolroomis
assumed;extensionornewbuildingisnotenvisagedfor FEEDContractortoreviewandrecommend
theProject.COMPANYtoconfirm.
2.5. ScopeofWork CompanytoadvicemakeofDCS/ESD/F&Gsystemat DCS System in Habshan 0,1,2,4ABB &
followinglocations Habshan3(OGDIII)Yokogawa
Doc.no.PE7172SOW
001Rev0 HabshanplantDCS/ESD/F&G ESD System in Habshan 0,1 Yokogawa
OGDIIIDCS/ESD/F&G 2 ABB CS300 & 3,4 ICS Triplex from
Cl.no.6.7.1DCS&ESD
HFGRDCS/ESD/F&G Rockwell
systems
Note:EPCforESDupgradeforHabshan2is
underprogressandnewESDwillbeABB800XA
2.6. General OEMinvolvementisnotconsideredforControlsystem
adequacytocaterfornewsignalsofproject.Adequacy Adequacyintermsofspace,power,cabling,
reportwillbepreparedbasedonexisting systemperformance(controllerload,controller
Marshalling/systemGAdrawings,I/Oassignment,wiring memoryusage,networkloadetc.)needstobe
diagram,etc.andphysicalverificationduringsitevisitin includedinthescope.
consultationwithoperations.COMPANYtoconfirm.
2.7. ScopeofWorks FireandGasdetector layout will be prepared based on Confirmed.
PE7172SOW001 GASCO HSE Philosophy and exiting F&G detection

HTSPPF110 6|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
Rev.0 philosophy.SeparateF&Gdetectionstudyisnotrequiredfor
thislimitedprojectscopeofwork.
Section10. COMPANYtoconfirmBiddersunderstandingiscorrect.
SAFETY&LOSSPREVE
NTION
FireandGa
sdetectionstu
dy
2.8.
PROCESS ScopeofWork MaterialSelectionandCorrosionControl
Doc.no.PE7172SOW In brief, the project requirement is to provide
001Rev0 interconnection between Habshan2 and Habshan3 flare
Section6.11 header, utilize Habshan2 FGRU and provide additional
liquidsealdrumandassociatedsystemforHabshan3.
MaterialSelectionand
CorrosionControl Since, the modifications are associated with the existing AdequacyoftheH2FGRUmetallurgyforH3
3.
plant flare systems, it is proposed to follow the existing flaregastobeverifiedbytheCONSULTANT
(subsection6.11.7)
similar system metallurgy for the new piping and
equipment.Similarly,existingHabshan2FGRUmetallurgy
can be considered adequate for routing for Habshan3
flareGas.
COMPANYtoconfirm.
do ScopeofWork AsperpreFEEDdocumentscope
COMPANYSOWisveryclear.ALLaffectedPSVs
3.1. Doc.no.PE7172SOW Effectofbackpressureontheflareheader,reliefcapacity
tobechecked.
001Rev0,Appendix of the each PSVs, compressor seal vents are left to be

HTSPPF110 7|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
VPreFEEDdocument studiedindetailinFEEDstage.
PCRPE7172 a. CONSULANT scope is limited to report
backpressurevaluesforthevariousrelief
scenarios, backpressure acceptability for
theselectedexistingPSVs.Studyneednot
to be extended to each PSV and Backpressurenonacceptabilityifanyamongall
associated piping. Accordingly, no detail thePSVsandthemodificationsrequiredforthe
modifications in PSVs and associated tail samewiththecostestimatetobeprovided.
pipesistobestudied.



b. CONSULTANT to check feasibility of flare TheimpactontheexistingPSVs(backpressure
recoverywithminimumimpactonexisting nonacceptability)andpipelinetobeprovided
plant PSVs, pipings etc. Habshan2 FGRU forthespecifiedflaregasrecovery.
suitabilitywillbecheckedaccordingly.
COMPANYtoconfirm. TheadequacyoftheHabshan2FGRUtobe
verified.
ScopeofWork AsperpreFEEDdocumentscopesketch a. Confirmed.P&IDtagstobe
followed.
Doc.no.PE7172SOW a. As per sketch provided with preFEED
b. Confirmed.P&IDtagstobe
001Rev0,Appendix documentthetagnumberofFGRUKODis
followed.
VPreFEEDdocument indicated as 771V002. CONSULTANT

3.2. PCRPE7172 understanding is that the correct tag
YES.Confirmed
number is 771V202 in line with the

provided P&IDs and description

mentioned for FGRU in main scope of

workdocument.Tieinlocationofthe16

HTSPPF110 8|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
interconnection line is to be considered
upstream of this KOD 771V202 in line
withthemarkupP&ID.
COMPANYtoconfirm.



b. As per sketch provided with preFEED
document the tag number of the Flare
KOD is indicated as 371V102A/B. YES.Confirmed.
CONSULTANT understanding is that the
correct tag number is 371V101 in line
with the provided P&IDs and description
mentioned in main scope of work
document. Tie in location of the 16
interconnection line is to be considered
downstreamofthisKOD371V101inline
withthemarkupP&ID.
COMPANYtoconfirm.
ScopeofWorks Bidderunderstandsthatthetagno.ofFlareKODrumis371
PE7172SOW001 V101andnot371V102A/Basmentionedinschematic.And
Rev.0 thereisonlyoneKODrumofHabshanIII. Confirmed.P&IDtagstobefollowed.
COMPANYtoconfirmBiddersunderstandingiscorrect.
3.3.
Appendix5Prefeed 371V101istheTagNo
DocumentforPCRPE
7172,Attachment1
SchematicDrawing

HTSPPF110 9|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
ScopeofWorks Bidderunderstandsthatthetagno.ofSuctionKODrumof
PE7172SOW001 Habshan II is 771V202 and not 771V002 as mentioned in
Rev.0 schematic.
Confirmed.P&IDtagstobefollowed.
3.4.
Appendix5Prefeed COMPANYtoconfirmBiddersunderstandingiscorrect. 771V202istheTagNo
DocumentforPCRPE
7172,Attachment1
SchematicDrawing
ScopeofWorks Bidder understands that the suitability study of the
PE7172SOW001 Hydrocarbon Gas Recycle compressor in Habshan II for
Rev.0 revisedflow/streamisnotinBiddersscopeofwork. TheadequacyoftheHabshan2FGRUtobe
3.5.
verified.
Section6Consultant COMPANYtoconfirmBiddersunderstandingiscorrect.
ScopeofWork
ScopeofWorks Bidderunderstandsthatthestudyoftheupstreamrelief
PE7172SOW001 system(PSVsandCompressorsealvents)visavis
Rev.0 additionalbackpressureduetothemodifications
Itisinthescopeofthebidder.
3.6. suggestedunderthisProjectisnotinBiddersscopeof
Refercommentfor3.1
Section6Consultant work.
ScopeofWork
COMPANYtoconfirmBiddersunderstandingiscorrect.
ScopeofWorks BidderunderstandsthatthestudyforColdrelieffrom
PE7172SOW001 HabshanIIIandimpactonwatersealdrumisnotin
3.7. Rev.0 Biddersscopeofwork. Itisinthescopeofthebidder.

Section6Consultant COMPANYtoconfirmBiddersunderstandingiscorrect.

HTSPPF110 10|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
ScopeofWork

Adequacyofthe BIDDER understands that adequacy of the existing Flare
existingFlaregas gas recovery compressor for handling the normal flare
3.8. recovery gas from Habshan 3 also has to be verified during this Yes
compressor FEEDproject.
COMPANYtokindlyconfirmBIDDERsunderstanding.
Effectofincreased BIDDER understands that the effect of increased normal
normalback back pressure on the HabshanI/II/III flare due to the
pressureonthe proposedinterconnectionwithHabshanIIIflarehastobe
HabshanI/II/III studied in FEED and suitable mitigations are to be
3.9. flareduetothe recommended. Any engineering for modification which Yes
proposed mayberequired duetothis isproposedwillbehandled
interconnection separately.
COMPANYtokindlyconfirmBIDDERsunderstanding.
HabshanIIandIII BIDDERunderstandsthatbothHabshanIIandIIIflaregas
flaregasrecovery recovery will be carried out simultaneously. As per the
SOW, since the compressor capacity is 5 MMSCFD, any Ifthecombinedsuctionflowismorethan5.0
increase in the suction flow above 1.9 MMSCFD from MMSCFD,ithastocausethePCVsonthe
3.10. Habshan II and 3.1 MMSCFD from Habshan III will cause respectiveflarestobeopened.Suitablecontrol
an increase in the pressure and opening of PCVs on schemetobedevisedintheFEED
respectiveHabshanIIorIIIflares.
COMPANYtokindlyconfirmBIDDERsunderstanding.
3.11. ReferSOWPage BIDDERkindlyrequestsCOMPANYtoclarifythesoftware MIcrostation/Autocadwillbesufficient.

HTSPPF110 11|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
31,Section7,last expectedtobeusedforP&IDsandPFDs.
line
ReferSOWPage8, BIDDER understands from the purpose of the three
section4, bulletedpointsistohighlighttheoverallobjectiveofthe
3.12. 3bullets project,however,thescopeofworkshallbelimitedtoas YES
indicatedinthepreFEEDdocument.
COMPANYtokindlyconfirmBIDDERsunderstanding.
ReferSOWPage8, BIDDER understands that parallel operation of both
Section6,Point1c. Habshan3 and Habshan2 flares is not intended as per
3.13. original design and the same is not the objective of this YESCONFIRMED
project.
COMPANYtokindlyconfirmBIDDERsunderstanding.

ELECTRICAL SOWClause6.6 ElectricalMotorforthePumpsareverysmall(<11kW)as
perthepreliminaryestimationandwillrunfor
intermittentdutyonly,thusfollowingareassumed: 1. Confirmed.
2. Notagreed.FEEDcontractorto
1. Poweradequacycheckisconsideredforthe communicatewithVendorifany
switchgearfromwherethemotorsunderthe modificationisrequired.
4. scopeshallbefed,howeverPowersystemstudy 3. Notunderstandthebidderquestion.
(loadflow,shortcircuit,motorstartingetc.)isnot 4. Agreed.
envisagedforadditionofsuchsmallmotorandis 5. Agreed.
notconsidered. 6. Agreed.
2. Identificationofsparefeedersisconsidered,
whereasmodificationrequiredifanyshallbe

HTSPPF110 12|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
coveredinOEMscopeonly.NoOEMinvolvement
isconsideredduringFEEDstage.
3. Specification/datasheetfortheswitchgearisnot
considered,howeverOEMscopeforthe
switchgearmodificationisconsideredwherethe
companyexistingspecification/datasheetshallbe
referred.
4. ItisassumedthatSubstationbuilding
Expansion/extensionisnotrequired.
5. Asperthescopeexistingundergroundinstallation
istobeavoided,bidderassumesthatexisting
cabletrenchisnottobeusedandnewcable
trenches/ductbank/traysisconsideredfornew
cables,howevertrialpitsexcavationshallbekept
inthescopeofEPCcontractorwhereEPC
contractorshallverifythebestpossiblecable
routeproposedduringFEEDEngineering.
6. NoLongleaditemisenvisaged.
COMPANYiskindlyrequestedtoconfirmtheabovepoints.
4.1. Clause6.6 Earthingcalculationisnotconsideredandthenew
equipmentandstructuresisconsideredtobeconnected
totheexistingearthgrid.ExistingEarthingdrawing(As Agreed.
built)isconsideredtobeupdated.
COMPANYtoconfirm.

HTSPPF110 13|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery

4.2. Clause6.6 ExistingLightingdrawing(Asbuilt)isconsideredtobe


Agreed.
updated.
4.3. Clause6.6 ExistingHAClayout(Asbuilt)andExistingHACschedule
Agreed.
(Asbuilt)areconsideredtobeupdated.
4.4. Clause6.6 Existingcableroutingdrawing(Asbuilt)isconsideredto
Agreed.
beupdated.
4.5. Clause6.6 Lightningprotectionisnotenvisaged.Companyto Notagreed.Biddertofollowexistingadjacent
confirm. unitsphilosophy.
4.6. Clause6.6 ExistingLoadSummary(Asbuilt)isconsideredtobe
Agreed.
updated.
4.7. Clause6.6 ExistingCableschedule(Asbuilt)isconsideredtobe
Agreed.
updated.
4.8. Clause6.6 Tieinscheduleisconsidered. Agreed.
4.9. Clause6.6 ExistingLVSwitchgearSLD(Asbuilt)isconsideredtobe
updated.UPSSLD(ifrequired)isconsideredtobe Agreed.
updated.
4.10. Clause6.6 Motorschematicisnotconsideredandexistingphilosophy
isconsideredtobefollowedforwhichtheexistingvendor
drawingisconsideredtobereferencedintheOEMscope Agreed.
ofwork.
COMPANYtoconfirm.

HTSPPF110 14|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery

4.11. Clause6.6 Demolitiondrawing(ifrequiredonly)shallbeprepared. Agreed.


4.12. General Ifanyeditablefilesfortheabovementioned/ Availability of native files on case to case basis
documents/drawingsis/arenotavailable,thenonly and consider preparation of drawings /
preparationofhandmarkupisconsideredand documentswhereverunavailable.
reproducingthewholedocumentisnotconsidered. The existing drawings, documents and
COMPANYtoconfirm. calculationsifavailableshallberetrievedbythe
successful bidder in whatever form available.
Existing asbuilt / available documents relevant
to the scope of work shall be collected by the
successful bidder, from the site design office in
the available format. Required site visits /
engineering shall be performed to obtain the
missingdata.Itshallbetheentireresponsibility
of the FEED consultant to verify the actual
conditionsatsiteinordertocompletethework
aspersite surveyandCOMPANYspecifications.
FEEDCONSULTANTshallresolveallthedetected
discrepancies/designissuesifany.
Incasedesigncalculationsanddrawingsarenot
available,Consultantshallperformsitesurveyto
collect all required information and shall carry
out all necessary calculations, develop required
deliverable, based on Companys current DGS
andAddendums.
Bidder shall confirm understanding and

HTSPPF110 15|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
adherence.

4.13. Clause6.12.4,Page25 IntheSOWitiswrittenthatTheeffectofthestray


currentofcathodicallyprotectedundergroundservices
(insidetheplantarea)onthenearbyreinforcedconcrete
structure(foundation,sumps,etc)needtobeevaluated. ItisaFEEDConsultantsresponsibilitytoidentify
Necessarymeasurestobeimplementedtoprotectthe theextendoftheevaluation,asperGASCODGS.
reinforcementsteelfromgettingcorroded.
COMPANYtoconfirmwhatistheextendofevaluationof
theeffectofstraycurrent.
4.14. Clause6.12.4,Page26 Iftheaboveevaluationisnotrequired,then
CathodicProtectionscopeisnotenvisagedasthereisno
Notagreed.Anewliquidsealdrumandalso
newtanksorburiedpipeline.Alsononeofthenew
newundergroundoverflowdrumandsumpare
equipmentisdealingwithaggressiveeffluentssuchas,
envisagedinthisproject.
brinewater,seawaterchemicals,sulfuretc.
COMPANYtoconfirm.
4.15. APPENDIXIV_FEED Electricalengineeringdesignbasisisconsideredasapart
DELIVERABLESLIST ofOverallDesignBasis.Bidderassume,itwillnotbea
separatedocument. Confirmed.

COMPANYtoconfirm.
4.16. APPENDIXIV_FEED Bidderassumethataddingtwomotorsof(<11kW)willnot
DELIVERABLESLIST affecttheKeySingleLineDiagram,howevertherelevant Confirmed.
LVswitchgearSLDisconsideredtobeupdated.

HTSPPF110 16|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
COMPANYtoconfirm.
4.17. APPENDIXIV_FEED COMPANYiskindlyrequestedtoelaboratewhatisPower
Removedfromthescope.
DELIVERABLESLIST SupplyReport.
4.18. APPENDIXIV_FEED StandardInstallationDrawingsofCompanyshallbe
DELIVERABLESLIST followedfortheprojectandbidderassumesno
modificationintheexistingdrawings.Bidderunderstands Confirmed.
thatthesedrawingsarenottobereproduced.
COMPANYtoconfirm.
4.19. ScopeofWorks Bidderunderstandsthatpowerrequiredforthenewsystem
PE7172SOW001 isnominalandhence,afullfledgedPowerSystemstudy(on
Rev.0 ETAPor equivalent)comprising ofLoadFlow, ShortCircuit,
Motor starting, load shedding, harmonics, etc. is not
Section6.6Electrical required.
Cable Sizing and Voltage Drop calculations (or any other Confirmed.
equipment sizingcalculations) withLoad analysis, SLDsand
associated lists and layouts will be prepared to define the
powerrequirement.

COMPANYtoconfirmBiddersunderstandingiscorrect.

CIVIL/ PE7172SOW001, Alltheexistingundergroundservicesshallbeinvestigated As a part of FEED study, successful bidder shall
STRUCTURAL Section6.12.4 andthedetailsofreroutingorrelocationtobeprovided study all the available underground services
5.
Bidder understand that, underground utilities detection drawings,verifytheiradequacyandproposethe
survey need to be carried out as part of FEED study possibilities for relocation of u/g services. For

HTSPPF110 17|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
irrespectiveofAsbuiltdrawingsavailablewithCOMPANY. the additional requirement of u/g services
COMPANYtoconfirm. detection survey Scope of work, bidding,
evaluation, award, report review, etc. shall be
carriedoutbytheFEEDcontractor;aLumpsum
Optional Price to be quoted by the bidder in
thisregard.U/gdetectionsurveycostshallbeon
actualreimbursablebasis.Thesameapproachis
applicable for Topographic and Geotechnical
Surveys.
do PE7172SOW001, GAdrawings ofFlare Piperack provided in AppendixIIIof A key plan is provided indicating the schematic
AppendixIII scope of work are not legible and correlation with Piping pipe routing. Civil GAs and structural
GA drawing received with tender document is not calculations of Habshan 3 & FGR projects are
possible. available.PipingGAsarenotavailableandneeds
Bidder requests COMPANY to provide Area key plan to be extracted from 3D models. Space
5.1. drawing to identify the different segments of Flare availabilityinFlarepiperackandthesegmentsto
piperack. be utilized are to be studied as a part of FEED
study. For available drawings see the link
https://files.gasco.ae/MFT/jre_install.jsp?IDT=bfff53c5
15a84147a0736c1bf96c8d3d&ID=253df43d5607467c
924342716906ad69
TSM/C/GL/001 To estimate the efforts required to perform adequacy Due to the nonavailability of Piping GAs, Staad
(Guidelinesforthe check for existing Flare piperack, COMPANY to provide files (Tekla software used), existing Piperack
5.2. DesignAdequacy segment of existing flare rack for Category 1 & 2 of Unit371canbeconsideredasCategory2.
CheckofExisting affectedflarepiperack.
Piperacks)
5.3. TSM/C/GL/001 Adequacy check for existing flare piperack need to Adequacycheckofexistingpiperacktobecarried

HTSPPF110 18|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
(Guidelinesforthe perform at FEED stage to route new 16 interconnection
outbasedonthelatestdocumentDoc.No.TE
DesignAdequacy line. Bidder understand that structural adequacy and GU008GuidelinesfortheStructuralAdequacy
CheckofExisting foundation adequacy will be carried out at FEED stage.
CheckandModificationofExistingPiperacks
Piperacks),Section However, detailed connection design check, base plate (attachedherewith).Alladequacychecksshallbe
5.1.10 andanchorboltcheckswillbecarriedoutatEPCphaseof carriedoutatFEEDstageincludingfoundations,
project. baseplate&anchorbolts.Onlyconnections
COMPANYtoconfirmbiddersunderstanding. designwillbecheckedatEPCstage.Allthese
informationaredetailedintheaboveguidelines.
SRC020RPT40000 COMPANYtoconfirmwhetheranyotheradequacyreports Civil/StructuralGAdrawingsandcalculation
310(Consultancy available with COMPANY for remaining portion of Flare reportsareavailableinpdfformatforHabshan3
ServicesforStructural piperacktillHabshan3HCFlareKOD371V101. &FGRprojects.
5.4. Integrity/Adequacy
CheckofExistingPipe
RacksatHabshan
PlantPhase2
ScopeofWorks This list does not mention many Engineering deliverables
PE7172SOW001 such as Adequacy study of Structural Frames and
Rev.0 FoundationsforaffectedPipeRackframes,NewPipeRack
structuresandFoundationrelatedcalculationsanddrawings
AppendixIV , New Equipment Foundation drawings , Civil / Structural
Confirmed.AllCivil/Structuraldeliverables
5.5. deliverablelist MTO,InputtoEPCscopeofworketc.
relevanttotheScopeofworkshallbeconsidered.

ReferringClauseno.4.0,6.0and6.12.4ofDocumentNo.
PE172SOW001Rev0bidderunderstandsaboveitems
aremandatoryrequirementswithFEEDprogressionand
essentialpartofEPCTenderITTdocuments.

HTSPPF110 19|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery

COMPANYtoconfirmBiddersunderstandingiscorrect.

ScopeofWorks Civil/StructuralDeliverablelist(page47of60,doc.No. DevelopmentofCivil/StructuralDesignBasis
PE7172SOW001 PE172SOW001Rev0)doesnotmentiondevelopmentof shallbebasedonthenewcivil/structuraldesign
Rev.0 Civil/StructuralDesignBasisandrelevantSpecifications requirementsasperthescopeofworkandthose
requiredforITT.Bidderunderstandsthesewillbedirectly ofexistingpiperackadequacystudies.
AppendixIV availablefromCOMPANYDGSdocumentsandBidderwill
5.6. deliverablelist nothavetopreparethesedocumentsaspartofthisFEED. AsfarasDGSsareconcerned,latestrevisionsof
Civil/StructuralDGSsshallbeprovidedtothe
COMPANYtoconfirmBiddersunderstandingiscorrect. contractor,alongwiththeapplicableaddendums
usedinanyoftherecentprojects;theyshallbe
followedandincludedasapartofEPCbidswith
suitablechangesifrequired.

PIPING Section6.2,Page9of Offersfromthreevendorsshallbeconsideredforthe
61LLI evaluation.
6. Confirmed.
Maximumthree(03)ofbiddersofferfortheTBE.
COMPANYtoconfirm.
6.1. Section6.3,Page9of Bidderunderstandsthat,alltieintoexistinglinewillbe
61 performedduringtotalshutdownperiod.Hottappingis
Earlytieinsfor notenvisagedintheproject.
Confirmed.
Habshan2flare COMPANYiskindlyrequestedtoconfirmBidders
headerduringTotal understanding.
S/DinFebruary2018
6.2. Section6.4,Page9of RequirementofUltrasonicthicknesstestingforthe FEEDCONSULTANTshallberesponsiblefor

HTSPPF110 20|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
61 projectisnotcleartotheBidder. accuracyandadequacyofthecollecteddata
TopographicalSurvey, COMPANYisKindlyrequestedtoclarifytherequirement relevanttoprojectscopeandverifythesameby
SoilInvestigationand ofsamefortheproject. conductingtheTopographicalSurvey,Soil
UltraSonicThickness InvestigationandUltraSonicwallThickness
testing testingforanytieinsoftheexisting
undergroundserviceswhereapplicableto
identifyanyconstructabilityIssues.
6.3. Section6.9.2,Page16 BIDDERunderstandsthatalltheengineeringwillbedone Biddertobeinformedthatbeinformedthatfor
of61 using2DAutoCAD.3DModellingisnotenvisagedinthe H3FlarepiperackwedonothavePipingGA
3Delectronicdesign project.COMPANYtoConfirm. routingdrawings(civilGAisavailable)only3D
reviewsofPlot modelisavailable.PortionswhereFGRprojectis
arrangements routed,therearepipingGAs.Biddertoextract
thepipingGADsforthesubjectprojectscope
fromtheavailable3DmodelfromHabshanplant
orextractitinHabshanplantdocumentation
officeanduseitfurtheractivities.
HoweverforEPCSOW,3Dmodeltobeincluded
forareathatalreadyhave3DPDSmodel.

6.4. Page43of61 Bidderunderstandthat,COMPANYspecificationwillbe
COMPANYDGSSpec followedfortheproject.Foranyadditionalrequirement(if
any,whichisnotincludedinDGS),Addendumtothe
Confirmed.
COMPANYDGSwillbeprepared&issuedforProject
purpose.
COMPANYtoConfirm.
6.5. Page50of61,Section Vibrationstudyrequirementshallbedecidedbasedon Confirmed.

HTSPPF110 21|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
8 FEEDdetailssuchasTieinlocations,Piperouting,Process
PipingVibration flowconditionetc.CompanyDGSwillbefollowedtotake
AnalysisReportsas necessaryprecautionforavoidanceofvibration.
required COMPANYtoconfirm.

6.6. ScopeofWorks Bidder requests COMPANY to provide GASCO Habshan
PE7172SOW001 Plot plan showing the area reserved for the new
Preliminary PreFEED Piping route markup has
Rev.0 equipmentcomingunderthisproject.
beenprovidedalongwiththisTC1reply.

General
6.7. ScopeofWorks Bidder understands that native files of all the existing
FEEDConsultanttoconsiderpreparationofnative
PE7172SOW001 drawing required for the project shall be provided by files of drawings / documents wherever
Rev.0 COMPANYinAutoCADformat. unavailable.
COMPANYtoconfirmBiddersunderstandingiscorrect.
General
6.8. ScopeofWorks Bidderunderstandsthatthisprojectwillbecarriedoutin2D Bidder to be informed that be informed that for
PE7172SOW001 and3Dmodelisnotenvisaged. H3 Flare piperack we do not have Piping GA
Rev.0 BidderunderstandsthatnecessaryreviewbyCOMPANYwill routingdrawings(civilGAisavailable)only3D
be done on 2D drawings during normal COMPANY review modelisavailable.PortionswhereFGRprojectis
Section6.9.2Design cycle. routed,therearepipingGAs.Biddertoextractthe
Reviews. piping GADs for the subject project scope from
3Delectronicdesign COMPANYtoconfirmBiddersunderstandingiscorrect. the available 3D model from Habshan plant or
reviewsofPlot extract it in Habshan plant documentation office
arrangements, anduseitfurtheractivities.
equipmentlayouts However for EPC SOW, 3D modelto be included
andmajor/criticalline forareathatalreadyhave3DPDSmodel.

HTSPPF110 22|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
routingsarerequired
6.9. Piping:General BIDDER understands that the COMPANY will provide the COMPANY will provide available soft files in
latest AUTO CAD as built soft files such as Plot Plans, AUTOCADorMicroStation.Biddertobeinformed
As Built latest soft
GADs of existing facilities for further update to include thatbeinformedthatforH3Flarepiperackwedo
files
projectscopeofwork. not have Piping GA routing drawings (civil GA is
available) only 3 D model is available. Portions
No CAD conversion of manual drawings to AUTOCAD
whereFGRprojectisrouted,therearepipingGAs.
format is envisaged for the brown field work. And
BiddertoextractthepipingGADsforthesubject
applicable manual GA drawings at modification location
project scope from the available 3D model from
will be revised to show project requirements using GTX
Habshan plant or extract it in Habshan plant
RasterwithAUTOCAD.
documentationofficeanduseitfurtheractivities.
COMPANYtokindlyconfirmBIDDERsunderstanding.
6.10. Piping:General BIDDER kindly requests COMPANY to provide the Pre
PreFEEDStudy FEED study Plot Plan and Piping routing study or GADs Seereplyin6.6.
forestimationpurpose.

6.11. 6.9 Piping BIDDER understands that the COMPANY will provide the
Engineering: Under existing pipe wall thickness measurements at TieIn Company will not provide the existing pipe wall
6.9.1 TieIns, Bullet locationandTieInpointintegrityassessmentreportto thickness measurements, it is FEED Consultants
Number4 finalizethetieinpointlocation. responsibility to review the piping material
specificationsforwallthicknessverificationofthe

existinglinesandcomplywithcriteriasetinDGS
TieIns shall meet COMPANYtokindlyconfirmBIDDERsunderstanding. 1300100forintegrityofthetieinstofinalizethe
criteria set in tieinpointlocation.
specifications DGS
1300100, Piping Tie
Ins.

HTSPPF110 23|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery

6.12. 6.9 Piping BIDDER understands that the COMPANY will provide the
Engineering: Under applicable unit asbuilt 3Dmodel for further update to
6.9.2DesignReviews. includetheprojectscopeofwork.

3D electronic design COMPANYtokindlyconfirmBIDDERsunderstanding. COMPANYwillprovideavailable3Dmodelsthat
reviews of plot plan aresubjecttoConsultantsvalidation.
arrangements,
equipment layouts
and major / critical
line routings are
required.

HSE/ Section6.1 Bidderunderstandsthat,onlyupdateofexistingHSEIAis
PROCESS requiredandnofreshHSEIAshallbeneeded.COMPANY
HSEIAStudy
7. SAFETY willprovidetheexistingHabshanareaHSEIAstudy(native
files)toHSEIAConsultant.
COMPANYtoconfirm.
Section6.1 Bidderunderstandsthat,hiringandmanagingHSEIA
7.1. Consultant,isunderbiddersscope. Confirmed.
HSEIAStudy
COMPANYtoconfirm.
Section6.13 Scopeforfirefightingfacilitiesisnotclearlydefined.
FEEDconsultanttoconsideradditionoffire
Consideringthescopeofproject,bidderdontenvisage
7.2. FireFightingFacilities fightingequipmentasneededforthenew
anyrequirementsforfirefighting.
extendedfacilities.
COMPANYtoconfirm.
7.3. ScopeofWorks BasedonlimitedProjectSOW:

HTSPPF110 24|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
PE7172SOW001 a. It is assumed that this Project will be
Rev.0 awardedHSEIADeMinimus.
b. The SOW will not involve
Section6.1 review,updateandvalidate of existing
HSEIAStudy HabshanHSEIAstudy.

COMPANYtoconfirmBiddersunderstandingiscorrect.
ScopeofWorks Bidderunderstandsthatthebelowmentionedscopeisnot
PE7172SOW001 partofthisProject
Rev.0 a. Firewatersystem a. FEEDContractortofollowexistingnearby
b. Buildingdesignsuchasplan,firewall,me facilitiesandadd(identify)/checkifitis
7.4.
Section6.13 ans of egress and ventilation needed.
FireFightingFacilities buildingdesign. b. Confirmed.

COMPANYtoconfirmBiddersunderstandingiscorrect.
ScopeofWorks Bidderunderstandsthatthebelowmentionedscopeisnot
PE7172SOW001 partofthisProject
Rev.0 1)WaterSpraySystem FEEDContractortofollowexistingnearby
2)FoamSystem facilitiesandadd(identify)/checkifitis
7.5.
Section6.13.1 3)Gases(CarbondioxideandINERGEN)substationsorbuildi needed.
SelfSupportingSystem ngs.

COMPANYtoconfirmBiddersunderstandingiscorrect.
ScopeofWorks Bidderunderstandsthatthebelowscopementionedunder
7.6. PE7172SOW001 DesignReviewsectionisnotpartofthisProject Confirmed.
Rev.0 o DesignReviews/Performoverallreviewfor

HTSPPF110 25|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
safetyandfireprotection.
Section6.9.2
DesignReviews COMPANYtoconfirmBiddersunderstandingiscorrect.


ScopeofWorks FireandGasdetector layout will be prepared based on
PE7172SOW001 GASCO HSE Philosophy and exiting F&G detection
Rev.0 philosophy.SeparateF&Gdetectionstudyisnotrequiredfor
thislimitedprojectscopeofwork.
Section10. COMPANYtoconfirmBiddersunderstandingiscorrect..
7.7. Confirmed
SAFETY&LOSSPREVE
NTION
FireandGa
sdetectionstu
dy

7.8. MECHANICA ScopeofWork Existing Flare Gas Recovery System including Flare Gas ItisinFEEDConsultantscopetoverify/validate
L/ROTARY Recovery Compressors (771C201) in Habshan2 are usageofexistingcompressorfornewgas
Doc.no.PE7172SOW
proposedtobeusedforflaregasrecoveryinhabshan3. streamswithfollowingdeliverables;
001Rev0
Suitability check of this existing system/ compressors for Preparation of COMPRESSOR mechanical
Cl.no.2Project revisedoperatingconditionsisnotmentionedinthescope datasheetforadditionalprocesscases.
Background ofCONSULTANT. Checkonexistingcompressor(Aerodynamic
FlareGasRecovery Is the suitability of the compressors & associated system compressorperformance)
Compressors(771C alreadycheckedforrevisedoperatingcondition? Impactifanyondownstreamequipment.
201) Do the COMPANY expect CONSULTANT to check the Check on existing dry gas seals and leakage
rates.
same?
Suitability of compressor to handle H2 and

HTSPPF110 26|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
If the compressor suitability is to be checked with the H3 flare gases together (min, normal ,
compressormanufacturer,hemaychargefortheservices. maximumexpected).
Are these charges, if any, shall be reimbursed by the Endorsement from Compressor OEM on
COMPANY? compressor suitability along with the
submissionofnewPERFROMANCECURVES.
Impact of molecular weight, inlet
temperaturesetc.onthecompressor.

7.9. ScopeofWork Existing MO Booster Compressors (Unit 13 and 113) in
Habshan2 are proposed to be used for further
Doc.no.PE7172SOW
compressionofflaregasrecoveryinHabshan3.
001Rev0
Suitabilitycheckofthisexistingsystem/compressors for
Cl.no.2Project revisedoperatingconditionsisnotmentionedinthescope
Background ofCONSULTANT.
MPBooster Is the suitability of the compressors & associated system
Compressors(Unit13 Seeabove
alreadycheckedforpossiblerevisedoperatingcondition?
and113). Do the COMPANY expect CONSULTANT to check the
same?
If the compressor suitability is to be checked with the
compressormanufacturer,hemaychargefortheservices.
Are these charges, if any, shall be reimbursed by the
COMPANY?
7.10. ScopeofWork Based on the definition of 6month delivery period for
long lead items, only long lead rotating equipment
Doc.no.PE7172SOW
considered by the CONSULTANT is Seal Drum Over Flow Noted.
001Rev0
Pump.
Cl.no.6.2LongLead Material Requisition, Technical Queries & Technical Bid

HTSPPF110 27|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
Items Evaluation Report for the same is considered as
deliverables.
MaterialRequisitionshallbefloatedtosomevendorsfrom
ApprovedVendorListfromtheCOMPANY.
Offers from three vendors shall be considered for the
evaluation.COMPANYtoconfirm.


7.11. App 4: FEED Only pumps are required in this project as per the PID
Deliverable list MR markup and these pumps are not long lead. Hence
andTBT BIDDER understands that there are no MR or Technical Notagreed.Seeabove.
bidevaluationreportrequiredforanyMachineryitem.
COMPANYtokindlyconfirmBIDDERsunderstanding.
7.12. App 4: FEED SincethepumpsarelocatedontheTank,settingplanis
Deliverable list notapplicableforthePump. Confirmed.
Settingplan COMPANYtokindlyconfirmBIDDERsunderstanding.
7.13. App 4: FEED
Deliverable list Since the pumps are not critical equipment, Vendor
Vendor prequalificationreportisnotapplicable. Confirmed.
prequalification COMPANYtokindlyconfirmBIDDERsunderstanding.
report

8. MECHANICA Sec. 6.2: Long Lead COMPANYtokindlyclarifythecriteriaforLongLeadItems AllVesselsinvolvedintheprojectareconsidered
L/STATIC Items (LLI). asLLI.

HTSPPF110 28|P a g e
HabshanTechnicalServicesSubDivision
PlantProjectsSection
ProjectNo. PE7172
ProjectTitle PE7172 H3 FLARE GAS ROUTE TO H2 FGR
Ref.DocumentNo. TSSA Agreement Date. 26th of February 2017

TECHNICALCLARIFICATIONNo.1
Companyreply
S.No. Discipline TenderReference BiddersQuery
BIDDERunderstandsthatthatitbasedondeliverytimeof
equipment(i.e.morethan6Months).
COMPANYtokindlyconfirmBIDDERsunderstanding.
8.1. App 4: FEED a) BIDDIER understands that ENGINEER needs to follow
Deliverable list COMPANYvendorlist.
Vendor lists for b) BIDDER understands that prequalification Confirmed.
Critical Equipment & questionnaire/reportisnotrequired.
Prequalification
COMPANYtokindlyconfirmBIDDERsunderstanding.
questionnaire

9. MATERIAL ScopeofWork MaterialSelectionandCorrosionControl
Doc.no.PE7172SOW In brief, the project requirement is to provide
001Rev0 interconnection between Habshan2 and Habshan3 flare
Section6.11 header, utilize Habshan2 FGRU and provide additional
liquidsealdrumandassociatedsystemforHabshan3.
MaterialSelectionand
CorrosionControl Since, the modifications are associated with the existing Notaccepted.BiddertofollowrevisedSOW.
plant flare systems, it is proposed to follow the existing
(subsection6.11.7)
similar system metallurgy for the new piping and
equipment.Similarly,existingHabshan2FGRUmetallurgy
can be considered adequate for routing for Habshan3
flareGas.
COMPANYtoconfirm.

HTSPPF110 29|P a g e