No Task Name DurationPred

A Pekerjaan Persiapan 2 days


1 Pembersihan Lokasi 2 days
2 Bowplank 1 day 3
B Pekerjaan Galian 3 days
3 Galian Tanah 3 days 4
C Pekerjaan Pondasi 3 days
4 Urugan Tanah Bawah Pondasi 1 day 4FS+2 days
5 Pasangan Batu Kali 3 days 8FS-1 day
6 Urugan Kembali 1 day 9FS-1 day
D Pekerjaan Beton Bertulang 5 days
7 Sloof 5 days 10

12FS-2 days
8 Kolom 4 days
E Pekerjaan Dinding 4 days
9 Pasangan Bata 4 days 13

15FS-2 days
10 Plesteran + Aci 4 days
11 Cat 3 days 16FS-1 day
Resource Tenaga Resource Material

PK2
Borongan Rp 200.000

PK2

PK2
PK 1, TB2 batu kali 1 m3, semen 7 zak, pasir 1 m3
PK1

Borongan Rp.3000.000

Borongan Rp.4000.000

PK2,TB2 bata 500, semen 10 zak, pasir 3 m3

PK2,TB3 semen 10 zak

PK1,TC2 cat 5 kg