Professional Documents
Culture Documents
Project Semester - Goal Report
Project Semester - Goal Report
GOAL REPORT
(Project Semester June December 2016)
Submitted by
Jatin Maggo
101302046
Preparation of Sub-grade
Laying of GSB and WMM
Laying of Dense Bituminous Macadam (DBM) and
Bituminous Macadam (BM){ Bituminous Work}
Preparation of Sub-grade
Laying of GSB and WMM
Laying of Dense Bituminous Macadam (DBM) and
Bituminous Macadam (BM){ Bituminous Work}
Laying of DLC and PQC
Foundation
Sub Structure
Super Structure
Service Road
EXISTING ROAD WIDENING AND
STRENGTHNING WITHOUT SERVICE
GRANULAR SUB-BASE
This work shall consist of laying and compacting well-graded
material on prepared subgrade in accordance with the requirements of
the Specifications. The material shall be laid in one or more layers as
sub-base or lower sub-base and upper sub-base (termed as sub-base
here in after) as necessary according to lines, grades shown on the
drawings or as directed by and cross -sections the Engineer. The GSB
is to be constructed in two layers named as GSB1 (115 mm thickness)
and GSB2 (115 mm).
Methodology:-
Construction Operations include Preparation of subgrade, Spreading
and compacting, Surface Finish and Quality Control of Work.
WET MIX MACADAM SUB -BASE/BASE
This work shall consist of laying and compacting clean, crushed,
graded aggregate and granular material, premixed with water, to a
dense mass on a prepared subgrade/sub -base/base or existing
pavement as the case may be in accordance with the requirements of
these Specifications. The material shall be laid in one or more layers
as necessary to lines, grades and cross -sections shown on the
approved drawings or as directed by the Engineer. The WMM is to be
constructed in two layers as WMM1 (125 mm thickness) and WMM2
(125 mm).
Methodology:-
Preparation of base, Preparation of mix, Spreading of mix,
Compaction, Setting and drying.
PRIME COAT AND TACK COAT OVER GRANULAR
BASE
This work shall consist of the application of a single coat of low
viscosity liquid bituminous material to a porous granular surface
preparatory to the superimposition of bituminous treatment or mix.
The Prime coat of specification 6kg/10 sq. metre and tack coat of
3kg/10 sq. metre is to be laid.
Methodology:-
Setting Equipment, Preparation of road surface, Application of
bituminous primer, Curing of primer and opening to traffic.
DENSE BITUMINOUS MACADAM
DBM is also intended for use as road base material. This work shall
consist of construction in a single or multiple layers of DBM on a
previously prepared base or sub-base. The thickness of a single layer
shall be 50mm to 100mm. Materials include Bitumen, Coarse
aggregates, Fine aggregates, Filler. The DBM is to be constructed in
two layers named as DBM1 (60mm thickness) and DBM2 (60mm
thick).
Methodology:-
Laying of prime coat and tack coat before DBM, Mixing and
transportation of the mixture, Spreading and rolling.
BITUMINOUS MACADAM with same Methodology
SIMPLE FLYOVER-In this case, the main road is used for fast
traffic, which is made to pass at a high level by a bridge,
providing ramps on both the approaches; and the slow traffic is
made to pass underneath. Thus the traffics pass at two different
levels, and leave no chance for an accident.
COMPONENTS:-
CONSTRUCTION OF FLYOVER:-
RE WALL:-
PIPE CULVERTS:-
This work shall consist of furnishing and installing reinforced
cement concrete pipes, of the type, diameter and length required
at the locations shown on the drawings or as ordered by the
Engineer and in accordance with the requirements of these
Specifications.
EXCAVATION FOR PIPE- The pipes shall be placed in shallow
excavation of the natural ground or in open trenches cut in
existing embankments, taken down to levels as shown on the
drawings.
The pipe shall be placed where the ground for the foundation is
reasonably firm.
BEDDING FOR PIPE- The bedding surface shall provide a firm
foundation of uniform density throughout the length of the
culvert, shall conform to the specified levels and grade.
LAYING OF PIPE- The laying of pipes on the prepared
foundation shall start from the outlet and proceed towards the
inlet and be completed to the specified lines and grades.
JOINTING- The pipes shall be jointed either by collar joint or
by flush joint.
Backfilling upto300 mm above the top of the pipe shall be
carefully done and the soil thoroughly rammed, tamped or
vibrated in layers not exceeding 150 mm, particular care being
taken to thoroughly consolidate the materials under the
haunches of the pipe.
Total height of pipe culvert is 1800 mm is to be constructed.
Bottom encasing of M15 grade and top slab of M25 grade &
thickness 200 mm is to be constructed.
Width of Pipe Culvert , 1840 mm is to be constructed for final
completion with 100 mm covers on both side of 100 THK PCC.
MINOR BRIDGE:-
Minor Bridge from 17+986.900 Km (From
Kharar to Kurali) to 18+007.950 Km is to be
constructed.
Total Span of Bridge, 27m and max height
3.235m is to be constructed.
It will consists of 4 intermediate walls and 2
outer walls supporting bridges top slab and
bottom slab.
The outer walls, 400 mm wide and inner walls,
300mm width 450 mm is to be constructed.
Top slab of and bottom slab of 500 mm
thickness is to be constructed.
100 thk PCC is to be Laid of M10 grade of
concrete.
Methodology:- Compaction of earth
Tie Up of Bottom slab reinforcement
Placing of Binders
Reinforcement in Shear Key
Tie Up of Wall reinforcement
Shuttering Plates to be tied.
Casting of Bottom Slab using Boom
Pressure of Concrete Pump.
Curing of bottom Surface
Casting of walls and Top Slab with
prescribed measures.
Road surface to be constructed with
layers of constituent materials with
appropriate measures.
ACKNOWLEDGEMENT
I thank my Mentor and the concerned Engineers for their
support and sharing of meaningful and deep knowledge
related to various aspects of my Training Semester Project.