MC L 04 Pipework Reinstatement
MC L 04 Pipework Reinstatement
Contr Client
Item Description Initial Date Initial Date Remarks
1 CHECK LIST ITEMS
1.01 Temporary spades / blanks removed.
1.02 Permanent spades and blinds are installed as per P & ID.
1.03 Temporary piping fittings removed including any jumpers.
1.04 Check that all valves are installed in correct flow orientation.
1.06 Spools / valves / special items removed for test re-installed.
1.08 All punchlist items cleared.
1.09 Preservation requirements implemented.
1.10 Check that correct gasket is fitted at flanged joint.
1.11 Check for flange bolt - material and torquing.
1.12 Check pipe is clean internally, free of debris and dry.
Note: Tick all check item under OK - Satisfactory; N/A - Not Applicable; Punch items(s) are to be PL.
Company/Dept:
Print Name:
Signature:
Date:
Rev: A, (ID= 16208) - ConocoPhillips PIMS Printed by: Fadly, Maylan, 19-May-2013 15:09