Central Public Work Department

NIT No.-

Construction of 50 Bedded Composit Hospital at SHQ, BSF, Mawpat (Dumpling), Shillong


Name of Work & Location including internal Water Supply, Sanitary installation and internal electrical
installations).

Estimated Cost put to tender (Rs.) 131,031,447.00

Proforma for quoting the rates

Actual Tender Opening Date

Comparative Sheet Generated Date/Time

Name of the Firm M/s. Jaypee Projects Ltd.

Name of percentage above or below the estimated


Sr.No. Estimated cost % in Figures
component cost Total Cost

1 Civil Work 131,031,447.00 Below 9.60


118,452,428.09

Total Cost
131,031,447.00 118,452,428.09
-9.60

1 Only one of the options is to be filled. More than one option shall be rejected.
2 Rate filled in any form shall be considered only in %age
3 Rate filled at any other place in the document shall not be considered.
4 No condition shall be accepted.