GENERAL SCHEDULE OF DESIGN SHOP DRAWINGS (05 BRIDGES)

T Item works Times M-1 M1 M2 M3 M4


1 TOTAL SCHEDULE OF DESIGN SHOP DRAWINGS 114 days
2 PART I: CALCULATION 40 days
3 SANGKAE Bridge 8 days
4 Abutments 2 days
5 Piers 4 days
6 Piles 2 days
7 Bridge 79 8 days
8 Abutments 2 days
9 Piers 4 days
10 Piles 2 days
11 Bridge 80 8 days
12 Abutments 2 days
13 Piers 4 days
14 Piles 2 days
15 Bridge 81 8 days
16 Abutments 2 days
17 Piers 4 days
18 Piles 2 days
19 Bridge 82 8 days
20 Abutments 2 days
21 Piers 4 days
22 Piles 2 days
23 PART II: DRAWINGS 114 days
24 SANGKAE Bridge 31 days
25 Piles 3 days
26 Piers 7 days
27 Abutments 4 days
28 Superstructures (Main girder, deck slab, girder diaphragm...) 10 days
29 Box culvert 4 days
30 Miscellaneous (Approach road of bridge, Bearings, Expansion joint , Drain, Road signs...) 3 days
31 Bridge 79 25 days
32 Piles 3 days
33 Abutments 4 days
34 Piers 3 days
35 Superstructures (Main girder, deck slab, girder diaphragm...) 12 days
36 Miscellaneous (Approach road of bridge, Bearings, Expansion joint , Drain, Road signs...) 3 days
37 Bridge 80 18 days
38 Piles 3 days
39 Abutments 4 days
40 Superstructures (Main girder, deck slab, girder diaphragm...) 8 days
41 Miscellaneous (Approach road of bridge, Bearings, Expansion joint , Drain, Road signs...) 3 days
42 Bridge 81 20 days
43 Piles 3 days
44 Abutments 4 days
45 Piers 2 days
46 Superstructures (Main girder, deck slab, girder diaphragm...) 8 days
47 Miscellaneous (Approach road of bridge, Bearings, Expansion joint , Drain, Road signs...) 3 days
48 Bridge 82 20 days
49 Piles 3 days
50 Abutments 4 days
51 Piers 2 days
52 Superstructures (Main girder, deck slab, girder diaphragm...) 8 days
53 Miscellaneous (Approach road of bridge, Bearings, Expansion joint , Drain, Road signs...) 3 days