Data Uji LabTanah by Cacing
Cc 12.04
Cu 5.13
D35 0.562
D50 0.865
D90 2.196
11 Batas Konsistensi
Batas Cair - Liquid Limits ( 36.38
Batas Plastis - Plastic Limit 9.49
Indeks Plastisitas (Plasticit 26.89
12 Permeabity - permeabilitas
ANALISIS SARINGAN
Proyek : PBGN 622 Praktikum Lab. Pengujian Tanah Tgl Uji 17 Februari 2017
Lokasi/ Site : Area Gedung D9 Lab. Teknik Sipil UM Diuji Oleh : Kelompok 6
Konsultan : Prodi PTB 15 C JTS FT UM Sampel :1
a b c d e f g
9.525 541.50 566.00 24.50 24.50 2.50
4 4.750 457.50 480.90 23.40 47.90 4.88
10 2.000 421.50 520.00 98.50 146.40 14.91
20 0.850 421.40 704.60 283.20 429.60 43.76
30 0.600 406.90 597.10 190.20 619.80 63.14
40 0.425 408.10 493.40 85.30 705.10 71.82
50 0.300 405.70 498.60 92.90 798.00 81.29
100 0.15 412.60 515.30 102.70 900.70 91.75
200 0.075 409 462.7 53.7 954.40 97.22
Pan 0 436.9 464.2 27.3 981.70 100.00
100.00
80.00
60.00
% Komulatif lolos
40.00
20.00
0.00
10.000
17 Februari 2017
: Kelompok 6
% Kumlatif Tnh
Lolos
h
97.50
95.12
85.09
56.24
36.86
28.18
18.71
8.25
2.78
0.00
12.04
5.13
1.000
A. Batas Cair
38
37
37
36
% Kadar air 36
35
35
34
34
33
33
10 15 20 25 30
N (jumlah pukulan)
B. Batas Plastis
No Uraian Uji Sampel Uji
1 Berat cawan kosong (W1) gram 10.03
2 Berat cawan + tanah basah (W2) gram 22.3
3 Berat cawan + tanah kering (W3) gram 19.7
4 Kadar air (%) = {(W2-W3)/(W3-W1)}100% 26.89
ENSI TANAH
Tgl Uji 24 Februari 2017
Diuji Oleh Kelomok 6
Sampel 1
25 11
16.10
73.70
59.00
36.38 34.27
25 30 35
36.38
Sampel Uji
10.03
22.3
19.7
26.89
9.49
LABORATORIUM MEKANIKA TANAH
JURUSAN TEKNIK SIPIL FAKULTAS TEKNIK
UNIVERSITAS NEGERI MALANG
Alamat:Gd D9 Lantai 2 Kampus UM Jl Semarang 05 Malang Telp. 0341 587 082
UJI BERAT ISI TANAH (SOIL DENSITY), POROSITAS, ANGKA PORI (VOID RATIO),DERAJAT KEJENUHAN
(DEGREE OF SATURATION)
Proyek : PBGN 622 Praktikum Lab. Pengujian Tanah Tgl Uji 10 Februari 2017
Lokasi/ Site : Area Gedung D9 Lab. Teknik Sipil UM Diuji Oleh Kelompok 6
Konsultan : Prodi PTB 15 C JTS FT UM Sampel 2
N0 Uraian Uji 1 2
Sampel
No Uraian Uji
1 2
1 Berat picnometer kosong (W1) gram 58.50 159.00
2 Berat picnometer + tanah (W2) gram 115.20 270.50
3 Berat tanah (W2-W1) 56.70 111.50
4 Berat picnometer + tanah + air (W3) gram 188.60 485.50
5 Berat picnometer + air (W4) gram 162.00 425.00
6 Suhu (T) o C 25.00 25.00
7 Faktor koreksi suhu (Ct) 0.9992 0.9992
8 Berat picnometer + air terkoreksi (W4xCt) 161.87 424.66
9 Berat jenis (Gs) = (W1-W2)/(W4.Ct+W2-W1-W3) 1.89 2.20
10 Berat jenis rata-rata 2.05
JURUSAN TEKNIK SIPIL FAKULTAS TEKNIK
UNIVERSITAS NEGERI MALANG
Alamat : Gedung D9 Lantai 2 Kampus UM Jl. Semarang 5 Malang 65145 Telp. (0341) 587 082
#REF!
Proyek : PBGN 622 Praktikum Lab. Pengujian Tanah Tanggal Uji 17 Maret 2017
Konsultan : Area Gedung D9 Lab. Teknik Sipil UM Diuji Oleh Kelomopok 6
Sampel Uji : Prodi PTB 15 C JTS FT UM
1.000
Gaya Normal N= 5.00 Kg N= 10.00 Kg N= 15.00 Kg
0.900
Chart Title
Tegangan Normal = 0.1506 Kg/cm sqr = 0.3012 Kg/cm sqr = 0.4519 Kg/cm sqr
Dial Gaya Tegangan Dial Gaya Tegangan Dial Gaya Tegangan 0.800
Waktu Deformasi
Beban Geser Geser Beban Geser Geser Beban Geser Geser 0.700
Kalibrasi Proving Ring Div kgf Kgf/div Div Kgf Kgf/Div Data Specimen
0.151 0.561
10 0.8128 0.0813 50 4.06 0.0813 0.301 0.593 Specime Diameter =
20 1.6256 0.0813 100 8.13 0.0813 0.452 0.837 Tinggi =
30 2.4384 0.0813 160 13.00 0.0813 Tan 0.918 Luas =
40 3.2512 0.0813 200 16.26 0.0813 berat basah
Rerata 0.0813 0.0813 Proving Kalibrasi proving ring
0.06 #REF!
17 Maret 2017
Kelomopok 6
Chart Title
cm2)
Tg Normal (kg/cm2)
42.55
Data Specimen
6.5 cm
2.00 cm
33.20 cm sqr
113.2 g
0.0813 kg/div
GRAFIK UJI GESER GRAF UJGRAFUJ UIJGEGESER LANLGASUNG SUNG
LABORATORIUM MEKANIKA TANAH
JURUSAN TEKNIK SIPIL FAKULTAS TEKNIK
UNIVERSITAS NEGERI MALANG
Alamat : Gedung D9 Lantai 2 Kampus UM Jl. Semarang 5 Malang 65145 Telp. (0341) 587 082
Luas
Deformation Regangan
Dial Deform (Div) Dial Load (Div) Load P (Kg) Terkoreksi A'
(Cm) = L/L
(Cm2)
0.600
0.500
0.400
Te gangan
(Kg/Cm2)
0.300
0.200
0.100
0.000
0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00 20.00
%
R
g
n
n
e
)
TANAH
EKNIK
1
nggi Specimen (Cm) 6.60
ameter Specimen (Cm) 3.50
uas Tampang Tanah 9.625
alibrasi Proving Ring (Kgf/Div) 0.504
Kadar Air (%) 23.768569
0.000
0.112
0.251
0.359
0.439
0.463
0.486