MPN PROJECTS Electrical

Static Commissioning Checksheet E-008B


UPS / Battery System Sheet 1 of 3

Phase: Item/Tag No.

Project Name: Sub-System No.

Data Sheet System No.

Equipment Description

Sub-System Description

Location: Module Detail:

Drawing Reference Date Printed:

Item Description Yes No N/A

1 Verify equipment details correct against drawings / data sheet.

2 Carry out point to point verification and earth loop resistance check.

( Max value = 1.0 )

3 Verify cables are complete, tight and correct phasing / polarity.

4 Check charger / inverter cubicles are clean and free from dust and
moisture ingress.
5 Check insulation resistance of anti-condensation heater circuits.

( Min value = 1M )

6 Check insulation resistance of feeder and charger power circuits.

( Min value = 10M )

7 Verify charger / inverter MCB / fuse ratings and relay settings are
correct.
8 Verify batteries are installed, identified and polarity correct to vendor
layout.
9 Verify battery connections are tight, approved grease applied and
shrouds fitted.
10 Verify switchboard feeder cubicle number and labelling is correct.

11 Verify MCB / fuse ratings at feeder are correct for application.

12 Energise and verify satisfactory operation of anti-condensation heater


circuits.
13 Energise feeder cubicle and function check controls and ICS
interfaces.
14 Energise charger cubicles and check for correct phase rotation and
voltage.
15 Carry out live earth loop impedance test at charger panels.

( Max value = 1.0 )

16 Function check charger system in accordance with manufacturers


instructions.
17 Verify operation and settings of alarms and trips.
348793682.doc Rev C2
MPN PROJECTS Electrical
Static Commissioning Checksheet E-008B
UPS / Battery System Sheet 2 of 3

18 Verify satisfactory charging parameters.

19 Verify satisfactory discharge parameters. ( Record Test Results )

20 Verify satisfactory operation of UPS Inverter circuits.

21 Compile red line drawing where applicable.

Remarks

348793682.doc Rev C2
MPN PROJECTS Electrical
Static Commissioning Checksheet E-008B
UPS / Battery System Sheet 3 of 3

Completed by Approved by Accepted by Others


Company
Signature
Name
Date

348793682.doc Rev C2