Risk may be defined as an unexpected or an undesired outcome of an action or series of

actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory

Risk may be defined as an unexpected or an undesired outcome of an action or series of


actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory
Risk may be defined as an unexpected or an undesired outcome of an action or series of
actions. All human endeavors entail risk. In offshore field developments the risks that are of
greatest concern are those that can negatively affect the health and safety of individuals, the
environment, or the economics of the project.
6.1 Potential Areas of Risk
The following are potential areas of risk in a subsea development project.
6.1.1 Project Management
Poor interface planning and management.
Poor communications.
Unrealistic schedules or budgets.
Poor resource planning. Inadequate resources.
Poorly trained personnel.
Labour disputes.
Failure to identify or anticipate regulatory