Equipment Description
Sub-System Description
5 Carry out point to point verification and earth loop resistance check. (
Max value 1.0 ).
6 Verify incoming feeder cables are complete, tight and correct phasing.
13 Verify MCB / fuse ratings at feeder cubicle are correct for application.
Page 1 of 2
348476834.doc Rev C2
MPN PROJECTS
Static Commissioning Checksheet
Distribution Board
Form No. E-003B
18 Carry out live earth loop impedance test at Distribution Board busbars.
( Max value 1.0 ).
Note: Confirm that MCBs and RCDs have been fully tested at
Vendors workshop. Refer to vendors documentation for details.