BITS- NAB SHUTTERING MATERIAL ALLOCATION & SURPLUS STATUS AS ON 15-3-17

Block-C Block-B Block-D Block-A Total

2F 80 % Completed In Progress 80 % Completed

1F 100 % Completed Completed Hold 100 % Completed In Progress

GF 100 % Completed 100 % Completed

Shutt. Plate Area 1700 2200 1700 2450 8050 Sqm

Planned Shutt. Area 1700 Sqm 2200 Sqm 1700 Sqm 0 Sqm 5600 Sqm
Mat. Avail in work Sqm 2200 Sqm 340 Sqm Sqm 2540 Sqm
Material movement-1 (From Block-A-100%) 1700 Sqm
Material movement-2 (From Block-D-60%) 1020 Sqm
Material movement-3
Ext.Projection Slab for
340 Sqm 340 Sqm 680 Sqm
Upper floor
Mat. Further Required 340 Sqm 2200 Sqm Sqm 2720 Sqm 5260 Sqm

Expected Completion 30-4-17 31-5-17 30-4-17 20-6-17

Surplus-Stage-1 by 15-3-17 (Plywood, Runner, Acrospan, Box Section to be shifted to BITS-2 Project) 340 Sqm
Surplus-Stage-2 by 15-4-17 (Plywood, Runner, Acrospan, Box Section to be shifted to BITS-2 Project) 1100 Sqm
Surplus-Stage-3 by 31-5-17 (Plywood, Runner, Acrospan, Box Section to be shifted to Manjeera Project) 1700 Sqm
Surplus-Stage-4 by 20-6-17 (Plywood, Runner, Acrospan, Box Section to be shifted to Manjeera Project) 1400 Sqm
4540 Sqm
Balance Material to be required for Miscelaneous Works upto the Project completion date 1060 Sqm