Present Permit Issuing Process
Present Permit Issuing Process
Present Permit Issuing Process
Project Awarded
FOTT Shift leader visits work site @ 7:30 Hrs along with HSE for
authorizing hot work permit.
If area is safe,
NO
conducts gas test
Advantage Disadvantage
permit issuing process
Contractor can enter inside the No gas testing conducted prior to issue of
terminal for hot work preparation cold work permits.
activities without any delay.
Maintenance permit, urgent situation
Contractor can start cold work, permit comes without RA.
without any time delay.
Project Awarded
Shift leader/ shift supervisor shall check the area. HSE shall
review and clear the RA.
FOTT Shift leader visits work site @ 7:00 Hrs along with HSE for
authorizing permit.
Permit declined
Contractor conducts job specific tool box talk and starts the
work.