ID Task Task Name Duration Start Finish


Mode 31 Oct 07 Nov 14 Nov 21 Nov 28 Nov 05 Dec 12 Dec 19 Dec 26 Dec 02 Jan 09 Jan 16 Jan 23 Jan 30 Jan 06 Feb
1
2 REHABILITATION OF WATER STORAGE TANKS IN 50 days Mon 21/11/16 Fri 27/01/17
SPDC WEST,TUNU
3 ENGINEERING/PROCUREMENT 17 days Mon 21/11/16 Tue 13/12/16
4 Site survey 2 days Mon 21/11/16 Tue 22/11/16
5 Material procurement 5 days Mon 21/11/16 Fri 25/11/16
6 PRE-STARTUP AUDIT 7 days Sat 26/11/16 Mon 05/12/16
7 Kick-off meeting 1 day Sat 26/11/16 Sat 26/11/16
8 HSES Provisions 3 days Mon 28/11/16 Wed 30/11/16
9 Quality Assurance 3 days Thu 01/12/16 Mon 05/12/16
10 PREMOBILIZATION ACTIVITIES 3 days Wed 30/11/16 Fri 02/12/16
11 Premob inspection 3 days Wed 30/11/16 Fri 02/12/16
12 SITE MOBILIZATION 9 days Sat 26/11/16 Wed 07/12/16
13 Transport of materials to site 6 days Sat 26/11/16 Fri 02/12/16
14 Mobilization of personnel/equipment 3 days Mon 05/12/16 Wed 07/12/16
15 EXECUTION PHASE 21 days Thu 08/12/16 Thu 05/01/17
16 Erection of scaffolds 3 days Thu 08/12/16 Mon 12/12/16
17 Dismantling of existing Braithwaite Tank 3 days Tue 13/12/16 Thu 15/12/16
18 Fabrication of internal bracing,cleats and other 2 days Fri 16/12/16 Mon 19/12/16
accessories
19 painting 2 days Tue 20/12/16 Wed 21/12/16
20 Assembling of Braithwaite Tank 3 days Thu 22/12/16 Mon 26/12/16
21 Final painting 2 days Tue 27/12/16 Wed 28/12/16
22 Dismantling of scaffolds 2 days Thu 29/12/16 Sat 31/12/16
23 Commissioning 2 days Mon 02/01/17 Wed 04/01/17
24 Report writing 2 days Wed 04/01/17 Thu 05/01/17
25 DEMOBILIZATION 3 days Fri 06/01/17 Tue 10/01/17
26 Site restoration 2 days Fri 06/01/17 Mon 09/01/17
27 Project close-out 1 day Tue 10/01/17 Tue 10/01/17

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
Project: Project1
Milestone Inactive Task Manual Summary Rollup Progress
Date: Thu 17/11/16
Summary Inactive Milestone Manual Summary
Project Summary Inactive Summary Start-only

BENKLINE NIGERIA LIMITED CONTRACT NO: NG01020982

You might also like