Professional Documents
Culture Documents
5C TS&L Considerations Long Span Viaducts P Montemerlo J Tubbs
5C TS&L Considerations Long Span Viaducts P Montemerlo J Tubbs
5C TS&L Considerations Long Span Viaducts P Montemerlo J Tubbs
Presented by
Patrick D. Montemerlo, PE
Joel B. Tubbs, PE, SE
Introduction
Accommodation
of Horizontal
Curvature
Very High
Torsional
Capabilities
Geometry - Superstructure
Segmental Box Girder Superstructure Capabilities
Able to Adapt to Changes in Roadway Geometry
Highly Variable Wing Lengths
Geometry - Superstructure
Concrete Girders Have Geometric Limitations
Straight Concrete Girders Require Large Horizontal Radii
Smaller Radii Typically Requires Different Superstructure Type
Geometry - Substructure
Segmental Girder
Capabilities
Relatively Close
Bearing Offsets
Typically Larger
Bearing Loads
Geometry - Substructure
I-Girder or Curved Girder Capabilities
Relatively Wide Bearing Offsets
Typically Smaller Bearing Loads
Construction - Precasting
Girder Casting Yards
Common in Many Regions
Competitive Bidding
Construction - Precasting
Girder Casting Yards
Adaptable to Small Volume Needs
Generally Simple Casting Yard Geometry Control
Construction - Precasting
Precast Segmental Girder
Casting Yards
Typically Project Specific
Large Initial Investment
may be Required
Construction - Precasting
Precast Segmental Girder Casting Yards
Precise Casting Yard Geometry Control
Increased Storage Capabilities with Stacking
Construction - Transport
Precast Girders Trucks
Long and Typically Require Two Trailers per Girder
Construction - Transport
Segmental Precast Girders
Trucks
Compact and Typically Only One
Trailer Needed per Segment
Girder and Deck Delivered
Construction - Transport
Escort from Casting Yard
Necessary for Girders
Often Not Necessary for Light Rail
Precast Segmental Segments
Construction - Transport
Delivery
Precast Segments Often Fast Off the Truck
Ground or Bridge based Cranes
Construction - Erection
Setting of Girders
Careful Coordination Typically Required when using Two
Cranes
Construction - Erection
Setting of Segments
Able to Erect Segment
with One Crane or Gantry
Gantry Typically Large
Dollar Item
Construction - Erection
Final Placement
Girders Typically have Greater Placement Tolerances
Match-Cast Segmental Faces Require more Precise Placement
Construction - Schedule
Precasting/Fabrication
Precast Girders 5 to 7 Girders Per Week Per Casting Bed
Precast Segments 1 Segment Per Day Per Casting Bed
Steel Girders 1 Girder Per Week Per Fabrication Line
Construction - Schedule
Erection
Precast Girders:
2 to 3 Spans
of Girders Per
Day
Precast
Segments:
2 to 3 Span
Lines of
Segments Per
Week Per
Truss/Gantry
Construction - Schedule
Overall Schedule
Precast Segment Casting Yard Can Take Months to Setup
Girders can begin Production Quickly at Establish Plant
Construction - Schedule
Overall Schedule
Once Precast Segments are In-Place, the span is complete.
Precast Girders Still Need Deck Cast After Erection.
Construction - Schedule
Overall Schedule
Shorter
Bridge/Viaducts
Favors Typical
Girders
Longer Bridge/
Viaducts Favors
Segmental
Girders
Durability
Long Term Performance - Girders
Precast Girders Require Little Maintenance
Steel Girders Require Special Inspections and
Possibly Repainting
Durability
Long Term Performance Segmental
Segmental Girders Require Little Maintenance
May Require Special Inspection of External Post-
Tensioning
Aesthetics
Visual Continuity - Girders
Depending on Curve Geometry and Span Lengths, Different
Types of Girders May be Required.
Aesthetics
Visual Continuity - Segmental
Same Segmental Box can be Used for All Necessary
Geometry and Span Lengths
Aesthetics
Superstructure to Substructure
Visual Interaction
Aesthetics
Structural Transitions
Segmental Girders Tend to Have Smoother Transitions
Through Wing Length Variations.
Girders Typically Require Girders to Be Added or Removed.
Aesthetics
Visual Environment and Surroundings - Girders
Aesthetics
Visual Environment and Surroundings - Segmental
Economics and Cost Considerations
Initial Cost Considerations
Contractor Experience
Prefabrication
Construction Staging
Construction Schedule
Economics and Cost Considerations
Right-of-Way
Permanent Right-of-Way
Temporary Construction
Access
Superstructure Erection
Conclusion
Structure Layout
Design Considerations of
Bridge Elements
Geometry Capabilities
Construction Considerations
Durability of Bridge Elements
Aesthetic Considerations
Economic and Cost
Considerations
Conclusion
Which is Preferred?
Evaluate the Total
Project
Consider All Stakeholders
Project Decision Matrices
TS&L Considerations for Long Span Viaducts
in Urban or Pre-Urban Environments
QUESTIONS?
Presented by
Patrick D. Montemerlo, PE
Joel B. Tubbs, PE, SE