Risks to the Project

Risk Suggested Mitigations

1. Sourcing parts; delays, incorrect, out 1. Allocated time for ordering and
of stock receiving parts should incorporate time
for delays and delivery problems

2. Motor; due to the price of motors such 2. Look into sourcing a free
as that which we require for our motor/company sponsorship/building a
system, there is a high chance that half scale model (where a smaller
purchasing such a motor will eat the therefore less expensive motor is
majority, if not all, of our budget required)/second hand motor

3. Manufacture; compliance of parts, not 3. Ordering parts well ahead of time


enough time i.e. manufacture takes should allow for manufacture delays. A
longer than predicted time line should be drawn up to stick
to.