Note of discussion
2. Only rev.Awill be send to RMN for Approval.Rev.C will be send for Discussion with
RMN.PSI need to attach with Mod.Notice. No cloud.
5. Issue for comment drawing (C1) send to RMN for their review & comment. Ask for
discussion within 2 or 3 days (with letter). Any decision from RMN,record with RMN
sign.
6.75% to 90% is C(dwg for comment-from TSD & RMN).90% is A(dwg for approval to
RMN.No more discussion with RMN).100% is as built dwg(sign by RMN).Make
flowchart.
11. Look/review in detail PSI dwg. Recheck all transmittal & reviewed dwg.
12. Cable block diagram-System dwg(from OEM) doesnt need to be sent to RMN.
13. Reference dwg (dwg existing only)dont send to RMN.If reference dwg(OEM
dwg)send for info only.
RMN doesnt need to approved OEM dwgs(except for P&ID-for info only).
14. FAT procedure by OEM & reviewed by PSI & CSI,other integrators(if required).
15. TSD to check & review the test procedure.Dont modify the format as per
CTS(its ITT job).PSI review test procedure send to ITT.Dont send to RMN.
Prepared by,
Firdaus Mohd.