Stage Completion RFI-April

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

S.no. Section Incharge Date RFI no.

1 Ashok Rajjvale 31-Mar-17 CTP-2/D/WS-127/4.2/39104

2 Ashok Rajjvale 5-Apr-17

3 Ashok Rajjvale 31-Mar-17 CTP-2/D/WS-129/4.3/39115

4 Ashok Rajjvale 31-Mar-17 CTP-2/D/WS-131/2/4.3/39123

5 Ashok Rajjvale 31-Mar-17 CTP-2/D/WS-131/2/4.3/39128

5-Apr-17
6 Ashok Rajjvale

7 Syed Jafar Imam 31-Mar-17 CTP-2/D/WS-140/4.3/39157

8 Syed Jafar Imam 31-Mar-17 CTP-2/D/WS-141/4.2/39159

9 Syed Jafar Imam 31-Mar-17 CTP-2/D/WS-137/4.3/39164

10 Anjum Jauher 31-Mar-17 CTP-2/D/WS-136/2/4.1/39160

11 Anjum Jauher 31-Mar-17 CTP-2/D/WS-136/3/4.1/39161

12 Anjum Jauher 31-Mar-17 CTP-2/D/WS-137/4.1/39162

13 Anjum Jauher 31-Mar-17 CTP-2/D/WS-141/4.1/39166

14 SN Patil 5-Apr-17 CTP-2/D/WS-132/1/4.4/

15 SN Patil 5-Apr-17
Description

Stage Completion of Foundation of Pier P9 of Br no. 750

Stage Completion of Foundation of Pier P5 of Br no. 750

Completion of Br no. 764

Completion of Br no. 776

Completion of Br no. 778

Completion of Minor Bridge 759

Completion of Br no. 828

Stage completion of Foundation of Abutment A1 & A2 of Br no. 831

Completion of Br no. 808

Completion of Setting Out Plan for WS 136/2

Completion of Setting Out Plan for WS 136/3

Completion of Setting Out Plan for WS 137

Completion of Setting Out Plan for WS 141

Stage completion of 100% filling in Embankment of WS 132/1

Stage completion of 50% filling in Embankment of WS 131/2


Total value RFI received
Invoice
Status committed on Value 04th
Amount (in Cr) 30th Mar'17 April'17

0.68 Completed

0.68

1.22 Completed
3.38 2.4
0.3 Completed

0.2 Completed

0.3

0.05

0.63 Completed 0.74 0.69

0.06 Completed

0.044 Completed

0.061 Completed
0.14 0.25
0.061 Completed

0.085 Completed

0.81
1.34 0
0.53
Total 5.6 3.34
Completed 3.34
Will be completed Tod 2.37
Pending RFI value

0.98

0.05

1.34

2.37