CONSTRUCTION WORK COST

PL= 350
H= 300
TS= 350
M= 350
C= 350
S= 350
PT= 350
Supervisor= 500

Hourly Cost of
Schedule of Supervision Cost
Item No. Job Description Man-hour Rate Manpower
Manpower (Php/mh)
(Php/mh)
1 Demolition (Heavy Solid) 5.18 /cu.m. H 37.5 62.5
2 Tile setting 3.75 /sq.m. TS 43.75 62.5
3 Tile Backerboard/floor levelling 0.48 /sq.m. H, TS 81.25 62.5
4 Concreting (Pouring) 2 /cu.m. H, C, M, S 168.75 62.5
5 Ceiling works (assemblies) 2 /sq.m. H, C 81.25 62.5
6 Inst. of Ficem board 0.6 /sq.m. H, C 81.25 62.5
7 Painting works per coat (Manual roller or brush) 0.2 /sq.m. PT 43.75 62.5
8 Surface Preparation 0.37 /sq.m. PT 43.75 62.5
9 Inst. of Fixtures 8 /pc. PL, H 81.25 62.5
10 Plumbing/Electrical Roughing-ins 0.7 /ln-m PL, H 81.25 62.5
11 Cabinetry and Partition Inst. (Fabricated) 1.43 /sq.m. H, C 81.25 62.5
12 Woodworks and Cabinetry Fabrication 7.32 /sq.m. C 43.75 62.5
13 Paint Removal 1 /sq.m. PT 43.75 62.5
14 Restoration 1.5 /cu.m. M, H 81.25 62.5
15 Fabrication, Cutting, Bending of Rebars 0.03 /kg. S, H 81.25 62.5
16 Placing and Tying of Rebars 0.06 /kg. S 43.75 62.5
17 Manual mix concrete 6.4 /cu.m. 2H 75 62.5
18 Steelworks/Welding Fabrication - - - - -
Equipment cost (10%
Unit cost Unit
of labor cost)

10 569.80 Php/cu.m.
10.625 438.28 Php/sq.m.
- 69.00 Php/sq.m.
23.125 508.75 Php/cu.m.
14.375 316.25 Php/sq.m.
14.375 94.88 Php/sq.m.
- 21.25 Php/sq.m.
10.625 43.24 Php/sq.m.
14.375 1,265.00 Php/pc.
14.375 110.69 Php/ln-m
14.375 226.11875 Php/sq.m.
10.625 855.525 Php/sq.m.
10.625 116.875 Php/sq.m.
- 215.625 Php/cu.m.
14.375 4.74375 Php/kg.
- 6.375 Php/kg.
- 880 Php/cu.m.
- - -