ESTIMATE FOR DRAINAGE 18" RCCP(20 MODEL)

Materials QTY SKU Amount Total


cement 2 bag 222.93 445.86
wash sand 0.13 cu.m 70 9.1
Labor
1 Mason 2 day 350 700
3 Helper 2 day 840 1680
Total Cost 2834.96

ESTIMATE FOR DRAINAGE 24" RCCP(20 MODEL)


Materials QTY SKU Amount Total
cement 6 bag 222.93 1337.58
wash sand 0.55 cu.m 70 38.5
Labor
1 Mason 2 day 350 700
3 Helper 2 day 840 1680
Total Cost 3756.08

ESTIMATE FOR DRAINAGE SMALL BOX CULVERT(20 MODEL)


Materials QTY SKU Amount Total
cement 8 bag 222.93 1783.44
wash sand 0.61 cu.m 70 42.7
gravel 3/4 0.814 cu.m 420 341.88
10mm 23 L 135 3105
Tie Wire 1.5 kg 55 82.5
1/4 Ordinary Plywood 2 pc 300 600
Labor
1 Mason 3 day 350 1050
3 Helper 3 day 840 2520
Total Cost 9525.52

ESTIMATE FOR DRAINAGE BOX CULVERT 1(10 MODEL)


Materials QTY SKU Amount Total
cement 5 bag 222.93 1114.65
wash sand 0.37 cu.m 70 25.9
gravel 3/4 0.5 cu.m 420 210
10mm 12 L 135 1620
Tie Wire 1.5 kg 55 82.5
1/4 Ordinary Plywood 4 pc 300 1200
Labor
1 Mason 3 day 350 1050
3 Helper 3 day 840 2520
Total Cost 7823.05
ESTIMATE FOR DRAINAGE BOX CULVERT 2(10 MODEL)
Materials QTY SKU Amount Total
cement 6 bag 222.93 1337.58
wash sand 0.5 cu.m 70 35
gravel 3/4 0.638 cu.m 420 267.96
10mm 18 L 135 2430
Tie Wire 1.5 kg 55 82.5
1/4 Ordinary Plywood 4 pc 300 1200
Labor
1 Mason 3 day 350 1050
3 Helper 3 day 840 2520
Total Cost 8923.04