Professional Documents
Culture Documents
Final Feasibility Report - 2 PDF
Final Feasibility Report - 2 PDF
Final Feasibility Report - 2 PDF
Vijayawada-Gundugolanu Section
DTI 61 847 B03 i 0
FINAL FEASIBILITY REPORT
TABLE OF CONTENTS
0.2 RECENT HISTORY OF THE ROAD AND RELEVANT DOCUMENTS ................................. 0-5
0.2.1 Relevant documents ..................................................................................................................... 0-5
0.2.2 Existing Situation on NH-5 ........................................................................................................... 0-6
0.2.3 Recent history ................................................................................................................................ 0-6
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 B03 ii 0
FINAL FEASIBILITY REPORT
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 B03 iii 0
FINAL FEASIBILITY REPORT
LIST OF TABLES
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 B03 0-1 0
FINAL FEASIBILITY REPORT
0 EXECUTIVE SUMMARY
0.1 INTRODUCTION
0.1.1 Background
The Government of India has decided to upgrade 6500 km length of existing 4-lane
divided highways into Six-Lane divided carriageway under Phase-V of National Highway
Development project (NHDP). The Phase-V of NHDP is to be executed as BOT (Toll)
Project through Public Private Partnership (PPP) on Design-Build-Finance-Operate
(DBFO) pattern. The National Highways Authority of India (NHAI) has appointed BCEOM
Societe Francaise dIngenierie, France in Association with BCEOM India Pvt. Limited,
presently known as Egis India Consulting Engineers Pvt Ltd., as consultants to carry out
Feasibility study for upgrading the existing four lane highway to Six-Lane access control
highway from Chilakaluripet-Eluru-Rajahmundry section of NH-5 under DBFO pattern, for
which the consultants have completed the study and submitted the final feasibility report.
The new Six-Lane facility would be an access controlled highway through provision of
service roads, pedestrian and cattle underpass, vehicular underpasses, grade separators,
exit/entry ramps etc. The objective is to enhance operational efficiency of highway and
safety of the traffic & the road users.
The stretch from Vijayawada to Chilakalurpet has been prioritised by NHAI for which
tenders have been called and the work has been awarded on DBFOT pattern. The
feasibility report has been reframed for the balance stretch from Vijayawada to
Rajahmundry.
The present report has been prepared combining the earlier feasibility report and the
feasibility studies carried on the bypasses as draft combined Feasibility Report for
103.590Kms length of a section of NH-5 from Vijayawada Bypass (Km 0+000 to Km
47+880), Vijayawada (Km 1076+480) to Hanuman Junction (Km 1060+800), Hanuman
Junction Bypass (Km 0+000 to Km 6+720) and Hanuman Junction (Km 1055+650) to
Gundugolanu (Km 1022+480) in the state of Andhra Pradesh. The project highway
location map showing the existing road network from Vijayawada to Gundugolanu is
presented in following page.
The intention of this specific consultancy project is to study and report on the feasibility of
retrofitting the existing NH-5 from Vijayawada-Eluru-Gundugolanu from its existing
situation [a bypasses and 4-lane highway of about 103.580 Km in length] to a 4-lane and
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 B03 0-2 0
FINAL FEASIBILITY REPORT
6-lane highway. The objectives of the consultancy services are to prepare a proposal to
retrofit a six-lane cross-section on to the existing 4-lane highway in a manner which
ensures:
Enhanced safety of the traffic, the road users and the people living close to the
highway.
Minimal adverse impact on the road users and the local population due to
construction. Feasible and constructible options for the project with least cost options.
The Inception Report was the first significant report to be submitted under this Study as
per Terms of Requirements (TOR), and was submitted in the month of December 2006
(Vijayawada-Gundugolanu section), July 2010 (Vijayawada Bypass) and August 2010
(Hanuman Junction Bypass). The report focused on:
The Draft Feasibility Report is essentially presents the facility planning with options and
alternatives for 6 laning of existing 4 lane project highway, which was submitted in the
month of February 2006 (Vijayawada-Gundugolanu section) and December 2010
(Vijayawada Bypass).
The Final Feasibility Report presents the facility planning with options and alternatives for
6 laning of existing 4-lane Project Highway after exhaustive discussions with the NHAI
and the revised guidelines issued by NHAI.
Recently NHAI has issued the advertisement for finalizing the consultants to work on the
proposed bypass for the Vijayawada and Hanuman Junction city under NHDP, Phase-V.
Keeping in view of the proposed bypass, no elevated structures like flyovers were
proposed within the city limits of Vijayawada and Hanuman Junction city. Provision of
such structures will make the project unviable once the proposed bypass comes into
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 B03 0-3 0
FINAL FEASIBILITY REPORT
existence. Also keeping in view the present and future projected traffic, four and six laning
is proposed with minimum length of service roads.
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Vijayawada-Gundugolanu Section Reports code PAGE REV.
0-4 0
FINAL FEASIBILITY REPORT DTI 61 847 B03
Project Location Map, Vijayawada Bypass (47.88 Km), Vijayawada-Gundugolanu section (48.99Km) and Hanuman Junction Bypass (Km 6.72)
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 0-5 0
FINAL FEASIBILITY REPORT B03
The Consultant has collected as-built drawings (both in electronic form and hard copy),
DPR & other secondary relevant documents (in hardcopy) from NHAI.
The chainages on the old NH-5 followed a different chainage system. Old NH-5 had
different sections, i.e., Chennai-Vijayawada, Vijayawada-Visakhapatnam etc. Each
section had different set of chainages. The NHAI has issued a circular stating that new
chainage for NH-5 will start from the Baharagora (near Kolkata) to Chennai under Golden
Quadrilateral project.
Under this circular, the chainage from Kolkata to Chennai was changed, and the new
system of chainage has been adopted. The correlation with the new chainages and old
chainages were developed and these chainage equations were incorporated in the as-
built Drawings. Chainage equations were developed due to the construction of new
bypasses along the project highway. For easy reference the chainage equations and the
correlation between the old and as-built chainages along the project highway is given in
Table 0.1 below.
The old 2-Lane NH-5 has been upgraded to 4-Lane divided carriageway in the year of
1997-2003 under Golden quadrilateral project. The length of the project works out to be
103.590 Km as per the as-built and the DPR chainages.
An inventory was carried out by hand held GPS to understand the chainage variation in
each kilometre. The chainage is increasing from Vijayawada to Gundugolanu as per the
as-built chainage of NH-5 (from Kolkata to Chennai). The project starts at Km 0+000 to
Km 47+88 (Vijayawada Bypass), Km 1076+480 to Km 1060+800 (Gannavaram to
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 0-6 0
FINAL FEASIBILITY REPORT B03
The project highway has been divided into following three traffic homogeneous sections:
Vijayawada Bypass comprising of section 1 & 2,
Vijayawada bypass to Gundugolanu,
The salient findings of the traffic volume count surveys are as below:
Average Daily Traffic (ADT) in base year 2010 minimum is 21714 (Tollable PCUs)
and 25005 total PCUs in Vijayawada Bypass to Gundugolanu section.
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 0-7 0
FINAL FEASIBILITY REPORT B03
The traffic growth rates adopted for the project highway are finalized based on the past
trend analysis and analysis of the economic indicators of the project influence area and
presented below:
Table 0.2: Traffic Growth Rates
MAV MAV
Two Mini 2 Axle 3 Axle HCM/
Period Car Bus LCV up to >6
Wheeler Bus Truck Truck EME
6 Axle Axles
2011-15 8.7 7.0 5.5 5.5 6.6 6.6 6.6 6.6 6.6 6.6
2016-20 7.1 6.5 5.5 5.5 6.6 6.6 6.6 6.6 6.6 6.6
2021-25 5.3 6.0 5.0 5.0 6.1 6.1 6.1 6.1 6.1 6.1
>2025 5.3 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0
For capacity and level of service analysis, the AADT observed on the Project Road has
been projected with 5% growth rate and presented below:
Table 0.3: Projected Traffic for the Western Alignment Section 1
Car/ MAV MAV
Mini 2 Axle 3 Axle HCM/ Total
Year Jeep/ Bus LCV up to 6 >6
Bus Truck Truck EME PCUs
Van Axle Axles
2010 353 - - 328 1,103 1,287 147 - - 8,677
2015 453 - - 418 1,408 1,643 188 - - 11,079
2020 579 - - 533 1,798 2,097 239 - - 14,139
2025 739 - - 680 2,294 2,676 306 - - 18,046
2030 944 - - 868 2,927 3,417 391 - - 23,038
2035 1,205 - - 1,108 3,735 4,361 501 - - 29,410
2040 1,537 - - 1,413 4,767 5,565 639 - - 37,528
2045 1,962 - - 1,804 6,084 7,102 816 - - 47,898
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 B03 0-8 0
FINAL FEASIBILITY REPORT
Table 0.5: Traffic Projections for the portion from Vijayawada Bypass to Gundugolanu
MAV Agri
Car/ 2 MAV Animal Tollable
Mini 3 Axle up to HCM/ Two Auto Agri Tractor Cycle Total
Year Jeep/ Bus LCV Axle >6 Tempo Hand Cycle Others Traffic
Bus Truck 6 EME Wheeler Rickshaw Tractor & Rickshaw PCUs
Van Truck Axles drawn PUCs
Axle Trailor
2010 3,016 56 1,167 568 1,667 2,521 377 - - 2,873 663 610 17 64 7 339 24 2 21,714 25,005
2015 3,849 71 1,489 725 2,128 3,217 482 - - 3,667 846 779 22 82 7 434 29 2 27,714 31,901
2020 4,912 91 1,899 925 2,715 4,106 615 - - 4,680 1,079 994 27 105 7 554 38 2 35,364 40,694
2025 6,270 117 2,424 1,181 3,466 5,241 785 - - 5,973 1,379 1,269 34 134 7 708 48 2 45,143 51,932
2030 8,003 149 3,093 1,507 4,424 6,689 1,001 - - 7,624 1,760 1,619 44 171 7 903 62 2 57,610 66,263
2035 10,213 190 3,948 1,923 5,646 8,537 1,278 - - 9,729 2,246 2,066 56 218 7 1,152 79 2 73,527 84,553
2040 13,035 244 5,039 2,454 7,205 10,896 1,631 - - 12,416 2,867 2,637 71 278 7 1,472 101 2 93,842 107,900
2045 16,637 311 6,432 3,132 9,195 13,907 2,082 - - 15,847 3,659 3,365 91 355 7 1,878 129 2 119,773 137,702
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 B03 0-9 0
FINAL FEASIBILITY REPORT
IRC: 64 - 1990 stipulates a design service volume of 40,000 PCU per day for a four lane
divided carriageway with paved shoulders at level of service B and plain terrain. This can
be further increased upto 60,000 PCUs by adopting LOS C.
The Vijayawada bypass crosses 40,000 PCUs in the year 2042 and 2040 for the sections
1 & 2 respectively. Hence it may be prudent to consider them for four laning only.
The section between Vijayawada bypass to Gundugolanu reaches 40,000 PCUs in the
year 2020 and 60,000 PCUs in the year 2028. Hence it is necessary to consider it for 6
laning now itself.
There are three toll plazas along the project corridor. The details of the existing toll plazas
and their tolling sections are given in Table below.
Table 0.6: Existing Toll Plazas
Considering the development of the Vijayawada bypass, it is proposed to have total three
toll plaza two on the Vijayawada Bypass, one on section 1, one on section 2 and retaining
the existing toll plaza at Kalaparru.
Km 11+500
Kaza to Gollapudi (15.25 km of NH-5 is
1 Of proposed Vijayawad
Km 0 to Km 18+650 adjusted in the toll rate )
Bypass
Km 35+000
Gollapudi Chinnaavutapalli (24.2 km of NH-5 is
2 Of proposed Vijayawada
Km 18+650 to Km 47+880 adjusted in the toll rate)
Bypass
Kanakadurga Varadhi
Km 1050+780
Gundugolanu Includes Hanuman
3 Of Existing Vijayawada
Km 1076+480 to Km Junction (6.7 km) Bypass
Gundugolanu section
1022+480
As per the toll policy all the structures and bypasses costing more than Rs 10 crores need
to be charged separately at the toll rates specified in the policy. Since cost of the two
sections of Vijayawada bypass and the Hanuman Junction bypass are more than Rs 10
Crores each of them will be charged separately.
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 B03 0-10 0
FINAL FEASIBILITY REPORT
Table 0.8: Year wise and section wise Toll revenue for all the four options
The main issues identified are; Wrong Side Driving, Over Loading, Uncontrolled
accesses, Pedestrian Interference, Head Light Glare. The road is much less safe
currently than it should be for the following reasons:
There is no access control [except where some frontage roads are provided,
generally in towns] the road has far too many access points
The road mixes short distance [very local including animals herded on the road in
more rural areas] and long distance traffic so there are many movements [entering
the road, U turning in the medians, driving the wrong way down the road, grazing in
the median] which are incompatible with the high speed long distance facility this road
is supposed to provide.
The main junctions [mostly at grade] have poor advance signing, and should be
grade separated.
Little thought has been given in villages and towns crossed as to how the local
population crosses the main National Highway [other than by praying first then
running very quickly].
There is no existing highway traffic management system.
Guardrail [and barriers at approach to some bridges] is lacking in places, and hanging
loose in others.
In order for the proposed project and facilities to bring an improvement the following
principles should be followed:
A proper access control system should be put in place. This includes an access
system (service roads providing access to the abutting properties and possibly to the
local traffic, safe and comfortable grade separated crossings for motorised as well as
non motorised users, ramps and interchanges) and as a general principle features
preventing access (fences, curbs and barriers).
A treatment of the median in order to prevent front collision and wrong side driving as
well as limit head light glare
A proper signage in order to deliver adequate information to the user. This should
encompass the direction signs, as well as their coordination with markings. Markings
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 B03 0-11 0
FINAL FEASIBILITY REPORT
should be treated with sufficient care and maintained with a high level of performance
as they contribute significantly to improved traffic safety.
An adequate geometry on ramps with adequate design speeds. Essential features
like acceleration / deceleration / shelter / storage lanes, pedestrian / cattle / vehicular
underpasses and their approaches, bus bays / bus stops and truck lay bays; Proper
turning radii at the entry / exit of vehicular underpasses; Service road (minimum 5.5m
width) considered essential for circulation, merging and diverging of local traffic.
Removable median barriers at every 2Km will be provided along the Project highway
as specified in the Manual for allowing traffic on to the other side of the highway in
case of lane closures.
The general objectives are for the concessionaire to make the main NH-5 road [and the
service roads] as safe as possible for all users. The concessionaire shall follow [and shall
also show it has followed] all relevant Indian publications on road safety, especially The
Manual for Safety in Road Design (A guide for Highway Engineers) prepared in
September 1998 for MOST.
A formalised safety audit procedure must be followed by the concessionaire during the
detailed design [and during the Construction and post construction periods].
Fibre Optic Cable is present all along the project road on either side. In the 4-laning civil
works a number of ducts were provided to shift these cables. Besides these ducts the
Fibre Optic Cable also present buried in the ground in the road way width.
0.6.3 Impact
An important part of the later detailed design will be to fully determine impacts and
design, in conjunction with utility companies, the diversions or strengthening or crossing
(via pipe crossings to be provided under the roadwork contract) locations and works. It is
also very important to note that in urban road projects service relocations are an
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 B03 0-12 0
FINAL FEASIBILITY REPORT
important part of the preplanning, both on the actual work [definition and phasing] and
especially on the material procurement side, as in simplistic terms one cannot relocate
power lines, telephone lines and waterlines without at least a reasonable amount of
cable, pipes and fittings already in stock and immediately available.
It should be noted that there may be additional land requirements identified in the final
design as the available ROW is insufficient to accommodate the moving of utility services
and the tree planting proposals.
The terrain along the Project Highway is fairly level with gently rolling terrain up to north
end of the project highway as the project highway passes through Eastern Ghats.
Number of streams, nallas and rivers originate and flow in the easterly direction ultimately
discharging into the Bay of Bengal. There are total eight major bridges along the Project
Highway. Streams are mostly rain fed and are perennial in nature. Some of the rivers and
streams have been harnessed by constructing dams and barrages which in-turn supply
water through a network of canals. There are number of outlets for major and minor
irrigation tanks. Apart from these, Irrigation canals are being constructed as part of
Polavaram and Pushkara canal projects. The details of eleven major bridges are given in
the following table.
Table 0.9: List of Existing and Proposed (Bypass) Major Bridges
Width
S. Length Deck Type of
Chainage Location Span of
No (m) Width(m) Superstructure
CW(m)
LHS 24.53+
(New) 36.38+
PSC T-Beam &
1 1040+481 37.15+ 159.59 7.5 9.91
RHS Voided slab
36.85+
(New)
24.68
LHS
(New)
2 1034+907 4 x 32.30 129.2 7.5 9.91 PSC T-Beam
RHS
(New)
Vijayawada Bypass
1 x 14
15+970 (VUP)+
PSC T-Beam &
1 (Krishna New 101 x 30+ 3144 7.5 12
slab
River) 1 x40+
2 x30
PSC T-Beam &
2 43+250 New 2 x 30 60 7.5 12
slab
The discharge from upstream all along the project highway is duly accounted for, in
designing the cross drainage works including culverts during the 4 lane implementation.
The concessionaire shall examine in detail all the problems on existing cross-drainage
culverts and bridges and propose new ones with adequate waterway, vertical clearance
and width suiting to the 6-lane facility.
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 B03 0-13 0
FINAL FEASIBILITY REPORT
Earthen longitudinal drains at isolated locations are present on both sides at the end of
ROW and have adequate section to cater to the requirements for efficient drainage and
suitably connected to proper outfall in the streams. These existing drains have to be
widened and have to be re-built with proper outfalls.
The lined drains provided in the built-up areas have a width varying from 1.2 to 2m and a
depth of 1m covered with concrete blocks. Generally all concrete drains in the project
road are in good condition. Further widening of road will require the shifting of these
concrete drains to the extreme edge of the new carriage way.
The risk of erosion of embankment, side slopes and surface drainage on high
embankments shall be tackled by providing kerb and channel longitudinal drains at the
end of the paved shoulder and chutes at suitable intervals along the embankment.
Embankment slopes are proposed to be pitched as necessary to prevent rain cuts and
erosion.
Design standards developed under this study are meant to supplement the separate
NHAI Manual for 4 and 6 Laning, if any contradiction exist the requirements in the Manual
take precedence. It should be noted that the geometric standards [and design speeds
following] pertain to the mainline. Service roads can [generally should] be designed for
significantly lower design speeds and also to flood more often than the mainline [i.e. in
places they can be at a lower level than the mainline, but not so low that they are very
frequently flooded, since they have to be maintained by the concessionaire].
The terrain in the project stretch is plain in general with the cross slope of the country
remaining very much less than 10%.
Many median openings currently exist, and generally the intent [on safety/access control
grounds] is to close as many as possible. As per the guidelines given in the 6-laning
Manual, removable median openings will be provided at every 2 kilometer interval.
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 B03 0-14 0
FINAL FEASIBILITY REPORT
To determine the condition of the existing pavement, which is a major existing asset, the
following was carried out in December 2006:
Visual road and pavement condition survey - including cracks, rutting, edge-break,
ravelling, patching, apparent pavement failure, drainage structures etc.;
Preparation of road condition strip plans;
Road [bridges and the like] and Roadside Inventory
Previous materials reports have been analysed, and fresh rock / soil samples collected
and tested. The requirement of widening from 4 to 6-lanes between Vijayawada to
Gundugolanu involved collecting information on various construction materials, their
quality and quantities. The location and study of the required materials was made easy by
the data collected during a similar exercise undertaken earlier when the existing 2-lane
road along the above mentioned stretch, was widened to 4-lane.
The analysis of the result showed that it is reasonable to conclude that the prospects of
obtaining suitable and good quantities of various highway materials appeared bright.
However, it does not in any way reduce the significance of collecting reasonable number
of each type of material and subjecting them to proper engineering tests in a recognised
laboratory by the concession company when construction of the new widening project
becomes a reality.
Once the as-built drawings and site conditions were examined it became obvious that the
6-laning [along with service roads] could not generally be fitted into within the available
right-of-way. This is especially stringent in urban areas, as well as in other places.
Therefore, the bypasses were proposed for Vijayawada and Hanuman Junction cities
which are included in the report.
The Right of Way details (roadway width in meters) collected from the NHAI local offices
[in November/December 2006] are presented in the following sections. Discussions with
local NHAI and Revenue officers reveals that the recent land-take for 4-laning of project
road was restricted only to the minimum required for the construction of additional 2-lanes
on the sections other than bypasses. It is also learned that the ROW boundary stones
established in some sections are destroyed locally by the public for various reasons
including farming. Subsequently the details collected were randomly verified on the field
wherever possible and found to be relatively close to the widths provided by these
organisations.
The right of way required for 4 and 6-laning with service roads is in the order of 60m
(Vijayawada Bypass), 54m-70m (Existing NH in rural and urban areas), and 80m
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 B03 0-15 0
FINAL FEASIBILITY REPORT
(Hanuman Junction Bypass) which includes provision of shoulders and wider service road
to cater the mixed local traffic. An additional land is required at junctions, entry/exit
facilities, interchange for the provision of cross structures and for wayside amenities and
drainage channel relocation. Based on typical cross sections. and these assumptions, the
land acquisition requirement for the recommended is assessed and summarised in the
following tables.
Table 0.10: Preliminary Cost Estimates and R&R Budget
Sl No Item Units Quantity Rate (Rs) Amount (Rs )
1 Compensation cost for land
Land cost Acres 1272.747 1200000 1527296400
2 Compensation cost for structures
Pucca
Sq Mts 102543.28 5510 565013473
Structures
Semi-Pucca
Sq Mts 28482.08 2960 84306957
Structures
Kutcha
Sq Mts 8358.91 1400 11702474
Structures
3 Other Assets and Minor structures
Compound
Mts. 2550.15 400 1020060
walls
Agri. Pump-sets No. 20 120000 2400000
4 Other R&R assistance costs
8% of the Total Coast (1+2+3) Lumpsum 175339149
Total (1+2+3+4) 2367078513
0.11 STRUCTURES
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 B03 0-16 0
FINAL FEASIBILITY REPORT
The type of superstructures for minor bridges/underpasses/ROBs are RCC solid slab,
RCC/PSC T-beam, box girder etc. in most bridges resting on RCC and C.C. gravity type
substructure supported on open/well/pile foundations. RCC box type structures have
been observed at a number of locations. There is 1 no. old arch type structure on the
project road.
The condition of most of the structures is generally good. Some common distresses
observed are spalled concrete; exposed and corroded reinforcement in slabs, piers and
abutments; damaged /missing RCC railing and kerb, depositions of debris and growth of
vegetation on pier caps and in vent ways, damaged asphaltic/RCC wearing coat,
damaged expansion joints; undismantled steining of well foundations; missing, choked
drainage spouts, leakage around holes for drainage spouts; approach slab settlement,
settlement of embankment around abutments, damaged metallic crash barriers in
structure approaches etc. In few structures, plasterwork/guniting is observed at soffit of
slab, piers and abutments which hides the actual condition of the structures.
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 B03 0-17 0
FINAL FEASIBILITY REPORT
Bus Shelters
Highway lighting
Pedestrian Guard Railing
Safety Barrier
Traffic Signs and road marking
Hectometre/ Kilometre / Boundary Stone
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 B03 0-18 0
FINAL FEASIBILITY REPORT
Service Roads: Provide 5.5m service roads on both sides about 71.268 kilometers,
the service roads will be discontinued at locations of major bridges, ROBs and Toll
plazas.
Intersections:
Improvement of 5 minor intersections on existing NH.
Entry/Exit facility:
The entry/ exit facility has been proposed for safe merging/exit of through traffic and
the slow/local traffic
Lay Bays and Amenities: Provide 8 bus bays with shelter on service road wherever
applicable, 3 Comprehensive Wayside Amenities including truck lay bays.
Others: Provide Highway Traffic Management System, User Facilities, Roadside
Furniture and safety features, lighting.
INR 1401 Crores i.e. Rs. 13.52 Crores/km for Vijayawada Gundugolanu
section including Vijayawada and Hanuman Junction Bypasses.
0.14 MAINTENANCE
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of NH-5, Reports code PAGE REV.
Vijayawada-Gundugolanu Section
DTI 61 847 B03 0-19 0
FINAL FEASIBILITY REPORT
0.14.2 Principles
Maintenance [if done fully and properly] generally [when averaged out] often represents
about 2.5% [annually, including labour, and all necessary works] of the value of the roads
and bridges. Usually the costs follow a rough cycle, annually lower when no major
pavement or reconstruction works are done on the highway (say years 1 to 4, 6 to 9 etc.
when major overlays are done every 5 years or so), then with major increases every time
a pavement overlay is carried out (say every 5 years or so). However this is not the only
cost cycle, as over time one also has to consider maintenance [and eventual
replacement] of electrical [including lighting], toll collection, and communication
equipment, and then there are other cost cycles, some completely unpredictable like
weather damage, emergencies and the like, and some more predictable like replacement
of road markings. Additionally with a road of this length [103.580km] the cycle is not
necessarily the same on every kilometer section, so figures tend to get more averaged
[and also depend to some extent on the implementation schedule of the 6 laning], rather
than being relatively low 4 years out of 5 then with sharp peaks every 5 years or so. The
concessionaire will need to set up [and thereafter implement to an acceptable standard] a
Maintenance Plan that carries out the corresponding activities.
Special maintenance plans will be necessary for the toll plazas and associated
equipment and the Highway Traffic Management System.
Egis BCEOM International, France in association with Egis India Consulting Engineers Pvt Ltd
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
Chapter 1: Contents
1. INTRODUCTION ...................................................................................................................... 2
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
1. INTRODUCTION
1.1 GENERAL
1.1.1 Background
The National Highways Authority of India (NHAI) has been entrusted with the development,
maintenance and management of such of the National Highways as entrusted to it by the
Government. Under NHDP Phase-V Programme, the Government has decided to convert some of
the existing four lane highways into six lane highways. These projects are to be executed by private
entrepreneurs as DBFO Projects. NHAI invited consultancy services for the Preparation of Feasibility
for the selected sections of National Highways.
The design and construction is to be performed in two steps namely the preparation of feasibility-
cum-preliminary design by a technical consultant followed by the detailed design and construction by
a private concessionaire as DBFO project for each highway in the programme.
This report covers the feasibility-cum preliminary design work by the Consultant for an approximately
103.58 km section of NH5. This work was carried out over the period from November 2006 to [and
including] early March 2007 (Vijayawada-Gundugolanu section), June 2010 (Vijayawada Bypass), &
July 2010 (Hanuman Junction Bypass). The project location map is presented in the following pages
through Figure 1 to Figure 2.
Major settlements/ towns along the project road are: Vijayawada, Gannavaram (houses airport for
Vijayawada), Hanuman Junction and Eluru. One Bypass exists along the corridor, listed bellow
Sl. No Name of Bypass Location Length Remark
1 Eluru Bypass North of town 17 km New Alignment
Total length of bypasses (km) 17 km
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
There are two toll plazas located along the corridor [albeit these are temporary affairs the
permanent plazas are not yet constructed]. The toll plaza locations and the associated road sections
are presented in the table below:
Section length
S. No. Location Toll Section
(km)
1 Pottipadu (Km 1072+580)* 39.1 Vijayawada Hanuman Jn.
Hanuman Jn.
2 Kalaparru (Km 1050+720)* 39.1
Eluru/Gundugolanu
Total length # 78.2 km
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
The National Highways Authority of India (NHAI) has been entrusted with the development,
maintenance and management of such of the National Highways as entrusted to it by the
Government. Under NHDP Phase-V Programme, the Government has decided to convert some of
the existing four lane highways into six lane highways. These projects are to be executed by private
entrepreneurs as DBFO Projects. NHAI invites consultancy services for the Preparation of Feasibility
for the selected sections of National Highways.
The Feasibility Reports thus prepared shall contain, inter alia, the scheme and lay out of the
development of the highway and the project facilities, preliminary design and costing. The report will
form the basis on which a Financial Consultant and a legal consultant, appointed separately in the
next three months, will prepare an RFP document for inviting bids from private entrepreneurs to
award a BOT (Toll) concession. The concession will be on DBFO pattern, wherein the
concessionaire shall, in accordance with a model concession agreement approved by the
Government, take full responsibility to carryout the detailed design, construction, maintenance and
operation of the project highway and the project facilities conforming to the standards specified in the
said agreement. He will obtain all the finances required for the project, and eventually transfer the
project to NHAI after expiry of the concession period in a state as specified in the concession
agreement. The Feasibility Report would thus provide all the technical details, based on which
realistic bids are received from the prospective bidders.
The consultant shall prepare the lay out of the 6 lane facility clearly spelling out the feasible
engineering, technological and management solutions (without detailed design). While evolving these
solutions the Consultant shall always bear in mind that main focus of the assignment will be on
retrofitting a six lane cross section over the existing 4 lane cross section such that the improved
highway is safe, efficient and convenient to the users as well as public living adjacent to the highway.
The Consultants proposal shall ensure the following:
The highway is safe for the road users and the public living adjacent to the highway
Operation of the highway is smooth and efficient
Construction is least disruptive to the users and the public
Land acquisition is kept to the barest minimum
Facilities created already during 4- laning are utilized to the maximum extent
Constraints of site are got over by proven technological solutions
Within the given constraints, the solutions are sound, economical, constructible, and
manageable.
Estimation and analysis of transport demand based on the available data with
consultants
Alternate alignment studies and finalization of bypass alignment
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
Detailed topographical survey covering all physical features within proposed ROW
(60/80m)
Preliminary design for costing purpose of highway and structures
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 10-1 0
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 10-2 0
10.1 INTRODUCTION
The design standards for the project highway has been adopted after reviewing the relevant latest
Indian Roads Congress Codes (IRC), Manual of Specifications and Standards for Six Laning of
National Highways Through Public Private Partnership published by Ministry of Shipping, Road
Transport & Highways and international standards such as AASHTO etc.
The various design elements and factors, which govern the functioning of any highway, can be
broadly grouped under the following:
o Horizontal Alignment
o Vertical Alignment
Subsurface drainage
The basic design philosophy is based on the consideration of providing suitable alignment, cross-
sectional layout, geometrics, safety and access control to cater to the fast and uninterrupted
movement of through traffic. It is also based on the consideration that the widening proposals should
be to the extent feasible within the present Right of Way (ROW) or with minimum land acquisition.
The design speed is the guiding criteria for correlating features such as sight distance, curvature and
super elevation upon which the safe operation of the vehicle depends. The design speed
recommended for different terrain classification system for the project highway is as follows:
Design Speed(kmph)
Terrain Cross Slope (%)
Ruling Minimum
Plain 0-10 100 80
Rolling >10 - 25 80 65
Mountainous >25 - 60 50 40
Steep > 60 40 30
The terrain in the project stretch is virtually all plain with the general cross slope of the country
remaining very much less than 10%.
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 10-3 0
As per NHAI guidelines for Vijayawada-Gundugolanu section, the available Right of Way (ROW)
along the newly constructed bypass during four lane construction is 60m. The available ROW in the
some villages is varying from 20m to 40m. However the project is a retrofitting of a 6 laning scheme
onto the existing situation which will require significant land take. At many isolated locations more
land will be required to suitably accommodate the proposed underpasses, entry/exit ramps, rest
areas, toll plazas and way side amenities etc.
As per NHAI guidelines for Vijayawada/Hanuman Junction bypasses, proposed right of way for the
new bypass alignments is 60/80m. Consultants want to propose a right of way width of 80m, to
accommodate service roads and also to locate various utilities and also to have provision for the
future widening, if required.
The details of cross sectional elements adopted for the project road are as per 4 Laning and 6 Laning
Manual. In straight reaches, a camber of the same value as the existing 4 lane pavement is to be
provided. The adopted cross sectional elements are presented in the following sections.
10.5 SUPERELEVATION
Super elevation is provided for all the horizontal curves with radius less than 2000 m in order to
counteract the effect of centrifugal force. As per IRC: 38 -1988, super elevation to fully counteract the
centrifugal force for 75% of the design speed of 100 km/h neglecting the lateral friction developed will
be adopted in design.
2
e = (V) / 225 R
The maximum super elevation is limited to 7% for Vijayawad-Gundugolanu section and Hanuman
Junction bypass and 5% for Vijayawada bypass as per codal requirement. It must be noted that the
superelevation to be adopted should generally be exactly the one already constructed under the
previous 4 laning,
The tangent sections, circular curve and transition curve elements are the major component of
Horizontal alignment. A balanced control on the above elements is required to provide safe and
continuous flow of vehicles under the general traffic conditions. The horizontal circular curve radius of
360m or more is required to meet the requirement of the design speed of 100kmph.
Transition curves in the form of spiral between the tangent sections and circular curve element are
designed to satisfy the requirements of allowable rate of change in experiencing centrifugal
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 10-4 0
acceleration by the user and attaining super-elevation on carriageway for the circular curve. For the
horizontal curves with radius of curvature less than 2000 m, transition curves are generally provided
on both ends of circular curve. The minimum transition lengths suggested in the IRC guideline are
indicated in the in the following sections.
There are two major elements in vertical geometry of an alignment i.e. longitudinal gradient and
vertical curve. The following gradients for Plain / Rolling terrain conditions are given below.
Gradients up to the ruling gradient would be used as a matter of course in design. The limiting
gradients would be used where topography of a place compels this course or where the adoption of
gentler gradients would add enormously to the cost. Further, the steepest gradient or exceptional
gradient is meant to be adopted only in very difficult situations and for short lengths not exceeding
100m at a stretch.
Due to changes in grade in the vertical alignment of the highway vertical curves at the interchanges
and at locations where underpasses are to be inserted different grades will be provided in the design
so as to smoothen the vertical profile resulting in easing off of the changes in the gradients for the
fast moving vehicles. Both summit curves and valley curves will be introduced as per IRC guidelines.
The length of summit curve and valley curves (L) is guided by S, the sight distance and the deviation
angle (N).
2
i) When the length of the curve is greater than the sight distance L = NS / 4.4
ii) When the length of the curve is less than the sight distance L = 2 S 4.4 / N
i) when the length of curve is greater than the stopping sight distance
2
L = NS / (1.5 + 0.035 S)
ii) when the length of curve is less than the stopping sight distance
L = 2 S (1.5 + 0.035 S) / N
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 10-5 0
Lengths of speed change lanes for interchanges recommended are given below. Maximum vertical
gradient of 3.3 % generally would be adopted in design.
Adequate drainage is a primary requirement for maintaining the structural condition and functional
effect of a good pavements structure including sub grade. Pavement must be protected from any
ingress of water. Otherwise over a period of time it many weaken the sub grade by saturating it and
cause distress in the pavement structure. The GSB layer shall extend through the full formation width
and shall act as the drainage layer for effective subsurface drainage.
Table 10.1 : Design Parameters for Vijayawada-Gundugolanu section and Hanuman Junction
Bypass [100 Kmph Design Speed]
S. No. Description Details
1 Design Speed 100 Kmph
2 Lane width 3.5 m
Rural 4.5m
3 Raised Median
Urban 1.2m
4 Median side paved strip (Shy distance) 0.25 m
5 3-Lane carriageway 10.5m
6 Paved Shoulder 1.5m
Rural 2.0m
7 Earthen Shoulder
Urban 1.5m
8 Pavement & Paved shoulder 2.50%
Camber
9 Earthen shoulder 3.00%
10 Width of Service Road 5.5 m
11 Separation Island Between carriageway & Service road in Urban 1.5m
12 Minimum width of Footpath 1.5m
Rural 2.0m
13 Utility Corridor
Urban 1.5m
14 Maximum superelevation 5.00%
15 Minimum Stopping Sight Distance (SSD) 180 m
16 Minimum Intermediate Sight Distance (ISD) 360 m
17 Minimum radius of horizontal curve 360 m
18 Minimum radius of horizontal curve without transition 2000 m
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 10-6 0
Table 10.2: Design Parameters for Vijayawada Bypass [100 Kmph Design Speed]
S. No. Description Details
1 Design Speed 100 Kmph
2 Lane width 3.5 m
Rural 4.5m
3 Raised Median
Urban 1.2m
4 Median side paved strip (Shy distance) 0.25 m
5 2-Lane carriageway 7.0m
6 Paved Shoulder 1.5m
Rural 2.0m
7 Earthen Shoulder
Urban 1.5m
8 Pavement & Paved shoulder 2.50%
Camber
9 Earthen shoulder 3.00%
10 Width of Service Road 7.0m
11 Separation Island Between carriageway & Service road in Urban 1.5m
12 Minimum width of Footpath 1.5m
Rural 2.0m
13 Utility Corridor
Urban 1.5m
14 Maximum superelevation 5.00%
15 Minimum Stopping Sight Distance (SSD) 180 m
16 Minimum Intermediate Sight Distance (ISD) 360 m
17 Minimum radius of horizontal curve 360 m
18 Minimum radius of horizontal curve without transition 1800 m
19 Min. vertical gradient 0.30%
20 Absolute maximum vertical gradient 3.30%
21 Maximum grade change not requiring vertical curve 0.50%
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 10-7 0
The cross drainage structures shall be classified as culverts, minor bridges and major bridges
depending up on the length of structure as per IRC standards. Structures up to 6m length fall into the
category of culverts, more than 6m and up to 60m in length as minor bridges and beyond this as
major bridges.
The design standards and loading to be considered for culverts, bridges, underpasses, flyovers and
ROBs shall be those laid down in the latest IRC codes and/or IS codes. Where the said codes are
found wanting or are silent other codes at national or international level shall be followed in
consultation with the client. ROBs shall be planned and designed in consultation with the concerned
Railway Authorities.
1. The Indian Road Congress (IRC) codes will be the basis of bridge designs, underpasses and
flyover/ ROBs. For items not covered by latter, provisions of Special Publications and
Specification for Roads and Bridges published by IRC shall be followed.
2. Grades of Concrete for superstructures will be as per MOST Specifications and IRC
Standards. The Minimum grade shall be M40 for PSC and M30 for RCC respectively.
3. For all new 3-lane structures, 3-lane live load will be considered as per IRC-6.
4. Locations of new Minor Bridges will generally be guided by the alignment of the highway.
But, for major bridges, the bridge location and its alignment shall override the highway
requirement in that portion.
5. On economic considerations and for ensuring good riding quality, wherever possible, for the
new bridges the layout of the existing bridges having a number of small spans will be
modified by decreasing the number of spans, maintaining the piers parallel and in line with
those of the existing structure.
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 10-8 0
6. The deck will have 2.5% unidirectional camber/cross fall and the wearing course will be of
uniform thickness of 15 mm Mastic and 50 mm BC. For high traffic density, thickness of
mastic and BC shall be 25 mm and 40 mm respectively.
7. In general it has been observed during the preliminary study that the type foundations for the
existing bridges have not suffered any distress.
8. Pile foundations may be adopted for flyovers and ROB structures, depending on the
properties of the strata based on sub-soil investigation reports to be carried out by
Concessionaire.
Flyovers
Where flyovers are proposed, minimum vertical clearance above the cross roads will be 5.0 m.
Where viaducts [continuous] are proposed and the intent is to also use the road under for vehicular
traffic [as in a 4 lane continuous viaduct with the current road retained under] then all the structure
vertically above the roadway under should have the 5.0 m clearance [and this includes the underside
of the crossheads on the columns].
In general, the following aspects are taken into account while planning for the new bridges and
structures:
Aligning the piers with those of the existing structure to avoid cross currents and obstruction
to flow;
Minimum distance from the existing structure consistent with construction requirements and
hydraulic consideration;
Minimum number of spans consistent with road deck levels and minimum vertical clearance
above design HFL
Continuity (Except deck continuity) to be provided in superstructure for better riding quality.
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 10-9 0
(a) For culverts in new carriageway, minimum span and vent height will be kept equal to that of
those in the existing carriageway; raising of deck level according to highway alignment will
be made wherever required.
(b) Weak and non-functional culverts to be dismantled and new culverts to be constructed with
carriageway and median matching with highway plan and profile.
(c) For central widening to three lane, new abutments will be provided on both sides of the
existing culverts. Existing slab to be dismantled and new slab with specified camber to be
cast for the full length.
(d) Culverts in service road locations to be extended up to the road side longitudinal drain.
(e) In new alignments and bypasses, sufficient numbers of balancing culverts are to be provided
wherever alignment crosses through flat agricultural fields and lies in close vicinity to high
embankments of railways and flood bunds.
(f) In case of culverts whose bed and floor have scoured off severely and considerable afflux is
observed, the same will be replaced with new culverts having adequate vents or with a minor
bridge, based on adequate hydrological studies.
(g) Culverts will be designed for IRC Class-A / Class-70R Tracked / Class-70R Wheeled
Loading as per relevant IRC Codal Provisions.
(h) Culverts shall be constructed for full formation width of the roadway.
(i) For pipe culverts, expansion chambers shall be provided at median/ between main
carriageway and service road for proper maintenance.
(j) All cross drainage pipe culverts with less than 900 mm diameter shall be replaced with new
1.2 m (minimum) diameter pipe culverts.
Repair and rehabilitation of existing bridges shall be carried out by a specialised agency. Before
taking up any repair ( except for items essential for road user safety/ make safe items), a project level
investigation shall be carried out for finding out the cause of distress and to suggest the
rehabilitation / strengthening measures required.
Egis Bceom International, France in Association with Egis India Consulting Engineeers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-i 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-1 0
11.1 Introduction
Pavement design basically aims at determining the total thickness of the pavement structure as
well as the thickness of the individual structural components for carrying the estimated traffic
loading under the prevailing environmental condition and adopted maintenance strategy with
satisfactory performance of the pavement will result in higher savings in terms of Vehicle
operating costs and travel time. Many design methods, from purely empirical to rigorous
analytical ones are available, and these are practiced in different parts of the world. In our
country, the generally adopted method of design of flexible pavement is the one recommended in
IRC: 37-2001, Guidelines for the Design of Flexible Pavements, is also an analytical method of
pavement design. For the effective design of pavement, rehabilitation proposals, there must
needs to assess the availability & suitability of potential construction material sources in the
project vicinity. Various engineering surveys and materials investigation has been carried out as
part of feasibility study and were discussed in the following sections.
This section presents the pavement and materials investigations followed by design process and
the resulting design recommendations.
The visual pavement condition survey was carried out using Viziroad equipment along the project
road. The equipment is composed of
The equipment was set up for logging the following defects elements and data:
Longitudinal cracking in 3 levels
Rutting/Deformations in 3 levels
Alligator cracking in 3 levels.
Patching in 3 levels.
Potholes in 3 levels
Stripping in 3 levels
Transverse cracking in 3 levels.
Border erosion in 3 levels
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-2 0
Vizir Index
The Vizir index is a quality index as defined from the French Central Road Laboratory. It uses
several matrices and a decision tree to construct a final note from 1 to 7 (computed for
elementary sections of 500m) as follows.
Severity
1 2 3
Damage
Severe deformations, Deformations severely
Perceptible to user
Deformation localized subsidence or affecting safety or
but small
rutting rutting travel time
f < 2 cm
2 f 4 cm f 4 cm
Markedly branched
Hair line cracks in wheel Open and/or branching and/or wide open
Cracking
tracks or centerline cracks cracks; edges
sometimes damaged
Very open crazing
Tighter crazing (<50cm)
Fine crazing with no forming blocks (<20
sometimes accompanied by
Crazing loss of materials cm), sometimes
loss of materials, stripping,
large mesh ( > 50 cm) accompanied by loss
and incipient potholes
of materials
Either re-building Surface work related to type A defects
of part or all of
pavement
Repair Visible damage to
Or surface work Repair has stood up well
repair itself
related to type B
defects
If
0 1-2 3 4-5
Id
0 1 2 3 4
1-2 3 3 4 5
3 4 5 5 6
4-5 5 6 7 7
First Damage Index
Extent
0 to 10 % 10 to 50 % > 50%
Severity
1 0 0 0
2 0 0 +1
Surface Condition Index Is
Scale from 1 (best) to 7 (worst)
3 0 +1 +1
Correction for repairs
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-3 0
Pavement condition and actions required corresponding to various values of damage Index Is:
Rating 1 or 2
o Little or no cracking or deformation
o Good surface condition requiring no (or only just requiring) immediate maintenance.
Rating 3 or 4
o Cracks with little or no deformation, or deformation without cracking
o intermediate surface condition, bad enough to trigger maintenance work in the absence
of any other consideration
Rating 5-6-7
o Extensive cracking and deformation
o poor surface condition requiring major maintenance or overlay work
This rating can be cross-linked with deflection data and roughness data for further refinement of the
maintenance, overlay or reconstruction works to be selected. From the analysis of data reveals the
following description of the pavement.
Km Summary condition
Relative good section, low/medium rutting due to flow. Localised severe
1076+480 1062+080
alligator/longitudinal cracks.
Mainly DBST section with structural rutting and extensive, sometimes
1062+080 1061+080 severe alligator cracking. This section is structurally not sound and not
adapted to the existing traffic.
Mainly DBST section with structural rutting and extensive, sometimes
1056+080 1022+480 severe alligator cracking. This section is structurally not sound and not
adapted to the existing traffic.
The roughness survey of the project road was carried out in December 2006 on existing NH-5.
Roughness was measured using a Farnell bump integrator coupled to the Viziroad equipment.
The roughness of the measured section can be divided in 2 main sections.
In the above section we observe clearly the bad impact of transitions to bridges and slabs.
Settlements and lack of transition slabs are deteriorating the roughness significantly.
We also observe that the roughness on the old pavement [the original 2 lane road which was
then incorporated into the 4 laning] is in general significantly worse than on the new pavement.
In this section, roughness is mostly affected by the quality of the used asphalt mix, subject to
flow and plastic rutting and not much affected by structural defects.
The results of the roughness survey are shown at the end of the following section.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-4 0
Roughness was measured on the project section in both directions, in the slow lane, using the
bump (Farrell type on the rear axle of the vehicle). Before measurements the equipment was
calibrated according the specifications of the WB (WB technical paper 47).
Calibration.
Calibration was performed on 8 representative sections, grouped in 4 blocks of 400 m.
Each block was preceded by a lead-in section of 200 m, having a similar roughness to gain and
stabilize speed of the measuring vehicle. Each section was measured 5 times at a speed of 40
km/h and 5 times with a speed of 40 km/h. Those speeds allow evaluating the impact of the
speed on the measurements.
Every section was marked with paint on the road and in both wheel paths the elevation was
measured using a topographic level with intervals of 50 cm.
The roughness of each track was computed in IRI (m/km) according the algorithm defining IRI
computation from topographic surveys, as published by the World Bank using the program
available with the Viziroad equipment.
The roughness of both wheel paths for one test section was average to represent the
representative roughness of the section, as seen by the bump integrator mounted on the rear
axle of the measuring vehicle
The results of the topographic survey and the resulting roughness are summarized in the
following table: The correlation between the number of bump counts and the roughness
measured by topographic survey is shown below for both the 40 and 50 km/h runs.
One can observe that the result almost independent from the speed, as long as we stay within
the limits of 40 to 50 km/h. This allows us to use a unique correlation for all speeds within those
limits.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-5 0
5
CNT50
4 CNT40
3 Linear (CNT50)
Linear (CNT40)
2
0
0 10 20 30 40
A Materials Report for this project has been produced as a separate stand alone document [see
end of this chapter]. Previous materials reports have been analysed, and fresh rock / soil samples
collected and tested. The findings are very briefly summarised below:
Some slushy stretches were observed in some stretches and the top 300mm thick layer is to be
replaced with suitable borrow soil. The approximate total length of such stretches is 2.0 kms.
Apart from these slushy stretches, the soils in most of the other stretches satisfy embankment
requirements. For sub-grade formation it is preferable to provide soils producing a minimum 4-
day soaked CBR of 10%.Some Soils from borrow sources need blending with sand for producing
a CBR of 10%.
Test results of soil samples collected along the proposed alignment of Vijayawada bypass are
tabulated in table below.
a) Tenali (Vejella), Kaakni, Lam, Koppuravuru, Mangalagiri, Krishna bridge approaches and
Vaddeswaram in Guntur District.
Pond Ash: As per the recent Government of India notification, it is mandatory to use pond ash
for road construction works. However as per MoEF and NHAI guidelines, the usage of pond (fly)
ash is proposed for high embankment portions, bridges, flyovers, underpasses and ROB
approaches. Pond ash is to be covered with suitable soils on top and sides as per IRC guidelines.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-6 0
Vijayawada to Eluru:
Borrow areas for construction of embankment and subgrade were identified from the available
reports. Similarly, useable stone metal quarries, water and sand sources with their locations were
identified for the new construction. All materials complied well with respect to their engineering
and quality aspects.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-7 0
Modified
Sand Content /
Atterberg Limits Proctor Test
Gradation
Soil Values
S.N. Mediu Classi FSI CBR
Sampled at Ch. Fine MDD Remarks
Natural m Silt & ficatio (%) (%)
Gravel sand LL PL PI n (in OMC
Moisture Coarse Sand Clay
(%) Sand (%) (%) (%) g/cc (%)
content (%) sand (%) size (%)
(%) )
(%)
1 Sample at Rly track Starting 25.6 1.20 2.80 9.40 13.4 73.2 59.4 22.9 36.5 16.5 19.0 50.0 --
2 Sample at Mandadam 28.2 0.00 0.80 01.8 04.4 93.0 64.6 27.6 37.0 16.9 19.8 60.0 --
Sample at Nunna at Km
6 18.4 0.40 0.60 06.2 15.2 77.6 54.9 20.0 34.9 17.5 18.5 50.0 --
1072+930
7 Nunna to Gannavaram 16.0 0.00 0.60 23.6 40.8 35.0 28.1 11.7 16.4 22.6 7.47 0.00 17.8
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-8 0
Finally, the investigations then carried out led to the use of earth material from the borrow areas
located along NH5 and NH9 as follows:
NH5:
1. Km 1083+080 left side 7km - Sawan Gudem
2. Km 1081+380 left side
3. Km 1079+080 left side 6 km - Purushotam Patnam Quarry
4. Km 1074+080 left side 6km Veerapanneni gudem Quarry
5. Km 1059+080 left side 9 km - Kotta Palli Quarry
NH9:
1. Km 201.2 Right side, gravel quarry
2. Km 219.0 left side 1 km Munieru River Bed, sand source
3. Km.219.0 left side 2.0 km, gravel quarry
4. Km. 226.0, RS, Murieru River Bed, Sand
Sub base
The materials available in gravel/moorum quarries in the surrounding area contain high clay
contents and possess higher Liquid Limit and Plasticity Index values higher than the permissible
values. Percentage passing 75 micron sieve is also very high and these soils dont satisfy 10%
fines requirement as per clause 401 of MORTH Standard Specifications for road and bridge works.
Even blending with sand and stone dust will not satisfy most of the GSB and drainage layer
requirements. A minimum permeability of 20m/day is required for effective drainage layer. Hence
GSB as per grading III, II or grading I of table 400-2 with crushed aggregates may be provided.
All the mixes confirming to the above grading produce a minimum CBR of 30% required for sub
base. They also satisfy the permeability requirements of 20m/day and all the other MORTH and
IRC requirements.
Base and other Pavement courses
For the Vijayawada bypass, two important quarries at Perecherla and Palakaluru are available in
Guntur District. Two important quarries at Donabanda (Km 142+000 to Km 143+000 on NH-9)
and Ketanakonda (Km 1079+680 to Km 1079+580 on NH-5) are available in Krishna District.
Aggregates from these quarries are assessed for the suitability of aggregates for construction of
the base and pavement courses. These quarries were investigated for their suitability for
purposes of base course and other pavement courses, and were established as an acceptable
source for construction of base course and other pavement layers.
Sand Sources
The nearest source of sand (fine aggregate) in the stretch is Krishna river and quarries are
available at Seethanagaram in Guntur District and Damuluru and Moolapadu in Krishna District.
For the validation testing, the sand sample was collected from the river bed. The gradation test
performed on the sand sample indicated fineness modulus of 2.62 which lies between the F.M.
range of 2.6 to 2.9 indicating medium sand. The sample tested corresponded to Grade III. The
results of this sample show there is positive promise and potential for using this sand source for
construction works.
Moolapadu sand is suitable for filling and sand from Seethanagaram and Damuluru is suitable for
construction. Coarse sand available from Seethanagram and Damuluru quarries is suitable for use
in cement concrete works and in sand gravel mixes also.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-9 0
Construction Water
Water from Krishna river can be used for construction purpose. These are free from major
contamination and hence can be used as the water sources for concrete and construction of road
works. Also, tube wells at suitable places can be installed if necessary. Along with Krishna river
two more rivers were located on NH 5 and 9, which were mentioned below:
Water samples from these sources should be tested in laboratory for their suitability.
Eluru to Gundugolanu:
Borrow areas for embankment and subgrade construction inclusive of the quarry materials, water
and sand etc. meeting the technical as well as their quantity aspects were identified based on
existing reports as well as new test results.
In view of the above observations which were based on existing information as well as testing of
the limited soil, quarry and water samples, it seems reasonable to conclude that the prospects of
obtaining suitable and good quantities of various highway materials appears bright. However, it
does not in any way reduce the significance of the Concession Company collecting reasonable
numbers of samples of each type of material and subjecting them to proper engineering tests in a
recognised laboratory when construction of the new widening becomes a reality. Finally, the
investigations then carried out led to the use of earth material from the borrow areas located
along NH5 as follows:
NH-5:
1. Km 1059+080 left side 9 km - Kotta Palli Quarry
2. Eluru Bypass Km 1039+380 - Tamileru River Sand
3. Km 1039+380 Eluru Bypass, left side 6.6 km - Janam Peta quarry
4. Km 1021+080 left side 6.6 km sand gravel mix
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-10 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-11 0
BOT/DBFO basis. Assuming 3 years time required for construction of bypass, the road will be
operated from 2014.
Summarizing, the design period for the pavement structure for the new carriageway was
considered as 20 years.
Growth rates estimated for the Feasibility Study for 6 laning of Chilakaluripet-Vijayawada, NH-5
and Vijayawada-Eluru-Rajahmundry are suitably modified in the light of four laning of the
Hyderabad-Vijayawada section and adopted for the present study. The growth rates estimated for
the Vijayawada bypass are presented for the realistic scenario. The estimated/proposed growth
rates for different vehicle types are as below for Vijayawada bypass and main stretch and
hanuman junction :
Adopted growth rates for existing main carriageway and hanuman junction
The above growth rates of commercial vehicles have been considered for assessment of design
traffic in terms of MSA.
Estimated traffic of the Vijayawad bypass,Hanuman junction bypass and existing stretch has been
projected with below growth rates and presented for the year 2010. Table 11.1 gives the year
2010 (now base year) traffic volumes in terms of AADT for the entire bypass section, for the
calculation of design traffic in terms of MSA for pavement design.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-13 0
As the bypass is not having the bus traffic, the VDF for bus has not been considered. However, in
general the VDF for the bus in most of the cases equivalent to VDF of LCV.
From the above table it can be observed that, the 3-Axle trucks and MAV are overloaded by 20%
and 60 % respectively of the maximum permissible limits.
The strength of sub-grade in terms of California Bearing Ratio (CBR) is required for the design of
new flexible pavement if catalogue design of IRC: 37-2001 is used. The consultants had explored
and identified the potential borrow areas for the construction of sub grade and embankment
along the proposed bypass alignment. From this investigation and laboratory testing of soil
samples revealed that good strength soils with CBR values varying from 8% to 12 % are available
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-14 0
with reasonable lead. Also, as part of Feasibility study for Preparation of six-laning from
Vijayawada-Eluru-Rajamundry section, a number of borrow areas have been identified along the
project stretch as sources for embankment and subgrade filling material. Such investigation also,
shows that the borrow area soils of CBR 8% are available within the project vicinity with
reasonable lead (haulage distance) from site all along the project road.
Thus, a 4-day soaked CBR of 8 % has been considered as sub-grade strength for pavement
design for the entire project road except vijayawada bypass, where it has considered as 10%.
Base year traffic (vehicle category-wise & in terms of AADT), traffic growth rates, design life (in
terms of number of years) and vehicle damage factors are required to estimate the design traffic
in terms of equivalent standard axles. The following data have been considered to arrive at the
design traffic (MSA).
For flexible pavements, the percentage of vehicles in heaviest loaded lane can be determined as
per IRC: 37-2001 guidelines given below:
The details of MSA calculations are provided in Table 11.4 and the summary is abstracted at
Table 11.3 below.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-15 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-16 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-17 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-18 0
Design of new flexible pavement applies to the new carriageways for the proposed bypass with 6-
lane facility. The methodology recommended in IRC: 37-2001 has been adopted. The objective of
the pavement design is to provide the best combination and thickness of pavement structure
materials, over the sub-grade that will reduce the stress caused by loading to within the load-
carrying capacity of the sub-grade soil. Pavement structure worked out for the entire operation
period will be constructed in one-go before opening to traffic.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-19 0
The ultimate pavement structure to account for entire design life of 20 years (2014 to 2033) is
presented in Table 11.5 below.
Pavement composition
Design
Design
Design Section traffic (thickness of layers in mm)
CBR
(msa)
BC DBM WMM GSB
Vijayawada bypass-
10 94 49 128 250 200
Western section-1
Vijayawada bypass-
10 85 47 124 250 200
Western section-2
Hanuman Junction
8 53 41 121 250 200
bypass
Other than bypass
8 122 50 144 250 200
(existing main CW)
As mentioned earlier (Section 11.2.1), the proposed pavement design life of 20 years excluding
construction period was considered. Estimated traffic loading for 20 year concession period in
terms of cumulative standard axle load is quite low compared to the design traffic estimated for
main NH-5 from Vijayawada-Eluru-Rajahmundry section. Moreover, the assessment of traffic in
terms of number of commercial vehicles for such a distant horizon of 20 year from now has
doubtful precision. Also, vehicle fleet composition and vehicle damaging factors obtained today
may not remain same for a future period of 20 years. As per the latest codes and documents, the
strengthening/new construction shall be of 50mm BC. Thus, accordingly the BC layer of thickness
50mm has been considered and the proposed thicknesses and composition of pavement layers is
presented in the Table 11.5 below.
Pavement composition
Design
Design (thickness of layers in mm)
Design Section traffic
CBR
(msa) Sub
BC DBM WMM GSB
grade
Vijayawada bypass-
10 94 50 125 250 200 500
Western section-1
Vijayawada bypass-
10 85 50 120 250 200 500
Western section-2
Hanuman Junction
8 53 50 110 250 200 500
bypass
Other than bypass
8 122 50 140 250 200 500
(existing main CW)
A sub grade of 500mm thickness and 8% CBR is required as an integral part of the pavement
structure along the project road and 10% for Vijayawada bypass.
At the time of 6-laning construction, the existing pavement needs to be strengthened by flexible
overlay of 50mm BC to extend the design life with widening portion and matching of bituminous
concrete BC layer for both new construction and overlay.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-20 0
Service road pavement composition is designed for 10 MSA traffic loading as given in para 5.5.5
of Manual of Specifications & Standards for Six Laning of Highways through Public Private
Partnership published by IRC as SP:87-2010. The design CBR of 8% has been considered. The
composition and thickness of component layers as worked out is given in Table 11.6 below:
11.10.1 General
During the operational phase, the initial designed pavement structure will be subjected to both
load induced and environmental damages. The notion of pavement lifetime can not be easily
defined as development of fatigue damage is inherently random. Safety, riding comfort and cost
effectiveness concerns always require maintenance operations to be performed before complete
pavement failure. Thus, it becomes necessary for the Concessionaire to take up appropriate
maintenance measures to ensure that the functional quality does not fall below the prescribed
levels, and at the same time the structural integrity of the pavement is maintained so that it
serves well throughout the concession period without the need for un-scheduled rehabilitation or
reconstruction measures. During this period, performance of the pavement will be closely
monitored and appropriate maintenance actions taken to maintain its functional characteristics
and structural integrity.
Considering the design life of 20 years from traffic opening on to the new 4-lane bypass facility,
the following overlay treatments are proposed.
Type-I Overlay
In India, it has been observed that even if the bituminous crust is provided for 15 to 20 year
design period, first overlay is mostly required in the initial operating period of 6 to 8 years after
opening the traffic. During this period, certain damages in the form of undulation and unequal
settlements are anticipated in the pavement surface due to foundation settlement and
compaction of the body of the embankment. For correction of these, a profile correction course
(PCC) of variable thickness would be required. For this purpose, a combination of BC layer of
25mm with PCC of 25mm BC laid with total thickness of 50mm is proposed. Choice of DBM in its
place would have meant a much thicker mat, and also heterogeneous structure (DBM over BC).
Type -2 Overlay
This, comprising a thin surfacing course is essentially intended for restoring the riding quality
which might have deteriorated because of traffic action and other environmental problems. For
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 11-21 0
high-type roads, this is normally applied once in 6-8 years, and the same frequency is proposed.
The layer will be of BC, 40mm in thickness, using modified binder and 13mm nominal size
aggregate.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Draft Combined Feasibility Study for 4/6
Laning of Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 12-1 0
12.1 GENERAL..................................................................................................................................................2
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Draft Combined Feasibility Study for 4/6
Laning of Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 12-2 0
12.1 GENERAL
Once the as-built drawings and site conditions were examined it became obvious that the 6 laning
[along with service roads] could not generally be fitted into within the available right-of-way.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Draft Combined Feasibility Study for 4/6
Laning of Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 12-3 0
Preliminary Right of way details on northmost 200km section [Total existing ROW width]
120.0
100.0
80.0
ROW Width [m]
60.0
40.0
20.0
0.0
0+000 20+000 40+000 60+000 80+000 100+000 120+000 140+000 160+000 180+000 200+000
Km [Vijayawada - Divnacheru]
For the ease of analysis of land take requirements for the current objective of the project, the Right of
Way details are presented in different sections.
The right of way required for 6-laning with service roads is in the order of 54 meter in the urban
section which includes provision of shoulders and wider service road to cater the mixed local traffic
and 60 in 4 lane Vijayawada bypass, 70 in Existing NH5 widening to 6lane & 80 in Hanuman
Junction Bypass in the rural section. An additional land is required at junctions, interchange for the
provision of cross structures and for wayside amenities and drainage channel relocation. Based on
typical cross sections and these assumptions, the land acquisition requirement is assessed and
summarised in the following tables. It is apparent that the whole project road required acquisition all
along the section.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-1 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-2 0
13. STRUCTURES
13.1 INTRODUCTION
A visual inspection of existing structures on the project section was carried out in the period
December 2006 to January 2007. Coupled with this various relevant reports and inventories from
previous Consultants were collected from NHAI and read.
There are 2 major bridges (considering both the carriageway) on the project road. The
superstructures are of PSC / RCC T-Beam and Slab, voided slab type resting on RCC substructures
supported by Well / pile foundations.
The type of superstructures for minor bridges / underpasses / ROBs are RCC solid slab, RCC / PSC
T-beam, voided slab, box girder etc. in most bridges resting on RCC and C.C. gravity type
substructure supported on open / well / pile foundations. Few structures have RCC balanced
cantilever, superstructures also. RCC box type structures / U trough with simply supported
superstructures have been observed at some location. Some bridges have course rubble masonry
substructure and foundation.
The condition of most of the structures is generally good. Some common distresses observed are
spalled concrete; exposed and corroded reinforcement in slabs, piers and abutments; damaged
/missing RCC railing and kerb, depositions of debris and growth of vegetation on pier caps and in
ventways, damaged asphaltic / RCC wearing coat, damaged / missing precast slab, damaged
expansion joints; undismantled steining of well foundations; missing, choked drainage
spouts,leakage around holes for drainage spouts; spalled concrete and corroded reinforcement,
approach slab settlement, settlement of embankment around abutments, damaged metallic crash
barriers in structure approaches etc. In few structures, plasterwork is observed at soffit of box and
cantilever portion, which hides the actual condition of the structures. Bed protection provided, if
any, was not visible in general. Bridges in very bad condition, arch bridges and bridges having
course rubble masonry shall be replaced with new 3-lane structures.
The culverts observed along the project road are mainly of two type viz. RCC slab culverts and pipe
culverts. Some RCC box culverts are also there. The structural condition of pipe culvert is generally
good, except that some are partially choked or full buried. The condition of culverts is in general
good. Some common distresses noted are missing / damaged parapets; cracked / damaged
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-3 0
headwalls, abutments and wing walls; spalled concrete and corroded exposed reinforcement. Bed
protection provided, if any, was not visible.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-4 0
c) Absence of water collector channels and drainage chutes with stilling basins after
approach slab leading to scouring immediately on sides of wing walls.
d) Use of smaller stones of weight less than 40 kg in pitching of slopes.
e) Use of loose boulder pitching on slopes steeper than 1:2.
6. Debris on deck
Debris have collected towards the outer
edges of the carriageway thereby making
almost half a meter wide strip non usable
and causing blocking of drainage spouts. All
the strip seal expansion joints were also
found filled up by debris.
7. Drainage spouts
Drainage spouts are found to be having different distress in different structures as listed
below:
a) Missing spout grating.
b) Spout hole blocked by debris.
c) Leakage around drainage spout from holes made in deck slab for fixing spouts and
left unplugged.
d) Down take pipe of drainage spout ending at face of deck slab.
e) At some bridge locations, drainage spouts have not been provided at all.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-5 0
Precast expansion gap slabs provided in the Vasista bridge superstructure were found to
be damaged / partly missing. This situation is very dangerous for the road users,
particularly the two wheelers.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-6 0
14. Bearings
Bridges with solid slab decks have tarpaper on the abutments and piers. The RCC T- Beam
and slab superstructure are supported on elastomeric / rocker and Rocker cum roller / plate
bearings. The balanced cantilever bridges have metallic rocker and rocker cum roller
bearings.
15. Hydraulics
At most of the sites, growth of vegetation and trees was observed in the riverbed under and
around the bridges. Pedestrian tracks and bunds for storage of water are observed at some
sites. However, no serious problem of inadequacy of waterway, degradation of the bed or
excessive scour around abutments and piers was observed.
This approach slab settlement requires the following general [at many structures] remedial
measures:
a) Before taking up the rehabilitation of settlement of approach slab the embankment
quadrants around the wing walls shall be stablised first.
b) Loose boulder pitching on the settled/ failed embankment shall be removed and stacked
separately.
c) The exposed embankment shall be checked for present compaction conditions. The loose
material, if any, shall be removed and replaced with suitable materials duly compacted.
d) Thereafter, the embankment shall be built up to required levels.
e) Provide loose boulder pitching with boulders weighing not less than 40 kg over 150 thick
filter media.
f) Similarly, all areas of loose boulder pitching having smaller stones shall be replaced with
boulders weighing not less than 40 kg.
g) A toe wall shall be provided at the end of boulder pitching.
h) Provide water collector channels after end of approach slab for a length equal to 2.5 times
the height of embankment with a minimum length of 15 m.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-7 0
i) Provided RCC drainage chutes at 5 m intervals with one drainage chute at start and end of
water collector channel.
j) Provided stilling basins at end of drainage chutes duly protected from scouring.
k) Now, make up the settlement in approach slab and approach embankment with suitable
bituminous course.
l) In case settlement of approach slab has resulted in the end of approach slab resting on
bracket projecting from dirt walls projecting over the road surface, the approach slab shall
be dismantled and replaced with a new one after making up the settled parts.
The bridge is in good condition and can be retained in the present condition with minor repairs.
Blocked drainage spout pipes to be cleaned and missing gratings to be replaced. Damaged /
missing precast slabs in footpath to be replaced. The settlement of approach slab is proposed to be
suitably repaired for providing a smooth transition on to the bridge and to improve the riding
quality. It is proposed to provided water collector channels after the approach slabs alongwith
drainage chutes, with stilling basins at ground level, at 5 m intervals for preventing scouring near
edges of wing walls. Rehabilitate boulder pitching on earthfill around abutments.
Widening of existing 2x2 lane structures is not feasible because it is having eccentric
superstructure (towards outer edge) along with a PSC span resting on pile foundations.
13.5.2 Major bridge no. 64/5 at km 1040+481 across Tammileru River on Eluru Bypass
(New 4 lane)
The existing new 4 lane bridge on has 5 spans (1x 24.53 m + 1x36.38 m + 1x 37.15 m +
1x36.85 m +1x24.68 m) with a total length of 159.6 m. It has PSC T Beam and slab
superstructure for 3 nos. central span and voided slab superstructure for end spans. The
superstructure is supported on RCC circular piers resting on well foundations and RCC solid wall
type abutments resting on pile foundations. It has elastomeric bearings and strip seal type
expansion joints. Each 2-lane of existing bridge has 9.905 m deck width comprising of 7.5 m wide
carriageway and 1.865 m footpath including hand rail near outer edge and .54 m railing kerb
towards median. The end span towards Rajahmundry side also serves as an underpass.
The bridge is in good condition and can be retained in the present condition with repairs. Heavy
vibrations are noticed in end spans particularly on Vijayawada side which requires to be
investigated by a specialised agency for finding the cause and to propose & carry out necessary
rehabilitation measures. The settlement of approach slab is proposed to be suitably repaired for
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-8 0
providing a smooth transition on to the bridge and to improve the riding quality. It is proposed to
provided water collector channels after the approach slabs alongwith drainage chutes, with stilling
basins at ground level, at 5 m intervals for preventing scouring near edges of wing walls.
Rehabilitate boulder pitching on earthfill around abutments.
Widening of existing 2x2 lane structures is not feasible because it is having eccentric
superstructure (towards outer edge) along with a PSC / voided slab superstructures resting on well
/ pile foundations.
13.5.3 Major bridge no. 70/3 at km 1034+907 across Vyaskani River on Eluru Bypass
(New 4 lane)
The existing new 4 lane bridge on has 4 spans of 32.3 m each with a total length of 129.2 m. It
has PSC T Beam and slab superstructure supported on RCC circular piers resting on well
foundations and RCC solid wall type abutments resting on pile foundations. It has elastomeric
bearings and strip seal type expansion joints. Each 2-lane of existing bridge has 9.905 m deck
width comprising of 7.5 m wide carriageway and 1.865 m footpath including hand rail near outer
edge and .54 m railing kerb towards median. The end span towards Rajahmundry side also serves
as an underpass.
The bridge is in good condition and can be retained in the present condition with minor repairs.
The settlement of approach slab is proposed to be suitably repaired for providing a smooth
transition on to the bridge and to improve the riding quality. It is proposed to provided water
collector channels after the approach slabs alongwith drainage chutes, with stilling basins at
ground level, at 5 m intervals for preventing scouring near edges of wing walls. Replace the
damaged concrete near expansion joint and reset the expansion joint. Clean blocked drainage
spouts and replace the missing / damaged spout gratings.
Widening of existing 2x2 lane structures is not feasible because it is having eccentric
superstructure (towards outer edge) along with a PSC superstructure resting on well / pile
foundations.
Note: Existing 4-lane (2x2lane), Two Major bridges and Two ROBs in Eluru Bypass are having
superstructure with PSC T-Beam Girder Slab/Voided Slab/PSC Box Girder/RCC Box Girder,
supported on deep foundations. As such it is not possible to widen the existing four lane bridges
(2 x 2 lane) to six lane (2 x 3 lane) because the foundation type is deep foundation (Pile/Well)
which are designed for 2 lane loading only and widening of these foundations is not possible hence
they are not able to withstand for 3 lane loading so we have to dismantle and reconstruct the new
3 lane bridge at these locations. Dismantling of the existing structures is a difficult process and
reconstruction of new 6 lane bridges would increase the cost of the project. Therefore from the
economy considerations, the major bridges and ROBs in the Eluru Bypass are proposed for
retention without widening / reconstruction.
There are 4 Major Bridges (Total length > 60.0 m), 34 Minor Bridges (6.0 m < Total Length
<60.0m), 4 existing ROBs, 20 underpasses/ cattle crossings and 171 culverts on the various
sections of NH5 on the project road between Vijayawada and Gundugolanu.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-9 0
All the numbers of structures mentioned above are for individual 2 lane carriageway except for
culverts which are for 4 - lane. All the improvement proposals, except for culverts, refer to the
improvement of structure for individual carriageway. The improvement proposals for various types
of structures are as under:
i. All existing major bridges in good condition shall be retained with 2 - lane configuration for
individual carriageways with necessary repairs.
ii. Existing arch bridges and bridges in bad condition shall be replaced with new 3 lane
bridges.
iii. The span arrangement of new 3-lane major bridges shall be matched with the span
arrangement of the retained major bridges.
iv. The bridges with open foundations can be constructed at same location as that of existing
bridge.
v. The total deck with for the new 3-lane major bridges shall be kept as 14.05 m consisting of
10.5 m wide carriageway, 0.5 m edge shyness near median and 0.25 m shyness near
crash barrier alongside footpath, 1.5 m wide footpath, 0.5 m wide crash barriers on either
side of carriageway and 0.3 m wide steel railing kerb on outer edge of the footpath.
vi. For structures having width less than road cross section at that location, metallic crash
barriers shall be provided in the approaches on both sides of the structure. The length of
metallic crash barriers shall be kept in such a way that the splay is 1:10 so as to provide
a safe entry and exit from the structure having deck width lower than the respective road
cross section.
vii. The structural arrangement of ROBs shall be finalized keeping in view the Railways
requirements.
i. All structures in good condition having simply supported RCC solid slab superstructure and
open foundations shall be widened to 3-lane.
ii. Structures with well / pile foundations having 12 m total deck width shall be retained by
modifying the carriageway to 11.0 m with 0.5 m wide crash barriers on both sides of
carriageway after checking the structure for 3 lane live load.
iii. Structures with well / pile foundations having 9.8 / 10.25m total deck width shall be
retained by replacing the superstructure with equivalent or lower weight steel concrete
composite superstructures of total deck width 12.0 m. abutments (12 m) and piers / piers
caps shall be suitably widened to accommodate the new deck after checking the structure
for 3 lane live load and additional width. The backfill behind abutments and well cap
shall be replaced with one having following properties: 35, 1.8 t / m3 and c = 0.
iv. Structures with well / pile foundations having around 8 m total deck width shall be
replaced by new 3 lane structures.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-10 0
v. The new 3 lane structures shall be either located parallel to the existing structures with
well / pile foundations or constructed with longer spans such that the foundations of new
structures do not foul with those of existing structures. The structures with open
foundations can be constructed at same location.
vi. Arch bridges, bridges with CRM substructure & foundations and bridges in bad condition
shall be replaced with new 3 lane bridges.
vii. The span arrangement of new 3-lane structures shall be matched with the span
arrangement of the retained structures.
viii. The total deck with for the new 3-lane and widened structures having simply supported
RCC solid slab superstructure and open foundations shall be kept as 14.0 m consisting of
10.5 m wide carriageway, 0.5 m edge shyness near median, 1.5 m paved shoulder and 1.0
m earthen shoulder, 0.5 m wide crash barriers on median side and outer edge of deck
(partly covering earthen shoulder).
ix. For structures having width less than road cross section at that location, metallic crash
barriers shall be provided in the approaches on both sides of the structure. The length of
crash barrier shall be kept in such a way that the splay is 1:10 so as to provide a safe
entry and exit from the structure having lower deck width than the road cross section.
x. While widening the existing structures, traffic shall be diverted through temporary bailey
bridges or culverts, whichever is suitable to site conditions, constructed parallel to the
existing bridge.
13.6.3 Culverts
There are 171 culverts (pipe, slab and box) on the project road. These culverts are of 4 lane
configuration. At a few locations, pipe culvert on existing 2 lane has been extended by a slab /box
culvert on new 2- lane and vice versa. The culverts are generally in good condition. Broken or
missing parapet is a general distresses observed. Headwalls of some of the pipe culverts were
found cracked. Some pipes were found partly choked. Wing walls were found damaged at some
locations.
All the existing culverts, where still functioning and usable, shall be widened to six lanes with
opening at least equal to the existing culvert. The overall width of the culvert shall match with the
highway cross section at the particular location.
Major bridges
Number of bridges Number of bridges to be
Total number of major
retained without widened with new 2-lane
bridges
widening bridges
2 - -
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-11 0
Minor bridges
Number of
Number of
Number of bridges to Number of
bridges to be
Total number of bridges to be be replace bridges to be
widened with
minor bridges * retained without with new widened to 3-
new 2-lane
widening * 3-lane lane *
bridges *
bridges *
34 1 - 32 1
*each carriageway considered separately
ROBs
Number of
Number of ROBs
Number of ROBs to be bridges to be
Total number of retained to be
replace with new 3-lane widened with
ROBs without
ROBs new 2-lane
widening
bridges
2 2 - -
Culverts
Number of
culverts to be
Total number of Number of culverts to be Number of
replace with new
culverts* widened to 3-lane culverts retained
2/ 3-lane
culverts
171 21 150 -
All the structures shall be inspected by a specialized agency having relevant experience and
expertise. Both visual inspection and non destructive / destructive testing shall be carried out for
assessment of condition of the structure and to finalize its repair and rehabilitation. Based on the
defects observed and test results, a comprehensive repair and rehabilitation plan shall be prepared
for repair and rehabilitation of the distressed bridge components. Both testing and repair and
rehabilitation plan shall be got approved from Independent Consultant.
1. Remove debris/ vegetation from pier and abutment caps, expansion joints and bridge
deck.
2. Paint structure numbers in continuous and uniform chainage.
3. Provide water collector channels after end of approach slab for a length equal to 2.5 times
the height of embankment with a minimum length of 15 m.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-12 0
4. Provided RCC drainage chutes at 5 m intervals with one drainage chute at start and end of
water collector channel.
5. Settled filing around wing walls/ cantilever returns to be filled up, duly compacted, and
pitched with boulders in wire crates as per provisions of IRC: 89 and MoRT&H
specifications.
6. Clean drainage spouts. Provide missing / damaged gratings. Fill up the hole in deck slab
around spout. Replace drainage spouts with short or missing down take pipes. Install
missing drainage spouts at locations where they are missing / not provided at all originally.
7. Construct concrete inspection ladders on boulder pitching around abutment s for an easy
access to the river bed for inspection.
8. Remove vegetation from vent way and pitching around abutments.
9. False steining of well foundations shall be dismantled
10. Replace expansion joints of old bridges with T beam and slab superstructure with strip
seal type expansion joint after rehabilitating / strengthening / thickening the deck slab
near expansion joints suitably.
11. Provide 25 long splayed metallic crash barriers in approaches of bridges with deck width
lesser than the required configuration.
12. Replace / rehabilitate damaged stone pitching on embankments.
13. Replace / rehabilitate damaged upstream and downstream launching aprons of bed
protection works.
14. Replace all RCC railing adjoining carriageway with RCC crash barrier.
General
The project road is proposed to be developed as an access controlled highway so that the through
traffic can flow freely with least interference from the vehicles coming from the cross roads. The
Consultants examined the various junctions and studied their traffic patterns. On the basis of this
study, certain locations have been identified for locating Bypasses and flyovers / underpasses. The
underpasses and grade separators are proposed to cater for the width of the project road. Existing
4 lane underpasses are proposed to be widened to six lane configuration (See Chapter 18).
Bypasses
Vijayawada City falls between Km 1100+694(old chainage km 433+500) and Km 1090+000 (old
chainage km 14+000) on NH-5 where the project highway passes through Tadepalli, Benz circle of
Vijayawada City. The widening to six laning along existing alignment would involve significant land
acquisition, and demolition of existing properties along the highway. Keeping in view all the
representations, NHAI has asked the consultants to study and prepare a Feasibility Report for
providing bypass for Vijayawada City on NH - 5.
The section of NH-5 forming part of the project corridor passes through Gannavaram after crossing
the Vijayawada city. The terminating point is near Pedda Avutapalli on the eastern periphery of
Gannavaram. Traffic flowing between these points necessarily has to pass through thickly
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-13 0
developed area of Gannavaram, using existing 4-Lane NH-5 Road. Due to the congested traffic
flow conditions, Freight movement in this section will be very difficult in the future. This
necessitates the identification of bypass to the existing NH-5 at Gannavaram and Hanuman
Junction.
Flyovers
The flyovers have been proposed at urban locations and main junctions for free flow of through
traffic by elevating the main carriageway. The lifting of main carriageway will start at location
having adequate ROW for catering to width requirement of main carriageway, the generally 7.0 m
wide service roads [and / or ramps] on either side of the main carriageway, drains, footpath etc.
Similarly, the elevated road may be brought down at locations having adequate ROW for catering
to width requirements at start of lifting of main carriageway. Overall length of the flyover will be
determined based on the above considerations in addition to cross traffic / lower ROW etc. The
project road will fly over the cross roads providing minimum 5.0 m vertical clearance. The
standards for the flyovers and for the slip roads will be as per the Manual for 6 laning / IRC
guidelines. The superstructure may consist of precast girders with cast in situ diaphragms and deck
slab or a composite superstructure having steel girders and RCC deck slab.
Underpasses
Underpasses have been proposed to cater for the cross traffic and the pedestrians. While fixing the
vertical profile, the cross road RL is proposed to be depressed to the possible extent (keeping the
cyclones and cultivation in view) so that the existing pavement is least effected. For safety,
convenience and the local requirements; following types of underpasses have been proposed viz.
(i) Pedestrian underpass (PUP)/subways to cater for pedestrian and slow moving traffic
(ii) vehicular underpass (VUP) of 3 types to cater for vehicular traffic at state highways
and other road crossings
For Pedestrian underpass/subway RCC box structures with clear horizontal opening of maximum 6.
0 m and clear vertical opening of 2.5m have been proposed.
For vehicular underpasses when the project road crosses a cross road, the underpass will be a
single span 12m wide structure with vertical clearance of 5.0m has been proposed on roads
carrying heavy traffic. For other vehicular underpasses vertical clearance of 3.5m has been
proposed.
Flyovers are proposed at locations where the project road crosses a National Highway, or other
significant roads. The project road will fly over the National Highway and a divided six lane width
with individual supports has been proposed. The objective is to have the minimum structure
thickness realistically possible in the deck section as this will reduce the amount of existing road
wasted by the grade separation.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-14 0
Approaches
As the project road flies over the intersecting roads, adequate land width is needed for the normal
approach embankments. However, as almost all the locations of the proposed grade separators are
near the built-up areas, land acquisition may be difficult. Hence, reinforced soil structures are
proposed for the approaches, of all the flyovers, and some underpasses and some grade
separators.
6 Flyovers
13 Pedestrian Underpasses
10 Vehicular Underpasses
29 Minor Bridges on Vijayawada and Hanuman Junction Bypasses
6 Minor Bridges for Continuity of Service Roads
18 Minor Bridges for Continuity of Service Roads in existing Road
2 Major Bridges for Continuity of Service Roads
3 Major Bridges
3 ROBs
67 Culverts on both Bypasses
8 Culverts for Continuity of Service Roads
1 Foot over Bridge in existing Road
Vertical
S. Chainage Span Effective Total width*
Clearance Remark
No (km) arrangement length (m) (m)
(m)
Vijayawada Bypass
Start of
1 0+790 2 X 30 60 5.5 2 x 12 m
Bypass
NH 9
2 18+740 2 X 30 60 5.5 2 x 12 m
Crossing
3 47+350 2 X 30 60 5.5 2 x 12 m End of Bypass
Hanuman Junction Bypass
Start of
4 1+060 2 X 30 60 5.5 2 x 13.4m
Bypass
5 6+200 2 X 30 60 5.5 2 x 13.4m End of Bypass
Vijayawada Gundugolanu Section
6 1022+930 20+30+20 70 5.5 2 x 13.4m Gundugolanu
*: The total width excludes the clear gap between two super structures, which will be dictated by
the roadway alignment.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-15 0
Minimum
S. Chainag Span Total
Vertical Remark
No e km arrangement width* (m)
Clearance (m)
Vijayawada Bypass
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-16 0
Minimum
S. Chainage Span Total width*
Vertical Remarks
No km arrangement (m)
Clearance (m)
Vijayawada Bypass
1 12+305 1x12 5.5 2 x 12 Mandadam Road
2 31+190 1x12 5.5 2 x 12 Nunna Road
3 43+380 1x12 5.5 2 x 12 Agiripalli Road
Hanuman Junction Bypass
*: The total width excludes the clear gap between two super structures, which will be dictated by
the roadway alignment.
Proposed Span
Total
S.No Chainage arrangement Type of Structure SIDE
Width*
Nos x length (m)
1 3+360 1x31 PSC T girder and slab Both LHS & RHS 2x12
2 5+840 2x5x3 R.C.C Box cell Both LHS & RHS 2x12
3 8+210 2x26 PSC T girder and slab Both LHS & RHS 2x12
4 9+560 1x5x3 R.C.C Box cell Both LHS & RHS 2x12
5 10+450 1x4x2 R.C.C Box cell Both LHS & RHS 2x12
6 10+980 1x5x2 R.C.C Box cell Both LHS & RHS 2x12
7 13+020 2x4x2 R.C.C Box cell Both LHS & RHS 2x12
8 19+305 2x4x2 R.C.C Box cell Both LHS & RHS 2x12
R.C.C T-girder and
9 21+240 1x20 Both LHS & RHS 2x12
slab
10 22+035 1x5x3 R.C.C Box cell Both LHS & RHS 2x12
11 22+815 2x4x2 R.C.C Box cell Both LHS & RHS 2x12
R.C.C T-girder and
12 23+350 2x19 Both LHS & RHS 2x12
slab
13 24+350 2x5x2 R.C.C Box cell Both LHS & RHS 2x12
14 24+850 2x4x2 R.C.C Box cell Both LHS & RHS 2x12
15 26+350 1x5x3 R.C.C Box cell Both LHS & RHS 2x12
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-17 0
Proposed Span
Total
S.No Chainage arrangement Type of Structure SIDE
Width*
Nos x length (m)
16 29+340 1x25 PSC T girder and slab Both LHS & RHS 2x12
17 30+565 1x10 R.C.C Solid slab Both LHS & RHS 2x12
18 33+250 1x28 PSC T girder and slab Both LHS & RHS 2x12
19 33+715 2x4x2 R.C.C Box cell Both LHS & RHS 2x12
20 34+250 1x12 R.C.C Solid slab Both LHS & RHS 2x12
21 35+250 1x6x2 R.C.C Box cell Both LHS & RHS 2x12
22 36+500 1x12 R.C.C Solid slab Both LHS & RHS 2x12
23 40+900 1x10 R.C.C Solid slab Both LHS & RHS 2x12
24 42+690 1x5x2 R.C.C Box cell Both LHS & RHS 2x12
25 43+880 1x5x2 R.C.C Box cell Both LHS & RHS 2x12
26 44+690 1x25 PSC T girder and slab Both LHS & RHS 2x12
27 44+950 2x4x2 R.C.C Box cell Both LHS & RHS 2x12
Proposed Span
Total
S.No Chainage arrangement Type of Structure SIDE
Width*
Nos x length (m)
1 2+750 1x7.5x3.5m RCC Box Cell Both LHS & RHS 2x15.20
RCC T girder and
2 5+391 2x16 Both LHS & RHS 2x15.20
slab
*: Total width excludes the clear gap between the two superstructures, which will be dictated by
roadway alignment.
Span
Structure Chainage Total Width
S. No Arrangement Remarks
No Km (m)
(m)
MNB No:
1 1075+820 3 x 4.45 8.70 LHS & RHS
29/2
MNB No:
2 1072+737 3x6.80 8.70 LHS & RHS
32/2
MNB No:
3 1068+844 3 x 6.75 8.70 LHS & RHS
36/1
MNB No:
4 1067.326 6x6.75 8.70 LHS & RHS
37/6
MNB No:
5 1065+780 3 x 5.75 8.70 LHS & RHS
39/2
MNB No:
6 1062+540 2x3.90 8.70 LHS & RHS
42/1
MNB No:
7 1055+743 8x5.75 8.70 LHS & RHS
49/1
MNB No:
8 1037+246 1 x 9.30 8.70 LHS & RHS
67/3
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-18 0
Span
Structure Chainage Total Width
S. No Arrangement Remarks
No Km (m)
(m)
MNB No:
9 1030+415 5 x 6.40 8.70 LHS
76/1
MNB No:
10 1022+851 2 x 7.20 8.70 LHS
#: The length of structures indicated is absolute minimum which is equal to the length of the
existing structure. The actual length required for the service road structure may vary.
Proposed Span
Total
S.No Chainage arrangement Type of Structure SIDE
Width
Nos x length (m)
1 22+815 2x4x2m R.C.C Box cell Both LHS & RHS 2x8.75 m
2 24+850 2x4x2m R.C.C Box cell Both LHS & RHS 2x8.75 m
3 40+900 1x10m R.C.C Solid slab Both LHS & RHS 2x8.75m
Name
Proposed Span Total Width
S. Chainage of Type of
Arrangement Side (m)
No (km) River / structure
nos x length(m)
stream
Chimala PSC T girder Both LHS &
1 43+250 2 x 30 m 2x8.70m
Vagu and slab RHS
Name
Proposed Span Total Width*
S. Chainage of Type of
Arrangement Side (m)
No (km) River / structure
nos x length(m)
stream
PSC T
Krishna 1x14(Underpass) Both LHS &
1 15+970 girder and 2x12m
River +101x30+1x40+2x30 RHS
slab
PSC T
Chimala Both LHS & 2x12m
2 43+250 2x30 girder and
Vagu RHS
slab
*: Total width excludes the clear gap between the two superstructures, which will be dictated by
roadway alignment.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-19 0
Proposed Span
Total
S.No Chainage Arrangement Type of Structure
Width**
nos x length(m)
1 2+500 1x20+(3x24)*+1x20 R.C.C T-girder & slab and steel composite 2x12m
2 20+590 8x30+(3x24)*+8x30 P.S.C T-girder & slab and steel composite 2x12m
3 45+870 7x30+(1x24+1x30+1x24)+3x30 P.S.C T-girder & slab and steel composite 2x12m
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-20 0
** Total width of culvert shall match with the total width of approaches / highway including
earthen shoulders.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada-Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 13-21 0
** Total width of culvert shall match with the total width service road including earthen shoulders.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 14-1 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 14-2 0
There is no existing highway traffic management system. The O&M Contract is presently undertaken,
however these do not include any HTMS.
A full system needs to be provided [and fully maintained for the life of the concession agreement],
and the requirements for this Highway Traffic Management System shall be given in the Manual for 6
laning.
Real time 3-way communication system between data source-control center-data sources &
display units
Highway Patrol
Lighting System
The ATMS/HTMS system shall be as per the provisions of 6-Lane manual. In addition, a Backbone
Communication System, consisting of Optical Fibre backbone cable running along the project
highway, is needed to join all the above together.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 15-1 0
15.1 GENERAL..................................................................................................................................................2
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 15-2 0
15.1 GENERAL
The requirement for User Facilities and Wayside Amenities has to be in accordance with the
provision of guidelines of IRC SP: 87-2010. The important facilities like underpasses for vehicle
crossings, flyovers etc are mentioned in chapters-13 of this report, and in chapter 16. The specific
area of Amenity Areas and Parking Areas proposed along the project highway are covered hereafter.
For the road user, wayside amenities such as drinking water, telephone booths, bus shelters and
road side rest areas are of value. The industrialisation and socio-economic development has
increased the use of telephones. Telephone booths are often available in urban areas but their
provision along highway would also be beneficial. Road side rest areas are essential for long
distance road travellers of main highway. Long distance journeys cause driver fatigue resulting in
poor driving and increase in driver reaction time. In India such services are starting to be provided
but more are needed. To promote safer driving, drivers should be encouraged to have adequate rest
when they feel tired. The provision of rest areas which are conveniently located and are economical
and easy to maintain will help achieve this.
The general guidelines which shall be considered in the planning and designing of a wayside amenity
can be broadly as follow;
i. The facilities are to be provided along highway where these do not exist at present or lacking
ii. Easy availability of the required land for infrastructure development should be kept in view
iii. Site should be away from urban influence and any other similar wayside complex
iv. Feasibility of locating the facility close to scenic/historic/tourist spots should be kept in view
v. Desirably the site should be about 200m away from a road junction
vi. The road alignment should preferably have easy gradients in the vicinity of the complex
vii. Availability of infrastructure facilities like electricity, drinking water and drainage etc. near the
site should be duly considered
viii. From environmental considerations, the facility should create minimum disturbance to the
surroundings
ix. Availability of any existing petrol/repair/spare parts facilities near the proposed locations
should also be kept in view
x. The wayside amenity should be so planned as to allow phased development, subject to the
minimum stipulated scale of facilities being provided in the first instance
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 15-3 0
The Project Highway shall have rest areas as specified in Schedule C and be provided with facilities
for the users so as to provide safe and comfortable journey. For this purpose, rest areas shall be
planned with composite facilities for long distance travellers through personal cars, buses and goods
vehicles. Due consideration shall be given to the requirements of different classes of road users
including truck drivers.
Wherever some eateries or informal rest areas exist and cannot be relocated or accommodated
within the planned rest area, they would be separated from the main highway with separation-island
along with safe entry and exit with signs and markings.
Project Highway shall have Rest Area(s) planned such that they are spaced at the intervals of 90
minutes to one hour of driving time between two important cities/towns. They would not be located
between 5 km of a town or city or near interchange where entrance and exit ramps could cause
weaving conflict.
Rest areas shall be planned to cater for traffic moving in both directions such that there is no need for
the vehicles on one carriageway to cross over to the other carriageway. The entry to this Rest
Area(s) would be through deceleration lane and exit through acceleration lane. The minimum width of
these lanes shall be 5.5 m.
Rest Area(s) shall be designed for the expected peak hour long term clientage and shall provide
facilities for parking, restaurant, cafeteria, toilets, telephone and shops for selling items normally
required for traveling, fuel and garage for minor repair, telephone, first aid. The parking should
include parking for expected peak hour truck traffic and cafeteria suitable for fulfilling the need for
Indian truck drivers and shall be paved by CC blocks strong enough to withstand expected loadings.
The whole area shall be elaborately landscaped to provide a pleasing environment.
At locations along the Project Highway where some existing eateries (Dhaba) or other informal rest
areas are located, concessionaire shall make every attempt to shift the business of such
establishments to the identified planned rest area location(s) failing which a safe entry and exit to
these establishment and parking spaces for expected peak hour vehicles shall be provided with
proper signs and markings.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 15-4 0
To meet the requirements [90km spacing approximately] we required wayside amenities maximum at
two locations;
1. At KM 1023+080(Gundugolanu)
However keeping in view of the adjacent sections of NH-5 (the Project Highway) in which there could
be already these facilities exists or being proposed in NHDP projects, it is recommended to propose
these wayside amenities in integration with nearest available facility by the concessionaire after the
detailed designs.
The suggestive layout (extract from the six-laning Manual) of the comprehensive wayside amenity is
given in the Figure below.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 16-1 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 16-2 0
The Project road facility along the proposed 6 lane highway is proposed to meet the requirement of
Manual of Specifications and Standards for Six Laning of National Highways through Public Private
Partnership. The major project facilities are shall include:
Bus Shelters
Street lighting
Highway lighting
Pedestrian Guard Railing
Safety Barrier
Traffic Signs and road marking
Hectometre/ Kilometre / Boundary Stone
The Rest areas, Toll plazas, ATMS and other user facilities are described in Chapter 14, 15 and 16
respectively.
The project highway has the regular movement of the government and private buses. There are
about 80 numbers of existing bus ways and bus shelters on the existing 4 lane highway. The new
bus shelters have been provided for the convenience of bus commuters and safe and unimpeded
travel on main carriageway. The new bus shelters have been provided on the proposed service road
at the following locations, governing by site conditions, which will be decided during the detailed
designs by the concessionaire.
Name of
Existing Existing Chainage(LHS) Existing Chainage(RHS) Total
Amenity
1075+020,1065+400,1051+950, 1074+950,1065+500,1052+130,
Bus-Stop 1051+400 1050+280 8
Street lighting exists on the following sections [generally town section, or toll plazas. Most of this
lighting will require removal/replacement or upgrading [and thereafter maintaining and power
provision at night]. Virtually no junctions, other than in some urban areas, have lighting currently
provided.
Existing Lighting Locations
From Km post To Km post Location
1072+530 1072+630 Toll Plaza
1050+670 1050+770 Toll Plaza
The street light and high mast light system have to provide in accordance with the manual provisions.
Tentatively the street light has been proposed along the town/ villages for safe movement of traffic on
the service road. The village/urban locations where street light is to be provided are given below.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 16-3 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 16-4 0
The proper lighting has been proposed at all Pedestrian Subway & Underpass, Vehicular
Underpasses.
The all entry exit ramps along the project highway should be properly lighted. The lighting system
has been proposed at all the bus shelters and the rest area.
The High mast lighting has been proposed at the following location along the project highway:
Toll plaza Location
o Kalaparru (KM 1050+720)
Flyover locations
o Gundugolanu ( KM 1022+930)
On the proposed bypasses Provide High mast lighting at locations specified below .
S. No Chainage, Km Location
Vijayawada Bypass
1 0+795 Start of Bypass Jn.
2 11+500 Toll Plaza Vijayawada Bypass Section 1
3 18+740 At NH 9 flyover/Grade separator
4 35+000 Toll Plaza Vijayawada Bypass Section 2
5 47+350 End of Bypass Jn.
Hanuman Junction Bypass
6 1+100 Start of Bypass Jn.
7 6+000 End of Bypass Jn.
The pedestrian guard railing between the service road and the main carriageway has to be provided
along the urban sections and the villages/towns area along the project highway for the safe
movement of the pedestrian traffic. The railing is not required along the length of villages where the
underpasses have been proposed.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 16-5 0
The pedestrian guard rails has to be provided between the nearest at grade junction and the bus
stop for the safe movement of the pedestrian traffic.
The W beam/ concrete safety barrier has been proposed along the project highway at following
locations:
Where the embankment height is 3m or more
Where the embankment is retained by retaining structure
Where the median is less than 4.5m
Both side approach for the Minor & Major Bridges
At sharp horizontal curves locations
The gantry sign mounted on post indicating the village name and the important road it would lead to
at all exit locations. The position of these signs should meet the requirement of the IRC 67.
The pavement marking along the project highway should meet the requirement of the IRC 35. The
proper zebra marking has been proposed at the Underpass locations for safe crossing of the
pedestrian traffic. The safety features such as delineators, cats eyes, hazard markers and safety
barrier at hazardous locations has been proposed on the project highway.
The Truck Lay byes & Rest areas have to be provided at the locations given below.
The hectometre/ Kilometre and Boundary stones have been proposed as per the requirement of the
six laning manual.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 17-1 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 17-2 0
17.1 INTRODUCTION
The scheme is the 96% widening of the existing road from 4 to 6 lanes, excluding a section of
about few km through ROB and Canal Bridges for a length of about 8km.
Service Roads: Provide 5.5m service road in rural areas for about 73.318 aggregate
kilometres and
Widening of ROB & Grade Separated Structures: Improvement and widening of 2 ROBs
and 10 Underpasses/Cattle crossings.
6 Flyovers
13 Pedestrian Underpasses
10 Vehicular Underpasses
Intersections: Improvement of 4 minor intersections of village access.
Lay Bays and Amenities: Provide 8 bus bays with shelter on service road wherever
applicable, 2 truck lay bays, 1 rest areas and 3 toll plazas with base camps.
Others: Provide Highway Traffic Management System, User Facilities, Roadside Furniture
and safety features, localised lighting.
The current right-of-way is insufficient for all this expansion, so some very significant land
acquisition [and property acquisition/demolition] is needed in towns [and some villages| However
where 4 lane continuous viaducts are proposed landtake [along with the accompanying very large
property demolition requirements] will be either eliminated or very much minimised
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 17-3 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 17-4 0
The scheme is proposed to widen the existing 4 lane road to 6 lane divided carriageway facility with
paved shoulder and service road. Table 17.2.2 and Table 17.2.3 indicate the location of different
types of road cross sections.
Table 17.2.2: Type of Road Cross Sections along the Project Highway
Chainage(km) Chainage(km)
S. Length CS S. Length CS
No From To (km) Type No From To (km) Type
Start of Vijayawada Bypass 31 40+849 41+384 0.535 2
1 0+000 0+100 0.100 1 32 41+384 43+067 1.684 1
2 0+100 0+491 0.391 1 33 43+067 43+732 0.664 2
3 0+491 1+190 0.699 2 34 43+732 45+687 1.955 1
4 1+190 2+444 1.254 1 35 45+687 46+059 0.372 3
5 2+444 2+556 0.112 3 36 46+059 47+017 0.958 1
6 2+556 3+736 1.180 1 37 47+017 47+742 0.725 2
7 3+736 4+248 0.512 2 38 47+742 47+780 0.038 1
8 4+248 11+200 6.952 1 39 47+780 47+880 0.100 1
9 11+200 11+800 0.600 9 End of Vijayawada Bypass
10 11+800 11+961 0.161 1 40 1076+480 1075+400 1.080 5
11 11+961 12+681 0.720 2 41 1075+400 1074+800 0.600 8
12 12+681 14+153 1.472 1 42 1074+800 1073+905 0.895 4A
13 14+153 17+770 3.617 3 43 1073+905 1073+505 0.400 8
14 17+770 18+316 0.546 1 44 1073+505 1072+980 0.525 5
15 18+316 19+169 0.853 2 45 1072+980 1071+844 1.136 4A
16 19+169 20+314 1.145 1 46 1071+844 1071+244 0.600 8
17 20+314 20+866 0.552 3 47 1071+244 1069+155 2.089 4A
18 20+866 22+574 1.708 1 48 1069+155 1068+755 0.400 8
19 22+574 23+047 0.472 2 49 1068+755 1068+120 0.635 5
20 23+047 24+463 1.416 1 50 1068+120 1067+720 0.400 8
21 24+463 24+955 0.492 2 51 1067+720 1066+380 1.340 4A
22 24+955 30+831 5.876 1 52 1066+380 1065+980 0.400 8
23 30+831 31+590 0.759 2 53 1065+980 1065+460 0.520 5
24 31+590 34+700 3.110 1 54 1065+460 1065+060 0.400 8
25 34+700 35+300 0.600 9 55 1065+060 1064+070 0.990 4A
26 35+300 35+703 0.403 1 56 1064+070 1063+470 0.600 8
27 35+703 36+199 0.496 2 57 1063+470 1060+800 2.670 4A
28 36+199 39+827 3.628 1 Start of Hanuman Junction Bypass
29 39+827 40+275 0.448 2 58 0+000 0+750 0.750 4
30 40+275 40+849 0.573 1 59 0+750 1+450 0.700 8
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 17-5 0
Chainage(km) Chainage(km)
S. Length CS S. Length CS
No From To (km) Type No From To (km) Type
60 1+450 2+642 1.192 4 80 1046.060 1042.450 3.610 4
61 2+642 3+350 0.708 8 81 1042.450 1041.850 0.600 5
62 3+350 3+700 0.350 4 82 1041.850 1040.300 1.550 4
63 3+700 4+300 0.600 4 83 1040.300 1039.630 0.670 5
64 4+300 5+650 1.350 4 84 1039.630 1039.180 0.450 4
65 5+650 6+350 0.700 8 85 1039.180 1038.530 0.650 5
66 6+350 6+717 0.367 4A 86 1038.530 1037.080 1.450 4
End of Hanuman Junction Bypass 87 1037.080 1036.080 1.000 5
67 1055.650 1055.105 0.545 4A 88 1036.080 1033.910 2.170 4
68 1055.105 1054.510 0.595 5 89 1033.910 1033.310 0.600 8
69 1054.510 1054.110 0.400 8 90 1033.310 1030.530 2.780 6
70 1054.110 1053.980 0.130 5 91 1030.530 1029.930 0.600 8
71 1053.980 1052.140 1.840 4A 92 1029.930 1027.487 2.443 6
72 1052.140 1051.740 0.400 8 93 1027.487 1027.080 0.407 7
73 1051.740 1051.080 0.660 4A 94 1027.080 1024.905 2.175 6
74 1051.080 1050.480 0.600 9 95 1024.905 1024.255 0.650 4
75 1050.480 1049.980 0.500 8 96 1024.255 1023.280 0.975 6
76 1049.980 1047.580 2.400 4 97 1023.280 1022.480 0.800 8
77 1047.580 1046.980 0.600 5 103.59
Total length km
78 1046.980 1046.660 0.320 4
79 1046.660 1046.060 0.600 5
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 17-6 0
6 Rural Six-lane cross section with retaining wall(s) at Canal locations where the existing median is 2.5m; Symmetrical widening. 8.373
7 Rural Six-lane cross section at Canal locations where the existing median of 2.5m to replace by crash barrier in Asymmetrical widening. 0.407
Six-lane Flyover/Underpass Approach cross section with 13.4m deck width with RE wall/RCC Retaining wall (excluding viaduct
8 portion) up to carriageway top level over which RCC crash barrier shall rest + 1.5m wide separator cum RCC lined cover drain between 9.208
Approach and 5.5m wide (excluding shyness) service road both side + 1.5m wide footpath cum utility duct both side after service road
9 Toll Plaza Locations 1.800
Total 103.59 km
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 17-7 0
The scheme for service roads is tabled in Table 17.3.1. Requirements are shown for both the left and
right of the existing road. The provisions of these service roads means new bridges [or underpasses]
are needed:
As crossing structures under the 6 lane carriageway [to link the LHS and RHS service roads
[see Table 17.3.2]
As crossing structures over the 6 lane carriageway [flyovers, footbridges], also see Table
17.3.2;
As structures on the service roads where drainage channels are crossed [i.e. matching the
drainage provisions on the 6 lane mainline] see Table 17.3.3.
Where crossing structures [and flyovers] are provided in some cases existing bridge decks need to
be raised [since the provision of each crossing structure means several hundred metres of existing
mainline roadway has to be re-profiled as approximately table in next page [exact details are subject
to detail design by the Concessionaire]. The amount of re-profiling is determined by the rise in
pavement level needed at the crossing location [this is a function of clearance provision, structural
height of roof of superstructure, and amount if any the crossing level of the structure can be
below the main road level]. Details in respect of the major bridges are described in Chapter 13
[section 13.5].
Details on the required removal of existing bridge defects, to be carried out by the Concession
Company, is given in Section 13.3. The scheme includes making most bridges on the road 6 lanes
[or equivalent of 6 lanes]. As most of the major bridges are 2 lanes in width [each way] and cannot be
widened the assumption used is most of the major bridges are retained unless there is a structural
problem already.
Table showing length of road to be realigned due to local rise of vertical profile [at underpass]
for installation of underpasses for cross access (Grades Table as per IRC)
Design Speed 100 Design Speed 80
Rise
Grade % Length Grade % Length
1 0.932 215 1.314 152
1.5 1.142 263 1.610 186
2 1.318 303 1.859 215
2.5 1.474 339 2.078 241
3 1.614 372 2.276 264
3.5 1.744 401 2.459 285
4 1.864 429 2.628 304
4.5 1.977 455 2.788 323
5 2.084 480 2.939 340
5.5 2.186 503 3.082 357
6 2.283 526 3.219 373
6.5 2.376 547 3.351 388
7 2.466 568 3.477 403
7.5 2.553 588 3.599 417
8 2.636 607 3.717 430
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 17-8 0
Table 17.3.2: Location of New Grade Separation Structures on the Mainline [6 laning section]
all structures 6 Lane [except where specifically stated]
S. Chainage Span Effective length Vertical Total width*
Remark
No (km) arrangement (m) Clearance (m) (m)
1 1022+930 20+30+20 70 5.5 2 x 13.4 Gundugolanu
New Flyover for Vijayawada Bypass
2 0+790 2 X 30 60 5.5 2 x 12.0 Start of Bypass
3 18+740 2 X 30 60 5.5 2 x 12.0 NH 9
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 17-9 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 17-10 0
#: The length of structures indicated is absolute minimum which is equal to the length of the existing
structure. The actual length required for the service road structure may vary.
*: Deck Width indicated is absolute minimum width of Service Road including 0.25m edge shyness
on both sides, 1.8m Foot Path with railing and 0.5m Crash Barrier both sides.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 17-11 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 18-1 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 18-2 0
The requirements for Construction Planning, Management and Technology is given in the Manual of
Specifications and Standards for Six Laning of National Highways through Public Private Partnership published
by Department of Road Transport & Highways Ministry of Shipping, Road Transport & Highways, Government
of India. In case of any contradiction between the Manual and this Chapter, the text in the Manual
shall govern.
The existing 4 lane highway shall remain in operation and continue to be tolled during the course of
construction for expansion of its capacity to 6 lanes. This will put some constrains on construction
activities. Accordingly, the choice by the Concessionaire of construction planning methods,
construction management and technological solutions shall be subject to the following constraints.
(1) The existing 2-lane facility, for each direction shall always be available, along main highway
or along diversion and no reduction in the capacity of the highway during construction shall
be permitted.
(2) Construction shall not cause any deterioration in level of service more than what is expected
due to the nominal increase in traffic.
(3) Since construction and operation shall be concurrent activities, construction shall not in any
way adversely affect safe and efficient operation of the highway.
(4) The construction of additional features (such as underpasses, service roads) may adversely
impact the lives and business activities of the people living close to the highway boundary.
Their safety and access needs during construction shall not be compromised.
(5) Construction traffic using the highway for approaching the construction site and parking of
construction vehicles on the highway will adversely affect the flow of normal highway traffic.
Therefore, the construction vehicles shall approach the construction site from an alternative
approach (say from service road or temporary haul roads) and park outside the existing
carriageway.
(6) No road space shall be used for erection of temporary works or erection and launching of
any overhead structural component for permanent work. All such erection and launching
shall be from near the edge of the ROW.
(7) Safety of the highway traffic during construction shall not be compromised and therefore, full
safety measures shall be taken during construction.
(8) No part of the existing carriageway shall be closed for facilitating construction without
creating equivalent road space. In case it is absolutely necessary to partially close the
carriageway, it shall be for a reasonable period to be decided by the Independent Engineer.
The most essential element of construction planning shall be to ensure that equivalent capacity is
created before closing any portion of the highway for construction. This can be done either by
constructing independent diversion (which can eventually serve as service road) or by constructing
temporary diversion by carving out road space from the existing central median.
Diversion roads shall have the same width as that of the carriageway being diverted so as to ensure
that capacity of the highway or the level of service is not reduced due to construction. It shall have
fluent geometry conforming to design speed of at least 60 kmph. The pavement shall be designed for
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 18-3 0
10 MSA. The diversion road shall be so planned with respect to alignment and grade that it can be
eventually used as a service road. Usually, the width of one side carriageway of the existing 4 lane
highway is 8.75m while that of the diversion road shall be 7.0m. The extra paved width of 1.75m that
will become available on the service road shall be at the cost of the concessionaire and will be
utilised for meeting local needs (e.g. for parking, passing places, etc.). Once the work on main
carriageway is completed and the use of the diversion road is not required, the entry to and exit from
the diversion road shall be permanently closed such that they are not used as unauthorised entry/exit
ramps.
In case space on the existing carriageway is to be created for use as diversion, it shall be done by
knocking off the central median, removing the filling and paving the median portion with crushed
stone drainage layer over the existing GSB sub base top level followed by WMM base bituminous
layer in thickness appropriate for traffic level of 10MSA. The knocked off median shall be replaced by
pre cast concrete crash barrier segments placed at the edge of the extended pavement and tied
together to provide stability against crash. This arrangement can provide only one extra lane of
diversion in the usual case where median width is only 4.5m.
Eventually the median has to be restored to its original condition by milling the pavement and
removing the bituminous layers and WMM base and leaving the GSB layer intact for median
drainage. The restored median kerb, however, shall extend up to the top of the drainage layer of the
existing pavement such that water in the median remains confined within the kerbs and drain through
the drainage layer. The milled pavement material can be used for service road construction with the
approval of Independent Engineer.
Construction shall be managed in such a way that sequence of construction operations, coordination
of various construction activities, logistics of material and equipment movement, community needs of
access and safety, and management of the highway traffic during construction lead to least
disruption during construction. Construction activities shall generally start at the periphery and
proceed towards the main highway in the end such that diversion alternatives are available when the
main highway becomes the centre of construction activities.
Subject to actual site requirement, the general sequence of construction activities shall be in the
following order:
I. Construction of haul roads
II. Construction of drains, toe walls
III. Construction of service roads, protection of cut slopes abutting properties (wherever
required)
IV. Construction of underpasses
V. Construction of embankment for widening of the carriageway up to sub grade level
VI. Barricading of the main carriageway at the shoulder marking
VII. Excavation of the earthen shoulder of the existing carriageway
VIII. Building of pavement layers
IX. Construction of bridges, culverts, flyovers, grade separators at various points of time as per
overall planning
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 18-4 0
Appropriate technological solutions shall be adopted to overcome some of the site constraints and to
ensure least disruption due to construction, as conventional technology in such cases may be unsafe
or disruptive. Some of the areas where innovations shall be required are shoring the cut slopes so
that adjoining properties are not endangered, pushing a box to provide an underpass, launching
large pre-cast elements for grade separators, underpasses, etc.
Shoring the cut slopes: Appropriate solutions shall be designed for permanent solution of the cut
slopes. Soil nailing, concrete buttresses, sheet piling or any other solution adequately designed and
approved by Independent Engineer shall be adopted.
1
Box pushing for construction of underpasses :
i) Adequate space for construction of casting and thrust beds shall be arranged
ii) Construction of thrust beds will involve deep excavation. The excavated face shall invariably
be shored/protected. Where such excavation is near some properties, it shall be ensured
that these properties do not suffer any damage.
iii) Top of the excavation shall invariably be cordoned/fenced to rule out any mishaps or
accident.
iv) The rate of construction (pushing) shall be regulated is a manner that the existing road on
top does not get damaged.
vi) After construction is completed, the thrust bed shall be back filled and compacted in layers to
its original density.
The excavation shall be done in a safe slope. Back filling the excavation after completion of
construction shall be done with selected soil and filter media and suitable drainage arrangement shall
be made for dissipating hydrostatic pressure.
Where pre cast segments are to be launched in position, the transporting, lifting and launching shall
be done from the haul roads/ service roads,
Grade separators/flyover shall be constructed in such a way that there is no need for erecting staging
from the road level and pre cast superstructure is launched in position without causing any significant
[or long term] interference with the highway traffic.
1
Actually there are very few if any places where on inspection this seems a practical construction method, but
this situation may change in detail design.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 19-1 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 19-2 0
19.1.1 Introduction
The preliminary Environmental Examination for the proposed project has been undertaken as a
parallel exercise with the Engineering Analysis, so as to bring out the environmental concerns in
planning and the proposed design. The basic aim of the present study is to assess the magnitude of
actual and potential environmental concerns due to conversion of the existing 4 lane National
Highways into six lanes. This is also to ensure that the environmental considerations are given due
weightage, in the design of proposed highway improvements being studied. Basic idea is to minimize
adverse environmental and social impacts with best possible engineering solutions at the optimal
cost to make development environmentally sound and sustainable.
Environmental Screening of the study area has the following major objectives:
The total length of the existing road under consideration is 48.99 km, which starts from Vijayawada
and traverses through towns of Gannavaram (houses airport for Vijayawada), Hanuman Junction and
Eluru. The project road passes through three districts i.e. Krishna, West Godavari and East Godavari
of Andhra Pradesh State. The area of direct influence will be confined in a linear fashion along the
corridor where the construction activities take place. The road is proposed to be retrofitted into six-
lane for which ROW supposedly, is available and only at places a ROW of 5 meters may be required
for acquisition. Therefore, the area of direct influence of 10 meters on either side has been
considered.
However, for various other environmental Components, which are likely to have a broader area of
influence, a distance of 10 Km. on either side of the road (as per the MOEF Notification of
Environmental Impact assessment, Government of India, 2006) has been used to define the indirect
area of Influence. Thus, the term project influence area referred in this chapter therefore, covers
both direct and indirect area of influence.
The Environmental Screening Report is based on field surveys and investigations made during site
visit, and include information depicting the existing environment characteristics as well as an
assessment of potential impact on the physical and natural environment of the area.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 19-3 0
Secondary Data
Secondary information on various environmental components such as physiography, soil, geology,
drainage, forest, ambient air quality, land-use, demography etc. have been collected from old reports
& various published sources to examine the baseline status of the environmental features in the
project influence area,
Local Concerns
In addition to the secondary data collected and the inventory information obtained, discussions with
the stakeholders including the local people and government officials have been held so as to provide
a realistic assessment of any significant/specific socio-environmental concerns due to proposed
project. These discussions helped in incorporating the views of the stakeholders.
Physical Resources
Topography
The configuration of the project area is more or less plain and lies in coastal Andhra Pradesh. The
area is crisscrossed with river Krishna river Godavari and network of various irrigation canals built on
the two rivers.
Situation
This section of project road passes through districts of Guntur, Krishna, W.Godavari and E. Godavari
in the State of Andhra Pradesh. The highway generally traverses through the agricultural zones, and
in the end passes for a short distance, close to Divencheruvu Reserve forest. The existing four lane
development itself is not witnessing designed traffic growths owing to the project highway, as per
discussions with stakeholders and the Engineering team, lying in agricultural hinterland with no major
commercial activity beyond the agricultural. This results in good environmental condition with air,
water & noise levels lying generally within limits. But, the situation may change with time
necessitating regular monitoring of the environmental parameters along the highway and especially
the towns by NHAI/Concessionaire, so that mitigation measures could be enforced in the event of air,
water, noise levels cross permissible levels
Geology, Soils
The vast stretch of the area is represented by Archaeans.The major geological formation in the area
are of Khondalites series with felspar-quartz-biotite genesis, felspar-quartz genesis. These are pre-
1
Source:Baseline Environmental status, vol.- IV EIA, RAP REPORT; ROAD CONSTRUCTION CONTRACT
PACKAGE AP-17
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 19-4 0
cambrian series and are coarse grained rocks and stretched from NE to SW with steep dips. The
general stratography of the area is presented in the following table:
Geology
Formation Age
Soils
The soil in the stretch is mainly red soil with texture sandy to silty clayey. The soils are mostly alluvial
derived soils. These are the soils in general with low to medium plasticity except at few locations with
high plastic clayey soils (black cotton). The soils lack adequate drainage and lead to deterioration in
the soil structure. The soils in general are fertile.
Climate
Rainfall The climate of the study area is tropical sub humid with annual precipitation ranging from
1400 - 1600 mm and potential evapo-transpiration varying from 1300-1500 mm. The rainfall in the
area is brought by two spells i.e. South-West monsoon (June-September) and North- East monsoon
(October to November)
Temperature The temperature of the region varies between 36-18 C. It is very warm in May with
a mean maximum temperature touching to 39 C. The seasonal variation in the temperature is
presented in the following table
Humidity - The climate in the region is generally sub-humid. The humidity is slightly less than the
adjacent coastal areas. The relative humidity ranges, generally, at 90 in the morning and 50 in the
evening.
Wind Speed and Direction - Winds are light to moderates in speed, except the gales blow during a
depression or a storm. The winds in the area in general are South-west during the monsoon season
and also in the month of November. While during October and February, winds are Northerly or
north-easterly in the mornings. And, in the afternoons mostly they are northerly or north-east and
south-east directions. In the summer season, winds blow commonly between south-east and south-
west.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 19-5 0
turmeric, carrot, paddy, black gram, green gram, wheat, groundnut, jowar, bajra and maize. The main
cash crops are sugarcane, chillies, cotton, coconut, tobacco etc.
Water Resources
The project Highway lies in the catchments of River Krishna & River Godavari which are the two
major rivers of this region. The waters of both Rivers Krishna and Godavari are believed to be sacred
and holy. The characteristic feature of the Godavari river catchment is formation of islands (Lanka).
The ground water table varies from 8m to 80m in the project area. Wells, hand pumps and water
supply through pipelines are the main sources of the drinking water whereas water from irrigation
canals is used for agricultural purpose.
Water Quality
Water quality along the road is good as reported by the local communities. There are no major
pollution sources in the area. However, the water sources, where construction activity is proposed,
should be monitored after the detail designing is done, during construction and operation, to
contain/mitigate any probable pollution.
Air Quality
Ambient air quality of the area lies within permissible limits as per the discussion with the State
Pollution Control Board personnels owing to the highway passing through agricultural hinterland and
the traffic volumes being lesser than the designed. The concessionaire should monitor the air quality
in consultation with the, Regional office of the State Pollution Control Board, so that appropriate
mitigation measures may be adopted if the air quality exceeds the permissible limits of CPCB (Table)
to minimize the adverse effects on the environment.
Respirable
50 g/m 120 g/m 60 g/m
Respirable 3 3 3
Annual *
Particulate particulate
Matter (RPM)
size less than
75 g/m 150 g/m 100 g/m
3 3 3
10 m 24 hours** Matter sampler
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 19-6 0
Time Residential,
Sensitive Industrial Method of
weighted Rural &
Pollutant Area Area Measurement
Average Other Areas
AAS Method after
0.50 g/m 1.0 g/m 0.75 g/m
3 3 3
Annual *
sampling using
Lead (Pb) EPM 2000 or
0.75 g/m 1.5 g/m 1.00 g/m
3 3 3
24 hours** equivalent filter
paper
3 3 3 Non-dispersive
8 hours** 1.0 mg/m 5.0 mg/m 2.0 mg/m
Carbon infrared
Monoxide (CO) 3 3 3
Spectroscopy
1 hour 2.0 mg/m 10.0 mg/m 4.0 mg/m
Noise Level
Since the traffic volume on the project road is not much and the highway is generally passing through
open and agricultural fields, noise is not a major problem at present. But, it may be an irritant in city
areas, in future, with the growth in traffic. Noise level monitoring should be carried out, by the
concessionaire during construction and operation, in city/built up areas so that proper mitigation
could be developed as and when the noise level exceeds the standards.
Industries
The sections of NH-5 passes, primarily, through agricultural area but there are, also, some medium
and small size industries. The area has cotton ginning/spinning mills, tobacco based industry, paper
mills, rice mills, saw mills, sugar mills etc. Vijayawada Thermal Power Plant is situated in the project
area.
Mines and Quarries
The project corridor has lime mining, Granite quarries and stone crushers.
Ecological Resources
Trees/Vegetation within corridor of impact
The road alignment passes primarily through rich agricultural fields. In the end of the section it
passes close to Devencheruvu reserve forests. Large number of trees / plants of various species
planted along the avenue and median exist within and outside the ROW. The Photo shows the
2
typical plantation along the project road. Ecological assessment indicates that approximately 14680
trees exist (on both sides of the road) within the R.O.W.
2
Source: Saplings planted in the avenue after construction of existing highway ,PIU NHAI, (Vijayawada, Rajahmundri)
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 19-7 0
Wildlife
The project highway does not pass through any ecologically sensitive area.
Social Forestry
The avenue and median plantations have been done under social forestry scheme along the highway
at various locations. Divisional Forest Office, Vijayawada, W. Godavari and E. Godavari have the
responsibility of maintenance of this plantation.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 19-8 0
The major land use pattern along the project road is agricultural, interspersed with small and
medium size industries cotton ginning/spinning, sugar mills, paper mills, rice mills, stone
crushers etc.
The quality of environmental parameters i.e. Air Quality, Water Quality and Noise levels is
good.
The noise level is expected to be high at town junctions during peak traffic.
River Krishna is the major rivers of South India, which cross the project road.
Vijayawada Thermal Power Plant is situated in the vicinity of project area, which is a major
source of electricity generation.
Large number of saplings which have been planted on the avenue i.e. 14680 approx. of
various species exists, which are likely to be impacted due to proposed expansion of the
project highway. The proposed development will result in removal of some of these
saplings/plants.
Town areas along the highway e.g. Hanuman junction at Km. 46.0 from Vijayawada, popular
for the shrine, poses a practical challenge for fitting in the extra lanes.
There are a number of religious structures, falling within the corridor of impact.
Potential Impacts
The main environmental impacts have been analyzed covering Environmental Resources, Human
Use Values and Ecological Resources. A brief description of these impacts is given herewith.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 19-9 0
Mitigation Measures
On the basis of information collected during Environment Screening Survey, the following mitigation
measures as given in the following Table have been proposed.
Environmental
Mitigation Measures Locations
Parameters
Air and Noise (i) By improving intersections; (ii) By removing At all towns e.g.
Quality traffic bottlenecks; (iii) By maintaining a steady Gannavaram, Vijayawada,
Improvements stream flow of traffic and by segregating slow Hanuman Junction
and fast moving traffic.
(ii) Noise barriers, if a section regularly, has Various town areas falling
parameters above permissible levels and on the project highway
plantation at sensitive areas
Drainage and Run (i). Provision of adequate size and number of All along the project road
off of Water cross-drainage structures to ensure efficient
cross- drainage
Contamination of (i) Construction work near water bodies will be At all water bodies
water quality avoided especially during monsoon periods
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 19-10 0
Environmental
Mitigation Measures Locations
Parameters
(ii) All waste arising due to project activities will
be disposed off, as per State Pollution Control
Board norms
Loss of Trees (i) Through proper design to minimize cutting
of trees.
(ii) Compensatory
Afforestation at a rate decided by the forest Trees which are going to be
department of the trees which are going to be felled.
cut.
Road Safety (i) Design improvement at crossings and where At congested locations.
Improvement traffic is mixing
(ii) Segregation of slow traffic in congested
areas by providing service roads
(iii) Provision of proper signage & proper
lighting arrangement to avoid accidents.
(iv) Traffic management plans will be prepared
for congested locations
Recommendations
On the basis of the field study conducted and data analysis from environmental point of view,
following points should be considered while finalizing the alignment / engineering design.
There does not seem to be any major environmental issue along NH-5
The traffic volumes are not high apparently bringing environmental parameters like air and
noise within permissible limits. But, with the proposed development it may become a cause
of concern in future. Thus, it is recommended that these parameters be monitored during
construction and operation so that a suitable mitigation be designed, if they rise beyond
permissible limits especially in towns.
The traffic junctions, along the highway, itself are having free access and is cause of concern
for the current traffic. Thus it is recommended to have suitable designs to improve safety.
The existing highway is passing through cities and towns with undersigned intersections
creating a hazardous situation in present low volume of traffic. Even in town/
villages/countryside there is a tendency to move in wrong lane which necessitates controlled
access and designed intersections for smooth and unhindered traffic movement.
There are number of shrines along the highway which pose a problem for the proposed
expansion. This problem of fitting in extra lanes is more pronounced in towns like Hanuman
Jn. This makes it pertinent to take up the project in phases removing such bottlenecks, while
the work is carried out on easier sections.
Clearance Requirements
th
The project can be undertaken, as per the Environmental Notification of 14 September
2006, after taking Prior Environmental Clearance from the concerned regulatory authority, in
the Ministry of Environment and Forests for matters falling under Category A in the
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 19-11 0
Schedule and at State level the State Environment Impact Assessment Authority (SEIAA) for
matters falling under Category B in the Schedule(Annexure 20.1), before any construction
work, or preparation of land by the project management except for securing the land, is
started on the project or activity.
The clearance from State Irrigation department will be required for shifting the canals along
the highway.
The existence of Vijayawada Thermal power Plant requires that use of fly ash in construction
in the radius of 100 Km (from the thermal power plant)
The proposed development along the existing highway with avenue plantation, all along,
warrants obtaining a clearance as per Andhra Pradesh (Protection of Trees and Timbers in
Public Premises) Rules 1989.
If any land is required to be acquired from the Divencheruvu reserved forest than also it can
be done by approaching the forest authorities at regional/Central level.
The NOC/ Certificate to erect & operate for siting labour camps, construction machinery will
be required from the State/Central Pollution Control Board.
Due to insufficient existing RoW in places where the currently proposed RoW is ranging between
54m in urban areas and 70m in rural areas, further acquisition is required for 6-laning of existing road
with service roads. In addition to this, new bypasses were proposed to Vijayawada city and Hanuman
Junction town where the entire project road passes through open agricultural and non-agricultural
fields owned by both private and Government (Revenue Department etc.), The estimated land
required for the widening of existing 4 lane road to 6 lane road and for laying of 4 lane new bypass
for Vijayawada city and 6 lane new bypass to Hanuman Junction town with other road safety
improvements such as creation of new underpasses, flyovers, etc is about 515.28 Ha.
The land required by the project for the construction of proposed new by-pass falls under two
classifications:
Public land owned by the State Government and administered by other departments
such as Revenue Department etc; and
Private land.
As per the preliminary assessment and base line verification survey, in about 60% of the cases the
project will require full demolishing or loss of residential or commercial structures to the extent that
either resettlement or relocation will be necessary. While in the remaining 40% of the structures
which are partially affected, in most cases only a narrow frontage strip of several meters or less will
be affected. Which thereby implies only compound wall or fences, yards, may be removed excluding
the areas where market centers are located. In market areas or where the concentrations of
residential structures are dense the requirement of resettlement and relocation options needs to be
adopted. In some cases, small portions of roadside dwellings and business will be affected. In
addition to the permanent structures a number of kiosks are also affected due to the project.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 19-12 0
The estimated number of structures identified and verified of which are affected completely or
partially is about 1114 structures. Of the total affected structures, 1024 are private (91.92%), 53 are
owned by the government (4.76%), and 37 structures (3.32%) are owned by the community in the
form of religious and other properties. Details are presented in below Table.
The estimated land requirements are resulting in complete or partial displacement of about 1024
private structures. Of the total affected structures, 506 are residential (49.41%), followed by 311
commercial (30.38%) and 44 are both residential and commercial (4.3%). A considerable number
163 (15.91%) of affected structures are found to be compound walls, bathrooms, basements, cattle
sheds, car parking sheds etc. Most of the commercial establishments are provisional (kirana) shops,
hotels, mechanic shops and few industrial units.
A total of 85 common properties are affected across the project road. Details of the usage of these
common properties such as religious places, government buildings of which a majority is bus
shelters/bus stands, are given in below Table.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 19-13 0
Of the total 1114 structures affected under both private and common property resources a majority
418 (37.52%) are Pucca, followed by 411 (36.89%) structures which are Semi-Pucca. The total area
affected by these 1114 structures is about 139384.27 square meters. Details are presented in Table
below.
Observed across the type and usage of the total affected structures, majority of the residential
(37.23%), and other structures (52.57%) including Community Property Resources are pucca in
nature. Whereas, regarding Commercial (42.48%) and Residential cum Commercial (54.55%)
structures are concerned majority of the affected structures are of Semi-Pucca in type. Details are
presented in below Table.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 19-14 0
(i.e.), the district collector and/or NHAI staff) through notification in the official gazette by the Central
Government.
Although NHAI Act significantly reduces the time frame for acquisition, the rules and principles of
compensation are derived from the LA Act of 1894 amended from time to time. The Act covers only
legal title holders and provides for: (i) market value of the land; (ii) a solatium of 30% on the market
value for compulsory acquisition; (iii) additional amount for trees, crops, houses or other immovable
properties; (iv) damage due to severing of land, residence, place of business; (v) compensation to
sharecroppers for loss of earning; and (vi) an interest of 12% on the market value from the date of
notification of award.
Both the LA Act and the NHAI Act do not address many of the social and economic issues
associated with displacement and resettlement of illegal or non-titled informal settlers/squatters.
However, in many donor-funded projects, NHAI assists affected persons even without any legal titles.
As presented in Chapters A and B, the impacts of the present project are also on the roadside
SBEs/households people who are non-titled informal dwellers and encroachers.
That project affected families (PAF) not only lose their lands, other assets and
livelihoods, they also experience adverse psychological and social/cultural
consequences;
That cash compensation alone is often inadequate to replace lost agricultural land,
homesteads and other resources. Landless labourers, forest dwellers, tenants, artisans
are not eligible for cash compensation;
The need to provide relief especially to the rural poor (with no assets), small and
marginal farmers, SCs/STs and women;
The importance of dialogue between PAFs and the administration responsible for
resettlement for smoother implementation of projects and R and R.
The policy is in the form of broad guidelines and executive instructions and will be applicable to
projects displacing 400 families or more in plain areas and 200 families or more in hilly areas.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 19-15 0
As far as the present project is concerned the NRRP states (Para 7.19) that in case of linear
acquisitions, in projects relating to railway lines, highways, transmission lines, laying of pipelines and
other such projects where in only a narrow stretch of land is acquired for the purpose of the project or
is utilized for right of way, each Khatedar in the affected family shall be offered by the requiring body
an ex-gratia payment of such amount as the appropriate Government may decide, but not less than
20,000 rupees, in addition to the compensation or any other benefits under the Act or programme or
scheme under which the land, house or other property is acquired. Further it says that if as a result of
such land acquisition, the land-holder becomes landless or is reduced to the status of a small or
marginal farmer, other rehabilitation and resettlement benefits available under the policy shall also
be extended to such affected family.
The benefits for PAFs who after land acquisition become landless or small or marginal farmer include
allotment of land extent of actual land loss subject to a maximum of one hectare of irrigated land or
two hectares of un-irrigated land or cultivable wasteland, if Government land is available in the
resettlement area and one-time financial assistance of Rs 15,000 and Rs 10,000 for land
development in case of allotment of waste land/degraded land and agricultural and respectively. If
the PAFs are not provided with alternative land they will be given rehabilitation grant equivalent to
750 days of minimum agricultural wages.
The benefits extended to the displaced families owning house include free house site to the extent of
actual loss but not more than 250 square meters in rural areas and 150 square meters in urban
areas. Other benefits such as shifting allowance, subsistence allowance and assistance for small
trader and artisan are also extended to the displaced families.
The policy does recognize some significant principles. It requires projects to (a) minimize
displacement and to identify non-displacing or least-displacing alternatives; (b) plan the resettlement
and rehabilitation of APs including special needs of tribals and vulnerable sections; (c) provide a
better standard of living to PAFs; and (d) facilitate harmonious relationships between the requiring
body and PAFs through mutual cooperation.
Minimization of Impact
Based on the impact on the properties and the land required and the consultations certain measures
are proposed to reduce and minimize the impact. Distinct design approach is adopted for open rural
areas. There are very few built up places at the starting point of the newly proposed bypass. So in
these locations the widening and approach to the bypass road may have to be restricted to reduce
the negative impact by constructing retaining/RE wall for identified underpasses etc. However, during
preparation of the detailed project report, due consideration needs to be given to minimizing negative
impacts within the limitations of technical requirements and cost effectiveness.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 19-16 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 2-1 0
Chapter 2: Contents
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 2-2 0
2.1.1 General
This section of National Highway No. 5 was widened over the period 1997 to 2004 from 2 to 4 lanes
[it had previously been 2 lanes in width for many years]. The majority of the widening was done on
line, but some new bypasses were created. Brief details are given below.
The existing road before taking up 4-laning works consist of 2-lane carriageway of width varying from
6.5 to 7m except for some isolated built-up section where the carriageway width varies from 10 to
14m. The existing pavement is of flexible type with thin bituminous surfacing at the top developed
since ages. The average pavement thickness is of the order 600mm. The project road over different
sections was strengthened and widened 20 years back. In recent past 1 complete new alignments
(Eluru bypass) were developed to 4-lane configuration.
The project road follows different chainage systems as it has developed under different contracts
over different periods. For easy reference the chainage equations over the entire project road section
is given in table 2.1.1.
Km 0+000 Km 47+880
(Existing NH-5 Chainage (Existing NH-5
47.88 Proposed Vijayawada Bypass
Km 422+800,New Ch Chainage Km
1112+044) 1076+480)
Gannavaram-Hanuman
Km 1076+480 Km 1060+800 15.68
Junction (Existing NH-5)
Km 6+720
Km 0+000
(Existing NH-5 Proposed Hanuman Junction
(Existing NH-5 Chainage 6.72
Chainage Km Bypass
Km 1060+800)
1055+650)
Hanuman Junction-
Km 1055+650 Km 1022+480 33.17
Gundugolanu (Existing NH-5)
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 2-3 0
Very important documents were then copied; less important documents were just listed and returned
to NHAI [where they are still available at NHAI if needed in the future concession company design
work].
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 20-1 0
20.1 GENERAL..................................................................................................................................................2
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 20-2 0
20.1 GENERAL
This section describes, at this feasibility stage, the method of costing and gives the cost estimates.
Cost estimation is an important component of the feasibility study as it provides vital input to financial
evaluation. The cost estimates have been prepared for widening the existing 4 lane divided
carriageway with 1.5m paved shoulder and 1m earthen shoulder into 6 lane divided carriageway with
1.5m paved shoulder and 2m earthen shoulder.
This includes overlay of 40mm by bituminous concrete on the existing pavement, widening of cross
drainage structures, providing service roads, longitudinal drains, road furniture, bus bays, Toll plaza,
Interchanges/Intersections etc.
20.2 QUANTIFICATION
The quantification of most of the items which are uniformly occurring are calculated on per Km basis,
derived from typical cross sections. The quantification of structures is based only on Square meters
of widening, re/new construction for each structure and lump sum provision for rehabilitation on
square meter basis.
The construction items covered in cost estimates are: site clearance, earthwork in case of widening
and raised pavement, Pavement in carriageways and shoulders, bridges and culverts, and
miscellaneous items such as side drains, road furniture, interchanges / intersections, bus bays, Toll
Plazas, HTMS and utility relocations etc.
The rate analysis for the Construction Items has been done based on standard data book published
by MORT & H and the basic rates are taken from Common Standard Schedule of Rates 2010-11,
Govt of Andhra Pradesh. The machinery rentals of 2001-2002 are considered from Standard Data
Book and Increased @5% per year to bring it to the current date.
The unit rates adopted in Preliminary Cost estimate are presented in Table 20.1
Rate:
S. No Items Description Unit Rs.
1 Clearing & Grubbing Ha. 42722
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 20-3 0
Rate:
S. No Items Description Unit Rs.
9 Dense Bituminous Macadam Cum. 6583
10 Bituminous Concrete Cum. 7313
11 Kerb Rm 219
12 Slab/Box Culvert Sqm 30000
13 Bridges Sqm 30000
14 Underpass Sqm 30000
15 Long viaduct Sqm 30000
16 Major Bridge Sqm 60000
17 ROB Sqm 40000
20.4.1 Road
The cost of the road portion has been worked out on a per km basis separately for widening and
overlaying of the existing road in rural and urban sections. This cost is based on typical cross
sections given in Drawings [and accompanying annex].
Escalation has been calculated on the assumption that the project duration is 30 months. Escalation
taken for the 1st year is 5%, second year 10% and third year 15%. The progress considered during
the first year is 20%, second year 40% and third year 40%.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 20-4 0
The overall construction cost of the Project works out to Rs. 1427 Crores.
Abstract of the cost for Vijayawada - Gundugolanu Sections including Vijayawada and Hanuman
Junction Bypass and Major Bridge on Krishna River) are tabulated below.
VIJAYAWADA
Bill GUNDUGOLANU
Description
No.
Amount (Rs .in figures )
2 Earthworks 1,352,686,776
8 Junctions 252,107,618
Micsellaneous works
12 Lightings Urban Areas, Major intersections, flyover and toll Plaza 163,199,999
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 20-5 0
17 Photographs 815,910
The Additional cost for pre-construction activities to be incurred by NHAI is as under (in Crores)
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 21-1 0
21.1 INTRODUCTION. 2
21.2 M AINTENANCE 2
21.2.1 Purpose and Scope................................................................................................................2
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 21-2 0
21. MAINTENANCE
21.1 INTRODUCTION
This Chapter outlines the normal Maintenance Requirements of a Highway [in Section 21.2] and
what should go into the Highway Maintenance Plan [that will have to be drawn up by the
Concessionaire], then mentions the additional requirements that pertain to a toll road [in Section
21.3].
Obviously the maintenance will be carried out by the Concessionaire, under the requirements of the
Concession Agreement.
Maintenance [if done fully and properly] generally [when averaged out] often represents about 2.5%
[annually, including labour, and all necessary works] of the value of the roads and bridges. Usually
the costs follow a rough cycle, annually lower when no major pavement or reconstruction works are
done on the highway (say years 1 to 4, 6 to 9 etc. when major overlays are done every 5 years or
so), then with major increases every time a pavement overlay is carried out (say every 5 years or
so). However this is not the only cost cycle, as over time one also has to consider maintenance [and
eventual replacement] of electrical [including lighting], toll collection, and communication equipment,
and then there are other cost cycles, some completely unpredictable like weather damage,
emergencies and the like, and some more predictable like replacement of road markings. Additionally
with a road of this length [183.7km] the cycle is not necessarily the same on every km section, so
figures tend to get more averaged [and also depend to some extent on the implementation schedule
of the 6 laning], rather than being relatively low 4 years out of 5 then with sharp peaks every 5 years
or so.
21.2 MAINTENANCE
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 21-3 0
The main purpose of highway maintenance is to maintain the highway network [in this case
particularly a significant section of NH5] for the safe and convenient movement of people and goods.
a) Safety
i) Complying with statutory obligations
ii) Meeting users needs
b) Serviceability
i) Ensuring availability
ii) Achieving integrity
iii) Maintaining reliability
iv) Enhancing quality
c) Sustainability
i) Minimising cost over time
ii) Maximising value to the community
iii) Maximising environmental contribution
Each of these objectives is equally relevant to the management function, which brings together
highway maintenance, improvement and management.
Highway maintenance is a wide-ranging function and this section assumes the following types of
activity:
b) Routine Regular consistent schedule for patching, cleaning, landscape maintenance and other
activities
Within each of these types of maintenance there are various maintenance activities applying to
highway elements usually grouped as follows:
Reactive
- All elements sign and make safe
- All elements provide initial temporary repair
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 21-4 0
- Highway register
- Management of utilities
- Licenses for highway occupation
- Other regulatory functions encroachment, illegal signs etc
Weather and other Emergencies
- Flooding
- High winds
- High temperatures
- Other emergencies
The Concessionaire will need to set up [and thereafter implement to an acceptable standard] a
Maintenance Plan that carries out the above mentioned activities. Some selected recommendations
as to what goes into this plan follow.
Comprehensive and accurate records should be kept of all highway maintenance activities
undertaken, particularly safety and other inspections, identifying the time and nature of any response,
including nil returns, and subsequent required follow up action.
Coordination of Records
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 21-5 0
The failure of street lighting and illuminated signs and signals could have implications for the safety
of users. It will therefore be necessary to establish priorities for responding to reported lamp failures,
together with a regime of regular monitoring based on principles of risk assessment. Additionally
[quite obviously] the Concessionaire will have to pay for the power requirements of the lighting.
Roughness of Road
Parts of the existing road need a roughness correction. This will need to be done by a thin asphalt
overlay. Thereafter there will be requirements in the Concession Agreement to retain low roughness
levels, and to do this it is likely that every 5 to 6 years or so an asphalt overlay [4 to 5cm thick] will be
needed on most parts of the main road [and at say every 8 to 10 years on the service roads]. The
overlay will also serve a separate purpose of pavement strengthening.
Service inspections should be strongly focussed on ensuring that NH5 [and associated service
roads] meets the needs of users and comprise more detailed specific inspections of particular
highway elements to ensure that they meet requirements for serviceability. The category includes
inspections for regulatory purposes which are also primarily intended to maintain highway availability
and reliability. It also includes less frequent inspections for highway integrity. The extent of the
service inspection regime adopted by the Concessionaire is discretionary and the advice given in the
following paragraphs may be subject to local variation in the light of individual circumstances.
Service inspections are primarily designed to identify deficiencies compromising the reliability,
quality, comfort and ease of use of the highway, from the users point of view. Although not intended
for identifying defects that could potentially compromise user safety, any such defects observed
during service inspections should be recorded and dealt with in the same way as for a safety
inspection.
Special arrangements for frequent inspection of areas that may be particularly susceptible to
risk of flooding either from topological factors outside the highway or from frequent silting of
systems. Frequency of these inspections will depend on local circumstances but could form
part of safety inspections. They should be carried out during or immediately following periods
of heavy rain as opportunity allows;
Gullies in other areas should be cleansed annually and arrangements made for non
functioning gullies to be recorded for more frequent or detailed attention. Grips and ditches,
which may be obstructed by the growth of vegetation or damaged by traffic should be
cleared of vegetation and dug out when required. In most cases the responsibility for
maintenance of ditches will rest with the adjoining landowner;
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 21-6 0
Culverts under roads, where there is a need to inspect for structural damage and blockages.
Culverts and manholes should be inspected every year, more frequently in wooded areas,
and cleaned when required ;
Piped drainage, which includes a wide variety of conduits and filter drains, which may be
susceptible to siltation or blockage. Piped drainage soakaways and associated systems
should be inspected and cleared when required, but at not more than 5 year intervals. Where
the serviceability of such piped drainage is critical to flood prevention or there is evidence
that more regular attention is necessary then the frequency may need to be significantly
increased;
Surface boxes and ironwork for both drainage and nondrainage applications, which should
be inspected during safety and service inspections for carriageways, footways and service
roads.
Significant embankments and cuttings should be defined and an inspection regime identified based
upon the geological characteristics and the potential risk of slippages or rockslides. Service
inspection arrangements should be usually is programmed wherever possible to follow periods of
heavy rain.
All trees within and adjoining the highway should be examined annually for potentially dangerous
conditions [and then if need be cut back]. Surface damage to carriageways, footways and service
roads, associated with root growth should be recorded as part of Safety or Service Inspections for
those elements.
Safety fences and pedestrian rails should be inspected at intervals of five years in respect of
mounting height, surface protective treatment and structural condition. Bolts of safety fences should
be checked every two years [note there are indications on some sections that theft of guardrail and
bolts may be a problem]. Pedestrian rails, boundary fences and barriers for which the
Concessionaire is responsible, should be inspected in respect of integrity and, where appropriate,
stockproof qualities, during the course of service inspections of carriageways, footways and service
roads. A higher frequency may be necessary in some locations (e.g. in areas with known higher
incidence of vandalism). Inspections of structural condition and protective treatment should be
carried out at intervals of two years.
Vegetation potentially obscuring traffic signs should be recorded during safety inspections and
service inspections of carriageways, footways and service roads and treated accordingly. Additional
inspections may be needed during periods of maximum growth.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 21-7 0
Special signing schemes may deteriorate more quickly than conventional signing. They are also
likely to have been installed to improve network safety and inspection arrangements should reflect
this. Block work chevrons are likely to need inspecting and cleaning annually.
The condition of nonilluminated traffic signs should be inspected at least every two years in daylight,
and repeated at night for degradation of colour, retroreflectivity, deteriorating fittings, legibility
distance, and average surface luminance, after cleaning. More frequent inspections may be
necessary for strategic routes and main distributors, where more consistent high standards are
desirable. Cleaning may be necessary annually or more frequently where subject to heavy soiling.
Optical inspections and cleaning of illuminated signs should be carried out at regular intervals of no
greater than one year. A visual inspection of the sign supports should be carried out at the same
time. Nighttime inspections should be undertaken in conjunction with those for street lighting faults.
It is recommended that a group lamp replacement strategy be adopted for illuminated traffic signs.
The lamp period replacement period will depend upon the type of lamp and its annual burning hours.
Inspections should initially be visual. . Any suspect areas identified by the visual inspection should be
noted and further testing instigated. The coefficient of retroreflection of sign face sheeting is a
specialist site test that may require the services of a specialist organisation. The acceptable level of
retroreflection is 80% of the as new value where higher performance materials are used.
Inspection of signs at minor roads should be included in the inspections of signs on the major road to
which they control entry.
Inspections in respect of wear, spread, colour, skid resistance and retroreflectivity should be
undertaken at intervals of one year for paint markings and two years for thermoplastic markings.
Inspections for reflective conspicuity should be carried out at intervals of one year during the hours of
darkness. Inspections should initially be visual. Any suspect areas identified by the visual survey
should be considered for more detailed technical investigation depending on circumstances.
Service inspections of road traffic signals may not be necessary in relation to the functioning of the
internal equipment as this may be provided through remote monitoring of the installation. The remote
monitoring system may also identify the need for lamp replacement but bulk changing is likely to be
preferred. Signal lenses should be cleaned at minimum annually.
Service inspections of the physical condition of controller and auxiliary equipment cabinets and of
other site hardware should be carried out at intervals of one year, and inspections in respect of
electrical safety should be carried out at intervals of five years. Inspections should be visual, by
remote monitor, or by approved test equipment.
Electrical safety Inspections should be undertaken at a frequency no greater than every six years.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 21-8 0
Service inspections of street lighting are necessary, in accordance with standard practice.
Structural inspections of bridges and structures are necessary in accordance with established
practice. At minimum every year all bridges should be visually inspected [and this includes accessing
all bearings and underside of decks] by a professional bridge engineer working for the
Concessionaire [who shall produce a report of his findings for both the Concessionaire and NHAI],
and necessary resulting minor works [repair, cleaning] shall be scheduled and carried out within one
month of the inspection [i.e. cleaning of vegetation, dirt and the like]. Any more important defects
[bearing failures, other problems] or significant repairs needed should be acted on by the
Concessionaire [following agreement with NHAI] and repaired / resolved as soon as possible
[i.e.latest within the same year] after the inspections.
The most significant financial investments in highway maintenance will be in repairing, reconditioning
and reconstructing highway pavements, in particular those of carriageways. In order to ensure value
for money from this investment, the Concessionaire will need to have available, information on the
nature and severity of deterioration in order to determine the most appropriate maintenance
treatment. There are a number of types of survey, each providing information from a differing
perspective, and which in combination can provide a comprehensive picture of the condition of the
asset.
The method and level of detail adopted will depend upon the circumstances of the case, and usually
a structured visual inspection will be undertaken initially, to be supplemented by other methods as
necessary. Survey methods include:
NHAI should define standards [in the Concession Agreement] for the condition of each element of
the highway, which they consider necessary to meet the requirements for safety, serviceability and
sustainability. Where these standards are not met they should set targets for attaining them and
sustaining them in the long term.
NHAI should also set standards and targets for achievement in respect of response times to
inspections and user concerns. They should also work towards setting standards and targets relating
to quality of management and service delivery and possible contributions from changes in materials
and treatments.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 21-9 0
NHAI should ensure that all standards are formally adopted [by the Concessionaire] and published
as part of a Highway Maintenance Plan. They will also need to be consistently applied and reviewed
at intervals in the light of changing circumstances.
Special maintenance plans will be necessary [from the Concessionaire] for the toll plazas and
associated equipment and the Highway Traffic Management System.
The buildings and toll booths will be in constant [generally 24 hr a day] use. Furniture and equipment
will need to be constantly cleaned and maintained. Additionally it is likely that intermittently the whole
electrical/communication/collection equipment associated with toll collection systems will need to be
upgraded or replaced [as it becomes obsolescent] as a rough rule of thumb this might be at 10 year
intervals.
The Highway Traffic Management System will need to be staffed and maintained, and sufficient fuel
provided for associated vehicles to operate. Maintenance of the electrical /communication /
observation / counting equipment is to some extent a specialist activity, and possibly the
maintenance of major portions might be done by the original supplier, or by a specialist company in
this field.
All vehicles purchased for the Highway traffic management system will need to be maintained, and
replaced once they get too old for practical use. Obviously the life expectancy of vehicles varies by
type and usage, but several vehicle fleets will likely need to be purchased [and later sold off when to
old] at various times during the Concession Agreement.
The whole electrical/communication equipment associated with the Highway Traffic Management
System will need to be upgraded or replaced [as it becomes obsolescent] as a rough rule of thumb
this might be at 10 year intervals.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 3-1 0
Chapter 3: Contents
3.6.2 Drains...................................................................................................................................................... 4
3.10 ROADSIDE FEATURES [REST AND SERVICE AREAS, PETROL STATIONS, OTHERS] ................................. 5
3.12 OTHER ROAD FEATURES [LIGHTING, SIGNALS, SIGNS, ROAD MARKINGS ETC.].................................... 7
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 3-2 0
In this Chapter we describe the existing road, and its specific features. Some further details are also
given in Chapter 4. The location map of project highway is shown in Figure 3.1.
3.2 BYPASSES
Major settlements/ towns along the project road are: Vijayawada, Gannavaram (houses airport for
Vijayawada), Hanuman Junction, Eluru. A number of bypasses exist along the corridor, the list of
towns for which bypasses are constructed are as below:
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 3-3 0
Design Standards
S. No. Description Details
1 Design Speed 100/80 Kmph
2 Lane width 3.5 m
3 Median Width (Generally) 4.5m
4 2-Lane carriageway 7.25m
Paved 1.5m
5 Shoulder
Earthen 1.0m
6 Service road 5.5/7.0m
The ten typical cross sections have been developed to upgrade the 2 lane project highway into
existing 4 lane divided carriageway.
3.4 TRAFFIC
In general traffic levels are higher to the south than the north [see figure traffic characteristics on
next page]. On the last 120km [north end] traffic levels are significantly lower than on the southern
78km section since a considerable amount of traffic diverts off the road at the junction as the
alternative route to Rajahmundry is shorter [see plan Competing Corridors two pages on]. The road
is not that busy, traffic levels as such that in capacity terms and for some sections [for a reasonable
level of service] 6 Laning is not really necessary for many years.
3.5 PAVEMENT
The existing pavement details are presented in Chapter 11 of this report separately.
The recent 4-lane construction of the project highway consists of mainly following type of pavement
composition:
From the pavement structure details as-built and DPR Study reports, it is evident that the pavement
structure along the entire Project Highway is varying; the resulting pavement structure over the main
carriageway is as follows;
Pavement thickness
Over
Widening of old 2-lane New Carriageway for 4-lane
No. Road Name Existing
BC DBM BC DBM WMM GSB SG BC DBM WMM GSB SG
Vijayawada- 130/ 130/ 130/
1 40 40 300 300 500+ 40 300 300 500
Eluru 150 150 150
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 3-4 0
Over
Widening of old 2-lane New Carriageway for 4-lane
No. Road Name Existing
BC DBM BC DBM WMM GSB SG BC DBM WMM GSB SG
130/
2 Eluru Bypass - 40 300 300 500
150
Eluru-
3 40 160 40 160 300 300 500 40 160 300 300 500
Gundlagolanu
3.6.1 Bridges
Refer to Chapter 13. It is very important to note that virtually no structure [on this 49.000 Km section]
was built to allow for future widening to 6 lanes.
Hence every structure requires widening [of if unwidenable then replacement for full 6 laning to
occur.
3.6.2 Drains
About 13km of lined drain exists along the Project Highway mainly at built-up areas where the
service roads are provided. The schedules of the lined drains are given in below.
LHS RHS
Offset
Offset
From km To km Remark From km To km from Remark
from CL
CL
Irrigation
1034+080 1022+880 15-20 m 1033+380 1022+480 13-30 m Major Canal
Channel
Total length 11.2 km Total length 10.9 km
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 3-5 0
There are many side accesses to the highway. There are no access control measures in place, and
as such many buildings/factories etc are built [and still being built] with direct access to NH5.
Additionally every town and village passed, except where frontage roads have been built; have many
local roads feeding into the mainline except where service roads are currently provided.
3.10 ROADSIDE FEATURES [REST AND SERVICE AREAS, PETROL STATIONS, OTHERS]
There are about several petrol stations along the road and several rest and service areas [under
construction in fact near finished but not yet all opened]. The rest areas include a 2 full fledge
amenity centres that are [end February 2007] now partly open.
3.11 SAFETY
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 3-6 0
Bullock carts, motorcycle, bicycles, and a government car all going down the fast lane [in the
wrong direction!]
The road is much less safe currently than it should be for the following reasons:
There is no access control [except where some frontage roads are provided, generally in
towns] the road has far too many access points [so you can and do drive straight into a
high speed road.
The road mixes short distance [very local including animals herded on the road in more
rural areas] and long distance traffic so there are many movements [entering the road, U
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 3-7 0
1
turning in the medians, driving the wrong way down the road , grazing in the median] which
are incompatible with the high speed long distance facility this road is supposed to provide.
The main junctions [mostly at grade] have poor advance signing, and should [in some cases]
be grade separated.
Little thought has been given in villages and towns crossed as to how the local population
cross the main National Highway [other than by praying first then running very quickly]. With
this standard of road crossing points should all be grade separated [up or down from the
highway] and with sufficient barriers [or fences] to force people to use the longer grade
separated access rather than the faster run across the road approach.
Guardrail [and barriers at approach to some bridges] is lacking in places, and hanging lose in
others. With the guardrail this might be in places because it appears the bolts get frequently
stolen.
3.12 OTHER ROAD FEATURES [LIGHTING, SIGNALS, SIGNS, ROAD MARKINGS ETC.]
Street lighting exists on the following sections [generally town section, or toll plazas. Virtually no
junctions, other than in some urban areas, have lighting provided]:
1
For instance having bullock carts walk down the fast lane [for a few km] at night in the wrong direction into
incoming traffic happens frequently, as does pedestrians crossing the road at night in dark areas drivers have
to be alert on this road [if not they will hit something].
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 4-1 0
Chapter 4: Contents
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 4-2 0
4.1.1 Project Appreciation, Review of Project Objectives and Scope as a result of Initial
assessment
This sub-section looks at the basic project objectives in light of the Consultants initial field
assessment.
The objectives of the consultancy services are to prepare a proposal to retrofit a six-lane cross-
section on to the existing 4-lane highway and new bypasses in a manner which ensures:
(i) Enhanced safety of the traffic, the road users and the people living close to the highway.
(ii) Enhanced operational efficiency of the highway.
(iii) Fulfilment of the access needs of the local population.
(iv) Minimal adverse impact on the road users and the local population due to construction.
(v) Feasible and constructible options for the project with least cost options.
NHAI are also currently preparing a Manual for 6 Laning of Existing 4 Lane Highways. We
believe the manual is likely to say something like:
A major requirement for the upgrading from four to six lanes is that the improved road should
be contained within the existing Right of Way (RoW) unless there is an exceptional reason
why this cannot be done. This requirement imposes constraints on the design and this
Manual demonstrates suitable measures to provide acceptable solutions while minimising
any additional land take requirements.
It will not be possible to fulfil the above requirement [keeping within the ROW] in some / many
locations. Initial Impressions from various site visits carried out in November 2006 are:
The road is 4 lanes wide everywhere, with sometimes some service roads adjacent where it
goes through urban [and village] areas
Parts of the road were definitely not designed for a 100 kph design speed [some horizontal
curves are 80 kph, even less in geometry terms]. A good car average driving speed in the
rural areas is about 80 kph [slowing at all bridges where the road is bumpy]
Cattle [and other livestock] are intermittently walked down the road [in either direction]
Most if not all of the road was recently built / widened of the previous 2 lane road [mostly by
one side widening [by adding 2 more lanes], with the old 2 lane carriageway now buried
under one side of the 4 lane road, but some new alignment bypasses were also built as well]
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 4-3 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 4-4 0
Rest and service area 2 of these exist along the project section. There are also a lot of petrol
stations with direct access to NH5
In very many places the current corridor right of way is insufficient for 6 laning [including
service roads]. This is especially so in the 3 more major urban areas crossed by the
project [where the current right of way appears to be just 23 m at minimum in places], but
also occurs in many villages passed through, and elsewhere.
Probably not quite enough ROW to fit in full 6 lane Here, at least on one side, there may just be
[with shoulders] and frontage roads room for full 6 laning with frontage roads
There are possibly up to 22 locations where grade separated interchanges should be added
if the current criteria for grade separation is followed. Many if not all of these locations would
require land take and building demolition [substantial] for the grade separation to occur.
All existing structures are for the current 4 lane situation. For full 6 laning all structures
[culverts, small bridges, long bridges] would need to be widened. Technically it is likely not to
difficult to widen the culverts, and probably some of the smaller bridges. However widening
of some of the smaller bridges, plus most if not all of the longer bridges [and this includes 3
substantial river crossings] looks difficult [if not impossible]
One of the existing long bridges, 2 lanes each direction [2 separate structures]
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 4-5 0
Apart for possible land take [and bridge] problems widening to 6 lanes [plus some
intermittent frontage roads, as they will not everywhere be needed in the rural areas] is likely
to be achievable especially in rural areas.
Rural sections
The current 4 lane situation with U turns is dangerous. In daytime [worse at night] local traffic
[bicycle, motorbike, car, lorry and bus, tractor towing hay etc.] drives the wrong way down the
carriageway to save a longer trip via the official route. At day and worse at night pedestrians
crossing the road are significantly at risk. However provision of service roads as necessary
[including if one wants to keep pedestrians of the 6 laning a lot of fencing], plus local access
from one side to the other, either over or under the current road is going to be difficult
[sometimes impossible], and in all events costly, especially as the majority of road [except for
one recent bypass] is on relatively flat ground, sometimes with lengths of canal alongside.
Even with frontage roads driving through these villages, especially at night, is dangerous due to
pedestrians crossing [and vehicles going the wrong way]
Vehicles drive both ways on the existing carriageway, not very safe
Many sections of the road are built adjacent to canals and drainage channels, this creates
difficult access problems where bridges over the canal exist
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 4-6 0
Canal [many km long] to left of parts of NH5, making widening slightly difficult [and frontage roads
virtually impossible here]
Whilst it is possibly to convert this section of road to a 6 lane section, along with new interchanges,
and service roads as needed, it is not an easy task. If everything is done then much land take and
property demolition will be needed [and this directly contradicts part of the basis project
requirements], and costs are likely to be much higher than the global cost of 5.78 crores / km [note:
this is a subjective assessment, we have not done the work needed yet to prove this].
Government basically wish this portion of NH5 to be widened to 6 lanes. However to achieve this
objective via a DBFO concession a number of parameters have to be met:
The project has to be financially viable (so the works and land take have to be affordable);
The project has to be acceptable [the Consultant thinks major demolition in every town and
village passed through is unlikely to be acceptable];
The project has to meet the desired objectives [including safety, local access needs etc.].
We suspect the cost of doing everything desired will be too high for a sensible concession
agreement to be negotiated and let. So the likely choice for Government is to compromise on some
of the desired objectives and standards [i.e. find ways to minimise cost and lessen the land take
problems, which may include even town detour / bypass roads if at all possible]. The Client has to
decide [as the study evolves] what requirements are sacrosanct and which may be varied, given a
likely desirable ceiling to the overall average cost per km. In the particular case of this project some
requirements that will need to be locally considered as the study evolves are likely to be;
How many interchanges and grade separated U turns and accesses are to be provided
[these are individually large cost items, and some interchange grade separations may be
quite expensive and involve possibly significant land take].
Is full on line widening through the major town areas [the available ROW in places drops
well below 30m] really a sensible option [a site visit by NHAI is highly recommended]. Bypass
alternatives may need to be studied, and this may require additional time and resources.
What to do with the major bridges [> 60m in length], leaving them as 4 lanes defeats the
objectives of everywhere widening to 6 lanes [and creates pinch points which are likely in
time going to be bottlenecks and also safety hazards]. Maybe more provision of service
roads to keep local and through traffic completely separated and less 4 to 6 general lane
widening may be a way forward.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 4-7 0
The above requirements are applicable to areas with adjacent constraints [towns, bridges, potential
interchange locations]. In rural locations the real constraints are predictable [carriageway and
embankment needs widening from 4 to 6 lanes, all structures and culverts need widening, limited
frontage roads will be needed], with one problem to sort out which is how cross access is provided.
The Draft Feasibility Study Report was submitted in early February 2007 (Vijayawada-Gundugolanu),
December 2010 (Vijayawada Bypass) and January 2011 (Hanuman Junction Bypass).
This Final Feasibility Report is essentially an update of the Draft report, with one scheme for 4/6
laning presented.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 5-1 0
Chapter 5: Contents
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 5-2 0
Alignment Sheets
Existing Vijayawada-Gundugolanu NH
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 5-3 0
It should be noted that as at end February 2007 possible about 1/3 of the alignment is shown in
Google earth in the clarity given immediately above, other areas have much poorer definition.
Most of the as-built drawings are available in electronic form; however there are a few hard copies
are also available and collected by the consultants.
KEY FINDINGS
The Terms of Reference specifies that The consultant shall also be fully responsible for the
accuracy of the physical and ground details, such as alignment, grade, right of way details, abutting
land use, and features existing within the right of way (such as service roads, drains, retaining/RE
walls, slope protection, culverts, bridges, junctions, subways/overpasses, grade separators, road
over bridges), pedestrian/cattle crossing facilities, bus/truck lay byes, utilities (like telephone, HT/LT
lines, water supply drainage/gas lines and OFC cables), plantation, road furniture, access to
properties/fuel stations, median openings, etc. The primary source of the existing ground and
physical features will be the as-built drawings of the existing four-lane highway.
The as-built drawing shows only the lane edges, some alignment details and does not have the
details of physical features, right of way, abutting land use and utility services and other important
features of roadway. The consultants have collected many missing details and presented these
details in the Strip Plans.
The cross sections drawings are complete with respect the setting details. The Cross Drainage works
drawings are also complete with respect to the setting details. However the horizontal and vertical
layout details presented in the as-built drawings are not sufficient for setting out geometry. The
Vertical Bench Mark details are given but the horizontal alignment details in terms of HIP and
coordinates are completely missing. The concessionaire has to carryout detail topographic surveys
including levelling for detailed design and sub-sequent layout in the field.
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 5-4 0
Topographic surveys with Total Station instrument were taken on the entire project road section,
through Vijayawada-Gundugolanu. The as-built drawings were reviewed to identify the location
where validation is critical to verify the geometric parameters, setting out details, physical features
and land use. The identification of particular location, the characteristics to be validated are
summarised below.
FIELD SURVEYS
Bench Marks
The Bench Marks for levels were given in the as-built drawings; however there is no details given on
traverse points/horizontal control pillars. The vertical control reference points (TBM) are marked
either on Median Kerb top, Bridge Kerb top, Culvert Head Wall/Parapet or on KM post, indicating with
paint. Many of the TBM marks are not visible on site, hence cannot establish validation. There is no
permanent type of control pillars observed along the entire project road. The complete list of TBM
details are presented in the DPR documents.
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 5-5 0
The basic objective of the topographic surveys is to capture the essential ground features along the
alignment in order to work out improvements, rehabilitation and upgrading costs. The detailed
topographic surveys are taken up after the completion of reconnaissance surveys.
Before taking up the detailed topographic surveys, alignment validation surveys have been carried
out for the proposed alignment. A detailed reconnaissance survey with Key professionals involved in
the Project is undertaken to validate the preliminary alignment keeping in view the following
parameters:
A pair of GPS control points has been established by using DGPS at every 5km interval. The
Traversing has been carried out in-between 2 GPS points located at an interval of 5Km and error has
been adjusted on all the Control points. The GTS benchmarks have been transferred to Benchmark
Pillars along the alignment by DT leveling.
The detailed topographic surveys are being carried out based on the control points established on
the side of the proposed corridor. Longitudinal and Cross section will be picked up at every 25m
interval for the survey corridor for a width of 50 m on either side of centerline. The topographic details
like cross Roads, Rail, Bridges, Culverts, Trees, Buildings, Religious monuments, Graveyards,
Pipelines, Traffic Signs, Waterways, Electric Poles, Telephone Poles, important structures found at
site will be taken within the survey corridor. All the main Junctions of NH and SH have been
surveyed for in detail for junction improvements/ interchanges.
At locations where developments have resulted in a requirement for adjustments in the alignment,
survey of existing alignment to be improved through minor adjustments by widening the width of
corridor, the Survey will extend a minimum of 200m either side of the center line and will be of
sufficient width to allow improvements, including at-grade intersections, to be designed where
existing roads cross the alignment. For roads proposed to be improved, the longitudinal sections
levels along the proposed centerline would be taken at every 25m interval.
The longitudinal sections and cross-sections are being surveyed for the streams crossing the
alignment to the extent depending on their catchment area. In general for all the Major bridge
locations the survey will be carried out for 500m on upstream and 500m on downstream side by
taking of cross-sections at 0m, 50m, 100m, 200m, and 500m on both sides and for the Minor bridge
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 5-6 0
locations the survey will be carried out for 300m upstream and 300m downstream side by picking
cross-sections at 0m, 100m, 200m, and 300m on both sides.
The survey data will be utilized to develop DTM useful for final design of bypass, earthworks and
other quantities for detailed cost estimates.
Project centerline has been designed to proper geometry. Revenue maps are being collected along
the project corridor and significant land marks/plot boundaries identified on the ground and co-
ordinates will be picked up on these control points. Digitization of Revenue maps will be done
simultaneously and with the help of co-ordinates picked up on control points, these revenue maps
will be oriented to extrapolate on the project centre line. The corridor of impact on revenue maps will
thus be established and Land acquisition Plans will be developed. Schedules for Land acquisition will
be prepared by collecting the revenue records from local revenue offices to know the title holders of
each plot. The LA schedules will be prepared showing the Plot No, Name of the Title holder and
extent of land affected.
Horizontal Alignment
Sufficient details were collected at horizontal curve location at selected chainages to assess and
validate the geometric characteristics for Vijayawada-Gundugolanu section. The following table
summarise these geometric characteristics.
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 5-7 0
From the above table it is evident that most of as-built details of horizontal alignment in terms of
bearing, distances and other geometric parameters are very close to results of validation survey. The
road was built four years before hence there could be slight variation in the details obtained when
compared to the as-built and variation could also be possible due to various type of surveys
instrument and time of surveys.
Vertical Alignment
Sufficient details were collected at vertical curve location at selected chainages to assess and
validate the geometric characteristics for Vijayawada-Gundugolanu section. The following table
summarise these geometric characteristics.
Vijayawada Gundanagolu
Lvc=438.449m Lvc=438.449m
As mentioned in the earlier chapter on As-Built drawings validation the alignment and profile details
in the as-built drawings are insufficient to check the layout characteristics. Hence the validation no
vertical alignment is limited to verifying the grades as-built and curve length if the details available.
From the above table it clear that there is not much variation in the results found compared to the
details given in the as-built drawings.
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 5-8 0
were then planned to capture the traffic and travel characteristics on the sections of the project
corridor. The surveys conducted include, classified traffic volume count surveys, origin-destination
surveys, intersection turning movement count surveys, pedestrian count surveys, speed & delay etc.
th th
The first traffic surveys were conducted between 10 Dec 2006 and 8 Jan 2007, under the
supervision of traffic engineer. The results from these traffic studies including traffic projections are
th
discussed in detail in Chapter 6 of this report. Further traffic surveys were carried out between 25
th
February and 6 March 2007 (Vijayawada-Gundanagolu section), and during this second period axle
load surveys were carried out in 1 location (Vijayawada-Gundanagolu section) [48hrs each location,
th th
traffic both ways weighed]. Further traffic surveys were carried out between 7 December and 13
December 2010 (Vijayawada Bypass).
Utilities Agencies have various degrees of authority to install their lines within the right of way of
roads. Depth, size, etc of utilities are based on the IRC98-1997 guidelines.
Coordinates of all the surface utilities, which include electric poles, telephone poles, towers,
transforms, over head electric and telephone lines etc., will be picked up during the detailed
topographic surveys. The details of underground utilities will be collected from the concerned
departments. The utility information from these sources will be drawn on the base plan to develop
utility shifting plans.
The information collected during reconnaissance and field surveys will be shown on a strip plan so
that the proposed improvements can be appreciated and the utilities required to be shifted for each
type can be assessed and suitable actions can be initiated.
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 5-9 0
Suitable recommendations will be made regarding making good the borrow areas and quarry areas
after the exploitation of materials for construction of works.
The Material Investigation aspect will include preparation and testing of bituminous mixes for various
layers and concrete mixes of different design mix grades using suitable materials (binders,
aggregates, sand filler etc.,) as identified during Material Investigation to conform to latest MORT&H
specification.
The following details have been collected for the Vijayawada/Hanuman Junction Bypasses project:
Catchment area
An index map to a suitable scale. i.e., Topo sheets in scale of 1:50000, showing the
alignment, location of proposed bridges etc. Drainage area mapping is done based on the
topo sheets, contours available from Bhuvan maps and Google maps.
Assessment of ground water condition (Water Table).
Reports from CWC and IMD for Flood Estimation
Flood Estimation reports from CWC for small catchments. This report forms the base for
preparing the synthetic unit hydrographs for the purpose of flood estimation.
Rainfall Isohyets for rainfall data for various return periods
Floods and Discharge Data
History of floods, if any and Survey of observed Maximum flood levels (OMFL) or High
Flood Level (HFL) with reference to GTS bench marks
Discharge details of canals from respective departments.
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 5-10 0
Survey Data
Geological information
Topo surveys data including the alignment survey
Bridge locations - Cross and Longitudinal Sections
There are 333 (Km 1076+480 to Km 1061+080 and Km 1056+08 to 1022+480) numbers of
structures (existing minor / major bridges, RoBs, and underpasses) of all 2lane configurations each
side and 128 (Vijayawada and Hanuman Junction Bypass) numbers of structures (minor / major
bridges, RoBs, and underpasses) on proposed bypasses. Out of which the total number of RoBs are
5. The list of the RoBs is given in the following table.
Vijayawada Bypass
Proposed Proposed
1 Km 2+500 - 112 12 112 12
Bypass Bypass
Proposed Proposed
2 Km 20+590 - 552 12 552 12
Bypass Bypass
Proposed Proposed
3 Km 45+870 - 378 12 378 12
Bypass Bypass
The following typical defects were noticed in the structures based on the visual inspection:
Settlement of approach slab
Damaged Hand Railing
Vegetation growth at up-stream and down-stream
Damaged metallic crash barriers in approaches
Missing / non uniform structure numbers and chainages
Debris on pier and abutment caps
Debris on bridge deck / expansion joints
Missing / damaged blocked drainage spouts
Un dismantled False steining of well foundations
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 5-11 0
Specific problems
1. Elastomeric bearings of end spans of ROB at km 1034+140 on Eluru Bypass (new 4-lane)
were found to be failed. The cause of failure requires to be investigated by a project level
inspection by a specialised agency. Thereafter, the bearings shall be replaced after carrying
out fresh designs, if required. The finding along with the photographs was reported to the
nd
Project Director, NHAI, Vijayawada vide our letter no. NHDP-V/PIU/07/01-011 dated 2
January 2007.
Environmental Screening of the study area has the following major objectives:
To delineate the major environmental issues and identify the potential hotspots, which
requires further study i.e. scope for EA,
The detailed analysis and results of Environment and Social Surveys are presented in chapter 19.
Egis Bceom International, France in Association with EGIS India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 6-1 0
Chapter 6: Contents
CHAPTER 6: CONTENTS ............................................................................................................................ 1
6 TRAFFIC SURVEYS AND ANALYSIS ................................................................................................ 2
6.1 GENERAL ............................................................................................................................................ 2
6.2 ESTIMATION OF BYPASS TRAFFIC ................................................................................................. 4
6.2.1 Bypass Alignment Options ....................................................................................................... 4
6.2.2 Traffic Estimation ..................................................................................................................... 5
6.2.3 Growth Rates ........................................................................................................................... 6
6.3 TOLLING STRATEGY ....................................................................................................................... 12
6.3.1 Stream wise Tollable Traffic ................................................................................................... 14
6.3.2 Toll Rate ................................................................................................................................. 14
6.3.3 Toll Revenue .......................................................................................................................... 16
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 6-2 0
6.1 GENERAL
The present project is development of new bypasses for the Vijayawada city and Hanuman Junction town
and four lane to six laning of Vijayawada-Gundugolanu section of NH-5. Vijayawada is thirty fourth largest
urban agglomerations in the country and comprises of Vijayawada Municipal Corporation (VMC),
Mangalagiri Municipality, 4 Panchayats and outgrowths. Vijayawada is the third largest city of the State of
Andhra Pradesh. The population of the city as per the 2001 census is 8,45,217 and is growing at an
average decadal growth rate of 39.72.
The existing NH-5 passes through the city. Two National Highways NH-5 and NH-9 intersect in the city.
NH-9 connects the city with Hyderabad, Capital of Andhra Pradesh and Machilipatnam, port town. NH-5
leads to Visakhapatnam and Chennai two of the busiest ports of India. Figure 6.1 presents the details.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 6-3 0
The 47.88 km long project corridor starts after Kaza toll plaza and continues to West of Vijayawada and
ends after Gannnavaram but before the Pottipadu toll plaza. The present project involves evaluation of
the technical feasibility of Vijayawada bypass with the 6 lane facility with partial/full access control through
provision of service roads, grade separation etc to ensure safety and the assessment of cost of
development. This Chapter discusses the traffic surveys conducted, traffic estimate for the bypass and
traffic projections etc.
Traffic surveys have been conducted in the 2007 for the project Feasibility Study for 6 Laning of
Vijayawada-Rajahmundry section, NH-5 and also Feasibility Study for 6 laning of Chilakaluripet-
Vijayawada section, NH-5. For the above studies, 7 days TVC count and 24 hours OD surveys has been
conducted at number of locations as per the requirements of NHAI. Detailed analysis of the traffic has
been presented in the Feasibility Report for the above projects. However, for the present study the traffic
data on either side of the bypass in the immediate vicinity has been used. The survey locations data
which is used in the present study are presented below at Table 6.1.
AADT Traffic at the Kaza & Pottipadu Toll Plaza locations is presented in the Table 6.2 below.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 6-4 0
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 6-5 0
The length details of the different options studied are presented in Table 6.3.
The western alignment will have two sections one from Kaza toll plaza (near) to NH-9 connecting
Hyderabad, and the second connecting NH-9 to near Gannavaram. The section wise traffic estimates for
year 2010 is presented in the Table 6-4 below:
The directional distribution of traffic for the year 2010 is presented graphically below:
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 6-6 0
For other vehicle types, a nominal growth rate of 2% per annum has been assumed for the study. As the
immediate influence area is agriculturally rich, the agricultural vehicles (non-motorised) are not expected
to diminish.
Estimated traffic of the Vijayawada bypass has been projected with 5% growth rate and presented for
the year 2010 and cardinal years in the Table below:
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 6-7 0
Table 6.6: Projected Traffic for the Western Alignment Vijayawada Bypass Section 1
Car/ MAV up
Mini 2 Axle 3 Axle MAV >6 HCM/ Total
Year Jeep/ Bus LCV to 6
Bus Truck Truck Axles EME PCUs
Van Axle
2007 305 - - 283 952 1,112 127 - - 7,493
2008 320 - - 297 1,000 1,168 133 - - 7,868
2009 336 - - 312 1,050 1,226 140 - - 8,262
2010 353 - - 328 1,103 1,287 147 - - 8,677
2011 371 - - 344 1,158 1,351 154 - - 9,107
2012 390 - - 361 1,216 1,419 162 - - 9,566
2,013 410 - - 379 1,277 1,490 170 - - 10,045
2014 431 - - 398 1,341 1,565 179 - - 10,552
2015 453 - - 418 1,408 1,643 188 - - 11,079
2016 476 - - 439 1,478 1,725 197 - - 11,630
2017 500 - - 461 1,552 1,811 207 - - 12,212
2,018 525 - - 484 1,630 1,902 217 - - 12,824
2,019 551 - - 508 1,712 1,997 228 - - 13,466
2,020 579 - - 533 1,798 2,097 239 - - 14,139
2,021 608 - - 560 1,888 2,202 251 - - 14,848
2,022 638 - - 588 1,982 2,312 264 - - 15,590
2,023 670 - - 617 2,081 2,428 277 - - 16,369
2024 704 - - 648 2,185 2,549 291 - - 17,188
2025 739 - - 680 2,294 2,676 306 - - 18,046
2026 776 - - 714 2,409 2,810 321 - - 18,949
2027 815 - - 750 2,529 2,951 337 - - 19,897
2028 856 - - 788 2,655 3,099 354 - - 20,893
2029 899 - - 827 2,788 3,254 372 - - 21,940
2030 944 - - 868 2,927 3,417 391 - - 23,038
2031 991 - - 911 3,073 3,588 411 - - 24,190
2032 1,041 - - 957 3,227 3,767 432 - - 25,403
2033 1,093 - - 1,005 3,388 3,955 454 - - 26,673
2034 1,148 - - 1,055 3,557 4,153 477 - - 28,007
2035 1,205 - - 1,108 3,735 4,361 501 - - 29,410
2036 1,265 - - 1,163 3,922 4,579 526 - - 30,880
2037 1,328 - - 1,221 4,118 4,808 552 - - 32,422
2038 1,394 - - 1,282 4,324 5,048 580 - - 34,043
2039 1,464 - - 1,346 4,540 5,300 609 - - 35,744
2040 1,537 - - 1,413 4,767 5,565 639 - - 37,528
2041 1,614 - - 1,484 5,005 5,843 671 - - 39,404
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 6-8 0
Car/ MAV up
Mini 2 Axle 3 Axle MAV >6 HCM/ Total
Year Jeep/ Bus LCV to 6
Bus Truck Truck Axles EME PCUs
Van Axle
2042 1,695 - - 1,558 5,255 6,135 705 - - 41,375
2043 1,780 - - 1,636 5,518 6,442 740 - - 43,444
2044 1,869 - - 1,718 5,794 6,764 777 - - 45,617
2045 1,962 - - 1,804 6,084 7,102 816 - - 47,898
2046 2,060 - - 1,894 6,388 7,457 857 - - 50,293
Car/ MAV up
Mini 2 Axle 3 Axle MAV >6 HCM/ Total
Year Jeep/ Bus LCV to 6
Bus Truck Truck Axles EME PCUs
Van Axle
2007 535 - - 213 1,502 700 140 - - 8,091
2008 562 - - 224 1,577 735 147 - - 8,496
2009 590 - - 235 1,656 772 154 - - 8,920
2010 620 - - 247 1,739 811 162 - - 9,370
2011 651 - - 259 1,826 852 170 - - 9,839
2012 684 - - 272 1,917 895 179 - - 10,334
2,013 718 - - 286 2,013 940 188 - - 10,852
2,014 754 - - 300 2,114 987 197 - - 11,394
2,015 792 - - 315 2,220 1,036 207 - - 11,964
2,016 832 - - 331 2,331 1,088 217 - - 12,562
2,017 874 - - 348 2,448 1,142 228 - - 13,192
2,018 918 - - 365 2,570 1,199 239 - - 13,848
2,019 964 - - 383 2,699 1,259 251 - - 14,542
2,020 1,012 - - 402 2,834 1,322 264 - - 15,271
2,021 1,063 - - 422 2,976 1,388 277 - - 16,035
2,022 1,116 - - 443 3,125 1,457 291 - - 16,836
2,023 1,172 - - 465 3,281 1,530 306 - - 17,680
2024 1,231 - - 488 3,445 1,607 321 - - 18,564
2025 1,293 - - 512 3,617 1,687 337 - - 19,490
2026 1,358 - - 538 3,798 1,771 354 - - 20,465
2027 1,426 - - 565 3,988 1,860 372 - - 21,492
2028 1,497 - - 593 4,187 1,953 391 - - 22,566
2029 1,572 - - 623 4,396 2,051 411 - - 23,697
2030 1,651 - - 654 4,616 2,154 432 - - 24,886
2031 1,734 - - 687 4,847 2,262 454 - - 26,135
2032 1,821 - - 721 5,089 2,375 477 - - 27,441
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 6-9 0
Car/ MAV up
Mini 2 Axle 3 Axle MAV >6 HCM/ Total
Year Jeep/ Bus LCV to 6
Bus Truck Truck Axles EME PCUs
Van Axle
2033 1,912 - - 757 5,343 2,494 501 - - 28,813
2034 2,008 - - 795 5,610 2,619 526 - - 30,255
2035 2,108 - - 835 5,891 2,750 552 - - 31,768
2036 2,213 - - 877 6,186 2,888 580 - - 33,361
2037 2,324 - - 921 6,495 3,032 609 - - 35,027
2038 2,440 - - 967 6,820 3,184 639 - - 36,778
2039 2,562 - - 1,015 7,161 3,343 671 - - 38,616
2040 2,690 - - 1,066 7,519 3,510 705 - - 40,549
2041 2,825 - - 1,119 7,895 3,686 740 - - 42,577
2042 2,966 - - 1,175 8,290 3,870 777 - - 44,705
2043 3,114 - - 1,234 8,705 4,064 816 - - 46,944
2044 3,270 - - 1,296 9,140 4,267 857 - - 49,292
2045 3,434 - - 1,361 9,597 4,480 900 - - 51,757
2046 3,606 - - 1,429 10,077 4,704 945 - - 54,345
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 6-10 0
Table 6.8: Projected Traffic for the portion from Vijayawada Bypass to Gundugolanu
MAV Agri
Car/ 2 MAV Auto Agri Animal Cycle Tollable
Mini 3 Axle up to HCM/ Two Temp Tractor Other Total
Year Jeep/ Bus LCV Axle >6 Ricksh Tract Hand Cycle Ricks Traffic
Bus Truck 6 EME Wheeler o & s PCUs
Van Truck Axles aw or drawn haw PUCs
Axle Trailor
2007 2,605 48 1,008 490 1,440 2,178 326 - - 2,482 572 527 14 55 7 293 21 2 18,757 21,605
2008 2,735 50 1,058 515 1,512 2,287 342 - - 2,606 601 553 15 58 7 308 22 2 19,693 22,682
2009 2,872 53 1,111 541 1,588 2,401 359 - - 2,736 631 581 16 61 7 323 23 2 20,679 23,816
2010 3,016 56 1,167 568 1,667 2,521 377 - - 2,873 663 610 17 64 7 339 24 2 21,714 25,005
2011 3,167 59 1,225 596 1,750 2,647 396 - - 3,017 696 641 18 67 7 356 25 2 22,798 26,251
2012 3,325 62 1,286 626 1,838 2,779 416 - - 3,168 731 673 19 70 7 374 26 2 23,938 27,560
2,013 3,491 65 1,350 657 1,930 2,918 437 - - 3,326 768 707 20 74 7 393 27 2 25,135 28,937
2014 3,666 68 1,418 690 2,027 3,064 459 - - 3,492 806 742 21 78 7 413 28 2 26,396 30,386
2015 3,849 71 1,489 725 2,128 3,217 482 - - 3,667 846 779 22 82 7 434 29 2 27,714 31,901
2016 4,041 75 1,563 761 2,234 3,378 506 - - 3,850 888 818 23 86 7 456 30 2 29,097 33,489
2017 4,243 79 1,641 799 2,346 3,547 531 - - 4,043 932 859 24 90 7 479 32 2 30,552 35,160
2,018 4,455 83 1,723 839 2,463 3,724 558 - - 4,245 979 902 25 95 7 503 34 2 32,079 36,918
2,019 4,678 87 1,809 881 2,586 3,910 586 - - 4,457 1,028 947 26 100 7 528 36 2 33,682 38,762
2,020 4,912 91 1,899 925 2,715 4,106 615 - - 4,680 1,079 994 27 105 7 554 38 2 35,364 40,694
2,021 5,158 96 1,994 971 2,851 4,311 646 - - 4,914 1,133 1,044 28 110 7 582 40 2 37,134 42,727
2,022 5,416 101 2,094 1,020 2,994 4,527 678 - - 5,160 1,190 1,096 29 116 7 611 42 2 38,994 44,866
2,023 5,687 106 2,199 1,071 3,144 4,753 712 - - 5,418 1,250 1,151 30 122 7 642 44 2 40,945 47,109
2,024 5,971 111 2,309 1,125 3,301 4,991 748 - - 5,689 1,313 1,209 32 128 7 674 46 2 42,994 49,465
2,025 6,270 117 2,424 1,181 3,466 5,241 785 - - 5,973 1,379 1,269 34 134 7 708 48 2 45,143 51,932
2,026 6,584 123 2,545 1,240 3,639 5,503 824 - - 6,272 1,448 1,332 36 141 7 743 50 2 47,398 54,525
2,027 6,913 129 2,672 1,302 3,821 5,778 865 - - 6,586 1,520 1,399 38 148 7 780 53 2 49,765 57,247
2,028 7,259 135 2,806 1,367 4,012 6,067 908 - - 6,915 1,596 1,469 40 155 7 819 56 2 52,253 60,106
2029 7,622 142 2,946 1,435 4,213 6,370 953 - - 7,261 1,676 1,542 42 163 7 860 59 2 54,863 63,107
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 6-11 0
MAV Agri
Car/ 2 MAV Auto Agri Animal Cycle Tollable
Mini 3 Axle up to HCM/ Two Temp Tractor Other Total
Year Jeep/ Bus LCV Axle >6 Ricksh Tract Hand Cycle Ricks Traffic
Bus Truck 6 EME Wheeler o & s PCUs
Van Truck Axles aw or drawn haw PUCs
Axle Trailor
2030 8,003 149 3,093 1,507 4,424 6,689 1,001 - - 7,624 1,760 1,619 44 171 7 903 62 2 57,610 66,263
2031 8,403 156 3,248 1,582 4,645 7,023 1,051 - - 8,005 1,848 1,700 46 180 7 948 65 2 60,488 69,572
2032 8,823 164 3,410 1,661 4,877 7,374 1,104 - - 8,405 1,940 1,785 48 189 7 995 68 2 63,512 73,046
2033 9,264 172 3,581 1,744 5,121 7,743 1,159 - - 8,825 2,037 1,874 50 198 7 1,045 71 2 66,689 76,694
2034 9,727 181 3,760 1,831 5,377 8,130 1,217 - - 9,266 2,139 1,968 53 208 7 1,097 75 2 70,023 80,528
2035 10,213 190 3,948 1,923 5,646 8,537 1,278 - - 9,729 2,246 2,066 56 218 7 1,152 79 2 73,527 84,553
2036 10,724 200 4,145 2,019 5,928 8,964 1,342 - - 10,215 2,358 2,169 59 229 7 1,210 83 2 77,203 88,778
2037 11,260 210 4,352 2,120 6,224 9,412 1,409 - - 10,726 2,476 2,277 62 240 7 1,271 87 2 81,060 93,209
2038 11,823 221 4,570 2,226 6,535 9,883 1,479 - - 11,262 2,600 2,391 65 252 7 1,335 91 2 85,113 97,867
2039 12,414 232 4,799 2,337 6,862 10,377 1,553 - - 11,825 2,730 2,511 68 265 7 1,402 96 2 89,370 102,762
2040 13,035 244 5,039 2,454 7,205 10,896 1,631 - - 12,416 2,867 2,637 71 278 7 1,472 101 2 93,842 107,900
2041 13,687 256 5,291 2,577 7,565 11,441 1,713 - - 13,037 3,010 2,769 75 292 7 1,546 106 2 98,536 113,296
2,042 14,371 269 5,556 2,706 7,943 12,013 1,799 - - 13,689 3,161 2,907 79 307 7 1,623 111 2 103,465 118,962
2,043 15,090 282 5,834 2,841 8,340 12,614 1,889 - - 14,373 3,319 3,052 83 322 7 1,704 117 2 108,639 124,907
2,044 15,845 296 6,126 2,983 8,757 13,245 1,983 - - 15,092 3,485 3,205 87 338 7 1,789 123 2 114,071 131,150
2045 16,637 311 6,432 3,132 9,195 13,907 2,082 - - 15,847 3,659 3,365 91 355 7 1,878 129 2 119,773 137,702
2046 17,469 327 6,754 3,289 9,655 14,602 2,186 - - 16,639 3,842 3,533 96 373 7 1,972 135 2 125,763 144,587
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 6-12 0
IRC: 64 - 1990 stipulates a design service volume of 40,000 PCU per day for a four lane divided
carriageway with paved shoulders at level of service B and plain terrain. This can be further increased
upto 60,000 PUCs by adopting LOS C.
The Vijayawada bypass crosses 40,000 PCUs in the year 2042 and 2040 for the sections 1 & 2
respectively. Hence it may be prudent to consider them for four laning only.
The section between Vijayawada bypass to Gundugolanu reaches the 40,000 PCUs in the year 2020 and
60,000 PUCs in the year 2028. Hence it is necessary to consider it for 6 laning now itself.
Tolling strategy in the present context is the identification of toll plaza locations and tolling sections, which
can fetch maximum revenue with minimum leakage and cost within the given constraints. Open tolling
system is to be adopted for the corridor. This means, flat toll rates calculated for the length of tolling
section(s) shall be charged at the respective toll plazas giving concessions/discounts as applicable to
local / frequent users as decided by authority.
The present package starts from the take off point of Vijayawada bypass 2.1 km after Kaza toll plaza (Km
422+800 new chainage) of Chilakaluripet-Vijayawada section to Gundugolanu (Km 1022+480) of
Vijayawada-Visakhapatnam section of NH-5. This comprises of Vijayawada bypass and Hanuman
Junction Bypass and existing Eluru bypass.
Vijayawada Bypass
The total length of the Vijayawada bypass is 47.880 km having two sections. The first section takes off 2.1
km after the Kaza toll plaza (Km 1112+044 new chainage) towards Vijayawada and joins NH 9 near
Gollapudi and is having a length of 18.650 km. The first section consists of bridge on Krishna river with a
length of 3.144 km. The second section starts from NH-9 and joins NH 5 at (Km 1076+480,
Chinnaautupalli) towards Eluru after Gannavaram and is having a length of 29.23 km. The distance
between the end of the bypass and Pottipadu toll plaza is 3.90 km.
Egis Bceom International, France in Association with BCEOM India Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 6-13 0
There is one bypass for the Hanuman Junction town having a length of 6.7 km.
Eluru Bypass
There is an existing Eluru Bypass for Eluru town.
The toll policy recommends an average distance between two toll plazas should generally be 60 km
except where it is not feasible to do so. Since the Vijayawada bypass is having two sections which will
have different traffic based on their origins and destinations, it is necessary to have two toll plazas on the
bypass one on each section.
There are three existing toll plazas in operation on NH-5, one at Kaza toll plaza (Km 1114+044), the
second one is at Pottipadu Toll Plaza (Km 1072+580) and third one at Kalaparru toll plaza (Km
1050+780). Since these three toll plazas are presently in operation, it is necessary to take them in to
consideration while finalizing the tolling sections of the project corridor. The details of the existing toll
plazas are summarised at Table 6-9 below:
Table 6.9: Existing Toll Plaza details
Length,
S. No. Existing Toll Plaza Chainage, km Section
km
1 Kaza Toll Plaza 1114+044 Km 1182+804 - Km 1100+184 81.6
2 Pottipadu Toll Plaza 1072+580 Km 1100+680 - Km 1061+580 39.1
3 Kalaparru Toll Plaza 1050+780 Km 1061+580 Km 1022+480 39.1
The Kaza toll plaza is collecing toll from Km 355.0 to Km 434.15 till the end of ongoing 6 laning, which
includes 15.25 km from the takeoff point of Vijayawada bypass to Kanakadurga Varadhi on the existing
NH 5 towards Vijayawada town. It is desirable not to disturb the existing concession of Kaza toll plaza.
The road users who desire to use the bypass road of section 1 will not be using the 12.5 km of the
existing NH 5 for which toll is already paid t toll at Kaza toll plaza and hence need not be double charged.
This point needs to be taken in to consideration.
Similarly the Pottipadu toll plaza is collecting toll from Km 1100+680 (Kanakadurga Varadhi) to Km
1061+580 which includes 24.2 km from the joining point of Vijayawada bypass to Kanaka durga Varadhi
on the existing NH 5 towards the Vijayawada town. The road users who desire to use the bypass road of
section 2 will not be using the 24.2 km of the existing NH 5 for which toll is already paid t toll at Pottipadu
toll plaza and hence need not be double charged. This point needs to be taken in to consideration.
The Kalaparru toll plaza is collecting toll from Km 1061+580 (Veleru town) to Km 1022+480
(Gundugolanu). The proposed toll plaza on section 2 of Vijayawada Bypass and Pottipadu toll plaza are
close by and hence it is proposed to do away with the Pottipadu toll plaza. Even the Pottipadu toll plaza
and Kalaparru toll plaza are close by.
Finally it is proposed to have total three toll plaza two on the Vijayawada Bypass , one on section 1, one
on section 2 and retaining the existing toll plaza at Kalaparru.
Km 11+500
Kaza to Gollapudi (15.25 km of NH-5 is
1 on proposed Vijayawada
Km 0 to Km 18+650 adjusted in the toll rate )
Bypass
Km 35+000
Gollapudi Chinnaavutapalli (24.2 km of NH-5 is
2 on proposed Vijayawada
Km 18+650 to Km 47+880 adjusted in the toll rate)
Bypass
Egis Bceom International, France in Association with BCEOM India Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 6-14 0
Kanakadurga Varadhi
Km 1050+780
Gundugolanu Includes Hanuman
3 on Existing Vijayawada
Km 1100+680 to Km Junction (6.7 km) Bypass
Gundugolanu section
1022+480
As per the toll policy all the structures and bypasses costing more than Rs 10 crores need to be charged
separately at the toll rates specified in the policy. Since cost of the two sections of Vijayawada bypass and
the Hanuman Junction bypass are more than Rs 10 Crores each of them will be charged separately.
The Toll Policy specifies four categories of traffic for the purpose of tolling and toll discount and they are:
Local Traffic means vehicles used for non-commercial purpose and includes personal vehicles of
residents of villages/towns/cities on Project Highway whose boundary falls within radius of 20 Kms of Toll
Plaza.
Frequent Travelers When the same mechanical vehicle has to use the said section frequently for the
entire month, the vehicle owner may obtain a monthly pass on the payment of charges equivalent to 2/3
rd the 50 single trip rates applicable to it.
Return Trips When the same mechanical vehicle has to cross the section more than once in a day, the
user shall have the option to pay the fee for the multiple trips at the rates one and half times the single trip
rate.
Exempt Vehicles Two wheelers, three wheelers, animal drawn vehicles and tractors with or without trailor
or trolley and other slow moving vehicles would not be allowed to use the main highway.
Accordingly traffic under different categories has been estimated from the OD Analysis. This information is
used for estimating the toll revenue under three different scenarios realistic, optimistic, and pessimistic.
The tolling rates are as per the notification issued under Section 8A of the National Highways Act, 1956
(48 of 1956), read with Rule 3 of the National Highways Fee (Determination of Rates and Collection)
Rules, 2008. The base toll rates for the different modes per km are given below:
The aforesaid rates are based on wholesale price index (WPI) for the month of December, 2007, which is
216.4.
Egis Bceom International, France in Association with BCEOM India Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 6-15 0
The rate of fee for use of bypass forming part of a section of a National Highway constructed with the cost
of rupees ten crores or more, for the base year 2007-08, shall be one and a half times the rate of fee
specified in sub-rule (2)
Provided that while computing the fee for a section of a National Highway of which such bypass forms a
part, the length of such bypass shall be excluded from the length of such section of National highway.
Provided further that where the cost of such bypass is less than rupees ten crore, then the rate of fee for
the use said bypass shall be the same as that of the section of the National highway of which it forma a
part.
Revision
The above rates shall be increased annually, without compounding, by 3 percent thereof with effect from
April 1, 2008 and such increased rates shall be deemed to be the base rates.
The applicable base rates shall be revised annually with effect from April 1 each year to reflect the
increase in WPI for the month of December of the immediately preceding year; but restricted to 40 % of
such increase in WPI.
Applicable fee rate=base rate + base rate X {(WPI A-WPI B)/WPI B} x0.4
Where,
Local traffic is defined as ones whose boundary falls within 20 Km of fees collection booth. The toll rates
for local users Rs 150/- per month with reference to the base year 2007-08 to be revised annually to
reflect the variation in WPI and then rounded off to the nearest 5 (five) rupees.
Return Trip
The return trips are charged at the rate of 1.5 times the single journey toll rate and will be valid for any
number of trips undertaken during that day of 24 hours.
Frequent Travelers
The frequent travelers are charged at the rate of 2/3rds of the 50 times the single journey toll rate.
WPI
Data from Central Statistical Organization has been collected and analyzed for long term trend. It is
observed that the long term growth in the WPI to be 5 %.
Egis Bceom International, France in Association with BCEOM India Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 6-16 0
The toll rates will be calculated for each of the tolling sections and will be rounded off to the nearest 5
rupee. The discount toll rates will be calculated as discussed above. Projected toll rates for each of the toll
plaza are presented in Table 6-13.
Toll revenue is calculated by multiplying the projected tollable traffic by category and the toll rates. The toll
rates are revised annually for the normal traffic and rounded to the nearest rupee. The local traffic toll
rates are revised every year and rounded to the nearest 5 rupees. The year wise toll revenue at each toll
plaza for each option is presented in Table 6-14. Since the toll rates for the bypasses are same
(irrespective of the cost of the bypass), the toll revenue for all the three options will be same. Hence one
revenue table is presented at Table 6-14.
Table 6.13: Year wise and section wise Toll revenue for all the four options
Egis Bceom International, France in Association with BCEOM India Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 6-17 0
The NPV @ 10%, 12% and 15% for all the four options is also calculated for 30 years and presented at
Table 5.18. This NPV refers to the toll revenue streams only.
Table 6.14: NPV for different discount rates
(Rs in Millions)
NPV 10% 12% 15%
NPV 30,308.39 23,075.82 16,157.01
Egis Bceom International, France in Association with BCEOM India Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 7-1 0
Chapter 7: Contents
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 7-2 0
7.1 INTRODUCTION
Initially, the corridor was widened to a four lane carriageway, with limited safety features included
in the design. Later in the year 2003, a study was commissioned to identify and design Minor
Improvements to National Highways by Span Consultants and Baptie India Jv.
The study identified projects such as crash barriers, improvements to lane markings, signage etc
and the recommendations of this study are under implementation. The project corridor is
proposed for improving to a six laning with access control and enhanced safety.
With this background, the consultants have conducted a safety issue analysis for the project
corridor based on accident information collected from the police department, site analysis etc.
This chapter discusses the identified safety issues, accident data analysis and proposed
measures to address the safety issues.
The consultants have conducted a site visit to identify safety issues and potential safety issues.
Some of these are as below:
portion. This is a major issue which could result in more severe accidents. The photographs
present some cases of wrong side driving. Such unexpected traffic situations on the road result in
avoidable accidents.
Over Loading
The overloading of vehicles is another problem on the project road and results in the poor visibility
for the traffic. Such overloading is more prominent in case of slow and agricultural vehicles. This
would not only obstruct the visibility but also reduce the lane width available for vehicles
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 7-3 0
overtaking and affect the level of service on the project road. The photographs below exhibit
some overloaded vehicles observed on the project road.
Uncontrolled accesses
There are many access points on to the project road and there is no control over the traffic
entering the project corridor. Most of the intersections are uncontrolled and those in the urban
areas are controlled through fixed time traffic signals or by police in the peak periods.
The above photographs present some typical intersections on the project corridor. Such
uncontrolled intersections pose a threat to safe movement of traffic on high speed corridors.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 7-4 0
These need to be addressed while upgrading the project corridor to a six lane access control
facility.
Pedestrian Interference
There are a number of settlements along the project road. Though the share of pedestrian
involved accidents is low but the interference with traffic is considerable. The following photos
illustrate the pedestrian interference with fast motorised traffic. Such interference will also affect
the smooth flow of traffic and may some times lead to accidents often fatal. Though there are
pedestrian over bridges at few locations, these are not being used and have now become a rest
place or restroom.
Other Issues
The road is much less safe currently than it should be for the following reasons:
There is no access control [except where some frontage roads are provided, generally in
towns] the road has far too many access points [so you can and do drive straight into a
high speed road.
The road mixes short distance [very local including animals herded on the road in more
rural areas] and long distance traffic so there are many movements [entering the road, U
1
turning in the medians, driving the wrong way down the road , grazing in the median]
which are incompatible with the high speed long distance facility this road is supposed to
provide.
The main junctions [mostly at grade] have poor advance signing, and should be grade
separated.
1
For instance having bullock carts walk down the fast lane [for a few km] at night in the wrong direction into
incoming traffic happens frequently, as does pedestrians crossing the road at night in dark areas drivers
have to be alert on this road [if not they will hit something].
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 7-5 0
Little thought has been given in villages and towns crossed as to how the local population
crosses the main National Highway [other than by praying first then running very quickly].
There is no existing highway traffic management system.
Guardrail [and barriers at approach to some bridges] is lacking in places, and hanging
loose in others.
The consultants are in the process of collecting the accident information for the project corridor.
However, accident data was made available for part of the corridor. This data has been analysed
to assess the accident trends, major causes for accidents, accident types for majority of accidents
etc. Though this part data could not provide on the magnitude of accidents on the corridor, but
this can definitely provide some vital information on the safety issues. Following paragraphs
present the results of accident analysis.
50
for traffic. However some variations 40
have been observed in the share of 30
major and minor accidents. 20
10
The Figure 7.1 presents the 0
distribution of accidents by severity. 2003 2004
Year
2005 2006
eh t
al
er
de ide
cd ile
O
ip
ia
je
m
in
th
E
c
w
S
d
tr
n
ni
O
r
ea
es
r
S
H dV
H
pa ed
R
it
r
ve
fr
H
ix
Si
Pe
e
it
it
it
H
it
Over speeding is the major cause of accident with more than 90 percent share in the total and the
balance are vehicle getting out of control of the driver.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 7-6 0
The data when analysed for type and location of accident revealed that about 30% of head on
collisions taking place in village areas and in curves and the rest at intersections which a major
issue is considering the existence
of divided carriageway. This clearly Intersection Curve
120
shows and supports the wrong Village Bridge
100 Others
side driving issue discussed earlier
80
in this chapter. Another issue that
%
60
is visible is the parking at the 40
intersection which calls for 20
enforcement and education. All the 0
accidents of hitting parked vehicles
le
de
n
n
t
d
er
ec
ip
in
ia
O
En
ci
th
Si
happened to be at intersection
tr
bj
Sw
eh
d
O
ur
es
r
ea
pa d O
m
ea
V
rt
de
cd
ro
H
ed
ve
(Figure 7.3).
xe
f
Si
Pe
it
rk
O
Fi
H
it
it
H
H
it
H
7.4 PROPOSED FACILITIES
Figure 7.3: Distribution by Accident Type
In order for these facilities to bring an improvement the following principles should be followed:
A proper access control system should be put in place. This includes an access system
(service roads providing access to the abutting properties and possibly to the local traffic,
safe and comfortable grade separated crossings for motorised as well as non motorised
users, ramps and interchanges) and as a general principle features preventing access
(fences, curbs and barriers,).
A treatment of the median in order to prevent front collision and wrong side driving as well
as limit head light glare
A proper signage in order to deliver adequate information to the user. This should
encompass the direction signs, as well as their coordination with markings. Markings
should be treated with sufficient care and maintained with a high level of performance as
they contribute significantly to improved traffic safety.
An adequate geometry on ramps with adequate design speeds. Essential features like
acceleration / deceleration / shelter / storage lanes, pedestrian / cattle / vehicular
underpasses and their approaches, bus bays / bus stops and truck laybys; Proper turning
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 7-7 0
radii at the entry / exit of vehicular underpasses; Service road (minimum 5.5m width)
considered essential for circulation, merging and diverging of local traffic.
7.5 CONCLUSIONS
The general objectives are for the Concession Company to make the main NH5 road [and the
service roads] as safe as possible for all users.
The Concession Company shall follow [and shall also show it has followed] all relevant Indian
publications on road safety, especially The Manual for Safety in Road Design (A guide for
Highway Engineers) prepared in September 1998 for MOST.
A formalised safety audit procedure must be followed [to optimise the safety process, and ensure
safety is properly and formally considered] by the Concession Company during the detailed
design [and during the Construction and post construction periods].
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 8-1 0
Chapter 8: Contents
8.2 IMPACT....................................................................................................................................................12
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 8-2 0
8. PUBLIC UTILITIES
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 8-3 0
The length of the electric services present are summarised in the following table.
Vijayawada Bypass:
The electric poles are very close at some locations and generally located on the edge of the right of
way. The electric line crosses the project highway at about 10 locations. The chainages and offset
distances from centre line are given in below table.
The Chainages and Offset distance form Centre Line
LHS RHS
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 8-4 0
LHS RHS
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 8-5 0
LHS RHS
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 8-6 0
LHS RHS
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 8-7 0
The HT Pylons are very close at some locations and generally located on the edge of the right of
way. The chainages and offset distances from centre line are given in below table.
The Chainages and Offset distance form Centre Line
The chainages and offset distances from centre line are given in below table.
LHS RHS
PCL
Offset from Min. Shift Offset from Min. Shift
Chainage
PCL (m) Reqd. (m) PCL (m) Reqd. (m)
18+730 25.243 13.757
18+770 27.261 11.739
20+580 16.562 22.438
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 8-8 0
OFC
The chainages and offset distances of OFC from centre line are given in below table.
LHS RHS
PCL Offset from Min. Shift Offset from Min. Shift
Chainage PCL (m) Reqd. (m) PCL (m) Reqd. (m)
47+790 12.23 26.77
LHS RHS
PCL
Offset Offset
Chainage Min. Shift Min. Shift
from PCL from PCL
Reqd. (m) Reqd. (m)
(m) (m)
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 8-9 0
LHS RHS
PCL
Offset Offset
Chainage Min. Shift Min. Shift
from PCL from PCL
Reqd. (m) Reqd. (m)
(m) (m)
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 8-10 0
LHS RHS
PCL
Offset Offset
Chainage Min. Shift Min. Shift
from PCL from PCL
Reqd. (m) Reqd. (m)
(m) (m)
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 8-11 0
Telephone poles
The chainages and offset distances from centre line are given in below table.
Chainages and Offset distance of TP form Centre Line
LHS RHS
PCL
Chainage Offset from Min. Shift Offset from Min. Shift
PCL (m) Reqd. (m) PCL (m) Reqd. (m)
2+300 34.787 4.213
2+780 21.803 17.197
2+800 26.6615 12.3385
OFCs
The chainages and offset distances of OFC from centre line are given in below table.
LHS RHS
PCL
Chainage Offset from Min.Shift Offset from Min. Shift
PCL (m) Reqd. (m) PCL (m) Reqd. (m)
0+085 13 26
0+175 27.2 11.8
0+180 13.19 25.81
0+325 6.308 32.692
0+350 10.434 28.566
1+40 35.453 3.547
No. of Capacity /
Name of the Operator Road Section From Km To Km
Ducts laid Specifications
Vijayawada-Gundugolanu section
DoT Eluru Bypass Km 1042+280 1 OFC
M/s. Tata Tele Services Ltd. 1076+480 1061+080 2 HDPE Pipes
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH-5
FINAL FEASIBILITY REPORT DTI 61 847 B03 8-12 0
No. of Capacity /
Name of the Operator Road Section From Km To Km
Ducts laid Specifications
M/s. Tata Tele Services Ltd. 1056+080 1037+080 2 HDPE Pipes
Vijayawada- 40mm dia HDPE
M/s. Wetware Infosys Ltd. 1076+480 1061+080 6
Gundugolanu ducts
Vijayawada- 40mm dia HDPE
M/s. Wetware Infosys Ltd. 1056+080 1024+080 6
Gundugolanu ducts
Besides these ducts the Fibre Optic Cable also present buried in the ground in the road way width.
8.2 IMPACT
An important part of the later detailed design will be to fully determine impacts and design, in
conjunction with utility companies, the diversions or strengthening or crossing (via pipe crossings to
be provided under the roadworks contract) locations and works. It is also very important to note that
in urban road projects service relocations are an important part of the preplanning, both on the
actual work [definition and phasing] and especially on the material procurement side, as in simplistic
terms one cannot relocate power lines, telephone lines and waterlines without at least a reasonable
amount of cable, pipes and fittings already in stock and immediately available.
Some installation of cross-ducting at standard intervals in urban and rural areas [for possible future
utility use] will also be necessary.
It should be noted that there may be additional land requirements identified in the final design as the
available ROW is insufficient to accommodate the moving of utility services and the tree planting
proposals.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 9-1 0
Chapter 9: Contents
9.1 HYDROLOGY................................................................................................................................ 2
9.3 COLLECTION OF DATA (FOR VIJAYAWADA & HANUMAN JUNCTION BYPASS) .................................. 3
9.3.1 Return Period and Rainfall.................................................................................................... 3
9.3.2 Cross-Sections and Longitudinal Section at Bridges ........................................................... 4
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 9-2 0
9.1 HYDROLOGY
Hydrology is one of the important aspects for design of bridge structures across streams. The main
objective is to determine the anticipated floods and other parameters such as design discharge, flow
velocity, HFL, scour depth, etc. The bridge structure should be designed such that it can pass the
anticipated floods without endangering the structure. The hydrological and hydraulic studies have
been carried out in accordance with IRC Special Publication No. 13-2004 (Guidelines for the Design
of Small Bridges and Culverts) and IRC: 5-1998 (Standard Specifications & Code of Practice for
Road Bridges, Section I General Feature of Design).
A long list of structures [mostly for drainage, canal crossings, rivers etc.] is given in Chapter 13,
section 13.2. Additionally quite a lot of smaller size crossing pipe and slab culverts exist.
The project influence area covered by the project road receives low to medium rainfall. The terrain is
generally plain. The soil is predominantly black cotton and clayey soils.
There is one major river (Krishna, tributaries of River Krishna, each crossed by long structures) and
many streams and canals are crossed by the project road.
There are a number of canals running parallel to the road and at right angles to these streams. At
some locations the streams terminate in the canals which obstruct the free flow of flood waters. This
arrangement leads to heading up of water and flooding on the up stream side.
The length of the structures present across these major rivers is presented in the following table.
It was noticed [during our recent inspections] most if not all of the smaller pipe culverts are blocked,
and this obviously may cause local problems in the wet season. These culverts must be cleaned out
and kept clean as necessary..
The widening of the road [to 6 Lanes] plus the addition of service roads will require more [and larger
capacity] longitudinal drainage. This must be included by the Concession Company in their detail
designs.
There are canals and irrigation channels running in close proximity to NH5 at a number of locations.
The details of canals running parallel along the project road in Vijayawada-Gundanagolu section are
given in the following table.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 9-3 0
There exist cross-drainage culverts and bridges on the existing road network. The adequacy of the
existing waterway has been examined in detail in respect of the existing road sections. However it
may be stated here that for the culverts having, inter-alia, inadequate waterway width it is proposed
that the Concession Company must examine in detail the all problems and propose new ones with
adequate waterway, vertical clearance and width suiting to the 6-lane facility.
The road surface drainage is achieved by providing appropriate cross fall/camber leading to
longitudinal drains with proper outfall. Earthen longitudinal drains at isolated locations are present on
both sides at the end of ROW and have adequate section to cater to the requirements for efficient
drainage and suitably connected to proper outfall in the streams. However in the widening these
drains have to be re-built with proper outfalls. The lined drains are provided in the built-up areas
having a width varying from 1.2 to 2m and a depth of 1m covered with concrete blocks. Generally all
concrete drains in the project road are in good condition. Further widening of road will required the
shifting of these concrete drains to the extreme edge of the new carriage way.
There is one major (Krishna) river crossing and 10 stream crossings on this bypass alignment.
Accordingly the data needed for both the structures was collected from field observations, surveys
and statistics (from concerned govt. dept), topo-sheets etc. The alignment is crossing the river
Krishna at approximately 5.8Km upstream of the Prakasam barrage. As per the norms of NHAI past
50 years maximum flood data was collected and it is observed that the flood that was observed in
October, 2009 is the maximum in the past 50 years. So, that flood was considered as the design
flood for fixing the MFL for the present river crossing. The catchment area of the streams is
calculated from the Topo-sheets available on a scale of 1:50000 and 1:250000. Basing on the
catchment area obtained, using various methods the maximum discharge is calculated.
As per IRC: 5 1998 (Standard Specifications and Code of Practice for Road Bridges, Section 1,
General Features of Design) the bridge is to be designed for a period of not less than 50 years. A
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 9-4 0
flood of this specified return period should pass easily through the structure, while an extraordinary
and rare flood may pass without doing excessive damage to the structure or the road.
The 50-year, 24-hour rainfall for the zone under consideration is 240mm. (Ref: Flood Estimation
Report for Eastern Coast Region (upper, lower & south), sub-zone 4 (a, b & c)), published by the
CWC). Catchment areas are marked on Topographic maps from Survey of India of 1:50,000 and
1:2, 50,000 scales.
For the calculation of discharge of the river and streams by Area-Velocity method, topographical
survey including leveling surveys were carried out across and along the watercourses to determine
the cross-section and the slope. A number of cross-sections have been taken at regular intervals on
both upstream and downstream side of the structure, including one at the proposed location of the
structure in accordance with IRC specifications.
Basing on the past records of the floods observed at barrage, the design flood (maximum flood) will
be decided and basing on the MFL observed at the barrage, approximate water level at the required
location will be estimated. If the location of the river crossing is within the impounded water zone the
same level observed at the barrage with some velocity head due to the inflow will be taken as the
MFL. If it is out of the impounded water zone, the flow depth for that particular discharge will be taken
as the MFL at the required location. Thereafter afflux will be calculated and the final MFL will be
fixed.
The peak discharge and the HFL shall be calculated by following methods
Area velocity method
Empirical methods
Q=AxV
2/3 1/2
= A x [(1/n) x (R) x (S) ]
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 9-5 0
Where
Empirical Methods
Where
The catchment area M can be determined from the toposheets or contours generated, Coefficient of
run-off C can be determined from IRC SP-13 depending upon the intensity of rainfall. This formula
gives a simplified approach and results are approximate. Comparison should also be made with
alternative methods for important structures.
Ryve's formula which is as under as per IRC SP-13.
2/3
Q = CM
Where
The catchment area M can be determined from the topo-sheets or contours generated, Coefficient of
run-off C can be determined from IRC SP-13 depending upon the intensity of rainfall. This formula
gives a simplified approach and results are approximate. Comparison should also be made with
alternative methods for important structures.
In hydraulic analysis, the Design HFL shall be calculated corresponding to the Design Discharge by
Mannings Equation at the bridge site, as described above.
When the waterway area of the opening of a bridge is less than the unobstructed natural waterway
area of the stream, i.e. when bridge contracts the stream, afflux occurs. The afflux will be calculated
using Molesworth formula as given below: -
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 9-6 0
( A / a)2 1
V2
h
17.88 0.015
Where,
h = afflux in meters
V = average velocity of water in the river prior to construction in m/sec
A = Unobstructed sectional area of the river at proposed site in sq.m.
a = Constricted area of the river at the bridge in sq.m.
The hydrological studies mainly comprise of two components namely the river crossing calculations
and the stream crossing calculations.
As mentioned earlier, the maximum flood is observed on Oct 2009. But as per the records there is
another similar flood that was observed in 1903 for which higher MFL (approx. 2 ft more than 2009
flood level) was recorded. Since the difference is not much we have considered 1903 flood levels to
be on the safer side. Basing on the calculations it is observed that the river crossing is coming into
the impounded water zone. Calculations are given below.
Maximum Flood Level Calculations
C/S Area for the design flow 12125.22845 sq.m
wetted Perimeter for the design flow 2627.65757 m
Slope (1 in ) based on the contours 933.023
Manning's "n" for natural earthen sections 0.035
Hydraulic Radius 4.614462928 m
Velocity at the river crossing 2.592586299 m/s
Discharge carrying capacity 31435.70114 Cum/sec
1110142 Cu.ft /sec
Design Discharge (discharge observed in Oct 2009) 1110104 Cu.ft /sec
Water level for the design max flow
Bed level observed at a specific point (selected at random in the
19.590 m
C/S)
Max water level for the flood discharge at the point 1.057 m
MFL due to the flow alone (not in the impounded water zone) 20.647 m
2
Velocity head (V /2g) 0.343 m
Probable max afflux due to the collision between the still water and
0.350 m
flowing water
MFL @ barrage 21.500 m
So Max of the two is of the impounded water level i.e 21.500 m
Adding the velocity head to it i.e. afflux due to the collision
21.850 m
between the impounded water and flowing water
Basing on the above calculations, the MFL at the river crossing is fixed. Basing on this the structure
will be designed.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 9-7 0
In present case Discharge is calculated by Area Velocity Method and Empirical Methods also.
Maximum of the discharge obtained by these methods is taken as Design Discharge. HFL is fixed to
match this Design Discharge with given cross section of the stream. Average depth of stream from
given cross section is considered and Vent-way is provided to cater this Design Discharge.
The calculations are given below in table for a brief glance.
SUMMARY OF BRIDGES
Vijayawada Bypass
1 3+360 0.000 29.624 27.500 1.159 30.000 0.919
2 8+210 99.015 345.278 21.381 2.524 36.000 3.886
3 21+240 22.650 194.347 21.900 2.270 20.000 4.376
4 23+350 14.575 82.054 18.961 2.203 25.000 1.553
5 30+565 2.163 19.619 20.660 2.013 10.000 1.036
6 33+250 2.073 19.006 19.268 1.562 15.000 0.924
7 34+250 0.000 19.307 21.000 1.648 10.000 1.367
8 36+500 0.659 8.046 21.887 1.017 12.000 0.800
9 40+900 3.230 26.503 22.195 2.096 10.000 1.539
10 43+250 40.323 196.117 21.915 2.502 50.000 1.628
Hanuman Junction Bypass
11 5+391 10.000 78.728 100.625 1.883 32.000 2.522
NOTE:
Catchment Area is considered 0 sq km since topo sheets received from GSI contains no stream at
that particular chainage.
Proper and adequate drainage of a road is very important for preventing damage to pavement
structure and for its efficient functioning. The main elements which contribute for drainage of the road
are:
i) Cross drainage
ii) Roadway including pavement surface drainage and
iii) Drainage at super elevated section.
The road surface drainage is achieved by providing appropriate cross fall/camber leading to
longitudinal drains with proper outfall. Earthen longitudinal drains at isolated locations are present on
both sides at the end of ROW and have adequate section to cater to the requirements for efficient
drainage and suitably connected to proper outfall in the streams.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Feasibility Study for 6 Laning of
Reports Code Page Rev.
Vijayawada Gundugolanu section, NH 5
FINAL FEASIBILITY REPORT DTI 61 847 B03 9-8 0
High embankment drainage particularly on high embankment approaches to bridges and road over
bridges have problems of erosion of embankment, side slopes and surface drainage in view of steep
longitudinal gradients on the approaches and roadway cross fall towards the embankment slopes.
This problem is proposed to be tackled by providing kerb and channel longitudinal drains at the end
of the paved shoulder and chutes at suitable intervals along the embankment. Embankment slopes
are proposed to be pitched as necessary to prevent rain cuts and erosion.
Egis Bceom International, France in Association with Egis India Consulting Engineers Pvt. Limited
Assessment of Design Traffic in terms of MSA
Homogeneous section (Vijayawada-Gundugilanu)
Design ESA
Commercial Vehicles Bothway (Vehicles/day)
in Million
Year
2-Axle 3-Axle
Bus LCV MAV Total Year Wise
Truck Truck
VDF values 0.62 0.62 2.43 6.46 18.13
Awarding &FC
4.06
Construction
8.32
period of 3yrs
10.60
12.54 1.94
16.49 5.89
20.64 10.0
24.99 14.4
29.56 19.0
34.36 23.8
39.40 28.8
44.70 34.1
50.25 39.7
56.09 45.5
6-lane facility
62.21 51.61
68.65 58.0
75.40 64.8
82.49 71.9
89.94 79.33
97.75 87.15
105.96 95.36
114.58 103.98
123.63 113.03
133.13 122.53