Equipment Description
Sub-System Description
2 Carry out point to point verification and earth loop resistance check.
4 Check charger / inverter cubicles are clean and free from dust and
moisture ingress.
5 Check insulation resistance of anti-condensation heater circuits.
( Min value = 1M )
7 Verify charger / inverter MCB / fuse ratings and relay settings are
correct.
8 Verify batteries are installed, identified and polarity correct to vendor
layout.
9 Verify battery connections are tight, approved grease applied and
shrouds fitted.
10 Verify switchboard feeder cubicle number and labelling is correct.
Remarks