Project Name: Construction Management and Supervision of Gomma Ana Road Project -URRAP-
Project Location : Jimma Zone , Gomma and Gera Ana's
Type of work: Consultancy Services for URRAP Roads Construction Management and Supervision
Consultant: ABT Consulting Engineers Plc
Employer: Oromia Roads Authority/Gomma Anas Roads Authority
Procurment Reference Number:
Supplied Car Advance Payments for Gomma and Gera Ana Project
Estimated Cost of Leased Supplied Car (Repayment within 4 Year period)
is about ETB 735,000.00 (Seven hundred thirty five thousand birr only)
For Consultant
Name ________________________
Signature_____________________
Date_____________________________
AP Construction Management and Supervision - 2008 Invoice Number - 1
Monthly Installment
Service Sum with VAT 70,236.05
Service Sum without VAT 61,074.83
Executed
Service sum previous 0.00
Service sum currently executed 70,236.05
Total Service sum 70,236.05
For Client
Name _____________________
Signature___________________
Date__________________________
ice Number - 1
Gomma Ana URRAP Construction Management and S
Project Name: Construction Management and Supervision of Gomma Ana Road Project -URRAP-
Project Location : Jimma Zone , Gomma and Gera Ana's
Type of work: Consultancy Services for URRAP Roads Construction Management and Supervision
Consultant: ABT Consulting Engineers Plc
Employer: Oromia Roads Authority/Gomma Anas Roads Authority
Procurment Reference Number:
Supplied Car Advance Payments for Gomma and Gera Ana Project
Estimated Cost of Leased Supplied Car (Repayment within 4 Year period)
is about ETB 735,000.00 (Seven hundred thirty five thousand birr only)
For Consultant
Name ________________________
Signature_____________________
Date_____________________________
AP Construction Management and Supervision - 2008 Invoice Number - 2
Monthly Installment
Service Sum with VAT 70,236.05
Service Sum without VAT 61,074.83
Executed
Service sum previous 0.00
Service sum currently executed 70,236.05
Total Service sum 70,236.05
For Client
Name _____________________
Signature___________________
Date__________________________
ice Number - 2
Gomma Ana URRAP Construction Management and S
Project Name: Construction Management and Supervision of Gomma Ana Road Project -URRAP-
Project Location : Jimma Zone , Gomma and Gera Ana's
Type of work: Consultancy Services for URRAP Roads Construction Management and Supervision
Consultant: ABT Consulting Engineers Plc
Employer: Oromia Roads Authority/Gomma Anas Roads Authority
Procurment Reference Number:
Supplied Car Advance Payments for Gomma and Gera Ana Project
Estimated Cost of Leased Supplied Car (Repayment within 4 Year period)
is about ETB 735,000.00 (Seven hundred thirty five thousand birr only)
For Consultant
Name ________________________
Signature_____________________
Date_____________________________
AP Construction Management and Supervision - 2008 Invoice Number - 3
Monthly Installment
Service Sum with VAT 70,236.05
Service Sum without VAT 61,074.83
Executed
Service sum previous 0.00
Service sum currently executed 70,236.05
Total Service sum 70,236.05
For Client
Name _____________________
Signature___________________
Date__________________________
ice Number - 3
Gomma Ana URRAP Construction Management and S
Project Name: Construction Management and Supervision of Gomma Ana Road Project -URRAP-
Project Location : Jimma Zone , Gomma and Gera Ana's
Type of work: Consultancy Services for URRAP Roads Construction Management and Supervision
Consultant: ABT Consulting Engineers Plc
Employer: Oromia Roads Authority/Gomma Anas Roads Authority
Procurment Reference Number:
Supplied Car Advance Payments for Gomma and Gera Ana Project
Estimated Cost of Leased Supplied Car (Repayment within 4 Year period)
is about ETB 735,000.00 (Seven hundred thirty five thousand birr only)
For Consultant
Name ________________________
Signature_____________________
Date_____________________________
AP Construction Management and Supervision - 2008 Invoice Number - 4
Monthly Installment
Service Sum with VAT 70,236.05
Service Sum without VAT 61,074.83
Executed
Service sum previous 0.00
Service sum currently executed 70,236.05
Total Service sum 70,236.05
For Client
Name _____________________
Signature___________________
Date__________________________
ice Number - 4
Gomma Ana URRAP Construction Management and S
Project Name: Construction Management and Supervision of Gomma Ana Road Project -URRAP-
Project Location : Jimma Zone , Gomma and Gera Ana's
Type of work: Consultancy Services for URRAP Roads Construction Management and Supervision
Consultant: ABT Consulting Engineers Plc
Employer: Oromia Roads Authority/Gomma Anas Roads Authority
Procurment Reference Number:
Supplied Car Advance Payments for Gomma and Gera Ana Project
Estimated Cost of Leased Supplied Car (Repayment within 4 Year period)
is about ETB 735,000.00 (Seven hundred thirty five thousand birr only)
For Consultant
Name ________________________
Signature_____________________
Date_____________________________
AP Construction Management and Supervision - 2008 Invoice Number - 5
Monthly Installment
Service Sum with VAT 70,236.05
Service Sum without VAT 61,074.83
Executed
Service sum previous 0.00
Service sum currently executed 70,236.05
Total Service sum 70,236.05
For Client
Name _____________________
Signature___________________
Date__________________________
ice Number - 5
Gomma Ana URRAP Construction Management and S
Project Name: Construction Management and Supervision of Gomma Ana Road Project -URRAP-
Project Location : Jimma Zone , Gomma and Gera Ana's
Type of work: Consultancy Services for URRAP Roads Construction Management and Supervision
Consultant: ABT Consulting Engineers Plc
Employer: Oromia Roads Authority/Gomma Anas Roads Authority
Procurment Reference Number:
Supplied Car Advance Payments for Gomma and Gera Ana Project
Estimated Cost of Leased Supplied Car (Repayment within 4 Year period)
is about ETB 735,000.00 (Seven hundred thirty five thousand birr only)
For Consultant
Name ________________________
Signature_____________________
Date_____________________________
AP Construction Management and Supervision - 2008 Invoice Number - 6
Monthly Installment
Service Sum with VAT 70,236.05
Service Sum without VAT 61,074.83
Executed
Service sum previous 0.00
Service sum currently executed 70,236.05
Total Service sum 70,236.05
For Client
Name _____________________
Signature___________________
Date__________________________
ice Number - 6
Gomma Ana URRAP Construction Management and S
Project Name: Construction Management and Supervision of Gomma Ana Road Project -URRAP-
Project Location : Jimma Zone , Gomma and Gera Ana's
Type of work: Consultancy Services for URRAP Roads Construction Management and Supervision
Consultant: ABT Consulting Engineers Plc
Employer: Oromia Roads Authority/Gomma Anas Roads Authority
Procurment Reference Number:
Supplied Car Advance Payments for Gomma and Gera Ana Project
Estimated Cost of Leased Supplied Car (Repayment within 4 Year period)
is about ETB 735,000.00 (Seven hundred thirty five thousand birr only)
For Consultant
Name ________________________
Signature_____________________
Date_____________________________
AP Construction Management and Supervision - 2008 Invoice Number - 7
Monthly Installment
Service Sum with VAT 70,236.05
Service Sum without VAT 61,074.83
Executed
Service sum previous 0.00
Service sum currently executed 70,236.05
Total Service sum 70,236.05
For Client
Name _____________________
Signature___________________
Date__________________________
ice Number - 7
Gomma Ana URRAP Construction Management and S
Project Name: Construction Management and Supervision of Gomma Ana Road Project -URRAP-
Project Location : Jimma Zone , Gomma and Gera Ana's
Type of work: Consultancy Services for URRAP Roads Construction Management and Supervision
Consultant: ABT Consulting Engineers Plc
Employer: Oromia Roads Authority/Gomma Anas Roads Authority
Procurment Reference Number:
Supplied Car Advance Payments for Gomma and Gera Ana Project
Estimated Cost of Leased Supplied Car (Repayment within 4 Year period)
is about ETB 735,000.00 (Seven hundred thirty five thousand birr only)
For Consultant
Name ________________________
Signature_____________________
Date_____________________________
AP Construction Management and Supervision - 2008 Invoice Number - 8
Monthly Installment
Service Sum with VAT 70,236.05
Service Sum without VAT 61,074.83
Executed
Service sum previous 0.00
Service sum currently executed 70,236.05
Total Service sum 70,236.05
For Client
Name _____________________
Signature___________________
Date__________________________