MONITORING TIMBUNAN

PEMBANGUNAN JALAN TOL


PASURUAN - PROBOLINGGO
ZONA 3
SISI K A N A N
STRUKTUR PERKERASAN
Rigid Pavement / tebal = 27 cm
Lean Concrete/tebal = 10 cm
Sub Base / Aggt. A / tebal = 25 cm
Sub-Grade Preparation
Layer 25
Layer 24
Layer 23
Layer 22
Layer 21
Layer 20
Layer 19
Layer 18
Layer 17
LAYER TIMBUNAN

Layer 16
Layer 15
PEKERJAAN TANAH

Layer 14
Layer 13
Layer 12
Layer 11
Layer 10
Layer 9
Layer 8
Layer 7
Layer 6
Layer 5
Layer 4
Layer 3
Layer 2 R1 - R3
Layer 1 = 20 - 40 cm R1 - R3
Tinggi Timbunan ( Rencana )
Site Clearing
Sub-Contraktor PT. Waskita Karya
Galian ( Perbaikan Tanah Dasar )
SISI K A N A N
31+300

31+275

31+250

31+225

31+200

31+175

31+150

31+125

31+100

31+075

31+050

31+025

31+000

30+975

30+950

30+925

30+900

30+875

30+850

30+825

30+800

30+775

30+750

30+725

30+700

30+675

30+650

30+625

30+600

30+575

30+550

30+525

30+500

30+475

30+450

30+425

30+400

30+375

30+350

30+325

30+300

30+275

30+250

30+225

30+200

30+175

30+150

30+125

30+100

30+075

30+050

30+025

30+000

29+975

29+950

29+925

29+900

29+875

29+850

29+825

29+800

29+775

29+750

29+725

29+700

29+675

29+650

29+625

29+600

29+575

29+550

29+525

29+500
S T A. 19+800 s/d 31+300

SISI K I R I
Galian ( Perbaikan Tanah Dasar )
Sub-Contraktor PT. Waskita Karya
Site Clearing
Tinggi Timbunan ( Rencana )
Layer 1 = 20 - 40 cm L1 - L4
Layer 2 L1 - L4
Layer 3
Layer 4
Layer 5
Layer 6
Layer 7
PEKERJAAN TANAH

Layer 8
Layer 9
LAYER TIMBUNAN

Layer 10
Layer 11
Layer 12
Layer 13
Layer 14
Layer 15
Layer 16
Layer 17
Layer 18
Layer 19
Layer 20
Layer 21
Layer 22
Layer 23
Layer 24
Layer 25
STRUKTUR PERKERASAN
Sub-Grade Preparation
Sub Base / Aggt. A / tebal = 25 cm
Lean Concrete/tebal = 10 cm
Rigid Pavement / tebal = 27 cm

Belum Bebas

Sudah Clearing

Timbunan
MONITORING TIMBUNAN
PEMBANGUNAN JALAN TOL
PASURUAN - PROBOLINGGO
ZONA 3
SISI K A N A N
STRUKTUR PERKERASAN
Rigid Pavement / tebal = 27 cm
Lean Concrete/tebal = 10 cm
Sub Base / Aggt. A / tebal = 25 cm
Sub-Grade Preparation
Layer 25
Layer 24
Layer 23
Layer 22
Layer 21

JEMB. SUNGAI KERAMAT STA 28+200


Layer 20
Layer 19

BOX UNDERPASS STA 27+972

BOX DRAINASE STA 27+660


Layer 18
Layer 17
LAYER TIMBUNAN

Layer 16
Layer 15
PEKERJAAN TANAH

Layer 14
Layer 13
Layer 12
Layer 11
Layer 10 R1 - R4
Layer 9 R1 - R4
Layer 8 R1 - R4
Layer 7 FDT 00/00/00 R1,R2 R1 - R4
Layer 6 FDT 00/00/00 R1,R2 R1 - R4
Layer 5 FDT 00/00/00 R1,R2 R1 - R4
Layer 4 FDT 00/00/00 R1,R2 R1 - R4
Layer 3 FDT 00/00/00 R1,R2 FDT 00/00/00 R1
Layer 2 FDT 00/00/00 R1,R2 FDT 00/00/00 R1
Layer 1 = 20 - 40 cm R1 - R2 FDT 00/00/00 R1,R2 FDT 00/00/00 R1
Tinggi Timbunan ( Rencana )
Site Clearing
Sub-Contraktor PT. GADING SEMESTA
Galian ( Perbaikan Tanah Dasar )
SISI K A N A N
29+475

29+450

29+425

29+400

29+375

29+350

29+325

29+300

29+275

29+250

29+225

29+200

29+175

29+150

29+125

29+100

29+075

29+050

29+025

29+000

28+975

28+950

28+925

28+900

28+875

28+850

28+825

28+800

28+775

28+750

28+725

28+700

28+675

28+650

28+625

28+600

28+575

28+550

28+525

28+500

28+475

28+450

28+425

28+400

28+375

28+350

28+325

28+300

28+275

28+250

28+225

28+200

28+175

28+150

28+125

28+100

28+075

28+050

28+025

28+000

27+975

27+950

27+925

27+900

27+875

27+850

27+825

27+800

27+775

27+750

27+725

27+700

27+675

27+650
S T A. 19+800 s/d 31+300

SISI K I R I
Galian ( Perbaikan Tanah Dasar )
Sub-Contraktor PT. GADING SEMESTA
Site Clearing
Tinggi Timbunan ( Rencana )
Layer 1 = 20 - 40 cm FDT 00/00/00 L1,L2 FDT 00/00/00 L1, L2
Layer 2 FDT 00/00/00 L1,L2 FDT 00/00/00 L1, L2
Layer 3 FDT 00/00/00 L1,L2 FDT 00/00/00 L1, L2
Layer 4 FDT 00/00/00 L1,L2 L1 - L4
Layer 5 FDT 00/00/00 L1,L2 L1 - L4

JEMB. SUNGAI KERAMAT STA 28+200


Layer 6 FDT 00/00/00 L1,L2 L1 - L4
Layer 7 FDT 00/00/00 L1,L2 L1 - L4

BOX UNDERPASS STA 27+972

BOX DRAINASE STA 27+660


PEKERJAAN TANAH

Layer 8 L1 - L4 L1 - L4
Layer 9 L1 - L4
L1 - L4
LAYER TIMBUNAN

Layer 10
Layer 11
Layer 12
Layer 13
Layer 14
Layer 15
Layer 16
Layer 17
Layer 18
Layer 19
Layer 20
Layer 21
Layer 22
Layer 23
Layer 24
Layer 25
STRUKTUR PERKERASAN
Sub-Grade Preparation
Sub Base / Aggt. A / tebal = 25 cm
Lean Concrete/tebal = 10 cm
Rigid Pavement / tebal = 27 cm

Belum Bebas

Sudah Clearing

Timbunan
MONITORING TIMBUNAN
PEMBANGUNAN JALAN TOL
PASURUAN - PROBOLINGGO
ZONA 3
SISI K A N A N
STRUKTUR PERKERASAN
Rigid Pavement / tebal = 27 cm
Lean Concrete/tebal = 10 cm
Sub Base / Aggt. A / tebal = 25 cm
Sub-Grade Preparation
Layer 25
Layer 24
Layer 23
Layer 22
Layer 21
Layer 20
Layer 19

BOX UNDERPASS STA 27+007


BOX UNDERPASS STA 27+407

BOX CULVERT STA 27+175


Layer 18
Layer 17
LAYER TIMBUNAN

Layer 16
Layer 15
PEKERJAAN TANAH

Layer 14
Layer 13
Layer 12
Layer 11
Layer 10
Layer 9
Layer 8 R1 - R4 R1 - R4
Layer 7 R1 - R4 R1 - R4
Layer 6 R1 - R4 R1 - R4 R1 -R4 R1 - R4
Layer 5 R1 - R4 R1 - R4 R1 -R4 R1 - R4
Layer 4 R1 - R4 R1 - R4 R1 -R4 R1 - R4
Layer 3 R1 - R4 R1 - R4 R1 -R4 R1 - R4
Layer 2 FDT 00/00/00 R1 FDT 00/00/00 R1 R1 -R4 R1 - R4 R1 - R2
Layer 1 = 20 - 40 cm FDT 00/00/00 R1 FDT 00/00/00 R1 R1 - R4 R1 - R3 R1 -R4 R1 - R4 R1 - R2
Tinggi Timbunan ( Rencana )
Site Clearing
Sub-Contraktor PT. LAJU MANDIRI PT. GADING S
Galian ( Perbaikan Tanah Dasar )
SISI K A N A N
27+625

27+600

27+575

27+550

27+525

27+500

27+475

27+450

27+425

27+400

27+375

27+350

27+325

27+300

27+275

27+250

27+225

27+200

27+175

27+150

27+125

27+100

27+075

27+050

27+025

27+000

26+975

26+950

26+925

26+900

26+875

26+850

26+825

26+800

26+775

26+750

26+725

26+700

26+675

26+650

26+625

26+600

26+575

26+550

26+525

26+500

26+475

26+450

26+425

26+400

26+375

26+350

26+325

26+300

26+275

26+250

26+225

26+200

26+175

26+150

26+125

26+100

26+075

26+050

26+025

26+000

25+975

25+950

25+925

25+900

25+875

25+850

25+825

25+800
S T A. 19+800 s/d 31+300

SISI K I R I
Galian ( Perbaikan Tanah Dasar )
Sub-Contraktor PT. LAJU MANDIRI PT. GADING S
Site Clearing
Tinggi Timbunan ( Rencana )
Layer 1 = 20 - 40 cm FDT 00/00/00 L1, L2 FDT 00/00/00 L1, L2 L1 - L3 L1 - L3 L1 , L2 L1 - L3 L1 - L4
Layer 2 FDT 00/00/00 L1, L2 FDT 00/00/00 L1, L2 L1 , L2 L1 - L3 L1 - L4
Layer 3 L1 - L4 L1 - L4 L1 , L2 L1 - L3
Layer 4 L1 - L4 L1 - L4 L1 - L3
Layer 5 L1 - L4 L1 - L4 L1 - L3
Layer 6 L1 - L4 L1 - L4 L1 - L3
Layer 7 L1 - L4 L1 - L4

BOX UNDERPASS STA 27+007


BOX UNDERPASS STA 27+407
PEKERJAAN TANAH

L1 - L4 L1 - L4
BOX CULVERT STA 27+175

Layer 8
Layer 9
LAYER TIMBUNAN

Layer 10
Layer 11
Layer 12
Layer 13
Layer 14
Layer 15
Layer 16
Layer 17
Layer 18
Layer 19
Layer 20
Layer 21
Layer 22
Layer 23
Layer 24
Layer 25
STRUKTUR PERKERASAN
Sub-Grade Preparation
Sub Base / Aggt. A / tebal = 25 cm
Lean Concrete/tebal = 10 cm
Rigid Pavement / tebal = 27 cm

Belum Bebas

Sudah Clearing

Timbunan
MONITORING TIMBUNAN
PEMBANGUNAN JALAN TOL
PASURUAN - PROBOLINGGO
ZONA 3
SISI K A N A N
STRUKTUR PERKERASAN
Rigid Pavement / tebal = 27 cm
Lean Concrete/tebal = 10 cm
Sub Base / Aggt. A / tebal = 25 cm
Sub-Grade Preparation
Layer 25
Layer 24
Layer 23
Layer 22
Layer 21
Layer 20
Layer 19
Layer 18
Layer 17
LAYER TIMBUNAN

Layer 16
Layer 15
PEKERJAAN TANAH

Layer 14
Layer 13
Layer 12
Layer 11
Layer 10
Layer 9
Layer 8
Layer 7
Layer 6
Layer 5
Layer 4
Layer 3 R1 - R2
Layer 2 R1 - R4
Layer 1 = 20 - 40 cm R1 - R4 R1 - R4
Tinggi Timbunan ( Rencana )
Site Clearing
Sub-Contraktor
Galian ( Perbaikan Tanah Dasar )
SISI K A N A N
25+775

25+750

25+725

25+700

25+675

25+650

25+625

25+600

25+575

25+550

25+525

25+500

25+475

25+450

25+425

25+400

25+375

25+350

25+325

25+300

25+275

25+250

25+225

25+200

25+175

25+150

25+125

25+100

25+075

25+050

25+025

25+000

24+975

24+950

24+925

24+900

24+875

24+850

24+825

24+800

24+775

24+750

24+725

24+700

24+675

24+650

24+625

24+600

24+575

24+550

24+525

24+500

24+475

24+450

24+425

24+400

24+375

24+350

24+325

24+300

24+275

24+250

24+225

24+200

24+175

24+150

24+125

24+100

24+075

24+050

24+025

24+000

23+975

23+950
S T A. 19+800 s/d 31+300

SISI K I R I
Galian ( Perbaikan Tanah Dasar )
Sub-Contraktor
Site Clearing
Tinggi Timbunan ( Rencana )
Layer 1 = 20 - 40 cm L1 - L4 L1 - L4
Layer 2 L1 - L4
Layer 3
Layer 4
Layer 5
Layer 6
Layer 7
PEKERJAAN TANAH

Layer 8
Layer 9
LAYER TIMBUNAN

Layer 10
Layer 11
Layer 12
Layer 13
Layer 14
Layer 15
Layer 16
Layer 17
Layer 18
Layer 19
Layer 20
Layer 21
Layer 22
Layer 23
Layer 24
Layer 25
STRUKTUR PERKERASAN
Sub-Grade Preparation
Sub Base / Aggt. A / tebal = 25 cm
Lean Concrete/tebal = 10 cm
Rigid Pavement / tebal = 27 cm

Belum Bebas

Sudah Clearing

Timbunan
MONITORING TIMBUNAN
PEMBANGUNAN JALAN TOL
PASURUAN - PROBOLINGGO
ZONA 3
SISI K A N A N
STRUKTUR PERKERASAN
Rigid Pavement / tebal = 27 cm
Lean Concrete/tebal = 10 cm
Sub Base / Aggt. A / tebal = 25 cm
Sub-Grade Preparation
Layer 25
Layer 24
Layer 23
Layer 22
Layer 21
Layer 20
Layer 19
Layer 18
Layer 17
LAYER TIMBUNAN

Layer 16
Layer 15
PEKERJAAN TANAH

Layer 14
Layer 13
Layer 12
Layer 11
Layer 10
Layer 9
Layer 8
Layer 7
Layer 6
Layer 5
Layer 4 R1 - R4
Layer 3 R1 - R4
Layer 2 R1 - R4
Layer 1 = 20 - 40 cm R1 - R4
Tinggi Timbunan ( Rencana )
Site Clearing
Sub-Contraktor PT. Gading S
Galian ( Perbaikan Tanah Dasar )
SISI K A N A N
23+925

23+900

23+875

23+850

23+825

23+800

23+775

23+750

23+725

23+700

23+675

23+650

23+625

23+600

23+575

23+550

23+525

23+500

23+475

23+450

23+425

23+400

23+375

23+350

23+325

23+300

23+275

23+250

23+225

23+200

23+175

23+150

23+125

23+100

23+075

23+050

23+025

23+000

22+975

22+950

22+925

22+900

22+875

22+850

22+825

22+800

22+775

22+750

22+725

22+700

22+675

22+650

22+625

22+600

22+575

22+550

22+525

22+500

22+475

22+450

22+425

22+400

22+375

22+350

22+325

22+300

22+275

22+250

22+225

22+200

22+175

22+150

22+125

22+100
S T A. 19+800 s/d 31+300

SISI K I R I
Galian ( Perbaikan Tanah Dasar )
Sub-Contraktor PT. Gading S
Site Clearing
Tinggi Timbunan ( Rencana )
Layer 1 = 20 - 40 cm L1 - L4 L1 - L4
Layer 2 L1 - L4 L1 - L2
Layer 3
Layer 4
Layer 5
Layer 6
Layer 7
PEKERJAAN TANAH

Layer 8
Layer 9
LAYER TIMBUNAN

Layer 10
Layer 11
Layer 12
Layer 13
Layer 14
Layer 15
Layer 16
Layer 17
Layer 18
Layer 19
Layer 20
Layer 21
Layer 22
Layer 23
Layer 24
Layer 25
STRUKTUR PERKERASAN
Sub-Grade Preparation
Sub Base / Aggt. A / tebal = 25 cm
Lean Concrete/tebal = 10 cm
Rigid Pavement / tebal = 27 cm

Belum Bebas

Sudah Clearing

Timbunan
MONITORING TIMBUNAN
PEMBANGUNAN JALAN TOL
PASURUAN - PROBOLINGGO
ZONA 3
SISI K A N A N
STRUKTUR PERKERASAN
Rigid Pavement / tebal = 27 cm
Lean Concrete/tebal = 10 cm
Sub Base / Aggt. A / tebal = 25 cm
Sub-Grade Preparation
Layer 25
Layer 24
Layer 23
Layer 22
Layer 21
Layer 20
Layer 19
Layer 18
Layer 17
LAYER TIMBUNAN

Layer 16
Layer 15
PEKERJAAN TANAH

Layer 14
Layer 13
Layer 12
Layer 11
Layer 10
Layer 9
Layer 8
Layer 7
Layer 6
Layer 5
Layer 4
Layer 3 R1 - R4
Layer 2 R1 - R4
Layer 1 = 20 - 40 cm R1 - R4 R1 - R2
Tinggi Timbunan ( Rencana )
Site Clearing
Sub-Contraktor PT. Gading S
Galian ( Perbaikan Tanah Dasar )
SISI K A N A N
22+075

22+050

22+025

22+000

21+975

21+950

21+925

21+900

21+875

21+850

21+825

21+800

21+775

21+750

21+725

21+700

21+675

21+650

21+625

21+600

21+575

21+550

21+525

21+500

21+475

21+450

21+425

21+400

21+375

21+350

21+325

21+300

21+275

21+250

21+225

21+200

21+175

21+150

21+125

21+100

21+075

21+050

21+025

21+000

20+975

20+950

20+925

20+900

20+875

20+850

20+825

20+800

20+775

20+750

20+725

20+700

20+675

20+650

20+625

20+600

20+575

20+550

20+525

20+500

20+475

20+450

20+425

20+400

20+375

20+350

20+325

20+300

20+275

20+250
S T A. 19+800 s/d 31+300

SISI K I R I
Galian ( Perbaikan Tanah Dasar )
Sub-Contraktor PT. Gading S
Site Clearing
Tinggi Timbunan ( Rencana )
Layer 1 = 20 - 40 cm L1 - L4 L1 - L4
Layer 2 L1 - L4 L1 - L4
Layer 3 L1 - L4
Layer 4 L1 - L2
Layer 5 L1 - L2
Layer 6
Layer 7
PEKERJAAN TANAH

Layer 8
Layer 9
LAYER TIMBUNAN

Layer 10
Layer 11
Layer 12
Layer 13
Layer 14
Layer 15
Layer 16
Layer 17
Layer 18
Layer 19
Layer 20
Layer 21
Layer 22
Layer 23
Layer 24
Layer 25
STRUKTUR PERKERASAN
Sub-Grade Preparation
Sub Base / Aggt. A / tebal = 25 cm
Lean Concrete/tebal = 10 cm
Rigid Pavement / tebal = 27 cm

Belum Bebas

Sudah Clearing

Timbunan
MONITORING TIMBUNAN
PEMBANGUNAN JALAN TOL
PASURUAN - PROBOLINGGO
ZONA 3
SISI K A N A N
STRUKTUR PERKERASAN
Rigid Pavement / tebal = 27 cm
Lean Concrete/tebal = 10 cm
Sub Base / Aggt. A / tebal = 25 cm
Sub-Grade Preparation
Layer 25
Layer 24
Layer 23
Layer 22
Layer 21
Layer 20
Layer 19
Layer 18
Layer 17

LAYER TIMBUNAN
Layer 16
Layer 15

PEKERJAAN TANAH
Layer 14
Layer 13
Layer 12
Layer 11
Layer 10
Layer 9
Layer 8
Layer 7
Layer 6
Layer 5
Layer 4
Layer 3
Layer 2
Layer 1 = 20 - 40 cm
Tinggi Timbunan ( Rencana )
Site Clearing
Sub-Contraktor
Galian ( Perbaikan Tanah Dasar )
SISI K A N A N

20+225

20+200

20+175

20+150

20+125

20+100

20+075

20+050

20+025

20+000

19+975

19+950

19+925

19+900

19+875

19+850

19+825

19+800
S T A. 19+800 s/d 31+300

SISI K I R I
Galian ( Perbaikan Tanah Dasar )
Sub-Contraktor
Site Clearing
Tinggi Timbunan ( Rencana )
Layer 1 = 20 - 40 cm
Layer 2
Layer 3
Layer 4
Layer 5
Layer 6
PEKERJAAN TANAH Layer 7
Layer 8
LAYER TIMBUNAN Layer 9
Layer 10
Layer 11
Layer 12
Layer 13
Layer 14
Layer 15
Layer 16
Layer 17
Layer 18
Layer 19
Layer 20
Layer 21
Layer 22
Layer 23
Layer 24
Layer 25
STRUKTUR PERKERASAN
Sub-Grade Preparation
Sub Base / Aggt. A / tebal = 25 cm
Lean Concrete/tebal = 10 cm
Rigid Pavement / tebal = 27 cm

Belum Bebas

Sudah Clearing

Timbunan

You might also like