Duyen Hai 3 Extension, Thermal Power Plant Project: Project: DH3 EXT. System: Startup Piping System
Duyen Hai 3 Extension, Thermal Power Plant Project: Project: DH3 EXT. System: Startup Piping System
End User:
Power Generator Corporation 1
Thermal Power Project Management Board 3
Owners Consultant :
Contractor :
Sumitomo Corporation
Customer:
The Babcock and Wilcox Company
Supplier :
Status of Revision
Revised
Rev. Date of Issue Description Prepared
Sheets
Initial
0 15/06/2016 - Palani
Submission
B&W comments
1 17/10/2016 - updated
Deep
Project: DH3 EXT.
System : Startup Piping System
NT PROJECT
ation 1
Management Board 3
ompany
Reviewed Approved
Palani Barani
Shameek Barani
Project: AES
System : WCT VSS
Lug Plate Design for Temporary Pipe Support of VSS & WCT
Pipe Dia. Dpipe
Thickness of Pipe tpipe
Material of pipe
Material of lug
Design temperature Td Pipe Max Design temp.
Allowable Stress Ft Lug plate
Smt Lug plate
One lug assumed with full load
Sustained Design Load P
(only metal weight)
One lug assumed with full load
Transient Design Load P
(only metal weight)
t thickness
H Height
Lug Size
W Width
D Hole Dia. = Pin Dia.+2 mm
4 x t a1
0.8 x D a1
(4/3)*a1 a2
Project: AES
System : WCT VSS
Lug Plate Design for Temporary Pipe Support of VSS & WCT
Weld Check
Fillet weld size =
weld length =
for sustained condition
Applied shear stress, fv = load (kips/inch) / weld leg size (inch)=
Allowable weld stress = 0.6 x Ft x w
35.00 inch
3.88 inch
SA 369 FP91
SA 387 GR.22 CL.2
200.00 F
27.50 ksi
33.00 ksi
88.00 kips
105.60 kips
1.26 inch
6.00 inch
12.00 inch
2.81 inch
4.59 inch
6.14 inch
1.69 inch
1.69 inch
5.04 inch
2.25 inch
6.12 inch
Ok
Ok
Ok
Project: AES
System : WCT VSS
0.47 inch
24.00 inch
7.76 ksi
16.50 ksi
OK
9.31 ksi
19.80 ksi
OK