Professional Documents
Culture Documents
CF Assignment
CF Assignment
1) Project Cost
Years (of construction) 1 2
Equipment cost 1.2 1.2
Erection cost 0.2
Other costs 0.3
2) Sales Volume
Years (of operations) 1 2 3
100 % Capacity 20000 20000 20000
Actual Capacity (%) 60% 80% 100%
Actual Capacity 12000 16000 20000
Selling Price per tonne 10000
Scenario 1
9000
Scenario 2
5830
Scenario 4
6.5%
Prakash Steel Ltd - Base Case
NPV 4.81
IRR 32.77%
Decision: Since the NPV of the project is positive, we accept the project
Notes
1) Terminal cash inflow = PAT + depreciation + Salvage + Recovery of net working capital
Terminal cash inflow = 2.11 + 0 + 2.70
Terminal cash inflow = 4.81
2) In cash flow statement, the year is for project which is different from the year of operations. The operations will begin only
3) Interest during construction period will not be considered
4) Allocated rent - from the existing expense, a part of it is charged to the project
5) Additional Working capital is a cash outflow (WC is a balance sheet item hence only additional should be considered)
6) FG stock has been valued based on Marginal costing
7) Creditors have been assumed to be only for raw materials
tions. The operations will begin only when the project is complete
NPV -0.12
IRR 11.40%
Decision: Since the NPV of the project is negative, we will reject the project
Notes
1) Terminal cash inflow = PAT + depreciation + Salvage + Recovery of net working capital
Terminal cash inflow = 0.89 + 0 + 2.53
Terminal cash inflow = 3.42
2) In cash flow statement, the year is for project which is different from the year of operations. The operations will begin only
3) Interest during construction period will not be considered
4) Allocated rent - from the existing expense, a part of it is charged to the project
5) Additional Working capital is a cash outflow (WC is a balance sheet item hence only additional should be considered)
6) FG stock has been valued based on Marginal costing
7) Creditors have been assumed to be only for raw materials
tions. The operations will begin only when the project is complete
NPV 1.63
IRR 19.35%
Decision: Since the NPV of the project is positive, we accept the project
Notes
1) Terminal cash inflow = PAT + depreciation + Salvage + Recovery of net working capital
Terminal cash inflow = 1.34 + 0 + 2.79
Terminal cash inflow = 4.14
2) In cash flow statement, the year is for project which is different from the year of operations. The operations will begin only
3) Interest during construction period will not be considered
4) Allocated rent - from the existing expense, a part of it is charged to the project
5) Additional Working capital is a cash outflow (WC is a balance sheet item hence only additional should be considered)
6) FG stock has been valued based on Marginal costing
7) Creditors have been assumed to be only for raw materials
tions. The operations will begin only when the project is complete
NPV 4.61
IRR 30.89%
Decision: Since the NPV of the project is positive, we accept the project
Notes
1) Terminal cash inflow = PAT + depreciation + Salvage + Recovery of net working capital
Terminal cash inflow = 2.12 + 0 + 2.70
Terminal cash inflow = 4.82
2) In cash flow statement, the year is for project which is different from the year of operations. The operations will begin only
3) Interest during construction period will not be considered
4) Allocated rent - from the existing expense, a part of it is charged to the project
5) Additional Working capital is a cash outflow (WC is a balance sheet item hence only additional should be considered)
6) FG stock has been valued based on Marginal costing
7) Creditors have been assumed to be only for raw materials
tions. The operations will begin only when the project is complete
NPV 4.01
IRR 29.54%
Decision: Since the NPV of the project is positive, we accept the project
Notes
1) Terminal cash inflow = PAT + depreciation + Salvage + Recovery of net working capital
Terminal cash inflow = 1.91 + 0 + 2.70
Terminal cash inflow = 4.61
2) In cash flow statement, the year is for project which is different from the year of operations. The operations will begin only
3) Interest during construction period will not be considered
4) Allocated rent - from the existing expense, a part of it is charged to the project
5) Additional Working capital is a cash outflow (WC is a balance sheet item hence only additional should be considered)
6) FG stock has been valued based on Marginal costing
7) Creditors have been assumed to be only for raw materials
tions. The operations will begin only when the project is complete
Particulars 1 2 3
Tonnes 12,000 16,000 20,000
Sales Value 108,000,000 144,000,000 180,000,000
Sales Value (in crores) 11 14 18
Less:
Raw Material Cost 7.00 9.33 11.66
Utilities 0.84 1.12 1.40
Employee cost 1.00 1.25 1.50
Depreciation 0.29 0.29 0.29
S&D 0.54 0.72 0.90
Admin 1.00 1.00 1.00
Interest on NWC 0.20 0.26 0.33
PBT (0.06) 0.43 0.92
Less: Tax - 0.13 0.32
PAT (0.06) 0.30 0.60
Operating Cash Inflow 0.23 0.59 0.89
Scenario 3 Scenario 4
4.61 4.01
30.89% 29.54%