MPN PROJECTS

Static Commissioning Checksheet


Distribution Board
Form No. E-003B
Phase: Item/Tag No.

Project Name: Sub-System No.

Data Sheet System No.

Equipment Description

Sub-System Description

Location: Module Detail:

Drawing Reference Date Printed:

Item Description Yes No N/A


1 Verify equipment details correct against drawings / data sheets.

2 Verify vendors certification documents complete and available.

3 Verify earthing is correct and conforms to design specification.

4 Measure earth bar resistance to general earth. ( Max value 0.1 ).

5 Carry out point to point verification and earth loop resistance check. (
Max value 1.0 ).

6 Verify incoming feeder cables are complete, tight and correct phasing.

7 Check correct operation of mechanical interlocks.

8 Verify fuse / MCB ratings are correct.

9 Verify correct connections of centre tap transformers and circuits if


applicable.
10 Busbar Insulation Tests ( Min value 50M @ 1000v )

11 L1 L2, L3, E L2 L1, L3, E L3 L1, L2, E

12 Verify switchboard feeder cubicle number and labelling is correct.

13 Verify MCB / fuse ratings at feeder cubicle are correct for application.

14 Function check feeder cubicle at switchboard and verify remote


shutdown circuits.
15 Energise Distribution Board and verify correct phase rotation.

16 Verify correct voltage outputs from centre tap transformers where


applicable.
17 Verify correct polarity, phasing and circuit at output terminals.

Page 1 of 2
348476834.doc Rev C2
MPN PROJECTS
Static Commissioning Checksheet
Distribution Board
Form No. E-003B
18 Carry out live earth loop impedance test at Distribution Board busbars.
( Max value 1.0 ).

Note: Confirm that MCBs and RCDs have been fully tested at
Vendors workshop. Refer to vendors documentation for details.
Remarks

Completed by Approved by Accepted by Others


Company
Signature
Name
Date

Page 2 of 2