DAFTAR KUANTITAS DAN HARGA

PEKERJAAN : PEMBANGUNAN POS JAGA KANTOR DPRA


LOKASI : BANDA ACEH

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME SAT
Rp. Rp.
1 2 3 4 5 6

A PEKERJAAN PERSIAPAN
1 Pemindahan Tiang Listrik 1,00 Unit 1.700.000,00 1.700.000,00
2 Pembersihan Lahan 1,00 Ls 500.000,00 500.000,00
3 Pengukuran dan Pemasangan Bouwplank 8,00 m' 50.000,00 400.000,00
2.600.000,00
B PEKERJAAN TANAH
1 Galian Pondasi 4,00 m3 31.000,00 124.000,00
2 Urugan Galian 1,00 m3 14.865,00 14.865,00
3 Timbunan Pasir Bawah Pondasi 0,24 m3 231.750,00 55.620,00
4 Timbunan Pasir Bawah Lantai 0,80 m3 231.750,00 185.400,00
5 Timbunan Tanah Bawah Lantai 1,20 m3 99.750,00 119.700,00
499.585,00
C PEKERJAAN PONDASI
1 Pasangan Batu Kosong Bawah Pondasi 0,48 m3 364.920,00 175.161,60
2 Pasangan Batu Gunung 1 : 4 3,36 m3 670.675,00 2.253.468,00
2.428.629,60
D PEKERJAAN BETON BERTULANG
1 Sloof 18/25 0,36 m3 4.131.110,00 1.487.199,60
2 Kolom Praktis 11/11 0,15 m3 6.240.827,00 906.168,08
3 Balok Latai 11/20 0,04 m3 3.227.722,00 142.019,77
4 Balok 11/15 0,13 Unit 4.650.000,00 613.800,00
5 Plat t = 10 cm (Atap Dak) 0,08 Unit 4.247.100,00 339.768,00
6 Plat t = 10 cm (Meja) 0,12 Unit 4.247.100,00 509.652,00
3.998.607,45
E PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasangan Bata 1/2 Bata 1 : 4 25,62 m2 105.363,00 2.699.400,06
2 Plesteran Bata 1 : 4 51,24 m2 39.650,00 2.031.666,00
4.731.066,06
F PEKERJAAN LANTAI
1 Lantai Beton Tumbuk 1 : 3 : 5 0,80 m3 696.950,00 557.560,00
2 Lantai Keramik 40 x 40 cm 4,00 m2 238.148,00 952.592,00
3 Keramik Meja 40 x 40 cm 1,40 m2 238.148,00 333.407,20
1.843.559,20

G PEKERJAAN PINTU DAN JENDELA


1 Kaca mati t = 10 mm 3,00 m2 450.000,00 1.350.000,00
1.350.000,00

H PEKERJAAN PLAFOND
1 Plafond Calsiboard + Rangka Metal Furing 8,75 m2 250.000,00 2.187.500,00
2 List Plafond 16,00 m' 18.500,00 296.000,00
2.483.500,00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME SAT
Rp. Rp.
1 2 3 4 5 6
I PEKERJAAN ELEKTRIKAL
1 Penyambungan Arus Listrik 1,00 Ls 2.500.000,00 2.500.000,00
2 Instalasi Listrik Lengkap Kabel 5,00 Titik 125.000,00 625.000,00
3 Lampu Downligh 4,00 bh 175.000,00 700.000,00
4 Stop Kontak (Panasonic) 2,00 bh 75.000,00 150.000,00
5 Saklar Tunggal (Panasonic) 1,00 bh 75.000,00 75.000,00
6 Saklar Ganda (Panasonic) 2,00 bh 75.000,00 150.000,00
4.200.000,00

J PEKERJAAN PENGECATAN
1 Cat Dinding Tembok (Dulux) 51,24 m2 34.273,00 1.756.148,52
2 Cat Plafond (Dulux) 8,75 m2 34.273,00 299.888,75
3 Cat Listplank (Caltilac) 3,27 m2 47.103,00 153.838,40
2.209.875,67
K PEKERJAAN ATAP
1 Rangka Atap Baja Ringan 11,60 m2 160.000,00 1.856.000,00
2 Atap Seng Metal (Emerald) 11,60 m2 105.650,00 1.225.540,00
3 Listplank 15,78 m' 35.000,00 552.300,00
3.633.840,00
I PEKERJAAN LAIN-LAIN
1 Pasangan Keramik Dinding Motif Batu Alam 2,80 m2 300.000,00 840.000,00
2 Relief Minimalis + Ornamen 1,00 Ls 1.000.000,00 1.000.000,00
1.840.000,00

JUMLAH 31.818.662,98
PPn 10 % 3.181.866,30
TOTAL 35.000.529,27
DIBULATKAN 35.000.000,00