Manhours for CS piping erection including fitup:

Take: Size of CS pipe spool: 6", spools: 2 Nos., each of 4 Mtr


Qty of erection: 48 IM, at elevation of 10 Mtr

Time
Sr. No. Activity Craft Qty MHrs Remarks
(Hrs.)
1 Scaffolding Scaffolders 6 8 48
Rigging of spool and Foreman: 0.5
2 4 3 12
placement in place Rigger: 4

Gascutter: 0.5
3 Bevelling of pipe 1 1 1
Grinder: 0.5

Fitter : 1
4 Alignment & Tack welding Helper: 1 3 2 6
Tack welder: 1

5 Contingency @ 20%* 13.4


Total 80.4 For 48 IM
A MHrs. Per IM: 1.7

Contingency for interruptioin in front/ modification / material handling delays


*
etc.