permit issuing process

Project Awarded

MS & RA Submitted &


NO Approved

Contractor approaches for cold work permit - 0700Hrs. Cold


work permit issued from 7:15Hrs to 7:30 Hrs

Contractor enters the gate through cold work permit, conducts


job specific tool box talk and prepares the site for hot work.

FOTT Shift leader visits work site @ 7:30 Hrs along with HSE for
authorizing hot work permit.

If area is safe,
NO
conducts gas test

FOTT Shift leader authorises permit to start the work.


Permit declined

FOTT Shift leader closes the permit in the evening

Advantage Disadvantage
permit issuing process

Contractor can enter inside the No gas testing conducted prior to issue of
terminal for hot work preparation cold work permits.
activities without any delay.
Maintenance permit, urgent situation
Contractor can start cold work, permit comes without RA.
without any time delay.

Shift leader and HSE can save the


time since the area is already
prepared for hot work.
permit issuing process

Project Awarded

Contractor submits permit 12 hours in advance along with RA


NO

Shift leader/ shift supervisor shall check the area. HSE shall
review and clear the RA.

Contractor approaches for permit - 0700Hrs.

FOTT Shift leader visits work site @ 7:00 Hrs along with HSE for
authorizing permit.

conducts gas test and


No if ok

FOTT Shift leader authorises the permit to start the

Permit declined
Contractor conducts job specific tool box talk and starts the
work.

FOTT Shift leader closes the permit in the evening


permit issuing process
Advantage Disadvantage

No of unplanned permits shall be Without a valid permit contractor has


reduced. to enter inside FOTT premises. The
security department to be informed
suitably.

The Shift leader who is reviewing the


permit and who is issuing the permit
will be different.

If the permit/RA comes in the evening


then there won't be anytime to review
RA.

Shift leader workload will increase.

The external and internal customers,


has to plan the activities correctly.