Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 186

SUMMARY OF COST

S. No. Particulars
A Civil & Architectural Works
B Electrical Work
C Sanitary, Plumbing and Water Supply
Total(A+B+C)
Discount If Any
Total After Discount
VAT @ 13% :
Total Cost with VAT :
OF COST

Amount (NRs.)
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
ABSTRACT OF COST SHEET

0
0
0

S.N. DESCRIPTION UNIT QUANTITY


A. CIVIL WORKS
1 EARTH WORKS
1.1 EARTHWORK IN EXCAVATION :

Excavation in foundations in all type of soils for foundation,


trenches, footing, pits, basement, etc. to the required depth
including dewatering by manual or mechanical means etc. as per
specifications with all contractors own machinery and
equipments, providing crossing of track, shoring, strutting,
timbering and buttressing with appropriate materials and all such
CFT 4837.36
measures necessary to retain in position the sides of the
foundation pit and including refilling the excavated material with
watering, ramming, leveling the site and disposing off the
surplus/unusable earth to outside the construction premises, etc.
all complete as per drawings, specifications and instructions of the
Engineer.

1.2 EARTH BACK FILLING :

Back filling in foundation, floors and sides of foundation with


approved soil obtained from the excavation at site and stacked at
site in layer not exceeding 15 cm thick (compacted thickness)
1.2.1 including transportation of soil, spreading in required line and CFT 1934.94
level, sprinkling water, ramming, compacting with mechanical
rammers, testing, etc., all complete as per drawing, specification
and instructions of the Engineer.

1.3 FLAT BRICK SOLING

Providing and laying one layer dry brick on flat soling in foundation
and floor with approved chimney made first class brick in required
SFT 1615.70
line and level including filling joints with sand all complete as per
drawings, specifications and instructions of the Engineer.

2 CONCRETE WORKS
2.1 PLAIN CEMENT CONCRETE

Providing and laying machine mixed Plain Cement Concrete of


nominal mix 1:3:6 (1 cement : 3 sand : 6 coarse aggregate ) for
leveling course in foundations and floor of building, pathway, etc in
all level with broken stone aggregate of size not more than 25 mm
CFT 404.83
of approved quality including formwork wherever necessary,
dewatering, batching, mixing, transporting, placing, compacting,
curing, including all lead and lift, etc. all complete as per drawings,
specifications and the instructions of the Engineer.
2.2 P.C.C. FOR R.C.C. WORKS
Providing and laying in position machine mixed and machine
vibrated design mix cement concrete of specified grade for
reinforced cement concrete work using OPC 43 grade cement
with various design mixes (various grades of concrete) with 20
mm graded machine crushed stone aggregate of approved quality
in various locations and heights including transportation of
concrete to site of placing, compaction, finished to required line
and level, protection and curing, etc. all complete as per drawings,
specifications and the instructions of the Engineer, but excluding
the cost of centring, shuttering, and reinforcement, but including
the cost of admixtures in recommended proportions (as per
IS:9103) to accelerate, retard setting of concrete improve
workability, improve strength without imparing strength and
durability as per direction of Engineer for the following grades of
the structural concrete: (Mix design is essential)
- do - as above but M20 concrete with minimum cement content
2.2.1 of 360 kg/m3 at any location, level, height and shape as shown in CFT 3061.58
the drawings and schedule.
2.2.2 RCC in Pergola CFT 18.56
3 FORM WORK
Supplying and laying centering, shuttering of various pattern
formworks with 19/12 mm thick water proof ply wood & steel
adjustable props for all kinds of RCC works for foundations,
columns, shear walls, beams, slab, staircase, lintel, sill, pergola,
including nails, propping scaffolding, staging, supporting and
bracing in proper lines and level, sealing the joints with heavy duty SFT 8204.99
brown self adhesive tape, aligning to line and levels including
Ties, PVC Spacer, Providing openings/ cutouts/ pockets, applying
deshuttering chemical, deshuttering as approved by the Engineer
etc., complete at all levels as per drawing, specifications and
instructions of the Engineer.
3.1 FORMWORK IN PERGOLA SFT 74.81
4 REINFORCEMENT WORK
Providing and fixing in position Fe 500 steel reinforcement of
various diameter confirming to relevant IS code in R.C.C. works
including straightening, cutting, bending, binding with 20 SWG
annealed wire for tying the reinforcement bars at each junctions
(binding wire shall not be measured separately) including all waste
and cut pieces, provision for adequate numbers of spacers, KG #REF!
chairs, providing and placing cement mortar (1:1) cover blocks to
keep the bars in intended position at all levels all complete as per
drawings, specifications and instructions of the Engineer.
(Authorized lap length and for the bar length exceeding 10 meter
in length shall be measured for the payment).
5 BRICK/ STONE WORKS
5.1 BRICK MASONRY WORKS ( 1 : 6 c/s )
Providing and laying first class chimney fired brick one or more
brick thick wall in cement mortar 1:6 (1 cement : 6 coarse sand) in
foundation upto plinth,superstructure and other specified places in
all heights and level including the cost of single or multi stage
scaffolding, soaking bricks, curing, raking joints, provision for
recesses, openings, toothing etc., all complete as per drawing,
specifications and instructions of the Engineer.
5.1.1 Below foundation CFT 908.15
5.1.2 Superstructure CFT 2088.69
5.2 HALF BRICK WORKS ( 1 : 4 c/s )
Providing and laying non-fairfaced half brick work masonry in
cement mortar 1:4 (1 cement:4 sand) in superstructure with
approved first class fired bricks in perfect line & level, required
size and shape at any height and level, including the cost of single
or multi stage scaffolding, cutting bricks to match with the bond of
one or more brick thick wall, cleaning, soaking of the bricks, SFT 2003.90
packing of the joints, raking joints, provision for recesses,
openings, curing, providing 25x3mm GI Straps Fixed to columns
at every 5th course of brick and 60mm width 14 gauge welded GI
mesh anchored to GI strap, all complete as per design, drawing,
specifications instructions of the Engineer.
6 DOOR AND WINDOW WORK
6.1 WOODEN WORK
6.1.1 WOODEN FRAME

Wood work in frame for doors, etc with good finish of approved
seasoned Salwood including fixing with necessary hold fast, as CFT 20.411
per drawing, specification and instruction of engineer, all
complete.
6.1.2 PANEL DOOR SHUTTER

32mm thick Ready made pannel shutter with good finish including
3 Nos. of 10cm hinge per leaf, 2 Nos.of 15cm long approved SFT 266.63
quality tower bolts, 2 Nos. of approved quality handles.1 No.
M.S.hook bolt per leaf fixing on wooden frame and one set of
Mortise Lock, as per drawing, specification and instruction of
engineer, all complete.
6.1.3 WOODEN FRAME WITH JALEE

Wooden shutter with jalee good finish including 3 Nos. of 10cm SFT 40.50
hinge per leaf, 2 Nos.of 15cm long approved quality tower bolts, 2
Nos. of approved quality handles.1 No. M.S.hook bolt per leaf
fixing on wooden frame and one set of Mortise Lock, as per
drawing, specification and instruction of engineer, all complete.
6.2 ALUMINIUM WORK
Providing, fabricating and fixing in position approved colour pure
polyester powder coated extruded aluminum of Alloy 78 series
with Thai or Chinese or equivalent section aluminum work for
doors, windows, ventilators and partitions with extruded built up
standard tubular and other sections of approved make, fixed with
rawl plugs and screws or with fixing clips, or with expansion hold
fasteners including necessary filling up of gaps at junctions, at top,
bottom and sides with required PVC/neoprene felt etc. Aluminum
sections shall be smooth, rust free, straight, mitered and jointed
mechanically wherever required including cleat angle, Aluminum
snap beading for glazing / paneling, C.P. brass / stainless steel
screws, infill panels with the material as shown in drawings;
including the cost of door lock, hinges, handles, hydraulic type
door closer, stays, roller, etc. with all required hardware all
complete as per drawings, specifications and instruction of the
Engineer : for the followings types of aluminum works:
6.2.2 DOOR AND WINDOW WORK SFT 545.00
7 FLOORING WORK
7.1 VITRIFIED CERAMIC TILE FLOORING
Providing and fixing 1st quality vitrified ceramic tiles in required
line, level conforming to the standard mentioned in specification of
minimum thickness 8mm of approved make (Somany tiles or
equivalent) in any colours , shades of any size as approved by
Engineer in skirting, floor and stair over cement screed with
SFT 907.90
cement paste and joint filed with waterproof non-shrink polymer
joint mortar in required colour, including surface preparation,
scaffolding, protection, etc. all complete as per drawings,
specifications and instructions. Tile cost shall include the cost of
base screed/mortar. (Tile base price = NPR 100 per sq.ft.).
7.2 GLAZED CERAMIC WALL TILE
Providing and laying 1st quality ceramic glazed tiles conforming to
the IS:15622 Group B III standard of minimum thickness 6mm of
approved make in all colours , shades of any size as approved by
Engineer in skirting, risers of steps and dados over cement mortar
1:4 (1 cement : 4 sand) and joint filed with waterproof non-shrink SFT 779.44
polymer joint mortar in required colour, including surface
preparation, scaffolding, protection, cleaning, etc. all complete as
pr drawings, specifications and instructions of the Engineer. (Tile
base price = NPR 100 per sq.ft.).
7.3 ROOF TILE SFT 59.38
7.3.1 RIDGE TILE RFT 13.16
7.4 IPS FLOORING
Providing and laying in required line, level and pattern 35 - 38mm
thick cement concrete flooring comprising an under layer of

cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone

aggregate 20mm and down grade) and finished top layer with a
SFT 1834.22
floating coat of neat cement slurry, with coving at corners etc. all

complete as per drawings, specifications and instructions. The


depth and pattern of the cement floor finish shall be maintained

keeping on the view of the thickness of upcoming floor finish layer.


7.4.1 CEMENT SKIRTING

Providing, laying cement sand skirting 3" height with 18mm thick
cement sand plaster of mix 1:3 (1 cement : 3 sand) with top layer
of 3 mm thick neat cement finish including mixing, laying, rounding
RFT 548.80
of junctions of floor and skirting, curing, protection, etc., all
complete as per drawing, specification and instructions of the
Engineer.

7.5 MARBLE STAIRCASE


Providing and fixing in position 25 mm thick gang saw cut mirror
polished (premoulded and prepolished) machine cut marble for
Passage and similar locations of required size of approved
shade, colour and texture laid over 20 mm thick base cement
mortar 1:4 (1 cement : 4 coarse sand) with joints treated with
white cement mixed with matching pigment, epoxy touch ups,
including rubbing curing, molding, 4 numbers of flame cut groove SFT 193.06
at each tread, polishing to edge to give high gloss finish at all
level, etc., all complete as per drawing, specification and
instruction of the Engineer. [Rate shall include for preparation of
base surface & finished the surface, protection with gypsum/pop
layer over plastic sheet and removing the same before handing
over, work at all levels, as directed by the Engineer].
7.6 MARBLESKIRTING
- do - as 7.3.1 above, but for skirting with rounding top edge. RFT 49.58
7.7 WOODEN HAND RAIL
Providing, fabricating and fixing in position pre-fabricated stainless
steel staircase railing as per drawing with 2 rows of 25mm
diameter Stainless Steel (SS) pipe, 60mm diameter SS handrail of
304 grade, 16 SWG thick to be supported at a distance of
maximum of 1.5 meters with a SS (304 grade) Balustrade to be RFT 49.58
fixed to the concrete member with anchor fasteners and the flats
with holes of 10 mm dia with all labour and materials and
consumables, grinding, milling, polishing etc. all complete as per
drawings, specifications and instructions of the Engineer.
8 PLASTER WORK
8.1 20MM THICK INTERNAL PLASTER WORK
Providing and applying at all levels and shape 20 mm thick
cement plaster in building inside in specified cement mortar in two
layers as 6 to 8 mm thick final coat with 1:6 (1 cement :6 fine
sand) cement mortar over the 12 to 14 mm thick 1:6 (1 cement : 6
coarse sand) under coat in all surface at all height including
mixing mortar, laying in perfect line, level and plumb and
finishining in regular and even surface including all necessary
single or multi-stage scaffolding, providing and fixing 200 mm wide
24 gauge GI Chicken wire mesh at junction of R.C.C. and SFT 6142.66
masonry, providing and fixing G.I. corner beads (in all edges of
plaster, free standing (isolated) columns, column projection),
making grooves and recesses, throating, dusting, dripping,
wetting, curing, protection, etc., all complete as per drawing ,
specification and instruction of the Engineer. [Rate shall also
include for providing drips band, moulds, groove, chicken wire
mesh at junction of RCC and masonry, G.I. Corner Beads, etc., to
complete the works at any heights].
8.2 CEILING WORK
12.5.mm, thick cement and sand plaster work of mix 1:4 (1
cement & 4 sand) in concrete surface, ceiling surface at all height
including mixing mortar, laying in perfect line, level and plumb and
finishing in regular and even surface including all necessary single
or multi-stage scaffolding, providing and fixing 200 mm wide 24
gauge GI Chicken wire mesh at junction of R.C.C. and
SFT 2019.86
masonry,making grooves and recesses, throating, dusting,
dripping, wetting, curing, protection, etc. all complete as per
drawing , specification and instruction. [Rate shall also include for
providing drips band, moulds, groove, chicken wire mesh at
junction of RCC and masonry, etc., to complete the works at any
heights].
8.3 20MM THICK OUTER PLASTER
Providing and applying at all levels and shape 20 mm thick
cement plaster in building exterior area in specified cement mortar
in two layers as 6 to 8 mm thick final coat with 1:5 (1 cement : 5
fine sand) cement mortar over the 12 to 14 mm thick 1:5 (1
cement : 5 coarse sand) under coat in all surface at all height
including mixing mortar, laying in perfect line, level and plumb and
finishing in regular and even surface including all necessary single
SFT 6171.19
or multi-stage scaffolding, providing and fixing 24 gauge GI
Chicken wire mesh at junction of R.C.C. and masonry, making
grooves and recesses, throating, dusting, dripping, wetting, curing,
protection, etc., all complete as per drawing , specification and
instruction of the Engineer. [Rate shall also include for providing
drips band, moulds, groove, chicken wire mesh at junction of RCC
and masonry, etc., to complete the works at any heights].
8.3.1 PLASTER IN PERGOLA SFT 99.00
9 WATER PROOF CEMENT PAINTING WORK
9.1 WATERPROOF CEMENT PAINTING WORKS
Providing and applying two or more coats of Silk Emulsion Paint
over a coat of cement primer of approved manufacturer as per

manufacturer's specifications to the surface of wall, ceiling, beams


columns, canopies, staircase, lobbies etc, all complete as per

drawings, specifications and instruction. The rates shall include


for scraping, washing the surface with water, surface preparation,

scaffolding etc., all complete as per the manufacturer's


recommendations and as approved by the Engineer.
9.1.1 Interior Painting Works ( Wall & Ceiling) SFT 8074.52
9.2 EXTERIOR WEATHER COAT PAINT

Providing and applying two or more coats of first quality hundred


percent acrylic paint (Apex weatherproof external emulsion or
approved equivalent manufactured by Asian Paints, Berger Paints,
or ICI, ) of approved shade and pattern to the exterior walls of
buildings etc., The rates shall include for scrapping etc., washing SFT 6171.19
the surface with water, applying a coat of approved quality water
base cement primer, surface preparation, scaffolding etc., all
complete as per the manufacturer's recommendations and as
approved by the Engineer.

9.2.1 OUTER WEATHER COAT PAINT IN PERGOLA SFT 99.00


10 MS PIPE KG 1111.89
11 SPIRAL IRON STAIRCASE

4"-6" Medium quality black pipe post with .5"x.5" square pipe
with black pipe hand rail of 1.25" used in making spiral iron
JOB 1.00
staircase of width 2'- 6" all completed as per specifications,
instructions and drawings.
12 GATE JOB 1.00
Total of Civil Works (without VAT) - Carried over to Summary :
B. ELECTRICAL WORK
1 FINAL DISTRIBUTION BOARDS
Design, fabrication, supply, delivery, installation, testing and
commissioning of fully enclosed front door operation double cover,
flush mounting following types of Final Distribution Boards F(DBs)
fabricated out of 1.6 mm steel sheet having separate
compartments for Incoming and Outgoing systems including all
fixing and connecting materials as per drawings specification and
instructions .(MCB Siemens/GE)

1.1 Main Distribution Panel/Board Nos. #REF!


Incoming
1 No 20 A TP MCB
Outgoing
24 Nos 16/10/6 A SP MCB
Copper Phase Bar, Neutral and Earth bars
1.2 Sub Distribution Board Nos. #REF!
Incoming
1 No 20 A TP MCB
Outgoing
12 Nos 16/10/6 A SP MCB
Copper Phase Bar, Neutral and Earth bars
1.3 Meterbox Nos. #REF!
2 CIRCUIT CUM POINT WIRING
2.1 General Service Light/Fan/Exhaust Fan Point Wiring

Supplying, wiring, testing and commissioning and putting into


operation for lights, ceiling fans, exhaust fans points using 2.5 sq
mm stranded copper conductor, 1100 volts grade, PVC insulated
wires drawn through pre installed PVC Pipe, cable
sleeves/support but including specifiied dia HDP pipes concealed
in wall and floor including all fixing and connecting materials. The
rate for point wiring shall include the circuit wiring from deginated
Distribution Board(DB) up to the first light/fan/control switch on
wards to light/fan then the looping between switches/ lights/fans/
etc.(No cable jointing is allowed except switch and fixture). The
cost shall be including modular plate flushed in required size of GI
box, but including GI fish wire, cutting and filling chases for
recessed pipes as deemed as per drawing and lay out plan all
complete.

2.1.1 One way Light/Fan Pts. #REF!


3 SWITCHES AND POWER SOCKETS
3.1 6/16 A Round Pin and 15 A Flat Pin Power Point Wiring (15A)
Nos. #REF!
3.2 5 A Socket Nos.
Supply, installation, testing and commissioning of following types
of modular formation flush mounted switch socket including GI
box to be installed in specified location and height all complete.
(Delta Vega, North West or equvalent)

4 LIGHTING FIXTURES AND ACCESSORIES


Light Fixture/Luminaire
Supply, storing, assembling, installation, testing and
commissioning of wall/ceiling, surface/recessed, suspended types
Flourescent/CFL lighting fixtures including lamp, power factor
improvement capacitor electronic ballast, control gear etc. and
including making connections with 1.5 Sq.mm PVC insulated
copper conductor wire complete as per specification(Wipro,
Decon, Homdec, Fiam or equvalent)

4.1 1X36 W Decorative FTL- Dome light make Homedec, Decon,


Fumagalli or equivalent -8" Brass base decorative dome light Nos. #REF!

4.2 Chandler light- Dome light make Homedec, Decon, Fumagalli or


equivalent- Chandlers 6-8 lamp medium Nos.

4.3 Foot recessed light- fluorescent tube light(FTL) set including tube,
condenser,starter, lamp holder, channel/batten made with pre-
phospated and powder coated CRCA steel all complete
accessories pre wired upto a terminal block. Philips, Wipro,Bajaj,
Havells, Osram, Crompton, Midea, Orient, Premier, Ohms, Legero Nos.
or equivalent - IP20 and IP65 non integral flexible LED Strip light
LS 06/26

4.4 Dome light- Dome light make Homedec, Decon, Fumagalli or


equivalent -8" Brass base decorative dome light Nos.

4.5 Exhaust Fan- Ceiling fans and exhaust fans,


Bajaj/Khaita/Orient/Crompton/Powerpack C/G. Almonard or Nos.
equivalent- 9" Exhaust Fan
4.6 Mirror light- Dome light make Homedec, Decon, Fumagalli or
equivalent- Wall bracket/ spot light/ mirror light/ bulk head medium Nos.
decorative
4.7 Wall light- Dome light make Homedec, Decon, Fumagalli or
equivalent- Wall bracket/ spot light/ mirror light/ bulk head medium Nos.
decorative
4.8 Pendent light- Dome light make Homedec, Decon, Fumagalli or
Nos.
equivalent- Dining Lamp
4.9 Call bell unit- Bell indicator- 4 way bell indicator with plate
Nos.
4.10 Telephone socket- Dyana White Plate Series Switch Socket
Anchor/ CPL/ NG/ Flux or ISI equivalent- Telephone Socket Nos.

4.11 Television socket- Dyana White Plate Series Switch Socket


Anchor/ CPL/ NG/ Flux or ISI equivalent- Television Socket Nos.

4.12 Internet socket- Dyana White Plate Series Switch Socket Anchor/
CPL/ NG/ Flux or ISI equivalent- RJ 45 8 way Computer Socket Nos.

4.14 TV Cable junction box- Sockets/ Telephone/ Computer Sockets/


TV Sockets- PVC Junction Box (8" x 10") Nos.

Total of Electrical Works (without VAT) - Carried over to Summary :


C. SANITARY WORK
1 SANITARY INSTALLATION
1.1 White glazed porcelain clay EWC Constellation commode with 'P'
and "S' trap and seat cover set. (Hindware, Paryware, Somany,
cera or equivalent.) Set #REF!

1.2 White glazed porcelian clay U-counter basin (Duravit, Grohe,


American Standard, Thai or equivalent.) complete set. Set

1.3 CP Soap Dish 150x150mm- Manufactured from C.P.- C.P. Soap


Nos.
Dish (Polyurethane)
1.4 5 mm thick looking mirror of approved make with CP mirror screws
Nos.
and clips, size 550x400mm
1.5 PVC Multi-floor trap with cover Nos.
1.6 150mmx150mm CP Paper holder- C.P. Accessories (Jacquar,
Somany, Essel or Equivalent)- toilet paper holder Set

1.7 Towel Holder- C.P. Accessories (Jacquar, Somany, Essel or


Equivalent)- Towel rod 3/4" x 24" size Set

1.8 Hand Spray Set


1.9 Shower Set
1.10 Stainless Steel Kitchen Sink mixture ( Grohe, Somany, Essel or
Set
equivalent)
2 WATER SUPPLY INSTALLATION
2.1 Astral or equivalent brand CPVC pipes SDR 13.5 including
clamps, nails and hooks, and all necessary CPVC specials
required for complete installation, cutting, jointing, sealing of joints
etc, installation of pipes and specials including making holes on
walls or floor and repairing the same to its original finish,
excavation and backfill in any type of soil. Pipes to be installed on
trenches or walls od floor as per drawings, specifications and
instructions, cleaning of the system, testing and ready for
operation. Measurements to be taken for running length of pipe
installed. The rate shall be inclusive of all necessary fittings but
excluding gate valves which shall be payable seperately.

2.1.1 CPVC Pipe SDR 11.5 (22.5 Kg/cm2)-32mm (1.25") dia.-


Chlorinated Poly Vinyl Chloride as per ASTM, CPVC SOLVENT
are as per ASTM F-493 2846 (Flowguard:astral, ajay, hilltake, RM #REF!
mangalam flow life, marvel or equivalent

2.1.2 CPVC Pipe SDR 11.5 (22.5 Kg/cm2)-25 mm (1") dia.- Chlorinated
Poly Vinyl Chloride as per ASTM, CPVC SOLVENT are as per
ASTM F-493 2846 (Flowguard:astral, ajay, hilltake, mangalam RM
flow life, marvel or equivalent

2.1.3 CPVC Pipe SDR 11.5 (22.5 Kg/cm2)-25 mm (1") dia.- Chlorinated
Poly Vinyl Chloride as per ASTM, CPVC SOLVENT are as per
ASTM F-493 2846 (Flowguard:astral, ajay, hilltake, mangalam RM
flow life, marvel or equivalent

2.2 CPVC Ball Valve


2.2.1 CPVC Ball Valve (CTS Sockets)-32 mm (1.25") dia.- Chlorinated
Poly Vinyl Chloride as per ASTM, CPVC SOLVENT are as per
ASTM F-493 2846 (Flowguard:astral, ajay, hilltake, mangalam No. #REF!
flow life, marvel or equivalent

2.2.2 CPVC Ball Valve (CTS Sockets)-25 mm (1") dia.- Chlorinated Poly
Vinyl Chloride as per ASTM, CPVC SOLVENT are as per ASTM F-
493 2846 (Flowguard:astral, ajay, hilltake, mangalam flow life, No.
marvel or equivalent

Roof Top PVC Water Tank- 200 lit - 5000 lit cap. (Aluminium
2.3 Nos.
Grating 4" dia.)
2.4 Stand for Water Tank Nos.
3 SEWER, RAIN AND WASTE WATER INSTALLATION

3.1 PVC Pipe including cutting, jointing, sealing with rubber washer
and solvent cement and all necessary rubber ringed moulted
fittings such as Tees, Y-Tees, Bend (with or without doors),
Reducers, Couplers, connector pieces, offsets etc. for complete
installation, PVC clamps, nails and hooks. Installation of pipes and
specials including making holes on walls or floor and repairing the
same to its original finish, excavation and backfill (compaction as
per civil works specifications) in any type of soil. Pipes to be
installed on trenches or walls or floor or hung to ceilings as per
drawings, specifications and instructions, cleaning of the system,
testing and ready for operation. The rate shall include for all
labour and materials required. The measurement shall be done for
running metre, fittings etc not payable seperately.

3.1.1 PVC Pipe -110 mm ED 4 kg/cm2 RM #REF!


3.1.2 PVC Pipe -75 mm ED 4 kg/cm2 RM
4 Tap- C.P. Accessories( Jacquar, Somany, Essel or Equivalent)-
Nos.
C.P. 15mm Bib Cock
Total of Sanitary Works (without VAT) - Carried over to Summary :

GRAND TOTAL WITHOUT VAT


VAT @ 13%
GRAND TOTAL AMOUNT (Nrs)
RATE AMOUNT

15.00 72560.42

11.00 21284.39

98.00 158338.60

370.00 149787.56
522.00 1598144.16

678.60 12596.51

96.00 787679.50

124.80 9336.60

117.00 #REF!
418.00 379608.31
427.00 891870.23

186.00 372724.80

9559.14 195114.10

770.54 205444.97

580.95 23528.39
596.00 324820.00

420.00 381316.74

420.00 327364.80

282.00 16743.75
398.00 5237.68
80.00 146737.82

78.00 42806.40

304.77 58839.51

147.21 7298.45
717.07 35552.56

45.00 276419.70

43.00 86853.89
46.00 283874.90

59.80 5920.20

29.00 234161.02

23.00 141937.45

29.90 2960.10
157.00 174566.20

11000.00 11000.00
150000.00 150000.00
y: #REF!

#REF! #REF!

#REF! #REF!

#REF! #REF!

#REF! #REF!

#REF! #REF!
35618.00
#REF! #REF!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

ary : #REF!
#REF! #REF!

#VALUE!

#VALUE!

#VALUE!
#VALUE!

#VALUE!

#VALUE!

#VALUE!
#VALUE!
#VALUE!

#REF! #REF!

#VALUE!

#VALUE!
#REF! #REF!

#VALUE!

#VALUE!
#VALUE!

#REF! #REF!
#VALUE!
#VALUE!
ary : #REF!

RAND TOTAL WITHOUT VAT #REF!


VAT @ 13% #REF!
AND TOTAL AMOUNT (Nrs) #REF!
S.No. DESCRIPTION UNIT QUANTITY

1 FLAT BRICK SOLING SQM 150.16


2 PCC CUM 11.46
3 PCC FOR RCC WORKS CUM 86.68
4 RCC IN PERGOLA CUM 0.53
5 REINFORCEMENT KG #REF!
6 BRICKWORK
6.1 Below foundation CUM 25.71
6.2 Superstructure CUM 59.14
7 HALF BRICK WORK SQM 186.24
8 TILE FLOORING SQM 84.38
9 WALL TILE SQM 72.44
10 ROOF TILE SQM 5.52
11 RIDGE TILE SQM 4.01
12 IPS FLOORING SQM 170.47
13 MARBLE STAIRCASE SQM 17.94
13 INTERNAL PLASTER SQM 570.88
10 OUTER PLASTER SQM 573.53
11 OUTER PLASTER IN PERGOLA SQM 9.20
TOTAL
QUANTITY IN CFT
RATE
AMOUNT
TOTAL AMOUNT

DESCRIPTION BRICK (NO.) CEMENT-OPC (BAGS)

UPTO DPC LEVEL 26793 265

WATER TANK 256 37

GROUND FLOOR 11409 178

FIRST FLOOR 12665 177

SECOND FLOOR 15240 103

TOTAL 66363 760


MATERIALS BREAKDOWN

BRICK (NO.) CEMENT-OPC (BAGS) CEMENT- PPC (BAGS) SAND (CUM)

6308.00
52.00 5.39
695.00 36.84
6.00 0.22

14400.00 37.00 7.71


33117.00 84.00 17.74
12535.00 42.00 5.59
12.00 1.27
10.00 1.09
2.00 0.08
2.00 0.06
46.00 3.07
6.00 0.32
67.00 13.42
81.00 12.33
3.00 0.20
66360 753 389 105.1246121
66360 753 389 3713.00
16 850 850 97
1061760 640050 330650 360161.13
#REF!

CEMENT-PPC (BAGS) SAND (CUM) AGGREGATE (CUM) STEEL

74 30.543 32.71 3523.42

1.93 3.87 747.83

96 23.531 22.25 3168.73

114 25.89 21.3 2869.89

111 23.509 12.23 1826.33

395 105.403 92.36 12136.20


AGGREGATE (CUM) STEEL (KG) G.I. BINDING WIRE (KG)

10.20
74.55
0.45
#REF! 200.00

6.14

91.34 #REF! 200


3225.97 #REF! 200
82.35 78 89
265658.90 #REF! 17800
MEASUREMENT SHEET

0
0
0

S.N. DESCRIPTION NO LENGTH


A. CIVIL WORKS
1 EARTH WORKS
1.1 SITE CLEARANCE 1
TOTAL
1.2 EARTHWORK IN EXCAVATION
FOR FOOTING
F 4 6.00
F1 8 6.50
F2 1 7.50
FOR SUBSTRUCTURE
GRID 1-1 1 6.25
GRID 2-2 1 6.00
GRID 4-4 1 5.50
GRID 5-5 1 6.25
GRID A-A 1 17.42
GRID B-B 1 15.42
GRID C-C 1 23.42
FOR STRAP BEAM
GRID 1-1 1 4.25
GRID 3-3 1 3.75
GRID 4-4 1 3.25
GRID 5-5 1 4.25
FOR TOE WALL
OUTSIDE 1-1
1 4.25
1 4.25
1 5.50
BOUNDARY WALL
1 16.00
1 31.58
1 54.17
1 31.58
FOR WATER TANK
1 15.00
SEPTIC TANK
1 9.00
SOAK PIT
1 28.27
TOTAL EARTHWORK EXCAVATION
1.3 EARTH BACK FILLING :
40% OF EARTHWORK EXCAVATION
TOTAL EARTH BACK FILLING
1.4 FLAT BRICK SOLING
FOR FOOTING
F 4 5.50
F1 8 6.00
F2 1 7.00
FOR SUBSTRUCTURE
GRID 1-1 1 6.25
GRID 2-2 1 6.00
GRID 4-4 1 5.50
GRID 5-5 1 6.25
GRID A-A 1 17.42
GRID B-B 1 15.42
GRID C-C 1 23.42
FOR STRAP BEAM
GRID 1-1 1 4.25
GRID 3-3 1 3.75
GRID 4-4 1 3.25
GRID 5-5 1 4.25
FOR TOE WALL
OUTSIDE 1-1
1 4.25
1 4.25
1 5.50
FOR ROOM
AB12 1 79.58
AB24 1 158.13
AB45 1 146.63
BC13 1 151.46
BC34 1 86.25
BC45 1 146.63
FOR WATER TANK
1 14.50
BOUNDARY WALL
1 16.00
1 31.58
1 54.17
1 31.58
SEPTIC TANK
1 8.50
TOTAL FLAT BRICK SOLING
1.5 DIGGING WELL FOR WATER
1 70.00
TOTAL
2 CONCRETE WORKS
2.1 PLAIN CEMENT CONCRETE
FOR FOOTING
F 4 5.50
F1 8 6.00
F2 1 7.00
FOR SUBSTRUCTURE
GRID 1-1 1 6.25
GRID 2-2 1 6.00
GRID 4-4 1 5.50
GRID 5-5 1 6.25
GRID A-A 1 17.42
GRID B-B 1 15.42
GRID C-C 1 23.42
FOR STRAP BEAM
GRID 1-1 1 4.25
GRID 3-3 1 3.75
GRID 4-4 1 3.25
GRID 5-5 1 4.25
FOR TOE WALL
OUTSIDE 1-1
1 4.25
1 4.25
1 5.50
FOR ROOM
AB12 1 79.58
AB24 1 158.13
AB45 1 146.63
BC13 1 151.46
BC34 1 86.25
BC45 1 146.63
FOR WATER TANK
1 14.50
BOUNDARY WALL
1 16.00
1 31.58
1 54.17
1 31.58
SEPTIC TANK
1 8.50
TOTAL PLAIN CEMENT CONCRETE
2.2 P.C.C. FOR R.C.C. WORKS
2.2.1 RCC[1:1.5:3] WORK
FOR FOOTING
F
RECTANGULAR PORTION 2 5.00
TRAPEZOIDAL PORTION 2 13.89
F (WITH STRAP BEAM)
RECTANGULAR PORTION 2 5.00
TRAPEZOIDAL PORTION 2 13.89
F1
RECTANGULAR PORTION 3 5.50
TRAPEZOIDAL PORTION 3 16.52
F1(WITH STRAP BEAM)
RECTANGULAR PORTION 5 5.50
TRAPEZOIDAL PORTION 5 16.52
F2
RECTANGULAR PORTION 1 6.50
TRAPEZOIDAL PORTION 1 22.52
FOR STRAP BEAM
GRID A-A 1 4.25
GRID B-B 1 3.75
GRID C-C 1 3.25
GRID D-D 1 4.25
FOR LOWER TIE BEAM
GRID 1-1 1 23.00
GRID 2-2 1 11.50
GRID 3-3 1 11.50
GRID 4-4 1 23.00
GRID 5-5 1 23.00
GRID A-A 1 33.42
GRID B-B 1 32.42
GRID C-C 1 33.42
FOR UPPER TIE BEAM
GRID 1-1 1 23.00
GRID 2-2 1 11.50
GRID 3-3 1 11.50
GRID 4-4 1 23.00
GRID 5-5 1 23.00
GRID A-A 1 33.42
GRID B-B 1 32.42
GRID C-C 1 33.42
OUTSIDE 1-1
1 4.25
1 4.25
1 5.50
FOR WATER TANK
2 14.00
2 4.25
2 14.00
SOAK PIT
1 12.57
SEPTIC TANK
2 8.00
COLUMN
UPTO DPC LEVEL
13 1.00
GROUND FLOOR
13 1.00
FIRST FLOOR
13 1.00
SECOND FLOOR
8 1.00
PROJECTION
8 1.00
BEAM
GROUND FLOOR
GRID 1-1 1 23.00
GRID 2-2 1 11.50
GRID 3-3 1 11.50
GRID 4-4 1 23.00
GRID 5-5 1 23.00
GRID A-A 1 33.42
GRID B-B 1 36.67
GRID C-C 1 37.67
FIRST FLOOR
GRID 1-1 1 28.50
GRID 2-2 1 11.50
GRID 3-3 1 11.50
GRID 4-4 1 23.00
GRID 5-5 1 23.00
GRID A-A 1 33.42
GRID B-B 1 36.67
GRID C-C 1 37.67
SECOND FLOOR
GRID 2-2 1 11.50
GRID 4-4 1 23.00
GRID 5-5 1 23.00
GRID A-A 1 12.75
GRID B-B 1 26.50
GRID C-C 1 26.50
SLAB
GROUND FLOOR
1 1027.80
STAIRCASE CORRIDOR 1 59.54
FIRST FLOOR
1 1027.80
STAIRCASE CORRIDOR 1 59.54
SECOND FLOOR
1 400.66
STAIRCASE CORRIDOR 1 59.54
STAIRCASE
GROUND FLOOR TO FIRST FLOOR
FIRST FLIGHT
WAIST SLAB 1 18.76
STEPS 6 0.81
LANDING 1 9.35
SECOND FLIGHT
WAIST SLAB 1 14.00
STEPS 4 0.81
THIRD FLIGHT
WAIST SLAB 1 18.76
STEPS 6 0.81
LANDING 1 6.44
FIRST FLOOR TO SECOND FLOOR
FIRST FLIGHT
WAIST SLAB 1 18.76
STEPS 6 0.81
LANDING 1 9.35
SECOND FLIGHT
WAIST SLAB 1 11.62
STEPS 4 0.81
THIRD FLIGHT
WAIST SLAB 1 18.76
STEPS 6 0.81
LANDING 1 6.44
GROUND FLOOR
SILL BAND
GRID 1-1
1 11.50
GRID 2-2
1 7.50
GRID 4-4
1 16.50
GRID 5-5
1 23.00
GRID A-A
1 33.42
GRID B-B
1 11.17
1 12.75
GRID C-C
1 26.75
BETWEEN 4-4 AND 5-5
1 8.50
BETWEEN 3-3 AND 4-4
1 7.83
BETWEEN A-A AND B-B
1 3.33
1 1.00
BETWEEN B-B AND C-C
1 2.33
LINTEL
GRID 1-1
1 11.50
GRID 2-2
1 7.50
GRID 4-4
1 16.50
GRID 5-5
1 23.00
GRID A-A
1 33.42
GRID B-B
1 11.17
1 12.75
GRID C-C
1 26.75
BETWEEN 4-4 AND 5-5
1 8.50
BETWEEN 3-3 AND 4-4
1 7.83
BETWEEN A-A AND B-B
1 3.33
1 1.00
BETWEEN B-B AND C-C
1 2.33
FIRST FLOOR
SILL BAND
GRID 1-1
1 16.00
GRID 2-2
1 11.50
GRID 3-3
1 8.50
GRID 4-4
1 17.00
GRID 5-5
1 17.00
GRID A-A
1 34.17
GRID B-B
1 4.25
1 6.25
1 12.75
GRID C-C
1 34.67
BETWEEN 3-3 AND 4-4
1 7.83
BETWEEN B-B AND C-C
1 4.42
1 2.33
LINTEL
GRID 1-1
1 16.00
GRID 2-2
1 11.50
GRID 3-3
1 8.50
GRID 4-4
1 17.00
GRID 5-5
1 17.00
GRID A-A
1 34.17
GRID B-B
1 4.25
1 6.25
1 12.75
GRID C-C
1 34.67
BETWEEN 3-3 AND 4-4
1 7.83
BETWEEN B-B AND C-C
1 4.42
1 2.33
SECOND FLOOR
SILL BAND
GRID 2-2
1 11.50
GRID 4-4
1 8.50
1 8.50
GRID 5-5
1 17.00
BETWEEN 3-3 AND 4-4
1 7.83
GRID A-A
1 12.75
GRID B-B
1 7.75
1 12.75
GRID C-C
1 22.50
BETWEEN B-B AND C-C
1 1.67
LINTEL
GRID 2-2
1 11.50
GRID 4-4
1 8.50
1 8.50
GRID 5-5
1 17.00
BETWEEN 3-3 AND 4-4
1 7.83
GRID A-A
1 12.75
GRID B-B
1 7.75
1 12.75
GRID C-C
1 22.50
BETWEEN B-B AND C-C
1 1.67
TOP OF PARAPET
TOP FLOOR 1 75.00
FOR POST 30 0.75
ROOF TOP 1 130.00
FOR POST 50 0.75
BOUNDARY WALL COLUMN
24 0.75
BOUNDARY WALL TOP BAND
1 16.00
1 31.58
1 54.17
1 31.58
TOTAL RCC WORK IN ALL FLOOR
2.2.2 RCC IN PERGOLA
SECOND FLOOR
X-DIRECTION 5 3.00
Y-DIRECTION 3 6.00
TOTAL RCC WORK IN PERGOLA
3.00 FORM WORK
FOR PCC WORK
FOOTING
FOR FOOTING
F 4 22.00
F1 8 24.00
F2 1 28.00
FOR SUBSTRUCTURE
GRID 1-1 2 6.25
GRID 2-2 2 6.00
GRID 4-4 2 5.50
GRID 5-5 2 6.25
GRID A-A 2 17.42
GRID B-B 2 15.42
GRID C-C 2 23.42
FOR STRAP BEAM
GRID 1-1 2 4.25
GRID 3-3 2 3.75
GRID 4-4 2 3.25
GRID 5-5 2 4.25
FOR TOE WALL
OUTSIDE 1-1
2 4.25
2 4.25
2 5.50
FOR WATER TANK
1 38.50

FOR RCC WORK


FOOTING
F 4 20.00
F1 8 22.00
F2 1 26.00
FOR STRAP BEAM
GRID A-A 2 4.25
GRID B-B 2 3.75
GRID C-C 2 3.25
GRID D-D 2 4.25
FOR LOWER TIE BEAM
GRID 1-1 2 23.00
GRID 2-2 2 11.50
GRID 3-3 2 11.50
GRID 4-4 2 23.00
GRID 5-5 2 23.00
GRID A-A 2 33.42
GRID B-B 2 32.42
GRID C-C 2 33.42
FOR UPPER TIE BEAM
GRID 1-1 2 23.00
GRID 2-2 2 11.50
GRID 3-3 2 11.50
GRID 4-4 2 23.00
GRID 5-5 2 23.00
GRID A-A 2 33.42
GRID B-B 2 32.42
GRID C-C 2 33.42
OUTSIDE 1-1
2 4.25
2 5.50
2 4.25
FOR WATER TANK
SIDE WALL 4 14.00
SIDE WALL 4 5.25
SIDE FOR BOTTOM SLAB 1 38.50
TOP SLAB 1 66.50
SIDE FOR TOP SLAB 1 38.50
SOAK PIT
1 28.27
SEPTIC TANK
FOR BASE 2 9.00
2 6.00
FOR TOP 1 9.00
1 30.00
COLUMN
UPTO DPC LEVEL
13 4.00
GROUND FLOOR
13 4.00
FIRST FLOOR
13 4.00
SECOND FLOOR
8 4.00
PROJECTION
8 4.00
BEAM
GROUND FLOOR
GRID 1-1 2 28.50
GRID 2-2 2 11.50
GRID 3-3 2 11.50
GRID 4-4 2 23.00
GRID 5-5 2 23.00
GRID A-A 2 33.42
GRID B-B 2 36.67
GRID C-C 2 37.67
FIRST FLOOR
GRID 1-1 2 28.50
GRID 2-2 2 11.50
GRID 3-3 2 11.50
GRID 4-4 2 23.00
GRID 5-5 2 23.00
GRID A-A 2 33.42
GRID B-B 2 36.67
GRID C-C 2 37.67
GRID D-D 2 20.50
SECOND FLOOR
GRID 2-2 2 11.50
GRID 4-4 2 23.00
GRID 5-5 2 23.00
GRID A-A 2 12.75
GRID B-B 2 26.50
GRID C-C 2 26.50
SLAB
GROUND FLOOR
1 1027.80
ABOVE STAIRCASE 1 59.54
FIRST FLOOR
1 1027.80
ABOVE STAIRCASE 1 59.54
SECOND FLOOR
1 400.66
ABOVE STAIRCASE 1 59.54

STAIRCASE
GROUND FLOOR TO FIRST FLOOR
FIRST FLIGHT WAIST SLAB 1 5.36
1 3.50
1 5.36
FIRST FLIGHT STEPS 6 3.50
1 5.36
FIRST LANDING 1 3.50
2 3.50

SECOND FLIGHT WAIST SLAB 1 4.00


1 3.50
1 4.00
SECOND FLIGHT STEPS 4 3.50
1 4.00

THIRD FLIGHT WAIST SLAB 1 5.36


1 3.50
1 5.36
THIRD FLIGHT STEPS 6 3.50
1 5.36
THIRD LANDING 1 3.50
2 3.50
FIRST FLOOR TO SECOND FLOOR
FIRST FLIGHT WAIST SLAB 1 5.36
1 3.50
1 5.36
FIRST FLIGHT STEPS 6 3.50
1 5.36
FIRST LANDING 1 3.50
2 3.50

SECOND FLIGHT WAIST SLAB 1 4.00


1 3.50
1 4.00
SECOND FLIGHT STEPS 4 3.50
1 4.00

THIRD FLIGHT WAIST SLAB 1 5.36


1 3.50
1 5.36
THIRD FLIGHT STEPS 6 3.50
1 5.36
THIRD LANDING 1 3.50
2 3.50
GROUND FLOOR
SILL BAND
GRID 1-1
2 11.50
GRID 2-2
2 7.50
GRID 4-4
2 16.50
GRID 5-5
2 23.00
GRID A-A
2 33.42
GRID B-B
2 11.17
2 12.75
GRID C-C
2 26.75
BETWEEN 4-4 AND 5-5
2 8.50
BETWEEN 3-3 AND 4-4
2 7.83
BETWEEN A-A AND B-B
2 3.33
2 1.00
BETWEEN B-B AND C-C
2 2.33
LINTEL
GRID 1-1
2 11.50
GRID 2-2
2 7.50
GRID 4-4
2 16.50
GRID 5-5
2 23.00
GRID A-A
2 33.42
GRID B-B
2 11.17
2 12.75
GRID C-C
2 26.75
BETWEEN 4-4 AND 5-5
2 8.50
BETWEEN 3-3 AND 4-4
2 7.83
BETWEEN A-A AND B-B
2 3.33
2 1.00
BETWEEN B-B AND C-C
2 2.33
FIRST FLOOR
SILL BAND
GRID 1-1
2 16.00
GRID 2-2
2 11.50
GRID 3-3
2 8.50
GRID 4-4
2 17.00
GRID 5-5
2 17.00
GRID A-A
2 34.17
GRID B-B
2 4.25
2 6.25
2 12.75
GRID C-C
2 34.67
BETWEEN 3-3 AND 4-4
2 7.83
BETWEEN B-B AND C-C
2 4.42
2 2.33
LINTEL
GRID 1-1 2
2 16.00
GRID 2-2
2 11.50
GRID 3-3
2 8.50
GRID 4-4
2 17.00
GRID 5-5
2 17.00
GRID A-A
2 34.17
GRID B-B
2 4.25
2 6.25
2 12.75
GRID C-C
2 34.67
BETWEEN 3-3 AND 4-4
2 7.83
BETWEEN B-B AND C-C
2 4.42
2 2.33
SECOND FLOOR
SILL BAND
GRID 2-2
2 11.50
GRID 4-4
2 8.50
2 8.50
GRID 5-5
2 17.00
BETWEEN 3-3 AND 4-4
2 7.83
GRID A-A
2 12.75
GRID B-B
2 7.75
2 12.75
GRID C-C
2 22.50
BETWEEN B-B AND C-C
2 1.67
LINTEL
GRID 2-2
2 11.50
GRID 4-4
2 8.50
2 8.50
GRID 5-5
2 17.00
BETWEEN 3-3 AND 4-4
2 7.83
GRID A-A
2 12.75
GRID B-B
2 7.75
2 12.75
GRID C-C
2 22.50
BETWEEN B-B AND C-C
2 1.67
PARAPET WALL
LOWER TERRACE
IN TOP 2 75.00
UPPER TERRACE
IN TOP 2 130.00
BOUNDARY WALL COLUMN
24 3.00
BOUNDARY WALL TOP BAND
2 16.00
2 31.58
2 54.17
2 31.58
TOTAL FORMWORK
3.1 FORMWORK IN PERGOLA
SECOND FLOOR
X-DIRECTION 5 3.00
Y-DIRECTION 3 6.00
SIDE 1 0.75
TOTAL FORM WORK IN PERGOLA
4 REINFORCEMENT WORK
TOTAL FROM BAR BENDING
5 BRICK WORK
5.1 9" BRICK WORK
5.1.1 BELOW FOUNDATION
IN SUBSTRUCTURE
GRID 1-1 1 23.00
GRID 2-2 1 11.50
GRID 3-3 1 11.50
GRID 4-4 1 23.00
GRID 5-5 1 23.00
GRID A-A 1 33.42
GRID B-B 1 32.42
GRID C-C 1 33.42
FOR TOE WALL
OUTSIDE 1-1
1 4.25
1 4.25
1 5.50
SOAK PIT
1 12.37
SEPTIC TANK
2 13.00
2 8.00
BOUNDARY WALL
1 16.00
2 31.58
1 54.17
TOTAL 9" BRICK WORK BELOW FOUNDATION
5.1.2 IN SUPERSTRUCTURE
GROUND FLOOR
GRID 1-1 1 11.50
W2 -1 7.00

GRID 2-2 1 11.50


D -1 4.00

GRID 5-5 1 23.00


D/W -1 9.00
W1 -1 6.00

GRID A-A 1 33.42

GRID B-B 1 11.17

GRID C-C 1 37.67


W1 -1 6.00
W3 -1 2.00
NO WALL -1 6.92
GLASS WALL -1 4.00
FIRST FLOOR
GRID 1-1
1 23.00
SD2 -1 6.00
W3 -1 2.00
GRID 5-5
1 23.00
SD1 -1 6.00
W1 -1 6.00
GRID A-A
1 33.42
GRID B-B
1 4.25
GRID C-C
1 37.67
W3 -2 2.00
W1 -1 6.00
NO WALL -1 4.00
SECOND FLOOR
GRID 2-2
1 11.50
W4 -1 3.00
GRID 4-4
1 11.50
W1 -1 6.00
D1 -1 3.00
GRID 5-5
1 23.00
SD1 -1 6.00
W1 -1 6.00
GRID A-A
1 12.75
GRID B-B
1 13.75
W4 -1 3.00
SD1 -1 6.00
GRID C-C
1 26.50
GLASS WALL -1 4.00
W3 -1 2.00
W1 -1 6.00
BOUNDARY WALL
1 16.00
1 31.58
1 54.17
1 31.58
PARAPET WALL
LOWER TERRACE
WALL POST 30 0.75
UPPER TERRACE
WALL POST 50 0.75
IN DESIGN FACE
LOWER TERRACE 1 75.00
UPPER TERRACE 1 130.00
TOTAL 9" BRICK WORK IN SUPERSTRUCTURE
5.2 4" BRICK WORK
GROUND FLOOR
GRID 4-4
1 23.00
D1 -1 3.00
NO WALL -1 3.50
BETWEEN B AND C
1 4.83
D2 -1 2.50
BETWEEN 3 AND 4
1 7.83
BETWEEN 4 AND 5
1 11.50
D1 -1 3.00
BETWEEN A AND B 1 5.50
D2 -1 2.50
GRID B-B
1 12.75
FIRST FLOOR
GRID 2-2
1 11.50
GRID 3-3
1 11.50
D1 -1 3.00
GRID 4-4
1 23.00
D1 -2 3.00

BETWEEN 3-3 AND 4-4


1 7.83
BETWEEN B-B AND C-C
1 6.84
D2 -1 2.50
BETWEEN B-B AND C-C
1 4.83
D2 -1 2.50
GRID B-B
1 21.75
SECOND FLOOR
GRID 4-4
1 11.50
D1 -1 3.00
BETWEEN 3-3 AND 4-4
1 7.83
GRID B-B
1 12.75
BETWEEN B-B AND C-C
1 6.84
D2 -1 2.50
PARAPET WALL
LOWER TERRACE
1 23.55
1 6.00
1 3.50
1 6.00
1 4.25
WALL
1 11.75
1 4.25
1 2.00
1 8.92
1 2.00
UPPER TERRACE
1 14.75

WALL
1 11.50
1 15.75
1 12.50
WALL 1 28.50
1 26.00
1 3.25
1 13.50
1 3.25
TOTAL 4" BRICK WORK
6 DOOR AND WINDOW WORK
6.1 WOODEN WORK
6.1.1 WOODEN FRAME
GROUND FLOOR
D
1 7.00
1 7.00
1 4.00
D1
2 7.00
2 7.00
2 3.00
D2
2 7.00
2 7.00
2 2.50
D/W
1 7.00
1 7.00
1 9.00
FIRST FLOOR
D1
3 7.00
3 7.00
3 3.00
D2
2 7.00
2 7.00
2 2.50
SECOND FLOOR
D1
2 7.00
2 7.00
2 3.00
D2
1 7.00
1 7.00
1 2.50
TOTAL WOODEN FRAME
6.1.2 WOODEN SHUTTER
GROUND FLOOR
D 1 3.50
D1 2 2.50
D2 2 2.00
D/W 1 8.50
FIRST FLOOR
D1 3 2.50
D2 2 2.00
SECOND FLOOR
D1 2 2.50
D2 1 2.00
TOTAL WOODEN SHUTTER
6.1.3 WODDEN SHUTTER WITH JALEE
GROUND FLOOR
D 1 3.50
SECOND FLOOR
D1 1 2.50
TOTAL WOODEN JALEE
6.2 ALMUNIUM ITEM
6.2.2 DOOR AND WINDOW WORK
GROUND FLOOR
W1 2 6.00
W2 1 7.00
W3 1 2.00
FIRST FLOOR
W1 2 6.00
W3 3 2.00
W5 1 4.00
SD1 1 6.00
SD2 1 7.00
SECOND FLOOR
W1 3 6.00
W3 1 3.00
W4 2 2.00
SD1 1 6.00
TOTAL ALUMINIUM WORK FOR DOOR AND WINDOW
7 FLOORING WORK
7.1 VITRIFIED CERAMIC TILE FLOORING
GROUND FLOOR
KITCHEN 1 8.00
DINING 1 8.42
TOILET 1 4.17
FIRST FLOOR
TOILET 1 4.17
TOILET 1 7.50
WALK IN CLOSET 1 7.50
BALCONY 1 13.50
SECOND FLOOR
TOILET 1 4.17
BALCONY 1 13.50
ROOF
LOWER TERRACE
1 22.92
1 26.42
1 14.50
TOTAL VITRIFIED CERAMIC TILE FLOORING
7.2 GLAZED CERAMIC WALL TILE
GROUND FLOOR
KITCHEN 1 8.00
TOILET 1 23.34
D2 -1 2.50
FIRST FLOOR
TOILET 1 23.34
TOILET 1 47.90
D2 -1 2.50
D2 -1 2.50
SECOND FLOOR
TOILET 1 23.34
D2 -1 2.50
TOTAL GLAZED CERAMIC WALL TILE
7.3 ROOF TILE
SECOND FLOOR
SIDE 1 15.00
SIDE 1 15.00
FRONT 1 29.38
TOTAL ROOF TILE
7.3.1 RIDGE TILE
SECOND FLOOR
FRONT 1 6.58
FRONT 1 6.58
TOTAL RIDGE TILE
7.4 IPS FLOORING
GROUND FLOOR
STORE 1 5.17
STAIRCASE AREA 1 11.50
LIVING ROOM 1 13.50
GUEST BEDROOM 1 13.58
CAR PORCH 1 12.17
IN FRONT OF TOILET 1 4.00
IN FRONT OF STORE 1 5.92
FIRST FLOOR
BEDROOM 1 13.58
BEDROOM 1 13.58
FAMILY ROOM 1 8.42
MASTER BEDROOM 1 13.50
STAIRCASE AREA 1 11.50
IN FRONT OF TOILET 1 4.00
SECOND FLOOR
BEDROOM 1 13.58
BEDROOM 1 13.58
STAIRCASE AREA 1 11.50
IN FRONT OF TOILET 1 4.00
TOTAL IPS FLOORING
7.4.1 CEMENT SKIRTING
GROUND FLOOR
GRID A-A 1 38.17
GRID B-B 1 29.67
GRID C-C 1 34.75
GRID 1-1 1 14.50
GRID 2-2 1 10.16
GRID 3-3 1 2.00
GRID 4-4 1 20.16
GRID 5-5 1 23.66
BETWEEN 2-2 AND 4-4 1 7.83
BETWEEN 4-4 AND 5-5 1 9.16
BETWEEN B-B AND C-C 1 2.66
BETWEEN B-B AND C-C 1 5.16
BETWEEN A-A AND B-B 1 3.74
FIRST FLOOR
GRID A-A 1 38.17
GRID B-B 1 28.67
GRID C-C 1 41.67
GRID 1-1 1 20.66
GRID 2-2 1 14.50
GRID 3-3 1 12.16
GRID 4-4 1 21.32
GRID 5-5 1 20.66
BETWEEN 2-2 AND 4-4 1 7.83
BETWEEN B-B AND C-C 1 2.66
BETWEEN B-B AND C-C 1 5.16
SECOND FLOOR
GRID A-A 1 14.75
GRID B-B 1 23.50
GRID C-C 1 29.50
GRID 2-2 1 13.50
GRID 4-4 1 21.32
GRID 5-5 1 20.66
BETWEEN 2-2 AND 4-4 1 7.83
BETWEEN B-B AND C-C 1 2.66
TOTAL CEMENT SKIRTING
7.5 MARBLE STAIRCASE
TREAD 28 3.50
RISER 32 3.50
FIRST LANDING 2 12.25
SECOND LANDING 2 12.25
TOTAL MARBLE STAIRCASE
7.6 MARBLE SKIRTING
GROUND FLOOR 1 24.79
FIRST FLOOR 1 24.79
TOTAL MARBLE SKIRTING
7.7 WODDEN HAND RAIL
3 LEGGED STAIRCASE
GROUND FLOOR 1 24.79
FIRST FLOOR 1 24.79
TOTAL HAND RAIL
8 PLASTER WORK
8.1 INTERNAL PLASTER WORK
IN 9" BRICK
SEPTIC TANK
2 7.00
2 4.00
GROUND FLOOR
GRID 1-1 1 12.00
W2 -0.5 7.00

GRID 2-2 1 12.00


D -0.5 4.00

GRID 3-3 1 2.00


GRID 5-5 1 24.50
D/W -0.5 9.00
W1 -0.5 6.00

GRID A-A 1 36.01

GRID B-B 1 9.92

GRID C-C 1 27.09


W1 -0.5 6.00
W3 -0.5 2.00
W5 -0.5 4.00

FIRST FLOOR
GRID 1-1
1 24.50
SD2 -0.5 6.00
W3 -0.5 2.00

GRID 5-5
1 24.50
SD1 -0.5 6.00
W1 -0.5 6.00

GRID A-A
1 36.67
GRID C-C
1 35.13
W3 -0.5 2.00
W1 -0.5 6.00
W5 -0.5 4.00

SECOND FLOOR
GRID 2-2
1 12.00
W4 -0.5 3.00
GRID 4-4
1 11.92
W1 -0.5 6.00
D1 -0.5 3.00
GRID 5-5
1 24.17
SD1 -0.5 6.00
W1 -0.5 6.00
GRID A-A
1 13.25
GRID B-B
1 14.25
W4 -0.5 3.00
SD1 -0.5 6.00
GRID C-C
1 27.67
W5 -0.5 4.00
W3 -0.5 2.00
W1 -0.5 6.00
4" BRICK WORK
GROUND FLOOR
GRID 4-4
2 21.00
D1 -1 3.00

BETWEEN B AND C
2 4.50
D2 -1 2.50

BETWEEN 3 AND 4
2 7.83

BETWEEN 4 AND 5
2 12.25
D1 -1 3.00

BETWEEN A AND B 2 5.50


D2 -1 2.50

GRID B-B
2 13.25
FIRST FLOOR
GRID 2-2
2 12.75

GRID 3-3
2 13.00
D1 -1 3.00
GRID 4-4
2 24.17
D1 -1 3.00
D2 -1 2.50
BETWEEN 3-3 AND 4-4
2 7.83
BETWEEN B-B AND C-C
2 7.42
D2 -1 2.50
BETWEEN B-B AND C-C
2 4.50
D2 -1 2.50
GRID B-B
2 21.75
SECOND FLOOR
GRID 4-4
2 12.00
D1 -1 3.00
BETWEEN 3-3 AND 4-4
2 7.83
GRID B-B
2 13.25
BETWEEN B-B AND C-C
2 4.50
D2 -1 2.50
TOTAL INTERNAL PLASTER
8.2 CEILING WORK
GROUND FLOOR
KITCHEN 1 8.00
STORE 1 5.17
DINING 1 8.42
LIVING ROOM 1 13.50
GUEST BEDROOM 1 13.58
CAR PORCH 1 12.17
SIDE OF STAIRCASE 1 5.34
IN FRONT OF STORE 1 5.92
FIRST FLOOR
BEDROOM 1 13.58
BEDROOM 1 13.58
TOILET 1 7.50
WALK IN CLOSET 1 7.50
FAMILY ROOM 1 8.42
MASTER BEDROOM 1 13.50
SIDE OF STAIRCASE 1 5.34
SECOND FLOOR
BEDROOM 1 13.58
TOILET 1 4.17
BEDROOM 1 13.58
STAIRCASE AREA 1 11.50
IN FRONT OF TOILET 1 4.00
TOTAL CEILING
8.3 OUTER PLASTER WORK
GROUND FLOOR
GRID A-A 1 38.17
GRID B-B 2 4.25
GRID C-C 1 44.00
W1 -0.5 6.00
W3 -0.5 2.00
W5 -0.5 4.00
FIRST FLOOR
GRID A-A 1 38.17
GRID C-C 1 41.67
W3 -1 2.00
W1 -0.5 6.00
W5 -0.5 4.00
GRID 1-1 1 26.00
SD2 -0.5 7.00
W3 -0.5 2.00
GRID B-B 1 9.25
GRID 5-5 1 26.00
SD1 -0.5 6.00
W1 -0.5 6.00
SECOND FLOOR
GRID A-A 1 14.75
GRID B-B 1 14.75
W4 -0.5 3.00
SD1 -0.5 6.00
GRID C-C 1 29.50
W3 -0.5 2.00
W1 -0.5 6.00
W5 -0.5 4.00
GRID 2-2 1 13.50
W4 -0.5 3.00
GRID 4-4 1 12.50
W1 -0.5 6.00
D1 -0.5 3.00
GRID 5-5 1 26.00
SD1 -0.5 6.00
W1 -0.5 6.00
BOUNDARY WALL
2 54.17
2 31.58
2 54.17
2 31.58
PARAPET WALL
LOWER TERRACE
2 23.55
2 6.00
2 3.50
2 6.00
2 4.25
WALL
2 11.75
2 4.25
2 2.00
2 8.92
2 2.00
UPPER MOST PORTION
1 75.00
UPPER TERRACE
2 14.75
2 11.50
2 15.75
2 12.50
WALL 2 28.50
2 26.00
2 3.25
2 13.50
2 3.25
UPPER MOST PORTION
ROOF TOP 1 130.00
LOWER TERRACE
POST 30 0.75
TOP PORTION-POST 30 0.75
UPPER TERRACE
POST 50 0.75
TOP PORTION-POST 50 0.75
TOTAL OUTER PLASTER
9.3.1 PLASTER IN PERGOLA
SECOND FLOOR
X-DIRECTION 20 3.00
Y-DIRECTION 12 6.00
TOTAL PLASTER IN PERGOLA
9 WATER PROOF CEMENT PAINTING WORK
9.1 INTERNAL WATER PROOF EMULSION PAINT
9" BRICK
GROUND FLOOR
GRID 1-1 1 12.00
W2 -0.5 7.00

GRID 2-2 1 12.00


D -0.5 4.00

GRID 3-3 1 2.00


GRID 5-5 1 24.50
D/W -0.5 9.00
W1 -0.5 6.00

GRID A-A 1 36.01

GRID B-B 1 9.92

GRID C-C 1 27.09


W1 -0.5 6.00
W3 -0.5 2.00
W5 -0.5 4.00

FIRST FLOOR
GRID 1-1
1 24.50
SD2 -0.5 6.00
W3 -0.5 2.00

GRID 5-5
1 24.50
SD1 -0.5 6.00
W1 -0.5 6.00

GRID A-A
1 36.67
GRID C-C
1 35.13
W3 -0.5 2.00
W1 -0.5 6.00
W5 -0.5 4.00

SECOND FLOOR
GRID 2-2
1 12.00
W4 -0.5 3.00
GRID 4-4
1 11.92
W1 -0.5 6.00
D1 -0.5 3.00
GRID 5-5
1 24.17
SD1 -0.5 6.00
W1 -0.5 6.00
GRID A-A
1 13.25
GRID B-B
1 14.25
W4 -0.5 3.00
SD1 -0.5 6.00
GRID C-C
1 27.67
W5 -0.5 4.00
W3 -0.5 2.00
W1 -0.5 6.00
4" BRICK WORK
GROUND FLOOR
GRID 4-4
2 21.00
D1 -1 3.00

BETWEEN B AND C
2 4.50
D2 -1 2.50

BETWEEN 3 AND 4
2 7.83

BETWEEN 4 AND 5
2 12.25
D1 -1 3.00

BETWEEN A AND B 2 5.50


D2 -1 2.50

GRID B-B
2 13.25
FIRST FLOOR
GRID 2-2
2 12.75

GRID 3-3
2 13.00
D1 -1 3.00
GRID 4-4
2 24.17
D1 -1 3.00
D2 -1 2.50
BETWEEN 3-3 AND 4-4
2 7.83
BETWEEN B-B AND C-C
2 7.42
D2 -1 2.50
BETWEEN B-B AND C-C
2 4.50
D2 -1 2.50
GRID B-B
2 21.75
SECOND FLOOR
GRID 4-4
2 12.00
D1 -1 3.00
BETWEEN 3-3 AND 4-4
2 7.83
GRID B-B
2 13.25
BETWEEN B-B AND C-C
2 4.50
D2 -1 2.50
CEILING PAINT
GROUND FLOOR
KITCHEN 1 8.00
STORE 1 5.17
DINING 1 8.42
LIVING ROOM 1 13.50
GUEST BEDROOM 1 13.58
CAR PORCH 1 12.17
SIDE OF STAIRCASE 1 5.34
IN FRONT OF STORE 1 5.92
FIRST FLOOR
BEDROOM 1 13.58
BEDROOM 1 13.58
TOILET 1 7.50
WALK IN CLOSET 1 7.50
FAMILY ROOM 1 8.42
MASTER BEDROOM 1 13.50
SIDE OF STAIRCASE 1 5.34
SECOND FLOOR
BEDROOM 1 13.58
TOILET 1 4.17
BEDROOM 1 13.58
STAIRCASE AREA 1 11.50
IN FRONT OF TOILET 1 4.00
TOTAL INTERNAL EMULSION PAINT
9.2 OUTER WEATHER COAT PAINT
9" BRICK
GROUND FLOOR
GRID A-A 1 38.17
GRID B-B 2 4.25
GRID C-C 1 44.00
W1 -0.5 6.00
W3 -0.5 2.00
W5 -0.5 4.00
FIRST FLOOR
GRID A-A 1 38.17
GRID C-C 1 41.67
W3 -1 2.00
W1 -0.5 6.00
W5 -0.5 4.00
GRID 1-1 1 26.00
SD2 -0.5 7.00
W3 -0.5 2.00
GRID B-B 1 9.25
GRID 5-5 1 26.00
SD1 -0.5 6.00
W1 -0.5 6.00
SECOND FLOOR
GRID A-A 1 14.75
GRID B-B 1 14.75
W4 -0.5 3.00
SD1 -0.5 6.00
GRID C-C 1 29.50
W3 -0.5 2.00
W1 -0.5 6.00
W5 -0.5 4.00
GRID 2-2 1 13.50
W4 -0.5 3.00
GRID 4-4 1 12.50
W1 -0.5 6.00
D1 -0.5 3.00
GRID 5-5 1 26.00
SD1 -0.5 6.00
W1 -0.5 6.00
PARAPET WALL
LOWER TERRACE
2 23.55
2 6.00
2 3.50
2 6.00
2 4.25
WALL
2 11.75
2 4.25
2 2.00
2 8.92
2 2.00
UPPER MOST PORTION
1 75.00
UPPER TERRACE
2 14.75
2 11.50
2 15.75
2 12.50
WALL 2 28.50
2 26.00
2 3.25
2 13.50
2 3.25
UPPER MOST PORTION
1 130.00
LOWER TERRACE
POST 30 0.75
TOP PORTION-POST 30 0.75
UPPER TERRACE
POST 50 0.75
TOP PORTION-POST 50 0.75
BOUNDARY WALL
2 54.17
2 31.58
2 54.17
2 31.58
TOTAL OUTER EMULSION PAINT
9.2.1 OUTER WEATHER COAT PAINT IN PERGOLA
SECOND FLOOR
X-DIRECTION 20 3.00
Y-DIRECTION 12 6.00
TOTAL OUTER WEATHER COAT PAINT IN PERGOLA

S.N. DESCRIPTION MATERIAL SIZE-MM


10 MS PIPE
SECOND FLOOR
RAILING Sq Pipe T-3 25
STAIRCASE
POST Sq Pipe T-3 50
POST Sq Pipe T-3 25
RAILING- BOUNDARY WALL
Sq Pipe T-3 50
Sq Pipe T-3 50
MAIN POST
MAIN POST Sq Pipe T-3 50
Sq Pipe T-3 50
Sq Pipe T-3 50

Sq Pipe T-3 25
Sq Pipe T-3 25
SMALL POST Sq Pipe T-3 25
Sq Pipe T-3 25
Sq Pipe T-3 25

Sq Band T-12.5 32
Sq Band T-12.5 32
HORIZONTAL BAND Sq Band T-12.5 32
Sq Band T-12.5 32
Sq Band T-12.5 32
TOTAL MS PIPE
11 GATE
OUTER FRAME- DOWNSIDE Sq Pipe T-2.2 32
OUTER FRAME- SIDE Sq Pipe T-2.2 32
OUTER FRAME- UPPER PART Sq Pipe T-2.2 32
OUTER FRAME- UPPER PART Sq Pipe T-2.2 32
MIDDLE POST Sq Pipe T-2.2 32
MIDDLE POST Sq Pipe T-2.2 32
INSIDE POST Sq Pipe T-2.2 25
TOTAL MS PIPE
ASUREMENT SHEET

BREADTH HEIGHT QUANTITY UNIT REMARKS

1.00
1.00

6.00 5.75 828.00


6.50 5.75 1943.50
7.50 5.75 323.44

1.75 3.00 32.81


1.75 3.00 31.50
1.75 3.00 28.88
1.75 3.00 32.81
1.75 3.00 91.46
1.75 3.00 80.96
1.75 3.00 122.96

2.17 5.75 53.03


2.17 5.75 46.79
2.17 5.75 40.55
2.17 5.75 53.03

1.75 3.00 22.31


1.75 3.00 22.31
1.75 3.00 28.88

1.25 1.42 28.40


1.25 1.42 56.05
1.25 1.42 96.15
1.25 1.42 56.05

5.25 5.50 433.13

6.00 4.50 243.00

28.27 5.00 141.37


4837.36 CFT

1934.94
1934.94 CFT

5.50 121.00
6.00 288.00
7.00 49.00

1.25 7.81
1.25 7.50
1.25 6.88
1.25 7.81
1.25 21.78
1.25 19.28
1.25 29.28

1.67 7.10
1.67 6.26
1.67 5.43
1.67 7.10

1.25 5.31
1.25 5.31
1.25 6.88

79.58 79.58
158.13 158.13
146.63 146.63
151.46 151.46
86.25 86.25
146.63 146.63

4.50 65.25

1.00 16.00
1.00 31.58
1.00 54.17
1.00 31.58

5.50 46.75
1615.70 SFT

70.00
70.00 NOS

5.50 0.25 30.25


6.00 0.25 72.00
7.00 0.25 12.25

1.25 0.25 1.95


1.25 0.25 1.88
1.25 0.25 1.72
1.25 0.25 1.95
1.25 0.25 5.44
1.25 0.25 4.82
1.25 0.25 7.32

1.67 0.25 1.77


1.67 0.25 1.57
1.67 0.25 1.36
1.67 0.25 1.77
1.25 0.25 1.33
1.25 0.25 1.33
1.25 0.25 1.72

79.58 0.25 19.90


158.13 0.25 39.53
146.63 0.25 36.66
151.46 0.25 37.86
86.25 0.25 21.56
146.63 0.25 36.66

4.75 0.25 17.22

1.00 0.25 4.00


1.00 0.25 7.90
1.00 0.25 13.54
1.00 0.25 7.90

5.50 0.25 11.69


404.83 CFT

5.00 0.67 33.50


13.89 0.83 23.06

5.00 0.67 33.50


13.89 1.17 32.51

5.50 0.67 60.80


16.52 0.83 41.13

5.50 0.67 101.34


16.52 1.17 96.64

6.50 0.67 28.31


22.52 1.17 26.35

1.17 1.83 9.10


1.17 1.83 8.03
1.17 1.83 6.96
1.17 1.83 9.10

0.75 0.75 12.94


0.75 0.75 6.47
0.75 0.75 6.47
0.75 0.75 12.94
0.75 0.75 12.94
0.75 0.75 18.80
0.75 0.75 18.24
0.75 0.75 18.80

0.75 1.00 17.25


0.75 1.00 8.63
0.75 1.00 8.63
0.75 1.00 17.25
0.75 1.00 17.25
0.75 1.00 25.07
0.75 1.00 24.32
0.75 1.00 25.07

0.75 1.00 3.19


0.75 1.00 3.19
0.75 1.00 4.13

0.50 5.00 70.00


0.50 5.00 21.25
4.25 0.42 49.58

12.57 0.33 4.15

5.00 0.33 26.40

1.00 3.25 42.25

1.00 8.58 111.54

1.00 8.58 111.54

1.00 8.58 68.64

1.00 3.33 26.64

0.75 0.75 12.94


0.75 0.75 6.47
0.75 0.75 6.47
0.75 0.75 12.94
0.75 0.75 12.94
0.75 0.75 18.80
0.75 0.75 20.63
0.75 0.75 21.19

0.75 0.75 16.03


0.75 0.75 6.47
0.75 0.75 6.47
0.75 0.75 12.94
0.75 0.75 12.94
0.75 0.75 18.80
0.75 0.75 20.63
0.75 0.75 21.19

0.75 0.75 6.47


0.75 0.75 12.94
0.75 0.75 12.94
0.75 0.75 7.17
0.75 0.75 14.91
0.75 0.75 14.91

1027.80 0.42 431.67


59.54 0.42 25.01
1027.80 0.42 431.67
59.54 0.42 25.01

400.66 0.42 168.28


59.54 0.42 25.01

18.76 0.42 7.88


0.81 4.88
9.35 0.42 3.92

14.00 0.42 5.88


0.81 3.25

18.76 0.42 7.88


0.81 4.88
6.44 0.42 2.70

18.76 0.42 7.88


0.81 4.88
9.35 0.42 3.92

11.62 0.42 4.88


0.81 3.25

18.76 0.42 7.88


0.81 4.88
6.44 0.42 2.70

0.75 0.25 2.16

0.75 0.25 1.41

0.33 0.25 1.36

0.75 0.25 4.31

0.75 0.25 6.27

0.75 0.25 2.09


0.33 1.25 5.26

0.75 0.25 5.02

0.33 0.25 0.70

0.33 0.25 0.65

0.33 0.25 0.27


0.33 0.25 0.08

0.33 0.25 0.19


0.75 0.25 2.16

0.75 0.25 1.41

0.33 0.25 1.36

0.75 0.25 4.31

0.75 0.25 6.27

0.75 0.25 2.09


0.33 1.25 5.26

0.75 0.25 5.02

0.33 0.25 0.70

0.33 0.25 0.65

0.33 0.25 0.27


0.33 0.25 0.08

0.33 0.25 0.19

0.75 0.25 3.00

0.33 0.25 0.95

0.33 0.25 0.70

0.33 0.25 1.40

0.75 0.25 3.19

0.75 0.25 6.41

0.75 0.25 0.80


0.33 0.25 0.52
0.33 0.25 1.05

0.75 0.25 6.50

0.33 0.25 0.65

0.33 0.25 0.36


0.33 0.25 0.19

0.75 0.25 3.00

0.33 0.25 0.95

0.33 0.25 0.70


0.33 0.25 1.40

0.75 0.25 3.19

0.75 0.25 6.41

0.75 0.25 0.80


0.33 0.25 0.52
0.33 0.25 1.05

0.75 0.25 6.50

0.33 0.25 0.65

0.33 0.25 0.36


0.33 0.25 0.19

0.75 0.25 2.16

0.75 0.25 1.59


0.33 0.25 0.70

0.75 0.25 3.19

0.33 0.25 0.65

0.75 0.25 2.39

0.75 0.25 1.45


0.33 0.25 1.05

0.75 0.25 4.22

0.33 0.25 0.14

0.75 0.25 2.16

0.75 0.25 1.59


0.33 0.25 0.70

0.75 0.25 3.19

0.33 0.25 0.65

0.75 0.25 2.39

0.75 0.25 1.45


0.33 0.25 1.05

0.75 0.25 4.22

0.33 0.25 0.14


0.33 0.25 6.19
0.75 0.25 4.22
0.33 0.25 10.73
0.75 0.25 7.03

0.75 5.00 67.50

0.92 0.25 3.68


0.92 0.25 7.26
0.92 0.25 12.46
0.92 0.25 7.26
3061.58 CFT

0.75 0.75 8.44


0.75 0.75 10.13
18.56 CFT

0.25 22.00
0.25 48.00
0.25 7.00

0.25 3.13
0.25 3.00
0.25 2.75
0.25 3.13
0.25 8.71
0.25 7.71
0.25 11.71

0.25 2.13
0.25 1.88
0.25 1.63
0.25 2.13

0.25 2.13
0.25 2.13
0.25 2.75

0.25 9.63

0.67 53.60
0.67 117.92
0.67 17.42

1.83 15.56
1.83 13.73
1.83 11.90
1.83 15.56

0.75 34.50
0.75 17.25
0.75 17.25
0.75 34.50
0.75 34.50
0.75 50.13
0.75 48.63
0.75 50.13

1.00 46.00
1.00 23.00
1.00 23.00
1.00 46.00
1.00 46.00
1.00 66.84
1.00 64.84
1.00 66.84

1.00 8.50
1.00 11.00
1.00 8.50

5.00 280.00
5.00 105.00
0.50 19.25
66.50 66.50
0.50 19.25

28.27 28.27

0.50 9.00
0.50 6.00
6.00 54.00
30.00

5.15 267.80

9.00 468.00

9.00 468.00

9.00 288.00

3.33 106.56

0.83 47.31
0.83 19.09
0.83 19.09
0.83 38.18
0.83 38.18
0.83 55.48
0.83 60.87
0.83 62.53

0.83 47.31
0.83 19.09
0.83 19.09
0.83 38.18
0.83 38.18
0.83 55.48
0.83 60.87
0.83 62.53
0.83 34.03

0.83 19.09
0.83 38.18
0.83 38.18
0.83 21.17
0.83 43.99
0.83 43.99

1027.80 1027.80
59.54 59.54

1027.80 1027.80
59.54 59.54

400.66 400.66
59.54 59.54

3.50 18.76
0.42 1.47
0.42 2.25
0.56 21.00
0.83 5.36
3.50 12.25
0.56 3.92

3.50 14.00
0.42 1.47
0.42 1.68
0.56 7.84
0.83 3.32

3.50 18.76
0.42 1.47
0.42 2.25
0.56 21.00
0.83 5.36
3.50 12.25
0.56 3.92

3.50 18.76
0.42 1.47
0.42 2.25
0.56 21.00
0.83 5.36
3.50 12.25
0.56 3.92

3.50 14.00
0.42 1.47
0.42 1.68
0.56 7.84
0.83 3.32

3.50 18.76
0.42 1.47
0.42 2.25
0.56 21.00
0.83 5.36
3.50 12.25
0.56 3.92

0.25 5.75

0.25 3.75

0.25 8.25

0.25 11.50

0.25 16.71

0.25 5.59
1.25 31.88

0.25 13.38

0.25 4.25

0.25 3.92

0.25 1.67
0.25 0.50

0.25 1.17

0.25 5.75

0.25 3.75

0.25 8.25

0.25 11.50

0.25 16.71

0.25 5.59
1.25 31.88

0.25 13.38
0.25 4.25

0.25 3.92

0.25 1.67
0.25 0.50

0.25 1.17

0.25 8.00

0.25 5.75

0.25 4.25

0.25 8.50

0.25 8.50

0.25 17.09

0.25 2.13
0.25 3.13
0.25 6.38

0.25 17.34
0.00
0.25 3.92

0.25 2.21
0.25 1.17

0.25 8.00

0.25 5.75

0.25 4.25

0.25 8.50

0.25 8.50

0.25 17.09

0.25 2.13
0.25 3.13
0.25 6.38

0.25 17.34

0.25 3.92

0.25 2.21
0.25 1.17

0.25 5.75

0.25 4.25
0.25 4.25

0.25 8.50

0.25 3.92

0.25 6.38

0.25 3.88
0.25 6.38

0.25 11.25

0.25 0.84

0.25 5.75

0.25 4.25
0.25 4.25

0.25 8.50

0.25 3.92

0.25 6.38

0.25 3.88
0.25 6.38

0.25 11.25

0.25 0.84

0.25 37.50

0.25 65.00

5.00 360.00

0.25 8.00
0.25 15.79
0.25 27.09
0.25 15.79
8204.99 SFT

0.75 33.75
0.75 40.50
0.75 0.56
74.81 SFT

#REF! KG

0.75 3.50 60.38


0.75 3.50 30.19
0.75 3.50 30.19
0.75 3.50 60.38
0.75 3.50 60.38
0.75 3.50 87.73
0.75 3.50 85.10
0.75 3.50 87.73

0.75 3.50 11.16


0.75 3.50 11.16
0.75 3.50 14.44

12.37 5.00 61.85

0.75 5.00 97.50


0.75 5.00 60.00

0.75 1.50 18.00


0.75 1.50 71.06
0.75 1.50 60.94
ION 908.15 CFT

0.75 7.83 67.56


0.75 5.00 -26.25

0.75 7.83 67.56


0.75 7.00 -21.00

0.75 7.83 135.12


0.75 7.00 -47.25
0.75 5.00 -22.50

0.75 7.83 196.34

0.75 7.83 65.62

0.75 7.83 221.31


0.75 5.00 -22.50
0.75 5.00 -7.50
0.75 7.83 -40.65
0.75 7.00 -21.00

0.75 7.83 135.12


0.75 7.00 -31.50
0.75 5.00 -7.50
0.75 7.83 135.12
0.75 7.00 -31.50
0.75 5.00 -22.50

0.75 7.83 196.34

0.75 7.83 24.97

0.75 7.83 221.31


0.75 5.00 -15.00
0.75 5.00 -22.50
0.75 7.83 -23.50

0.75 7.83 67.56


0.75 5.00 -11.25

0.75 7.83 67.56


0.75 5.00 -22.50
0.75 7.00 -15.75

0.75 7.83 135.12


0.75 7.00 -31.50
0.75 5.00 -22.50

0.75 7.83 74.91

0.75 7.83 80.78


0.75 5.00 -11.25
0.75 7.00 -31.50

0.75 7.83 155.69


0.75 7.00 -21.00
0.75 5.00 -7.50
0.75 5.00 -22.50

0.75 4.00 48.00


0.75 4.00 94.74
0.75 4.00 162.51
0.75 4.00 94.74

0.75 3.33 56.19

0.75 3.33 93.66

0.75 0.33 18.56


0.75 0.33 32.18
URE 2088.69 CFT

7.83 180.09
7.00 -21.00
7.83 -27.41
9.00 43.47
7.00 -17.50

9.00 70.47

9.00 103.50
7.00 -21.00
9.00 49.50
7.00 -17.50

7.83 99.83

7.83 90.05

7.83 90.05
7.00 -21.00

7.83 180.09
7.00 -42.00

9.00 70.47

9.00 61.56
7.00 -17.50

9.00 43.47
7.00 -17.50

7.83 170.30

7.83 90.05
7.00 -21.00

9.00 70.47

7.83 99.83

9.00 61.56
7.00 -17.50

3.33 78.42
3.33 19.98
3.33 11.66
3.33 19.98
3.33 14.15
3.33 39.13
3.33 14.15
3.33 6.66
3.33 29.69
3.33 6.66

3.33 49.12
3.33 38.30
3.33 52.45
3.33 41.63
3.33 94.91
3.33 86.58
3.33 10.82
3.33 44.96
3.33 10.82
2003.90 SFT

0.42 0.25 0.74


0.42 0.25 0.74
0.42 0.25 0.42

0.33 0.25 1.16


0.33 0.25 1.16
0.33 0.25 0.50

0.33 0.25 1.16


0.33 0.25 1.16
0.33 0.25 0.41

0.33 0.25 0.58


0.33 0.25 0.58
0.33 0.25 0.74

0.33 0.25 1.73


0.33 0.25 1.73
0.33 0.25 0.74

0.33 0.25 1.16


0.33 0.25 1.16
0.33 0.25 0.41

0.33 0.25 1.16


0.33 0.25 1.16
0.33 0.25 0.50

0.33 0.25 0.58


0.33 0.25 0.58
0.33 0.25 0.21
20.41 CFT
6.75 23.63
6.75 33.75
6.75 27.00
6.75 57.38

6.75 50.63
6.75 27.00

6.75 33.75
6.75 13.50
266.63 SFT

6.75 23.63

6.75 16.88
40.50 SFT

5.00 60.00
5.00 35.00
5.00 10.00

5.00 60.00
5.00 30.00
23.00 92.00
7.00 42.00
7.00 49.00

5.00 90.00
5.00 15.00
5.00 20.00
7.00 42.00
NDOW 545.00 SFT

12.33 98.64
12.25 103.15
7.50 31.28

7.50 31.28
5.00 37.50
7.17 53.78
3.25 43.88

7.50 31.28
3.25 43.88

5.25 120.33
7.50 198.15
7.92 114.78
NG 907.90 SFT

3.00 24.00
7.00 163.38
7.00 -17.50

7.00 163.38
7.00 335.30
7.00 -17.50
7.00 -17.50

7.00 163.38
7.00 -17.50
779.44 SFT

15.00 15.00
15.00 15.00
29.38 29.38
59.38 SFT

6.58 6.58
6.58 6.58
13.16 RFT

5.25 27.14
9.92 114.08
12.00 162.00
11.75 159.57
11.75 143.00
4.17 16.68
5.25 31.08

12.33 167.44
11.75 159.57
12.25 103.15
12.00 162.00
9.92 114.08
4.17 16.68

12.33 167.44
11.75 159.57
9.92 114.08
4.17 16.68
1834.22 SFT

38.17
29.67
34.75
14.50
10.16
2.00
20.16
23.66
7.83
9.16
2.66
5.16
3.74

38.17
28.67
41.67
20.66
14.50
12.16
21.32
20.66
7.83
2.66
5.16

14.75
23.50
29.50
13.50
21.32
20.66
7.83
2.66
548.80 RF

0.83 81.34
0.56 62.72
12.25 24.50
12.25 24.50
193.06 SFT

24.79
24.79
49.58 RF

24.79
24.79
49.58 RF

4.00 56.00
4.00 32.00

9.00 108.00
5.00 -17.50

9.00 108.00
7.00 -14.00

9.00 18.00
9.00 220.50
7.00 -31.50
5.00 -15.00

9.00 324.09

9.00 89.28

9.00 243.81
5.00 -15.00
5.00 -5.00
7.00 -14.00

9.00 220.50
7.00 -21.00
5.00 -5.00

9.00 220.50
7.00 -21.00
5.00 -15.00

9.00 330.03

9.00 316.17
5.00 -5.00
5.00 -15.00
9.00 -18.00

9.00 108.00
5.00 -7.50

9.00 107.28
5.00 -15.00
7.00 -10.50

9.00 217.53
7.00 -21.00
5.00 -15.00

9.00 119.25

9.00 128.25
5.00 -7.50
7.00 -21.00

9.00 249.03
7.00 -14.00
5.00 -5.00
5.00 -15.00
9.00 378.00
7.00 -21.00

9.00 81.00
7.00 -17.50

9.00 140.94

9.00 220.50
7.00 -21.00

9.00 99.00
7.00 -17.50

9.00 238.50

9.00 229.50

9.00 234.00
7.00 -21.00

9.00 435.06
7.00 -21.00
7.00 -17.50

9.00 140.94

9.00 133.56
7.00 -17.50

9.00 81.00
7.00 -17.50

9.00 391.50

9.00 216.00
7.00 -21.00

9.00 140.94

9.00 238.50

9.00 81.00
7.00 -17.50
6142.66 SFT

12.33 98.64
5.25 27.14
12.25 103.15
12.00 162.00
11.75 159.57
11.75 143.00
11.50 61.41
5.25 31.08

12.33 167.44
11.75 159.57
5.00 37.50
7.17 53.78
12.25 103.15
12.00 162.00
11.50 61.41

12.33 167.44
7.50 31.28
11.75 159.57
9.92 114.08
4.17 16.68
2019.86 SFT

10.50 400.79
10.50 89.25
10.50 462.00
5.00 -15.00
5.00 -5.00
7.00 -14.00

9.00 343.53
9.00 375.03
5.00 -10.00
5.00 -15.00
9.00 -18.00
9.00 234.00
7.00 -24.50
5.00 -5.00
9.00 83.25
9.00 234.00
7.00 -21.00
5.00 -15.00

9.00 132.75
9.00 132.75
5.00 -7.50
7.00 -21.00
9.00 265.50
5.00 -5.00
5.00 -15.00
7.00 -14.00
9.00 121.50
5.00 -7.50
9.00 112.50
5.00 -15.00
7.00 -10.50
9.00 234.00
7.00 -21.00
5.00 -15.00

4.00 433.36
4.00 252.64
4.00 433.36
4.00 252.64

3.33 156.84
3.33 39.96
3.33 23.31
3.33 39.96
3.33 28.31
3.33 78.26
3.33 28.31
3.33 13.32
3.33 59.38
3.33 13.32

0.33 24.75

3.33 98.24
3.33 76.59
3.33 104.90
3.33 83.25
3.33 189.81
3.33 173.16
3.33 21.65
3.33 89.91
3.33 21.65

0.33 42.90

3.33 149.85
0.75 16.88

3.33 249.75
0.75 28.13
6171.19 SFT

0.75 45.00
0.75 54.00
99.00 SFT

9.00 108.00
5.00 -17.50

9.00 108.00
7.00 -14.00

9.00 18.00
9.00 220.50
7.00 -31.50
5.00 -15.00

9.00 324.09

9.00 89.28

9.00 243.81
5.00 -15.00
5.00 -5.00
7.00 -14.00
0.00

9.00 220.50
7.00 -21.00
5.00 -5.00

9.00 220.50
7.00 -21.00
5.00 -15.00

9.00 330.03

9.00 316.17
5.00 -5.00
5.00 -15.00
9.00 -18.00

9.00 108.00
5.00 -7.50

9.00 107.28
5.00 -15.00
7.00 -10.50

9.00 217.53
7.00 -21.00
5.00 -15.00

9.00 119.25

9.00 128.25
5.00 -7.50
7.00 -21.00

9.00 249.03
7.00 -14.00
5.00 -5.00
5.00 -15.00
9.00 378.00
7.00 -21.00

9.00 81.00
7.00 -17.50

9.00 140.94

9.00 220.50
7.00 -21.00

9.00 99.00
7.00 -17.50

9.00 238.50

9.00 229.50

9.00 234.00
7.00 -21.00

9.00 435.06
7.00 -21.00
7.00 -17.50

9.00 140.94

9.00 133.56
7.00 -17.50

9.00 81.00
7.00 -17.50

9.00 391.50

9.00 216.00
7.00 -21.00

9.00 140.94

9.00 238.50

9.00 81.00
7.00 -17.50

12.33 98.64
5.25 27.14
12.25 103.15
12.00 162.00
11.75 159.57
11.75 143.00
11.50 61.41
5.25 31.08

12.33 167.44
11.75 159.57
5.00 37.50
7.17 53.78
12.25 103.15
12.00 162.00
11.50 61.41

12.33 167.44
7.50 31.28
11.75 159.57
9.92 114.08
4.17 16.68
8074.52 SFT

10.50 400.79
10.50 89.25
10.50 462.00
5.00 -15.00
5.00 -5.00
7.00 -14.00

9.00 343.53
9.00 375.03
5.00 -10.00
5.00 -15.00
9.00 -18.00
9.00 234.00
7.00 -24.50
5.00 -5.00
9.00 83.25
9.00 234.00
7.00 -21.00
5.00 -15.00

9.00 132.75
9.00 132.75
5.00 -7.50
7.00 -21.00
9.00 265.50
5.00 -5.00
5.00 -15.00
7.00 -14.00
9.00 121.50
5.00 -7.50
9.00 112.50
5.00 -15.00
7.00 -10.50
9.00 234.00
7.00 -21.00
5.00 -15.00

3.33 156.84
3.33 39.96
3.33 23.31
3.33 39.96
3.33 28.31
3.33 78.26
3.33 28.31
3.33 13.32
3.33 59.38
3.33 13.32

0.33 24.75

3.33 98.24
3.33 76.59
3.33 104.90
3.33 83.25
3.33 189.81
3.33 173.16
3.33 21.65
3.33 89.91
3.33 21.65

0.33 42.90

3.33 149.85
0.75 16.88

3.33 249.75
0.75 28.13

4.00 433.36
4.00 252.64
4.00 433.36
4.00 252.64
6171.19 SFT

0.75 45.00
0.75 54.00
RGOLA 99.00 SFT

LENGTH NO. OF PCS TOTAL LENGTH WEIGHT/M TOTAL WEIGHT

5.00 27 41.15 2.07 85.27

3.25 8 7.92 4.43 35.08


3.25 24 23.77 2.07 49.21

2.58 9 7.08 4.43 31.35


2.58 5 3.93 4.43 17.42
2.58 23 18.09 4.43 80.12
2.58 23 18.09 4.43 80.12
2.58 38 29.88 4.43 132.37

2.00 23 14.02 2.07 29.02


2.00 11 6.71 2.07 13.88
2.00 65 39.62 2.07 82.02
2.00 65 39.62 2.07 82.02
2.00 110 67.05 2.07 138.80

11.00 2 6.71 3.14 21.05


5.00 2 3.05 3.14 9.57
31.58 2 19.25 3.14 60.45
31.58 2 19.25 3.14 60.45
54.17 2 33.02 3.14 103.68
MS PIPE 1111.89 KG

12.00 1 3.66 2.06 7.53


6.00 2 3.66 2.06 7.53
2.00 2 1.22 2.06 2.51
4.50 2 2.74 2.06 5.65
12.00 1 3.66 2.06 7.53
6.75 2 4.11 2.06 8.47
6.75 32 65.83 1.58 103.69
MS PIPE 142.90 KG
999.68
A. CIVIL WORKS

1 EARTHWORK

1.2 Earthwork excavation in soft clay, silty soil including lift upto 1.5m and disposal upto 10m distance.
S.No. Particulars Unit Quantity Rate
A Labours
Unskilled md 0.70 635.00
Total - A
B Materials
Total - B
C Equipment
@ 3% of A 3.00%
Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per cu.m. of Earthwork in Excavation in foundation =
Rate per cu.ft. of Earthwork in Excavation in foundation =

1.3 EARTH BACK FILLING


1.3.1 Back filling with excavated materials including levelling, water spraying and compaction at 15 cm layers incl
S.No. transportationParticulars
from 10m distance. Unit Quantity Rate
A Labours
Unskilled md 0.5 635.00
Total - A
B Materials

Total - B
C Equipment
Compacting Machineries, water Charge, etc. 5.00%
Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per cu.m. of Earthwork Earth Filling Works using soil obtained at site =
Rate per cu.ft. of Earthwork Earth Filling Works using soil obtained at site =

1.4 Flat Brick Soling


S.No. Particulars Unit Quantity Rate
A Labours
Skilled md 0.5 865.00
Unskilled md 1.00 635.00
Total - A
B Materials
Brick no 420.00 14.40
Sand cu.m. 0.71 2,932.00
Total - B
C Equipment
-
Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per sq.m. of Dry Flat Brick soling =
Rate per sq.ft. of Dry Flat Brick soling =

2 CONCRETE WORKS
2.1 Providing and Laying P.C.C. 1:3:6 in foundation, under floor, etc. as lean/levelling concrete (1 cu.m.)
S.No. Particulars Unit Quantity Rate
A Labours
Skilled md 1.00 865.00
Unskilled md 4.00 635.00
Total - A
B Materials
Cement mt. 0.22 17,000.00
Aggregate 20 mm - 10 mm cu.m. 0.65 3,179.00
Aggregate 10 mm & down cu.m. 0.24 3,179.00
Coarse Sand cu.m. 0.47 2,932.00
Total - B
C Equipment
-
Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per cu.m. of P.C.C (1:3:6) =
Rate per cu.ft. of P.C.C (1:3:6) =

2.2 PCC FOR RCC WORK


2.2.1 Providing & laying PCC for RCC of grade M20 in Superstructure, deck slab and beam (per 1 cu.m.)
S.No. Particulars Unit Quantity Rate
A Labours
Skilled md 0.800 865.00
Unskilled md 7.000 635.00
Total - A
B Materials
Cement mt. 0.400 17,000.00
Aggregate 20 mm - 10 mm cu.m. 0.570 3,179.00
Aggregate 10 mm & down cu.m. 0.290 3,179.00
Coarse Sand cu.m. 0.425 2,932.00
Total - B
C Equipment
Electricity & Water Charge @2.50% of Labour Cost 2.50%
Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per cu.m. of R.C.C. of grade M20 =
Rate per cu.ft. of R.C.C. of grade M20 =

3.0 Providing, fixing & removing formwork for casting R.C.C. items as detailed below
3.1.1 Plywood Form works with steel adjustable pipe props for floor and slab including materials and removing w
transportation upto 30m (per 100 sq.m.)
S.No. Particulars Unit Quantity Rate
A Labours
Skilled md 17.20 865.00
Unskilled md 25.70 635.00
Total - A
B Materials
19mm ply board sq.m. 16.50 688.54
Local Wood cu.m. 0.232 67,990.70
Steel Pipe (MNB 50-M) nos. 4.40 2,230.00
Nail kg 25.00 112.00
Total - B
C Equipment

Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per sq.m. of Formwork in Slabs =
Note: Wood Re-use upto 6 times with 25% salvage value (1.68751.10.75/6 = 0.232)
Note: Ply Re-use upto 6 times with 10% salvage value (100 1.10.9/6 = 16.5)
Note: Pipe Re-use upto 50 times with 25% salvage value (88/500.75 = 1.32)

3.1.2 19mm Plywood Form works for beam including materials and removing with transportation upto 30m (per

S.No. Particulars Unit Quantity Rate


A Labours
Skilled md 2.67 865.00
Unskilled md 4.00 635.00
Total - A
B Materials
19 mm Ply board sq.m. 1.65 688.54
Local Wood cu.m. 0.039 67,990.70
Steel Adjustible Props nos. 0.40 2,230.00
Nail kg 2.50 112.00
Total - B
C Equipment

Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per sq.m. of Formwork in Beams=

Note: Wood Re-use upto 6 times with 25% salvage value (0.028851.10.75/6 = 0.039)
Note: Ply Re-use upto 6 times with 10% salvage value (11.110.9/6 = 1.65)
Note: Pipe Re-use upto 50 times with 25% salvage value (8/500.75 = 0.12)

19mm Plywood Form works for Column (Post) upto size 2m including materials and removing with transpo
3.1.3 30m ( per 4.2 sq.m.)
S.No. Particulars Unit Quantity Rate
A Labours
Skilled md 1.574 865.00
Unskilled md 2.361 635.00
Total - A
B Materials
19 mm Ply board sq.m. 0.693 688.54
Local Wood cu.m. 0.019 67,990.70
Steel Bolts kg 0.54 230.00
Nail kg 2.5 112.00
Total - B
C Equipment

Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per sq.m. of Formwork in Columns =

Note: Wood Re-use upto 8 times with 25% salvage value (0.1550.75/8 = 0.014)
Note: Ply Re-use upto 10 times with 10% salvage value (4.621.1x0.9/10 = 0..457)
Note: Bolts Re-use upto 125 times with 25% salvage value (10.68/1250.75 = 0.065)

2 Weighted mean Rate of Formwork


Formwork Location % Rate
Qty. Column/Shear Wall 25.00 1378.00
Qty. Beam 25.00 1128.00
Qty. Slab 50.00 816.00

100.00

Weighted Mean Rate of Formwork per sq.m. =


Weighted Mean Rate of Formwork per sq.ft. =

4 Providing, bending, placing in position, binding of Steel Reinforcement. (for 1 mt.)


S.No. Particulars Unit Quantity Rate
A Labours
Skilled md 12.00 865.00
Unskilled md 12.00 635.00
Total - A
B Materials
Reinforcement steel mt. 1.05 79,000.00
G.I. binding wire kg 10.00 89.00
Total - B
C Equipment
-
Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per metric tonne of Steel Reinforcement =
Rate per kg of Steel Reinforcement =

5 BRICK WORKS
5.1 230MM BRICK
Providing WORK
and laying first class chimney fired brick masonry works in cement mortar ( 1 : 6 ) in foundation
5.1.1 (per 1 cu.m.)
S.No. Particulars Unit Quantity Rate
A Labours
Skilled md 1.50 865.00
Unskilled md 2.20 635.00
Total - A
B Materials
Brick no 560 14.40
Cement mt. 0.07 17,000.00
Sand cu.m. 0.3 2,932.00
Total - B
C Equipment

Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per cu.m. of Chimney made Brickwork in foundation in cement mortar 1:6 =
Rate per cu.ft. of Chimney made Brickwork in foundation in cement mortar 1:6 =

5.1.2 Providing & laying first class chimney fired brick masonry works in cement mortar ( 1 : 6 ) in superstructure
S.No. Particulars Unit Quantity Rate
A Labours
Skilled md 1.5 865.00
Unskilled md 2.2 635.00
Unskilled for scaffolding md 0.45 635.00
Total - A
B Materials
First Class Brick no 560 14.40
Cement mt. 0.07 17,000.00
Sand cu.m. 0.3 2,932.00
Scaffolding 3% of Labour 3.00%
Total - B
C Equipment
-
Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per cu.m. of Chimney fired Brickwork in Superstructure in cement mortar 1:6 =
Rate per cu.ft. of Chimney fired Brickwork in Superstructure in cement mortar 1:6 =

5.2 110 mm ( Half Brick ) Thick chimney Fired brick works in cement mortar( 1 : 4 ) with hoop iron equivalent r
S.No. / 2-6 mm dia. Particulars
steel bar at every 4 courses Unit
of brick. (per 10 sq.m.)
Quantity Rate
A Labours
Skilled md 1.90 865.00
Unskilled md 2.60 635.00
Total - A
B Materials
First class chimney fired Brick no 673.00 14.40
Cement mt 0.11 17,000.00
Sand cu.m. 0.30 2,932.00
Steel kg 16.32 101.84
Scaffolding 3% of Labour 3.00%
Total - B
C Equipment
-
Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per sq.m. of Chimney Fired Brickwork half-brickwork in Superstructure in cement mortar 1:4 =
Rate per sq.ft. of Chimney Fired Brickwork half-brickwork in Superstructure in cement mortar 1:4 =

6 DOOR AND WINDOW WORK


6.1 WOODEN DOORS
6.1.1 Wooden frame (for 1 cu.m.)

S.No. Particulars Unit Quantity Rate


A Labours
Skilled md 34.00 865.00
Unskilled md 3.40 635.00
Total - A
B Materials
Seasoned sal wood cu.m. 1.10 224,670.52
Holdfast no. 92.00 150.00
Screws no. 184.00 2.25
Bitumen paint ls 1.00 670.00
Total - B
C Equipment
-
Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per cu.m. of sal wood frame =
Rate per cu.ft. of sal wood frame =

6.1.2 Shutter (for shutter size 1.07 m x 1.982 m = 2.114 sq.m.)


S.No. Particulars Unit Quantity Rate
A Labours
Skilled md 10.00 865.00
Unskilled md 1.00 635.00
Total - A
B Materials
32mm Redymade solid core door
sq.m. 2.114 2,044.40
shutter
Decorative wooden beads rm. 7.80 45.94
100 mm hinge no. 6.00 27.00
150 mm tower bolts no. 1.00 65.00
300 mm tower bolts no. 1.00 103.00
250 mm locking set set 1.00 252.00
150 mm handle set 1.00 444.00
Screws ls 1.00 250.00
Total - B
C Equipment
-
Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate persq.m. of shutter =
Rate persq.ft. of shutter =

6.1.3 Wooden Frame with Jalee (for Jalee size 1.07 m x 1.982 m = 2.114 sq.m.)
S.No. Particulars Unit Quantity Rate
A Labours
Skilled md 10.00 865.00
Unskilled md 1.00 635.00
Total - A
B Materials
Jalee sq.m. 2.114 270.00
Decorative wooden beads rm. 7.80 45.94
100 mm hinge no. 6.00 27.00
150 mm tower bolts no. 1.00 65.00
300 mm tower bolts no. 1.00 103.00
250 mm locking set set 1.00 252.00
150 mm handle set 1.00 444.00
Screws ls 1.00 250.00
Total - B
C Equipment
-
Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate persq.m. of Wooden frame with Jalee =
Rate persq.ft. of Wooden Frame with Jalee =

6.2 ALUMINUM WORKS


6.2.1 ALUMINUM DOOR AND WINDOW WORKS
Sliding window with fixed panels and ventilator but without flymesh shutter
In 88 x 38.1 x 1.3 mm with naturally anodized colour with the product of
Agrani Aluminium Nepal or Equivalent including 5mm thick glass
For Rate Analysis 1Sqm is Taken
Material Unit Quantity Rate

Almunium
(With Wage) 1 5581.065
Actual Rate
Rate Per Sqm Rate Per Sqft Contract Rate(1.15)
Rs 6418.00 Rs 596.00 Contract U.Rate

6.3 MS JALI WITH MS PIPE


ITEM :- Supplying & Fixing MS pipe with ms jali with paint etc Rate Analysis For :-1

Description Type Quantity Unit Rate


Labours Skilled 0.25 Nos. 865.00
Unskilled 0.50 Nos. 635.00
Materials MS PIPE 10.00 Kg 85.00
MS JALI 5.00 Kg 85.00

Enamel Paint with red oxide primer. Ls Nos. 50.00


UNIT RATE Actual Rate
2138.00 15 % Contractor overhead
PER SQM Grand Total

7 FLOORING WORKS
7.1 Non-Skid Vitrified Ceramic Tile (per 10 sq.m.)

S.No. Particulars Unit Quantity Rate


A Labours
Skilled md 13.00 865.00
Unskilled md 4.50 635.00
Total - A
B Materials
Non-Skid Vitrified Ceramic Tile sq.m. 11.00 2,152.00
Cement mt. 0.06 17,000.00
Sand cu.m. 0.15 2,932.00
White cement with pigment kg. 3.23 26.38
Total - B
C Equipment

Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per sq.m. of Non-Skid Vitrified Ceramic Tile Flooring =
Rate per sq.ft. of Non-Skid Vitrified Ceramic Tile Flooring =

7.2 Glazed wall Tile (per 10 sq.m.)


S.No. Particulars Unit Quantity Rate
A Labours
Skilled md 13.00 865.00
Unskilled md 4.50 635.00
Total - A
B Materials
Glazed wall Tile sq.m. 11.00 2,152.00
Cement mt. 0.06 17,000.00
Sand cu.m. 0.15 2,932.00
White cement with pigment kg. 3.23 26.38
Total - B
C Equipment

Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per sq.m. of Non-Skid Vitrified Ceramic Tile Flooring =
Rate per sq.ft. of Non-Skid Vitrified Ceramic Tile Flooring =

7.3 Roof Tile (per 10 sq.m.)


S.No. Particulars Unit Quantity Rate
A Labours
Skilled md 13.00 865.00
Unskilled md 4.50 635.00
Total - A
B Materials
Roof Tile sq.m. 14.00 775.00
Cement mt. 0.06 17,000.00
Sand cu.m. 0.15 2,932.00
Total - B
C Equipment

Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per sq.m. of Non-Skid Roof Tile Flooring =
Rate per sq.ft. of Non-Skid Roof Tile Flooring =

7.3.1 Ridge Tile (per 10 rm)


S.No. Particulars Unit Quantity Rate
A Labours
Skilled md 13.00 865.00
Unskilled md 4.50 635.00
Total - A
B Materials
Ridge Tile r.m 14.00 1,550.00
Cement mt. 0.06 17,000.00
Sand cu.m. 0.15 2,932.00
Total - B
C Equipment

Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per rm. of Non-Skid Ridge Tile Flooring =
Rate per rft. of Non-Skid Ridge Tile Flooring =
7.4 38 mm (1" ) thk. Cement Concrete Flooring (1:2:4) with Neat Cement Finishing (per 10 sq.m.)

S.No. Particulars Unit Quantity Rate


A Labours
Skilled md 1.50 865.00
Unskilled md 3.50 635.00
Total - A
B Materials
Cement mt. 0.13 17,000.00
Sand cu.m. 0.18 2,932.00
12 mm Aggregates cu.m. 0.36 3,179.00
Total - B
C Equipment/Others
-
Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per sq.m. of cement concrete flooring =
Rate per sq.ft. of cement concrete flooring =

7.4.1 Cement Sand Skirting 5" ht.

S.No. Particulars Unit Quantity Rate


Cement skirting rm. 1.00 222.07
Total
B Add 15% Contractor's OHP
Total (A+B) :
Rate per linear meter of cement skirting =
Rate per linear feet of cement skirting =

7.5 25 mm thick Marble flooring over 20 mm (average) thick base with joint finished flush Base with cement mo
S.No. cement : 2 coarse sand) (per 10 sq.m.). Unit
Particulars Quantity Rate
A Labours
Skilled md 2.00 865.00
Unskilled md 8.00 635.00
Total - A
B Materials
Cement mt 0.13 17,000.00
Sand cu.m. 0.18 2,932.00
20 mm thick Marble sq.m. 11.00 1,700.08
Oxalic acid kg 0.37 -
Maeen polish kg 0.12 200.00
Turpentine ( Nariol oil ) liter 0.54 214.00
Carborendom stone LS
Total - B
C Equipment/Others

Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per sq.m. of Marble Flooring =
Rate per sq.ft. of Marble Flooring =

7.6 1000mm high Custom made SS Railing (per 2.95 meter length)
S.No. Particulars Unit Quantity Rate
A Materials
Mild Steel Sections Pipe
60mm dia Hand Rail rm 3.85 435.00
25mm dia rm 11.00 205.00
100x100x6 mm Base Plate kg 3.10 115.00
M12 Bolt 75mm (Nos.) no. 24.00 50.00
Total - A
B Fixing in Position
Cutting & fixing charge 10.00%
Total - B
Total (A+B) :
C Add 15% Contractor's OHP
Total (A+B+C) :
Rate per linear meter of custom made 750 mm high Mild Steel Railing =
Rate per linear Feet of custom made 750 mm high Mild Steel Railing =

8 PLASTERING/ WALL FINISHING WORKS


8.1 20 mm thk. Cement Sand Plaster in two coats in cement mortar 1:6 (1 cement : 6 sand) (per 100 sq.m.)
S.No. Particulars Unit Quantity Rate
A Labours
Skilled md 14.00 865.00
Unskilled md 19.00 635.00
Total - A
B Materials
Cement mt. 0.57 17,000.00
Sand cu.m. 2.35 2,932.00
Corner beads, GI chicken wire-mesh,
nails etc. LS
Total - B
C Equipment/others
Scaffolding @ 3% of labour cost 3.00%
Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per sq.m. of 20 mm thick cement plaster on wall =
Rate per sq.ft. of 20 mm thick cement plaster on wall =

8.2 12.5 mm thk. Cement Sand Plaster (1:4) on Ceiling Surface (per 100 sq.m.)

S.No. Particulars Unit Quantity Rate


A Labours
Skilled md 15.00 865.00
Unskilled md 20.00 635.00
Total - A
B Materials
Cement mt. 0.538 17,000.00
Sand cu.m. 1.46 2,932.00
Total - B
C Equipment/others
Scaffolding @ 3% of lobour cost 3.00%
Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per sq.m. of 12.5 mm thick cement plaster on ceiling =
Rate per sq.ft. of 12.5 mm thick cement plaster on ceiling =
8.3 20 mm thk. Cement Sand Plaster in two coats in cement mortar 1:5 (1 cement : 5 sand) in exterior sur
S.No. sq.m.) Particulars Unit Quantity Rate
A Labours
Skilled md 14.00 865.00
Unskilled md 19.00 635.00
Total - A
B Materials
Cement mt. 0.69 17,000.00
Sand cu.m. 2.15 2,932.00
Corner beads, GI chicken wire-mesh,
nails etc. LS
Total - B
C Equipment/others
Scaffolding & safety provision 3.00%
Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per sq.m. of 20 mm thick cement plaster on exterior wall =
Rate per sq.ft. of 20 mm thick cement plaster on exterior wall =

9 PAINTING WORKS
9.1 Two or more coats of Silk Emulsion Paint with approved primer (per 100 sq.m)
S.No. Particulars Unit Quantity Rate
A Labours
Skilled md 12.00 865.00
Unskilled md 8.00 635.00
Total - A
B Materials
White cement primer coat kg 8.10 268.00
Emulsion Paint lt 16.00 522.00
Total - B
C Equipment/others
Electrical, scaffolding, sand papers, etc. 5.00%
Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per sq.m. of Waterproof Cement Paint =
Rate per sq.ft. of Waterproof Cement Paint =

9.2 Two or more coats of exterior weather coat paint (per 100 sq.m)
S.No. Particulars Unit Quantity Rate
A Labours
Skilled md 5.80 865.00
Unskilled md 5.80 635.00
Total - A
B Materials
Primer kg 8.10 268.00
Weather coat paint lit. 16.00 631.00
Filler putty kg 3.00 69.00
Total - B
C Equipment/others

Total - C
Total (A+B+C) :
D Add 15% Contractor's OHP
Total (A+B+C+D) :
Rate per sq.m. of Weather Coat Paint =
Rate per sq.ft. of Weather Coat Paint =

10 FOR MS PIPE
ITEM :- Supplying & Fixing MS square Pipe Rate Analysis For :-59.34

Description Type Quantity Unit Rate


Labours Skilled 1.00 Nos. 865.00
Unskilled 2.00 Nos. 635.00
Materials MS Square Pipe 59.34 Kg 87.00
nut, Bolts. 20.00 Nos. 28.00
Enamel Paint with primer. Ls Nos. 250.00
UNIT RATE Actual Rate
157.00 15 % Contractor overhead
PER Kg Grand Total
rate unit

865.0 md
715.0 md
715.0 md
635.0 md
865.0 md
865.0 md
865.0 md

17,000.00 ton
3,179.00 m3
2,932.00 m3
2,790.00 m3
76,350 ton
79,000 ton
89,000 ton
20.8 no.
14.4 no.
15.5 no.
4,415.00 m3
1,200.00 m3

RATE LIST

S. No. Particulars

Civil Works
Soil
Mud
Stone dust
Crushed Brick
Mine Stone (foruwa dhunga)

Wood Works
Local wood
19mm plywood
Shuttering plywood 12mm thick
Sal wood (upto 8 ft.)
8-12'
Sallo wood
block board
Wooden Planks (Jamun)
4mm ply (commercial)
6mm ply (commercial)
6mm ply (waterproofl)
4mm teak ply
688.957504 12mm commercial ply
Listi
18 mm ply 18mm thick- one side laminated
19 mm ply 19mm thick Nepal Board
Firewood

Carved Salwood Door Window in


Carved Salwood Ankhi Jhyal Dh

3"x4" Sisau Wood Handrail

Fiting & Fixing Works


Holdfast
Nails
Hinges SS 304
75 mm hinge
100 mm hinge
125 mm hinge
Hinges GI Enameled
75 mm hinge
100 mm hinge
125 mm hinge
Tower Bolts - Heavy Aluminium
100 mm tower bolt
150 mm tower bolt
300 mm tower bolt
Tower Bolts - Brass
100 mm tower bolt
150 mm tower bolt
300 mm tower bolt
SS Lever Handle
SS Handle 23"
Mortice lock set
Dorma/ Union
Godrej
Guide
300mm lock set (Simple)
Handle
Aldrops
250mm
300mm
Handle 150mm
Aluminium
Brass
SS
Floor Standing Door Stopper
CP
Brass
SS
Wall Mounted Door Stopper
Rubber
CP
Brass
SS
Eye Hook
Brass
Aluminium
CP
Mosquito proof wire mesh
GI wire mesh 24G
Barfi Jali
Normal Spring
Hydraulic Spring
8mm nut bolt
J-Hook
U-Hook
Bitumen washer
Steel Prop MNB 50-M
40mm screw

Bhusa
Gobar
Gum (mobicol, fevicol)
Equipmet for Khaksi

Glass & Board Works


3mm Glass
4mm Glass
5mm Glass
6mm Glass

Plain Gyp Board (square or tape


Design Gyp Board
Plain Metalised Polyster Board F
Design Metalised Polyster Board
Gyp Board Wall Partition
Gyp Board Wall Panelling
Plastic Felt (20x1 m roll)
Armstrong Mineral Fibre Board
GI Perimeter Channel
GI Intermediate Channel
GI Strap Hanger
Connection Clip
6mm dia. Dash Fastener
Soffit Cleat
Joint Filling Compound
Joint Tape
12mm dia. 40mm long 6mm dia.

Flooring Works
Rajasthani Marble
13mm
16mm
Granite
19mm
16mm
Oxalic acid
Maeen polish
Turpentine ( Nariol oil )
Carborendom stone
white cement
Tile/ Marble Adhesive
Polymer Tile Grout
3mm Marble chips
Homogenous Polished Vitrified F
Ceramic nonglazed tile
Ceramic glazed tile
Ceramic boarder tile
Porcelein nonglazed tile
Porcelein glazed tile
Vitrified Porcelain Polished Tile
Terrazo Tile
Porcelein boarder tile
Kota Stone
Sand Stone
Telia Tile 25mm
Bitumen
Bitumen
60mm concr Blocks
70mm concr Blocks
25mm Flag stone
37mm Flag stone
50mm Flag stone

Water Proofing Works


Water Proof Compound
500gauge Polythene Sheet
Tarfelt (12 m) (ISI mark)
1"x" Rainwater Protection Plas
Elastomeric Water Proofing
Integral Waterproofing Compoun

Painting Works
POP
Surki
Lime
White Lime
Aster for distemper
Aster for Enamel
Cement Primer
Metal Primer
Wood Primer
Distemper powder
Cement Paint
Emulsion
Enamel
Aluminum paint
Duracel paint
Ramtilak
Sand paper
Varnish
Chapra
Spirit
Apex paint
Red Oxide (Geru)
Tata Red Oxide
Linseed Oil
Gum (Mobicol, Fevicol)
Equipment for Khaksi
Filler
Whitening Powder (Chalk Powde
CCLEARSEAL (Elastomeric, Lon
Wall Guard WBA (Hygenic, Was
Red Oxide (Geru)
Primary coat

Roofing Works
CGI Sheet (24 G = 0.5mm)
CGI Sheet (26 G = 0.35mm)
Color CGI Sheet ( 0.43mm)
Color CGI Sheet ( 0.5mm)
Color Ridge Plane Sheet ( 0.5mm
Color Ridge Plane Sheet (28G)
Ridge Plane Sheet (28G)
Plain Sheet (28G)
Corrugated Fibre Glass 1.2mm
Corrugated Fibre Glass 2mm
Corrugated Fibre Glass 1.3mm

Slate
Clay Tile
Clay Ridge Tile

1" thk. Roofing Tile Shape Cuttin

Folded Metal Tile (MRI) - 1330 x


GI Black Nail
MRI Gutter
MRI Ridge/ Valley
MRI Sheet Flashing
MRI Box Barge Cover
Pressed Clay Tile

Metal Works
MS Grill 320mm (16.14 kg/m)
MS Grill 320mm (21.50 kg/m)
MS Collapsible gate (+fitting)
MS Rolling Shutter 16/18 gauge
Iron Gate 18 Gauge (+ fitting)
GI Barbed Wire (7m=1kg.)
GI Barbed Wire (7m=1kg.)
MS Black Pipe
"x" Square Pipes Railings wi
"x" Square Pipes Railings wi
Different Size MS Angles
10 SWGGI Chain Link 2"x2" me
MS Grill 320mm
Different Size MS Rods (TOR)
Different Size MS Rods (TMT)
MS Spiral Staircase with 4"-6" pi
Mild Strips of Various Sizes
MS Structural Steel
Aluminium Profile
Welding
Mosaic Tle
Oxalic Acid
Marble
Cement Paint
Steel Bolt

upto 10m distance.


Amount

444.50
444.50

-
-

13.34
13.34
457.84
68.68
526.51
527.00
15.00

mpaction at 15 cm layers including


Amount

317.50
317.50

15.88
15.88
333.38
50.01
383.38
383.00
11.00

Amount

432.50
635.00
1,067.50

6,048.00
2,081.72
8,129.72

-
-
9,197.22
1,379.58
10,576.80
1,058.00
98.00

ng concrete (1 cu.m.)
Amount

865.00
2,540.00
3,405.00

3,740.00
2,066.35
762.96
1,378.04
7,947.35

-
11,352.35
1,702.85
13,055.20
13,055.00
370.00

d beam (per 1 cu.m.) M20


Amount

692.00
4,445.00
5,137.00

6,800.00
1,812.03
921.91
1,246.10
10,780.04

128.43
128.43
16,045.47
2,406.82
18,452.28
18,452.00 done
522.00

w
g materials and removing with

Amount

14,878.00
16,319.50
31,197.50

11,360.91
15,773.84
9,812.00
2,800.00
39,746.75

-
70,944.25
10,641.64
81,585.89
816.00
ansportation upto 30m (per 10 sq.m.)

Amount

2,309.55
2,540.00
4,849.55

1,136.09
2,651.64
892.00
280.00
4,959.73

-
9,809.28
1,471.39
11,280.67
1,128.00

s and removing with transportation upto

Amount

1,361.51
1,499.24
2,860.75

477.16
1,291.82
124.20
280.00
2,173.18

-
5,033.93
755.09
5,789.02
1,378.00
344.50 8,612.50
282.00 7,050.00
408.00 20,400.00
36,062.50 163.86

1,035.00 Done rate/sq.m


96.00

mt.)
Amount

10,380.00
7,620.00
18,000.00

82,950.00
890.00
83,840.00

-
101,840.00
15,276.00
117,116.00
117,116.00 done
117.00

ortar ( 1 : 6 ) in foundation upto plinth


Done
Amount
non-fairface
1,297.50
1,397.00
2,694.50

8,064.00
1,190.00
879.60
10,133.60

-
-
12,828.10
1,924.22
14,752.32
14,752.00
418.00

tar ( 1 : 6 ) in superstructure (per 1 cu.m.) non-fairface


Amount

1,297.50
1,397.00
285.75
2,980.25

8,064.00
1,190.00
879.60
8.57
10,142.17

-
-
13,122.42
1,968.36
15,090.79
15,091.00 done
427.00

) with hoop iron equivalent reinforcement


Amount

1,643.50
1,651.00
3,294.50

9,691.20
1,808.80
879.60
1,662.03
98.84
14,140.46

-
-
17,434.96
2,615.24
20,050.21
2,005.00
186.00

Amount

29,410.00
2,159.00
31,569.00

247,137.57
13,800.00
414.00
670.00
262,021.57

-
-
293,590.57
44,038.59
337,629.16
337,629.00
9,559.14

Amount

8,650.00
635.00
9,285.00

4,321.86
358.33
162.00
65.00
103.00
252.00
444.00
250.00
5,956.19

-
-
15,241.19
2,286.18
17,527.37
8,291.00
770.54

Amount

8,650.00
635.00
9,285.00

570.78
358.33
162.00
65.00
103.00
252.00
444.00
250.00
2,205.11

-
-
11,490.11
1,723.52
13,213.63
6,251.00
580.95
Amount Grand Amount

5581.065 5581.06
5581.06
act Rate(1.15) 837.16
6418.22

nalysis For :-1

Amount Remarks
216.25
317.50
850.00
425.00

50.00
1858.75
278.81
2137.56

Amount

11,245.00
2,857.50
14,102.50

23,672.00
952.00
445.66
85.14
25,154.80

-
-
39,257.30
5,888.60
45,145.90
4,515.00 Done
420.00

Amount

11,245.00
2,857.50
14,102.50

23,672.00
952.00
445.66
85.14
25,154.80

-
-
39,257.30
5,888.60
45,145.90
4,515.00
420.00

Amount

11,245.00
2,857.50
14,102.50

10,850.00
952.00
445.66
12,247.66

-
-
26,350.16
3,952.52
30,302.69
3,030.00
282.00

Amount

11,245.00
2,857.50
14,102.50

21,700.00
952.00
445.66
23,097.66

-
-
37,200.16
5,580.02
42,780.19
4,278.00
398.00
ng (per 10 sq.m.)

Amount

1,297.50
2,222.50
3,520.00

2,210.00
527.76
1,144.44
3,882.20

-
-
7,402.20
1,110.33
8,512.53
851.25
80.00

Amount
222.07 222.07
222.07
33.31
255.38
255.38
78.00

d flush Base with cement mortar 1:2 (1


Amount

1,730.00
5,080.00
6,810.00

2,210.00
536.56
18,700.88
-
23.60
115.13
120.00
21,706.17

-
28,516.17
4,277.43
32,793.59
3,279.36
304.77

Amount
1,674.75
2,255.00
356.50
1,200.00
5,486.25

548.63
548.63
6,034.88
905.23
6,940.11
2,352.58
717.07

: 6 sand) (per 100 sq.m.)


Amount

12,110.00
12,065.00
24,175.00

9,690.00
6,890.20
450.00 800.00
17,030.20

725.25
725.25
41,930.45
6,289.57
48,220.02
482.00 done
45.00

Amount

12,975.00
12,700.00
25,675.00

9,146.00
4,280.72
13,426.72

770.25
770.25
39,871.97
5,980.80
45,852.77
458.53
43.00
ent : 5 sand) in exterior surface (per 100
Amount

12,110.00
12,065.00
24,175.00 with 10% wastage included

11,730.00
6,303.80
450.00
18,483.80

725.25
725.25
43,384.05
6,507.61
49,891.66
499.00
46.00

Amount

10,380.00
5,080.00
15,460.00

2,170.80
8,352.00
10,522.80

773.00
773.00
26,755.80
4,013.37
30,769.17
308.00
29.00

Amount

5,017.00
3,683.00
8,700.00

2,170.80
10,096.00
207.00
12,473.80

-
-
21,173.80
3,176.07
24,349.87
243.00
23.00

nalysis For :-59.34

Amount Remarks
865.00
1270.00
5162.58
560.00
250.00
8107.58
1216.14
9323.72
particulars rate unit

Labour:
skilled labour (sk)
semi skilled labour (ssk)
skilled carpenter (c.sk)
unskilled labour (usk)
Bar Bender
Painter
Mason

Materials:
cement 850.00 per bag
aggregate 90.00 per cft
river sand 83.00 per cft
mine sand 79.00 per cft
steel FY 415 (TOR) 76.35 kg 80.4833333333
steel FY 500 (TMT) 79.00 kg
binding wire 89 without vat
machine made brick
local (chimney made) brick
VSBK
dressed stone 125.00 per cft
stone/ boulder 79.00 per cft

Particulars Unit Rate Remarks

rks
cm 650.00
cm 650.00
ust cm 290.00
d Brick cm 1,272.92
one (foruwa dhunga) cm 1,200.00

Works
ood cm 67,990.70
lywood sm 688.54
ng plywood 12mm thick sm 667.12
d (upto 8 ft.) cm 214,674.96
cm 224,670.52
ood cm 39,874.93
ard sm 685.59
n Planks (Jamun) sm 706.40
y (commercial) sm 258.20
y (commercial) sm 408.82
y (waterproofl) sm 591.71
ak ply sm 817.64
ommercial ply sm 688.96
rm 29.00
hick- one side laminated board sm 1,032.81
hick Nepal Board sm 1,000.53
d kg. 20.00

Salwood Door Window includingsmf 53,800.00


sm
Salwood Ankhi Jhyal Dhoka includ 37,000.00

sau Wood Handrail rm 976.35

Fixing Works
nos 35.00
kg 112.00
SS 304
75 mm hinge no. 184.00
100 mm hinge no. 276.00
125 mm hinge no. 368.00
GI Enameled
75 mm hinge no. 15.00
100 mm hinge no. 27.00
125 mm hinge no. 42.00
olts - Heavy Aluminium
100 mm tower bolt no. 184.00
150 mm tower bolt no. 276.00
300 mm tower bolt no. 551.00
olts - Brass
100 mm tower bolt no. 112.00
150 mm tower bolt no. 168.00
300 mm tower bolt no. 336.00
er Handle 3,650.00
dle 23" 2,400.00
lock set
Dorma/ Union no. 1,255.97
Godrej no. 1,250.00
Guide no. 1,155.00
lock set (Simple) no. 206.00
no. 26.78

250mm no. 275.00


300mm no. 325.00
150mm
Aluminium no. 70.00
Brass no. 1,102.00
SS no. 180.00
anding Door Stopper
CP no. 220.00
Brass no. 180.00
SS no. 220.00
unted Door Stopper
Rubber no. 30.00
CP no. 140.00
Brass no. 140.00
SS no. 140.00
ok
Brass no. 54.00
Aluminium no. 30.00
CP no. 16.00
o proof wire mesh sm 74.00
mesh 24G sm 74.00
i sm 175.00
Spring no 110.00
c Spring no 1,250.00
t bolt nos 13.39
nos 50.00
nos 50.00
washer nos 3.00
op MNB 50-M no 1,156.69
crew nos 7.00

kg. 5.00
kg. 4.80
obicol, fevicol) kg. 216.30
et for Khaksi hrs. 150.00

Board Works
ass sm 516.48
ass sm 656.36
ass sm 882.32
ass sm 1,022.20

yp Board (square or tapered edgsm 225.96


Gyp Board sm 1,075.03
etalised Polyster Board False Ceism 1,075.03
Metalised Polyster Board False Csm 1,208.02
ard Wall Partition sm 1,248.16
ard Wall Panelling sm 828.52
Felt (20x1 m roll) sm 108.66
ng Mineral Fibre Board sm 753.20
meter Channel rm 55.00
mediate Channel rm 90.00
Hanger rm 75.00
ion Clip no. 12.00
a. Dash Fastener no. 8.00
eat no. 6.50
ing Compound kg. 50.00
pe roll 280.00
ia. 40mm long 6mm dia. Bolt Dano. 15.00

Works
ani Marble
13mm sm 1,700.08
16mm sm 1,764.64

19mm sm 3,615.36
16mm sm 3,174.20
cid kg. 115.00
polish kg. 200.00
ne ( Nariol oil ) lit. 214.00
ndom stone nos. 120.00
ment ton 26,375.00 26375
rble Adhesive kg. 75.00
Tile Grout kg. 155.00
arble chips cm 3,127.75
enous Polished Vitrified Floor Til sm 1,291.20
nonglazed tile sm 1,076.00
glazed tile sm 1,022.20
boarder tile sm 1,883.00
n nonglazed tile sm 1,291.20
n glazed tile sm 893.08
Porcelain Polished Tile sm 1,398.80
Tile sm 699.40
n boarder tile sm 1,506.40
one sm 1,129.80
one sm 1,345.00
e 25mm no 13.00
ltr 61.80
kg. 72.10
oncr Blocks sm 454.39
oncr Blocks sm 554.16
lag stone sm 355.08
lag stone sm 484.20
lag stone sm 591.80

roofing Works
roof Compound kg. 150.00
ge Polythene Sheet sm 83.75
12 m) (ISI mark) sm 110.72
ainwater Protection Plaster Line rm 56.65
eric Water Proofing sm 510.67
Waterproofing Compounds for joKg. 150.00

Works
kg 20.00
cm 2,000.00
cm 8,569.60
me kg. 40.00
r distemper ltr. 195.70
r Enamel ltr. 250.00
Primer ltr. 185.00
imer ltr. 238.00
rimer ltr. 376.00
er powder kg 141.00
Paint kg 74.00
n ltr. 425.00
ltr. 525.00
m paint ltr. 400.00
paint ltr. 375.00
k kg. 49.00
per kg 36.00
ltr. 222.00
kg 809.00
ltr 70.00
int ltr 520.00
de (Geru) ltr 121.00
d Oxide kg. 172.00
Oil ltr 400.00
obicol, Fevicol) kg. 130.00
ent for Khaksi hrs. 150.00
kg. 40.00
ng Powder (Chalk Powder) kg. 25.00
RSEAL (Elastomeric, Longlasting,
kg. 531.00
ard WBA (Hygenic, Washable, Hikg. 531.00
de (Geru) Sq.M. 8.00
coat Sq.M. 8.00

Works
eet (24 G = 0.5mm) sm 241.07 8035
eet (26 G = 0.35mm) sm 175.52 5850
GI Sheet ( 0.43mm) sm 265.77 8858
GI Sheet ( 0.5mm) sm 288.87 9628
dge Plane Sheet ( 0.5mm) rm 225.15
dge Plane Sheet (28G) rm 212.45
lane Sheet (28G) rm 193.36
eet (28G) sm 241.72
ted Fibre Glass 1.2mm sm 1,097.19
ted Fibre Glass 2mm sm 1,551.59
ted Fibre Glass 1.3mm sm 2,216.56

sm 299.23
e nos 15.45
dge Tile nos 26.26

Roofing Tile Shape Cutting Work sm 475.86

Metal Tile (MRI) - 1330 x 370 m sheet 976.00


k Nail nos. 4.84
ter rm 1,066.00
ge/ Valley rm 745.00
eet Flashing rm 752.00
x Barge Cover rm 850.00
Clay Tile SM 350.00

orks
320mm (16.14 kg/m) sm 1,936.80
320mm (21.50 kg/m) sm 2,580.00
apsible gate (+fitting) sm 5,770.41
ng Shutter 16/18 gauge sm 2,000.00
e 18 Gauge (+ fitting) sm 3,901.14
ed Wire (7m=1kg.) rm 12.86
ed Wire (7m=1kg.) kg. 90.00
k Pipe kg. 68.00 70
Square Pipes Railings with Sisausm 4,142.00
Square Pipes Railings with MS Ba sm 2,313.40
t Size MS Angles kg. 65.00
GGI Chain Link 2"x2" mesh size kg. 367.71
320mm kg. 140.00
t Size MS Rods (TOR) mt 81,850.00
t Size MS Rods (TMT) mt 79,700.00
al Staircase with 4"-6" pipe, foot rm 10,007.05
ps of Various Sizes kg. 79.00
ctural Steel kg. 84.00
um Profile kg. 375.00
cm 3.00
Sm 893.08
kg 115
SM 1549.44
kg 74
kg 230

You might also like