Daily Activity List
Daily Activity List
Daily Activity List
COMMISSIONING
No Time Place to meet PIC Sub System Sub System Description Remarks
1 09:00:00 HV/LV Switchboard Room 4 865.19 11 KV/690V, 4000 KVA, Topside Transformers Step 2.4.66 to 2.4.71
2 09:00:00 Shaker house roof 347.01A Pipehandling Crane 2401 Commission with gripper yoke on the same day.
3 10:00:00 TOPSIDE sWITCHBOARD 3 875.08 230V Lighting & Small Power Dist. Panel LP#8 STEP 1.1.1 TO 2.4.9
4 13:00:00 LIR AND DCR 875.27 DES 230V LIR and DCR Lighting & Small Power Dist. STEP 1.1.1 TO 2.4.9
Panel LP#1
5 13:30:00 Mud Pump Room 734.02 Pneumatic Control Valve System Commissioning manual testing of valves
ENERGIZING
No Time Place to meet PIC Sub System Sub System Description Equip Tag Description
1 09:30:00 AM Thruster Pump Room 1P 722.02 Auxillary Fresh Water Cooling System 722PA002B-DE01 Fresh Water Auxiliary Cooling
Pump #2 AC Motor
2 09:30:00 AM HV/LV Switchboard Room #4 873.04 690V Topside Switchboard No 4 873EN004 690V Topsides SWBD No.4
3 1:00:00 PM P-Tank Room 320.00 Mud Control System 329A1-IB106 MCS RIO cabinet
4 9:15:00 AM Thruster Pump Room 1P 721.05B Auxiliary SW Cooling (P) 721PA002B-DE01 Sea Water Auxiliary Cooling
Pump #2 AC Motor
Daily Inspection
No Time Place to meet PIC Sub System Sub System Description Equip Tag/ Type of Inspection
Package No
1 08:30:00 AM PURUSH 2632 314.01 Dual Wireline Riser Tensioners 314.01-J-001 Cables TP
2 08:30:00 AM PURUSH 2632 314.01 Dual Wireline Riser Tensioners 314.01-J-003 Cables TP
3 08:30:00 AM PURUSH 2632 324.03 Mud Transfer and storage system, incl Tank Washing 324.03-J-003 Cables TP
OBM Soap Injection Unit, Agitator, High Rate Mixer
4 08:30:00 AM PURUSH 2632 332.01 BOP & Diverter Control System 332.01-P-001 Cables TP
5 08:30:00 AM PURUSH 2632 423.01 LAN (Local Area Network) 423.01-N-015 Cables TP
6 08:30:00 AM PURUSH 2632 731.03 Starting Air System - Engine Room No.3 731.03-J-002 Cables TP
7 08:30:00 AM PURUSH 2632 804.01 Deck Drainage System - Non Hazardous 804.01-P-001 Cables TP
8 08:30:00 AM PURUSH 2632 811.00 Fire and Gas System (F&G, Cause & Effect) 811.00-J-003-02 Cables TP
9 08:30:00 AM PURUSH 2632 811.00 Fire and Gas System (F&G, Cause & Effect) 811.00-J-003-03 Cables TP
10 08:30:00 AM PURUSH 2632 814.01 Fire Fighting Water Mist System 814.01-N-001 Cables TP
11 08:30:00 AM PURUSH 2632 873.72 690V Drilling SWBD/ MCC No 2 873.72-J-002 Cables TP
12 08:30:00 AM PURUSH 2632 875.01 230V Lighting & Small Power Dist. Panel LP#1 875.01-L-007 Cables TP
Page 1 of 4
11-1112 ( West Rigel (CS60) )
Daily activities summary list
Page 2 of 4
11-1112 ( West Rigel (CS60) )
Daily activities summary list
Page 3 of 4
11-1112 ( West Rigel (CS60) )
Advance call out/ One day look ahead activities
COMMISSIONING
No Time Place to meet PIC Sub System Sub System Description Remarks
6 09:15:00 Mud Pump Room 734.02 Pneumatic Control Valve System Commissioning manual testing of valves
7 13:00:00 866.03 General UPS system GENERAL UPS 2, LER Room 4
Page 4 of 4