Professional Documents
Culture Documents
Chapter 1 - Introduction To Drilling Engineering Latest PDF
Chapter 1 - Introduction To Drilling Engineering Latest PDF
Chapter 1 - Introduction To Drilling Engineering Latest PDF
(CGE577)
CHAPTER 1:
INTRODUCTION TO DRILLING
SYSTEMS
CONTENTS
2
History of drilling
functions
Drillers terminology
It is in 1859 in Titusville,
Pennsylvania, USA (First
commercial well) drilled by Col
Edwin L. Drake
OIL
18/10/2016 2:09 PTG
How do we find the reservoirs?
9
Injection well
To store hydrocarbon mainly natural gas, disposing of unwanted
produced water or regaining the reservoir pressure by injecting
water, steam or gas into the reservoir.
Reentry well
Conducted on existing wells for the purpose of tapping deeper
producing zones, recompleting or drilling laterals from existing main
trunk (vertical, directional or horizontal)
Infill well
To replace depleted wells or drill additional wells to sustain
production economics in certain fields.
RIG
MECHANICS The actual drilling is often done by a
drilling contractor.
18/10/2016 2:09 PTG
DRILLING PERSONNEL
19
Toolpusher is employed by the drilling contractor to be in overall charge of the rig and
liaise with the company man.
The STP co-ordinates all the Drilling Contractors functions on the rig and is the main
contact with the Operators Senior Drilling Supervisor/ Companyman
The STP will probably have worked his way through the Rig Crew ranks to his present
position and have 10-20 years experience
On some rigs he is also the Offshore Installation Manager (OIM) which means that he
carries the legal responsibility for safety on board the rig. On other rigs the Barge Captain is
the OIM
On a floating rig such as a semi-submersible or Drillship, the following groups will report to
the STP
Drill Crew
Engineering Crew
Marine Crew
Subsea Engineers
Medics
Radio Operators
Driller
- The driller operates the pumps, drawworks and rotary
table via the drillers console ( a room of gauges, control
levers, rheostats and other pneumatic, hydraulic and
electronic instrumentation).
- The driller is sometimes referred to as the person who is
on the brake.
Assistant Driller
- He has many task to perform most vary depending on
particular drilling operation being carried out at the time.
- He is direct supervisor for Derrickman, Pumpman and
Roughnecks.
- He will relief Driller when driller take a short break.
Derrickman
- Working about 90 feet above the rig floor in the derrick.
- He handles the section of drill pipe under the direction of
the assistant driller.
- Works up in the derrick when tripping into or out of the
hole.
Pumpman
- He is assistant of Derrickman and responsible for the
maintenance and smooth operation of the mud pumps
and mud holding pits among other machines in the
mud pump room.
- Also assist the roughnecks when very busy on drill
floor and not required in the pump room.
Roughneck (Floorman)
- A low-ranking member of the drilling crew.
- Works on the rig floor in a team of three and is
responsible for the operation of equipment and
machines as required by the particular operation being
carried out at that time by the driller.
Motorman
- He is responsible for the operations and routine maintenance of the
prime movers.
- He can do minor repairs and will do other duties when needed.
18/10/2016 2:09 PTG
Support and Services Crew
26
Safety Officer
Rig Medic/ Doctor
Radio Operator
Storeman
A crew member who maintains stocks and distributes equipment
and parts on an offshore platform
Catering & Accommodation Crew
Lead by the camp boss who has the team of Chief Cook, Cook and
Cleaner.
They have responsibility to serve food and good accommodation
Cementer (1 on board)
The Cementer supports the process of preparing a well for
further drilling, production or abandonment.
Cementing a well is the procedure of developing and
pumping cement into place in a wellbore.
The cementer maintains the Cement Pump which is found
on board most rigs. He ensures that the pump is kept
ready to cement in casing or to plug off the well
In addition, the cementer will also operate the Cement
Pump for high pressure testing purposes, such as BOP
tests
Cementers normally evolve from Rig Crew backgrounds
Operation geologist
Drilling fluid Service Crew
Cementing Services Crew
Mud logging Crew
Directional Drilling Crew
Tubular Handling Crew
Wellhead Service Engineer
Electric Wireline Logging Crew
Testing Crew
Coring Crew, etc.
Sizes:
Available Casing Sizes :
36 in. OD
30 in. OD
24 in. OD, 20 in. OD
13 3/8 in. OD, 10 in. OD
9 5/8 in, OD, 7 in. OD
5 in. OD
4 in. OD
4 in. OD
18/10/2016 2:09 PTG
35
18/10/2016 2:09 PTG
36
18/10/2016 2:09 PTG
37
Rig vs Platform
38
Barges 39
Rigs
Marine Land
Semi-
Submersible Drillship Jacknife/ Portable Mast
Cantilever (Small)
Derrick
(Deeper)
Platform Submersible Jackup Barge
Jack-up Semi- Tender
submersible Assisted
Tender Self-
Assisted contained
Heli-transporatable rig
18/10/2016 2:09 PTG
INLAND BARGES
45
Production
Platform
Jack-up Rig
Jack-up has a floating hull with retractable legs which can be jacked
down to the sea bed. Hull can be lifted until it is clear off the sea surface.
The legs support the hull.
In shallow and relatively calm waters the Jack up has the advantage of
being able to leave a free standing well with a surface completion once it
is finished.
18/10/2016 2:09 PTG
49
TYPES OF DRILLING RIG
Semi-submersible Rig
Semi-submersible Rig
In areas where water depths exceed 100m and heavy weather can be
expected then semi-submersibles must be used.
Drill Ship
Drill Ship
Drillships are designed to carry out drilling operations in
ultra-deep waters where even most Semi-Submersibles can
not drill.
HOISTING
ROTARY SYSTEM
SYSTEM
DRILLING DATA
RIG ACQUISITION
POWER SYSTEM AND
COMPONENTS MONITORING
SYSTEM
Total power requirements for most rigs are between 1000 3000 hp
Old days used steam engine. Steam boilers are rarely used in present
operations due to the difficulty in transporting the boilers.
PRIME MOVERS
These are used to supply
power to drilling operations.
These can be steam engines,
electric motors, internal
combustion engine
Input Power:
Pi = QfH
2545
Methane -- 24,000
Exercise 1:
Function:
Used to lower or raise drill strings, casing string
and other subsurface equipment into or out of
hole.
Principal Components:
1. Derrick and substructure
2. Block and tackle
3. Draw works
Crown Block
Fast line
Dead line
Anchor
Storage Reel
Draw Works
Moving
Block
Mast
A portable derrick, one capable of
being erected as a unit
Fastline it is wound
onto the drawworks and
usually reeved around
the blocks several times
(moving line).
Deadline acts as an
anchor point below the
rig floor and does not
move
The tensile strength of the drilling line and the number of times
it is reeved through the blocks will depend on the load, which
must be supported by the hoisting system.
The tensile load (lbs.) on the fast line, Ff and dead line Fd in a
frictionless system can be determined from:
77
W W 1 E En
Fd W W
En n En
fast dead
Fd = W + F f + F s
Fd = load applied to the derrick
W = the total load supported by the drilling lines (lbs.)
n = the no. of lines reeved around the crown and travelling block
FA = W(n+4)/4n
FB = W/4
FC = W(En+2)/4En
FD = W(En+2)/4En
n4
Fde W
n
Derrick Design
1 E En
W
Fd En E (n 1) 1
Ed
Fde n4 E (n 4)
W
n
The derrick efficiency increases with the number of lines
strung between the crown block and travelling block.
Rig selection
85
Calculate
(i) the static tension in the fast line when upward motion is
impending,
(ii) the maximum hook horsepower available,
(iii) the maximum hoisting speed,
(iv) the actual derrick load
(v) the maximum equivalent derrick load, and
(vi) the derrick efficiency factor.
(i) the power efficiency of n=8 is given as 0.841. The tension in the fast line is:
W 300,000
Ff 44,590lbf
En 0.841(8)
(ii) The maximum hook horsepower available is :
Ph = E.I = 0.841 (500) = 420.5 hp
1 E En
Fd W
En
1 0.841 0.841(8)
(300,000) = 382,090 lbf
0.841(8)
(v) The maximum equivalent load is given by:
n4 84
Fde W (300,000) 450,000lbf
n 8
(vi) The derrick efficiency factor is
Fd 382,090
Ed 0.849 or 84.9% Answer
Fde 450,000 18/10/2016 2:09 PTG
Exercise
89
Calculate
(i) the static tension in the fast line when upward motion is
impending,
(ii) the maximum hook horsepower available,
(iii) the maximum hoisting speed,
(iv) the actual derrick load
(v) the maximum equivalent derrick load, and
(vi) the derrick efficiency factor.
the process of moving the drillstring out of the hole, change the bit or
alter the bottom-hole assembly, and lower the drillstring again into the
hole is referred.
2. Setting slips
4. Drillpipe is then
removed by attaching
pipe elevators to the
drillpipe and using the
drum hoist to raise the
drillpipe above the rig
floor.
1. Swivel :
Supports the weight of the drillstring and
permits rotation
2.Kelly:
Square or Hexagonal to be gripped easily.
Torque is transmitting through kelly
bushings.
4. Rotary Drive:
Provides the power to turn the rotary
table.
5. Drill Pipe:
Specified by (a) Outer Diameter
(b) Weight per foot
(c) Steel grade
(d) Range Length
Range Length (ft)
1 18 to 22
2 27 to 30
3 38 to 45
6. Drill Collar:
Thick walled heavy steel pipe used to apply
18/10/2016 2:09 PTG
weight to the bit.
The Rotary Table
95
Swivel
Kelly The rotation of the drill string is
enabled via a hexagonal section of
Kelly Bushing pipe Kelly which is 15 metres
long which locates in the rotary
table.
Rotary Table
The drill pipe and drill collars are
referred to as tubulars
Kelly
Kelly
bushing
Rotary table
Components:
1. Mud Pumps
2. Mud Pits
3. Mud Mixing Equipment
4. Contaminants Removal Equipment
Pumps:
Reciprocating Positive Displacement Piston
Pumps.
Two-Cylinders - Duplex (Double Acting
Forward-Backward)
Three-Cylinders - Triplex (Forward only
Single Acting)
Duplex Pump
There are two piston-cylinders
assemblies in a single crankshaft.
Solution:
The pump factor for a duplex pump:
Fp = (/2). Ls .(2.dL2 - dr2) . Ev
= (/2) (18) (2(6.5)2 - (2.5)2) . (0.9)
= 1991.2 in.3 /cycle
or = 0.2052 bbl/stroke. Answer
Triplex Pump
There are three piston-cylinder
assemblies. All the three pistons are
coupled to the single crankshaft.
110
Fp= Pump factor or pump displacement per cycle.
b) Flowrate in gal/min
a) 4.039 gal/cycle
b) 484.67 gal/min
c) 848.32 hp
Solution: TD
BHP = 0.052x10.5x10,600 = 5,788 psi,
Burst pressure at the surface when the annulus is
completely filled with gas =
5788 0.052x2.5x10,600 = 4410 psi,
5,000 psig BOP should be selected.
Gas Pf
Kick
6) DRILLING DATA ACQUISITION AND
MONITORING SYSTEM
116