Scrum 15 Days Sat 4/1/17 Thu 4/20/17
Scrum 15 Days Sat 4/1/17 Thu 4/20/17
Resource Names Mar '17 Apr '17 May '17 Jun '17
Mode 1926 2 9 162330 7 142128 4 111825
1 Scrum 15 days Sat 4/1/17 Thu 4/20/17
2 Create product Backlog 3 days Sat 4/1/17 Tue 4/4/17 Dibesh Shrestha Dibesh Shrestha
3 Plan sprint 4 days Wed 4/5/17 Sat 4/8/17 2 Dibesh Shrestha Dibesh Shrestha
4 Execute sprint process 3 days Mon 4/10/17 Wed 4/12/17 3 Dibesh Shrestha Dibesh Shrestha
5 Sprint review 4 days Thu 4/13/17 Tue 4/18/17 4 Dibesh Shrestha Dibesh Shrestha
6 sprint retrospectives 2 days Wed 4/19/17 Thu 4/20/17 5 Dibesh Shrestha Dibesh Shrestha
7
8 Extreme Programming 14 days Sat 4/1/17 Wed 4/19/17
9 Requirement gathering 3 days Sat 4/1/17 Tue 4/4/17 Arbindra Sutihar Arbindra Sutihar
10 Coding 3 days Wed 4/5/17 Fri 4/7/17 9 Arbindra Sutihar Arbindra Sutihar
11 Testing 3 days Sat 4/8/17 Tue 4/11/17 10 Arbindra Sutihar Arbindra Sutihar
12 Listening 3 days Wed 4/12/17 Fri 4/14/17 11 Arbindra Sutihar Arbindra Sutihar
13 Designing 4 days Fri 4/14/17 Wed 4/19/17 Arbindra Sutihar Arbindra Sutihar
14
15 RAD 24 days Sat 4/1/17 Tue 5/2/17
16 Scope 4 days Sat 4/1/17 Wed 4/5/17 Anish Shrestha Anish Shrestha
17 Purpose 5 days Thu 4/6/17 Tue 4/11/17 Anish Shrestha Anish Shrestha
18 Structure 5 days Wed 4/12/17 Tue 4/18/17 Anish Shrestha Anish Shrestha
19
20 System Design 4 days Wed 4/19/17 Mon 4/24/17 Anish,Arbindra,Dibesh Anish,Arbindra,Dibes
21
22 Implementation and Deployment 9 days Tue 4/25/17 Fri 5/5/17 Anish,Arbindra,Dibesh
23 Construction 3 days Tue 4/25/17 Thu 4/27/17
Page 1
ID Task Task Name Duration Start Finish Predecessors
Resource Names Mar '17 Apr '17 May '17 Jun '17
Mode 1926 2 9 162330 7 142128 4 111825
24 Testing 3 days Fri 4/28/17 Tue 5/2/17 23
25 System Deployment 3 days Wed 5/3/17 Fri 5/5/17