UTILISATION OF FUND UNDER LWE P.S AS STOOD ON 31.01.

2017
West Bengal Police Housing & Infrastructure Development Corporation Ltd.

Total Fund Accepted Value of Booked Total Expenditure


Sl. No. Name of the Project G.O No & Date Amount of A & A Refund Expenditure in %
Received Tender Expenditure with Refund

1 Construction of two storied Police Station at Kotshila in the district of Purulia. 20000000 18164200 19202259 19675540 98.3777

1.A Retaining wall for Kotshila P.S 442200 473281

18015/66/2010-NM/ANO-II(V)
DATE : 07.10.2011
2 Construction of two storied Police Station at Raipur in the district of Bankura. 20000000 67500000 18158908 19228266 19228266 96.14133
1ST INSTALL
1932-Sanction
Date : 19.12.2011
Construction of two storied Police Station at Lalgarh in the district of Paschim
3 2ND INSTALL 20000000 17636806 19049135 19049135 95.245675
Medinipur
87-Sanction/BMC/5B-130/10
Date : 22.05.2013

Construction of two storied Police Station at Sankrail in the district of Jhargram 3RD INSTALL
4 724-Sanction/HP/BMC/5B-130/10 20000000 45000000 18123630 19642136 19642136 98.21068
Police District.
Date : 26.11.2013

Construction of three storied Police Station at Kotwali (Patnabazar TOP) in the


5 20000000 129375000 1763857 17877370 18901943 94.509715
district of Paschim Medinipur.

944816 191648

5.A Boundary wall & Electrical works at Kotwali P.S 832925

6 Construction of three storied Police Station at Barabazar in the district of Purulia. 20000000 73125000 18132450 19625632 19999362 99.99681
4TH INSTALL
1167-Sanction/HP/BMC/5B-130/10
Date : 04.03.2014
UTILISATION OF FUND UNDER LWE P.S AS STOOD ON 31.01.2017
West Bengal Police Housing & Infrastructure Development Corporation Ltd.

Total Fund Accepted Value of Booked Total Expenditure


Sl. No. Name of the Project G.O No & Date Amount of A & A Refund Expenditure in %
Received Tender Expenditure with Refund
4TH INSTALL
1167-Sanction/HP/BMC/5B-130/10
Date : 04.03.2014
6.A Plastering and painting works for existing Barabazar Police Station, dist Purulia. 344985 373730

Construction of three storied Police Station at Binpur in the district of Jhargram


7 20000000 18189383 19722498 19722498 98.61249
Police District.

8 Construction of two storied Police Station at Arsha in the district of Purulia. 20000000 18180536 19879221 19879221 99.396105

8.A Construction of Garage & Generator Room for Arsha P.S in the district of Purulia. 0

9 Construction of three storied Police Station at Sarenga in the district of Bankura. 20000000 18150088 19502107 19502107 97.510535

Construction of three storied Police Station at Jhargram in the district of Jhargram


10 20000000 18128922 19131533 19131533 95.657665
Police District

11 Construction of two storied Police Station at Jhalda in the district of Purulia. 20000000 18223001 19714851 19714851 98.574255

12 Construction of two storied Police Station at Bundwan in the district of Purulia. 20000000 18123630 19648040 19648040 98.2402

Construction of two storied Police Station at Keshiary in the district of Paschim


13 20000000 18221232 19762379 19762379 98.811895
Medinipur.
UTILISATION OF FUND UNDER LWE P.S AS STOOD ON 31.01.2017
West Bengal Police Housing & Infrastructure Development Corporation Ltd.

Total Fund Accepted Value of Booked Total Expenditure


Sl. No. Name of the Project G.O No & Date Amount of A & A Refund Expenditure in %
Received Tender Expenditure with Refund

14 Construction of two storied Police Station at Simlapal in the district of Bankura. 20000000 19028986 19028986 95.14493
UTILISATION OF FUND UNDER LWE P.S AS STOOD ON 31.01.2017
West Bengal Police Housing & Infrastructure Development Corporation Ltd.

Total Fund Accepted Value of Booked Total Expenditure


Sl. No. Name of the Project G.O No & Date Amount of A & A Refund Expenditure in %
Received Tender Expenditure with Refund

15 Construction of three storied Police Station at Ranibandh in the district of Bankura. 20000000 18158908 19696721 19696721 98.483605

Construction of three storied Police Station at Gopiballavpur in the district of


16 370/BMC/e-bantan/SP/2015-16/SRE-II/15 20000000 17886600 16361613 16361613 81.808065
Jhargram Police District.
Dt. 30.10.2015

&

Construction of two storied Police Station at Goaltore in the district of Paschim 369/BMC/e-bantan/SP/2015-16/SRE-II/15
17 20000000 18224770 19883336 19883336 99.41668
Medinipur. Dt. 30.10.2015

18 Construction of two storied Police Station at Boro in the district of Purulia. 20000000 45000000 18223001 19771957 19771957 98.859785

Grand Total 360000000 360000000 348599624 0 348599624 96.8332288889


Balance of Fund Memo No of Submitted U.C Amount

ENGG/SCHM(LWE)/2958/2011/289
324460
DT. 24.09.15

ENGG/PR & UC/2904/2016/615


DT. 18.05.16

ENGG/SCHM(LWE)/2958/2011/528
771734 351646517
Dt. 10.03.2017

950865

357864

1098057

638
Balance of Fund Memo No of Submitted U.C Amount

277502

120779

497893

868467

285149

351960

237621
Balance of Fund Memo No of Submitted U.C Amount

971014
Balance of Fund Memo No of Submitted U.C Amount

303279

3638387

116664

228043

11400376