Estimate
Estimate
S Quanti
Description Unit Rate Rs. Amount Rs.
No ty
1 2 3 4 5 6
1 Hire and poerational charges of Vaccume Dewatering system including
power generator of not less than 35 KVA Capacity,driving about 28
numbers of filter points allround the pit at 1.00M regular intervals in to the
ground,connecting the filter points to the PVC pipe and then to the suction
motor, including lanour charges for driving the points,delivering the
discharge water to the nearest outlet,etc., complete as directed by the
Engineer-in-Charge.
Number of filter points used for 1 Job is 28 nos i.e total number of job are 56/28 = 2
jobs number of Day the Vacume dewatering system to be empoled for tacking each
foundation
2 Laying Sand Bags in the stipulated places including cost of rmpty cement
bag,sand,thread,stiching charges and labour charges
As per SSR/2015-16 Item No.2,pg.No. 332 25.60
Deduct O.H.C -3.15
TOTAL 22.45
4 selected earth with local materials (Table 400.13) by mix in place method normal
Construction of granular sub-base by providing local material spreading in uniform layers
compacting with smooth wheel roller to achieve the desired density complete as per
Clause 401.4 as per Technical Specification Clause 408 MORD.
Unit = cum
Taking output = 300 cum
a) Labour
Mazdoor (Skilled) day 2.48 320.00 793.60
Mazdoor (Unskilled) day 10.00 320.00 3200.00
b) Machinery
Three wheel 80-100 kN static roller @10 cum hour 30.00 1101.00 33030.00
Water tanker 6 kl capacity hour 5.00 630.00 3150.00
c) Material
selected earth cum 384.00 211.02 81031.68
Cost for 300 cum = a+b+c+d+e 121205.28
Rate per cum = a+b+c+d+e/300 404.02
SUB ESTIMATE FOR ROAD DIVERSION
CONSTRUCTION OF HIGH LEVEL BRIDGE ON PETACALAVA MINOR DRAIN @ 3.50 KM OPPOSITE SRMT STREET
IN RAMANAYYAPRTA OF KAKINADA
Sl. Total
Description Nos L B D Quantity Unit
No Amount
1 2 3 4 5 6 7 8 9
1 Supply and Fixing of Casurina Piles of size 50mm dia to 100 mm dia @ 300mm
center to center including sharping the ends removing of nots as direct including cost
and conveyance of all metials and all labour charges
4 Laying Sand Bags in the stipulated places including cost of rmpty cement
bag,sand,thread,stiching charges and labour charges
Sand Qty 1 x 1 10.00 1.20 2.00 24.00 Cum
5 S & F double layer of bamboo matting tarred on both sides including cost and
conveyance and lobour charges for all operations such as unloading and stacking at
site of work for verification, etc., complete.
1 x 2 10.00 1.20 24.00
24.00 62.40 6739
sqm 1 sqm
6 Forming embankment with borrowed useful earth from outside road
boundary by mechanical means upto SDR with all leads and lifts including
pre-watering of soil at borrow area, removal of top soil, excavation of soils
at borrowed area, conveyance of soil, depositing the soil on the
embankment, spreading soil, breaking clods, sectioning, grading and
consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet
requirement of table 300-2 of MoRT&H, including all hire and operational
charges of T&P and seigniorage charges, complete for finished item of
work as per MoRT&H specification 305
1 x 2 15.00 4.00 0.60 72.00
72.00 294.00 21168
cum
7 selected earth with local materials (Table 400.13) by mix in place method
normal Construction of granular sub-base by providing local material
spreading in uniform layers compacting with smooth wheel roller to
achieve the desired density complete as per Clause 401.4 as per Technical
Specification Clause 408 MORD.
1 x 2 15.00 4.00 0.20 24.00
24.00 404.02 9696
Cum 1 Cum
8 Providing, laying Reinforced cement concrete Hume pipes of 1000mm Dia.,
NP-3 class for pipe culverts including cost and conveyance of Pipes etc.,
complete and Labour charges for laying, jointing of 1000mm dia. R.C.C
Hume pipes in position including lifting, aligning, lowering and hoisting
etc., as per drawing and as per MoRT&H Specification 2900, 2905 and
2906 (4th Revision) and IRC Special Publication No: 13 and as directed by
the Engineer-in-Charge for finished item of work.
1 x 4 7.50 30.00
30.00 7066.00 211980
Rmt 1 Rmt
293800
DATA
Name of work:- CONSTRUCTION OF HIGH LEVEL BRIDGE ON PETACALAVA MINOR DRAIN @ 3.50
KM OPPOSITE SRMT STREET IN RAMANAYYAPRTA OF KAKINADA
1 Laying Sand Bags in the stipulated places including cost of empty cement
bag, sand, thread, stiching charges and labour charges with 14% overhead
charges and contractors profits.
1.00 Each SOR 2015-16 P. No. 35 item No. 2 25.60 each 25.60
25.60
or sa 25.60
Each
or say 62.40
1 Sqm
1000 mm Dia.,
(A) Labour
0.18 nos Mate 345.00 day 62.10
0.50 nos Mason 357.00 day 178.50
4.00 nos Mazdoor 295.00 day 1180.00
25 % MCA on Labour charges 1420.60 day 355.15
Total 1775.75
(B) Material
12.50 RM Cost of 1000mm Dia., pipes
Total 5975.57 RM 74694.63
(C) Over head charges @ 5% (10%-VAT) 74694.63
5.00 % Add for Over head charges @ 5% on (A)+(B)
(D) Total of (A) + (B)+( C) 3823.52
(E) Add Contractors Profit at 10% on (D) 80293.90
Cost per 12.5 metre (D)+(E) 8029.39
Rate for 1 RM 88323.29
Rate to be adopted 7065.86
7066.00
1 RM
ABSERVED DATA
5 Providing Casuarinas Balli Props - 4" to 5" dia - 20'-0" Height verticla posts
and 3" to 4" dia - 12'-0" Height Horizantal posts including cost and
conveyance of Casurina posts and lobour charges and fixing the Casurina
posts including all labour charges such as cutting the Casurina posts to the
required size and shape and bottom of the Casurina post and earthwork
excavation for providing holes for fixing Casurina post in position including
cost of nails for fixing, etc.,for all operations such as unloading and stacking
at site of work for verification, etc., complete.
Ref ::- For Bulk Bitumen 80/100, 60/70:- HPCL Price List With Effect From Dt. 01-01-2015
For Emulsion (Bulk) :- HINCOL Price List With Effect From Dt.01-01-2015
Bulk 80/100 Bulk 60/70
Emulsion (Bulk)
Grade Grade
Vizag Vizag Vizag
Lead from
Vizg
160.00 Kms 480.00 480.00 480.00
Lead charges for Bulk @
1.50 per KM
Page 8
Quantity Description of Item Rate per Amount
1.00 hr Motor Grador for Grading @ 100 cum per hour 3220.00 hr 3220.00
(C) Material
Coarse graded Granular sub-base material as per
Table 400-2 of MORT&H
1459.68 Cum 372219.25
9.5mm to 4.75mm @ 66%
255.00 cum (Av. rate of 9.5-11.2mm , 5-7mm & 2.36 - 5mm HBG M/C metal)
Total 492363.40
(E) Total of (A) + (B)+( C)+(D) 537766.00
(F) Add Contractors Profit at 13.615% on (E) 73216.84
Cost per 300 cum (E) + (F) 610982.84
Page 9
Quantity Description of Item Rate per Amount
Rate per 1 cum 2036.61
Rate to be adopted 2037.00
1 Cum
4 Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to Wet Mix
macadem specification including cost,seignorage of all materials and including premixing the
material with water at OMC in Mechanical mix plant carriage of mixed material by tipper to site ,
laying in uniform layers with paver in base courses on well prepared surface and compacting
with Vibratory roller to acheive the desired density etc., as directed by the Engineer-in-Charge
and as per MoRT&H specification.406 (4 th revision) for finished item of work. (Payment based on
levels for finished item of work)
Unit = cum Page 110,111 of MoRT&H SDB
Taking output = 20% cum
(A) Labour
0.48 nos. Mate 320.00 day 153.60
2.00 nos. Mazdoor skilled 375.00 day 750.00
10.00 nos. Mazdoor 320.00 day 3200.00
0% MCA on Labour charges 4103.60 Cum 0.00
Total 4103.60
(B) Machinery
6.60 hr Wet mix plant of 60 tonne hr. capacity 1650.00 hr 10890.00
6.00 hr Electric generating set 10% KVA 1320.00 hr 7920.00
6.00 hr front end loader 1 cum capacity 1650.00 hr 9900.00
6.00 hr Mechanical Paver finisher 100 TPH 2250.00 hr 13500.00
3.90 hr Vibratory roller 8-10 T 2609.10 hr 10175.49
3.00 hr Water tanker 630.00 hr 1890.00
Total 54275.49
(C) Material
89.10 cum 45 to 22.40mm IRC&MoRT&H HBG M/C metal@ 30% 1650.68 cum 147075.89
(Av. Of 40-45, 0%-27, 19-22mm )
118.80 cum 22.4 to 2.36mm IRC&MoRT&H HBG M/C metal@40% 1459.35 cum 173370.78
(Av. Of 19-22mm, 12-14mm, 9.5-11.2mm, 5-7mm,
2.36 - 5mm )
89.10 cum 2.36mm to 75 micron @ 30% (2.36mm & bel 931.35 cum 82983.29
Total 403429.96
(E) Total of (A) + (B)+( C)+(D) 461809.05
(F) Add Contractors Profit at 13.615% on (E) 62875.30
Cost per 225 cum (E) + (F) 524684.35
Rate per 1 cum 2331.93
Rate to be adopted per 1 cum 2332.00
Cum
4 Providing and applying Prime coat with bitumen Emulsion (Medium settting) (Bulk) using
Emulsion pressure distributor at the rate of 0.60 kgs per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom for finished item of work as per
MoRT&H Specification 503 (4th revision) and as directed by the Engineer-in-Charge.
unit = sqm Page 124 of MoRT&H SDB
Page 10
Quantity Description of Item Rate per Amount
Taking output = 3500 sqm
(A) Labour
0.08 nos. Mate 320.00 day 25.60
2.00 nos. Mazdoor 320.00 day 640.00
0% MCA on Labour charges 665.60 Cum 0.00
Total 665.60
(B) Machinery
2.80 hr Mechanical broom @ 1250 sqm/hr. 375.00 hr 1050.00
2.80 hr Air compressor 250 cfm 538.20 hr 1506.96
2.00 hr Emulsion pressure distributor @1750 sqm/hr 860.00 hr 1720.00
1.00 hr Water Tanker 630.00 h 630.00
Total 4906.96
(C) Material
2.1 MT Bitumen Emulsion @ 0.60 Kg / sqm 32883.14 MT 69054.59
Total 69054.59
(E) Total of (A) + (B)+( C)+(D) 74627.15
(F) Add Contractors Profit at 13.615% on (E) 10160.49
Cost per 3500 sqm (E) + (F) 84787.64
Rate per 1 sqm 24.23
Rate to be adopted. 24.20
1 Sqm
5 Providing and applying tack coat with bitumen Emulsion (Medium settting) (Bulk) using Emulsion
pressure distributor at the rate of 0.20 kgs per sqm on the prepared bituminous/granular surface
cleaned with mechanical broom for finished item of work as per MoRT&H Specification 503 (4 th
revision) and as directed by the Engineer-in-Charge.
unit = sqm Page 124 of MoRT&H SDB
Taking output = 3500 sqm
(A) Labour
0.08 nos Mate 320.00 day 25.60
2.00 nos Mazdoor 320.00 day 640.00
0% MCA on Labour charges 665.60 Cum 0.00
Total 665.60
(B) Machinery
2.80 hr Mechanical broom Hydraulic @ 1250% sqm/hr. 375.00 hr 1050.00
Page 11
Quantity Description of Item Rate per Amount
(F) Add Contractors Profit at 13.615% on (E) 3806.86
Cost per 3500 sqm (E) + (F) 31767.62
Rate per 1 sqm 9.08
Rate to be adopted 9.10
1 Sqm
6 Providing 25 mm thick compacted Semi-Dense Bituminous Concrete by hot mix plant using
hard blasted granite crushed aggregates of Grading -2 as per table 500-15 of specification 508
of MoRT&H (4th Revision), premixed with bituminous binder 60/70 grade @ 5% of mix and filler,
transporting the hot mix to work site, laying with mechanical paver finisher to the required grade,
level and alignment, rolling with smooth wheeled,vibratory and tandem rollers to achieve the
desired compaction as per MoRT&H Specification 508 (4th Revision) complete for finished item
of work in all respects as directed by Engineer-in-charge.
116.850 cum IRC &MORT&H HBG M/C chips 4.75 mm 983.85 cum 114962.87
and below @ 41%
Average rate of IRC&MoRT&H HBG M/C cum 0.00
metal of sizes 2.36 - 5mm and 2.36mm&
below
5.70 cum Filler @ 2% of weight of aggregates. 931.35 cum 5308.70
Total 1170384.92
(E) Total of (A) + (B)+( C)+(D) 1503473.11
Page 12
Quantity Description of Item Rate per Amount
(F) Add Contractors Profit at 13.615% on (E) 204697.86
Cost per 195 cum (E) + (F) 1708170.97
Rate per 1 cum 8759.85
Rate to be adopted 8760.00
1 Cum
Page 13
ROAD METAL RATES as per 2015-2016 SSR
Name of the Work::- CONSTRUCTION OF HIGH LEVEL BRIDGE ON PETACALAVA MINOR DRAIN @ 3.50 KM
OPPOSITE SRMT STREET IN RAMANAYYAPRTA OF KAKINADA
Machine
Lead in Initial cost less Blasting
Sl.No Description of Metal Source of Supply
Kms
Conveyance
stacking charges
crushing Toal Cost per Cum
charges
Supeintending Engineer
PR,Circle Kakinada
[RSR]Price adjustment] [Seigniorage Charges Statement] 15/103
Sub Total
Or say
2) APPROCHES
Forming embankment
1 1 Cum. 576.00 -- -- 1.00 -- -- 22.00 22.00
selected earth
Sub Total
Or say
ABSTRACT FOR SEGNIORAGE CHARGES
Provision for Seigniorage charges (in Bridge proper portion+Approches)
1 Bridge Portion Seigniorage charges
2 Approch Seigniorage charges
Or Say
Total
Amount
671
1586
2410
1449
3809
356
1056
208
281
562
359
73
12820
13000
12672
1641
14313
15000
13000
15000
28000
30000
[RSR]Price adjustment] [Seigniorage Charges Statement] 18/103
DATA FOR CD WORKS
Name of Work :
CONSTRUCTION OF HIGH LEVEL BRIDGE ON PETACALAVA MINOR DRAIN
@ 3.50 KM OPPOSITE SRMT STREET IN RAMANAYYAPRTA OF KAKINADA
2 Sand filling in foundations including cost and conveyence of all materials to site and watering,
tamping etc., complete for finshed item of work as per MoRT&H specification 304 (4th Revision)
and as directed by the Engineer - in - Charge.
Page 19
Quantity Description of Item Rate per Amount
3 Providing PCC(1:3:6) nominal mix in foundation with crushed stone aggregate 40 mm nominal
size mechanically mixed , placed in foundation and compacted by vibration including curing etc.,
including all other incidental and operational charges of all T&P etc., complete for finished item
of work as per MoRT&H specification 2100 (4th Revision) .
Unit = cum Page 331 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.64 nos Mate 320.00 day 204.80
1.00 nos Mason 420.00 day 420.00
15.00 nos Mazdoor 320.00 day 4800.00
0% MCA on Labour charges 5424.80 Cum 0.00
Total 5424.80
(B) Material
13.50 cum Cost of 40mm SS-5 HBG M/C metal 1426.35 cum 19255.73
6.75 cum Sand at site 1227.61 cum 8286.37
3.45 MT Cement at site 5920.00 MT 20424.00
Total 47966.10
Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 456.20 hr 2737.20
6.00 hr Generator set 30 KVA 816.80 hr 4900.80
2.00 hr Water tanker 6 KL capacity 630.00 hr 1260.00
Total 8898.00
(E) Total of (A) + (B)+( C)+(D) 62288.90
(F) Add Contractors Profit at 13.615% on (E) 8480.63
Cost per 15 cum (E)+(F) 70769.53
Rate for 1 cum 4717.97
Rate to be adopted 4718.00
1 Cum
Page 20
Quantity Description of Item Rate per Amount
6.75 cum Sand at site 1227.61 cum 8286.37
5.21 MT Cement at site 5920.00 MT 30843.20
Total 63083.30
Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 456.20 hr 2737.20
6.00 hr Generator set 30 KVA 816.80 hr 4900.80
Total 7638.00
78026.50
(D) Form work
4.00 % Form work @ 4% on (A)+(B)+( C) 78026.50 Cum 3121.06
(F) Total of (A) + (B)+( C)+(D)+(E) 81147.56
(G) Add Contractors Profit at 13.615% on (F) 11048.24
Cost per 15 cum (F)+(G) 92195.80
Rate for 1 cum 6146.39
Rate to be adopted 6146.00
1Cum
4 Vibrated cement concrete M 20 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost and conveyance of all materials to site and all labour
charges for machine mixing,laying in position, Compacting , Vibrating and curing including all
other incidental and all other operational charges of T&P required etc., complete as per
MoRT&H Specification 1500,1700, 2100 (4th Revision) VCC M-20 for footings.
Unit = cum Page 335 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate 320.00 day 275.20
1.50 nos Mason 420.00 day 630.00
20.00 nos Mazdoor 320.00 day 6400.00
0% MCA on Labour charges 7305.20 Cum 0.00
Total 7305.20
Page 21
Quantity Description of Item Rate per Amount
(B) Material
5.40 cum Cost of 40mm SS-5 HBG M/C metal 1426.35 cum 7702.29
5.40 cum Cost of 20mm SS-5 HBG M/C metal 1946.35 cum 10510.29
2.70 cum Cost of 10mm SS-5 HBG M/C metal 1516.35 cum 4094.15
6.75 cum Sand at site 1227.61 cum 8286.37
5.16 MT Cement at site 5920.00 MT 30547.20
Total 61140.30
Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 456.20 hr 2737.20
6.00 hr Generator set 35 KVA 816.80 hr 4900.80
Total 7638.00
76083.50
(D) Form work
4.00 % Form work @ 4% on (A)+(B)+( C) 76083.50 Cum 3043.34
(F) Total of (A) + (B)+( C)+(D)+(E) 79126.84
(G) Add Contractors Profit at 13.615% on (F) 10773.12
Cost per 15 cum (F)+(G) 89899.96
Rate for 1 cum 5993.33
Rate to be adopted 5993.00
1 Cum
5 Vibrated cement concrete M 20 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost and conveyance of all materials to site and all labour
charges for machine mixing, laying in position,Compacting, Vibrating and curing including all
other incidental and all other operational charges of T&P required etc., complete as per
MoRT&H Specification 1500,1700, 2200 (4th Revision) for Sub structure .VCC M-20 for Sub
structure of Retaining wall
Unit = cum Page 335,455 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate 320.00 day 275.20
1.50 nos Mason 420.00 day 630.00
20.00 nos Mazdoor 320.00 day 6400.00
0% MCA on Labour charges 7305.20 Cum 0.00
Total 7305.20
(B) Material
5.40 cum Cost of 40mm SS-5 HBG M/C metal 1426.35 cum 7702.29
5.40 cum Cost of 20mm SS-5 HBG M/C metal 1946.35 cum 10510.29
2.70 cum Cost of 10mm SS-5 HBG M/C metal 1516.35 cum 4094.15
6.75 cum Sand at site 1227.61 cum 8286.37
5.16 MT Cement at site 5920.00 MT 30547.20
Total 61140.30
Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 456.20 hr 2737.20
6.00 hr Generator set 35 KVA 816.80 hr 4900.80
7638.00
Page 22
Quantity Description of Item Rate per Amount
(D) Form work 76083.50
10.00 % Form work @ 10% on (A)+(B)+( C) 76083.50 Cum 7608.35
(F) Total of (A) + (B)+( C)+(D)+(E) 83691.85
(G) Add Contractors Profit at 13.615% on (F) 11394.65
Cost per 15 cum (F)+(G) 95086.50
Rate for 1 cum 6339.10
Rate to be adopted 6339.00
1 Cum
6 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters
including cost and conveyance of steel to site and all labour charges for fabrication of
reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc.,
complete including cost and conveyance of binding wire and all handling charges and
operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4th revision) and as per
I.S.1786 of 1985 for Sub structure of R.C.C items.
Unit = MT Page 459,460 of MoRT&H SDB
Taking output = 1 MT
(A) Labour
0.34 nos Mate 320.00 day 108.80
2.00 nos Black smith 320.00 day 640.00
6.50 nos Mazdoor 320.00 day 2080.00
0% MCA on Labour charges 2828.80 Cum 0.00
Total 2828.80
(B) Material
1.05 MT HYSD bars including overlaps 42000.00 MT 44100.00
6.00 Kg Binding wire 70000.00 MT 420.00
Total 44520.00
(D) Total of (A) + (B)+( C) 47348.80
(E) Add Contractors Profit at 13.615% on (D) 6446.54
Rate for 1 MT (D)+(E) 53795.34
Rate to be adopted 53795.00
1 MT
Page 23
Quantity Description of Item Rate per Amount
7 Providing HYSD bars (Fe-415) of different diameters, wrought and put up bars of all diameters
including cost and conveyance of steel to site and all labour charges for fabrication of
reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc.,
complete including cost and conveyance of binding wire and all handling charges and
operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4th revision) and as per
I.S.1786 of 1985 for foundations of R.C.C items.
Unit = MT Page 448 of MoRT&H SDB
Taking output = 1 MT
(A) Labour
0.40 nos Mate 320.00 day 128.00
2.00 nos Black smith 320.00 day 640.00
6.00 nos Mazdoor 320.00 day 1920.00
0% MCA on Labour charges 2688.00 Cum 0.00
Total 2688.00
(B) Material
1.05 MT HYSD bars including overlaps 42000.00 MT 44100.00
6.00 Kg Binding wire 70000.00 MT 420.00
Total 44520.00
(D) Total of (A) + (B)+( C) 47208.00
(E) Add Contractors Profit at 13.615% on (D) 6427.37
Rate for 1 MT (D)+(E) 53635.37
Rate to be adopted 53635.00
1 MT
8 Providing and laying of filter media with Granular materials / stone crushed aggregates
satisfying the requirements laid down in clause 2504.2.2 of MoRT&H specifications to a
thickness of not less than 600mm with smaller size towards the soil and bigger size towards the
wall and provided over the entire surface behind the abutment, wing wall and return wall to the
full height compacted to a firm condition including cost and conveyance of all metal and all
labour charges as directed by the departmental officers as per drawing and Technical
specifications as per clause 710.1.1 of IRC:78 and Clause 2200 of MoRT&H (4 th Revision) for
finished item of work.
Unit = cum Page 463 of MoRT&H SDB
Taking output = 10 cum
(A) Labour
0.32 nos Mate 320.00 day 102.40
7.00 nos Mazdoor for filling watering, ramming etc 320.00 day 2240.00
1.00 nos Mazdoor skilled 320.00 day 320.00
0% MCA on Labour charges 2662.40 Cum 0.00
Total 2662.40
(B) Material
Filter media of stone aggregate conforming
to clause 2504.2.2 of MoRT&H
6.00 cum Cost of 150mm size IRC soling stone (HBG) 746.35 cum 4478.10
6.00 cum Cost of 40mm size IRC HBG metal 1426.35 cum 8558.10
Total 13036.20
Page 24
Quantity Description of Item Rate per Amount
Machinery
0.06 hr Water tanker 6 KL capacity 630.00 hr 37.80
Total 37.80
(E) Total of (A) + (B)+( C)+(D) 15736.40
(F) Add Contractors Profit at 13.615% on (E) 2142.51
Cost per 10 cum (E)+(F) 17878.91
Rate for 1 cum 1787.89
Rate to be adopted 1788.00
1 Cum
Page 25
Quantity Description of Item Rate per Amount
Cost Per 30 RM (D)+(E) 6990.22
Cost per 1RM 233.01
Rate to be adopted 233.00
1 RM
10 Back filling behind Abutments with gravel including cost and conveyance of all materials to site
etc., complete as per Clause 710.1.4 of IRC : 78and as per MoRT&H Specification No. 2200
(4th Revision) and as per Drawing and technical specifications for finished item of work
Unit = cum Page 462 of MoRT&H SDB
Taking output = 10 cum
(A) Labour
0.28 nos Mate 320.00 day 89.60
7.00 nos Mazdoor 320.00 day 2240.00
0% MCA on Labour charges 2329.60 Cum 0.00
Total 2329.60
(B) Material
12.00 cum Cost of Granular material 274.02 cum 3288.24
Total 3288.24
Machinery
2.50 hr Plate compactor/Power rammer/road roller 58.00 hr 145.00
0.05 hr Water tanker 6 KL capacity 630.00 hr 31.50
Total 176.50
(E) Total of (A) + (B)+( C)+(D) 5794.34
(F) Add Contractors Profit at 13.615% on (E) 788.90
Cost per 10 cum (E)+(F) 6583.24
Rate for 1 cum 658.32
Rate to be adopted 658.00
1 Cum
Page 26
BRIDGE DATA
Name of Work ::- CONSTRUCTION OF HIGH LEVEL BRIDGE ON PETACALAVA MINOR DRAIN @ 3.50 KM
OPPOSITE SRMT STREET IN RAMANAYYAPRTA OF KAKINADA
FOR BRIDGE
Quantity Description of Item Rate per Amount
1 Earthwork in excavation of foundation of structures as per drawing and technical specification including setting
out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing sides of
bottom, back filling the excavation earth to the extent required etc., complete for finished item of work as per
MoRT&H specification 304(4th Revision)
Unit : Cum Page 323 of MoRT&H SDB
Taking out put = 240 Cum
a) excluding dewatering charges In all soils upto SDR upto 3.0 m depth using machinary
(A) Labour
0.32 day Mate 320.00 day 102.40
8.00 day Mazdoor unskilled 320.00 day 2560.00
0% MCA on Labour charges 2662.40 Cum 0.00
Total 2662.40
(B) Machinery
240.00 cum Rate as per G.O. Ms No 13.615, Dt 26/7/2005 13.00 cum 3120.00
(E) Total of (A) + (B) 5782.40
(F) Add Contractors Profit at 13.615% on (E) 787.27
Cost per 240 cum (E)+(F) 6569.67
Rate for 1 cum 27.37
Rate to be adopted 27.40
1 Cum
2 Providing PCC (1:3:6) nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically
mixed , placed in foundation and compacted by vibration including curing etc., including all other incidental and
operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification 213.6150
(4th Revision) .
Unit = cum Page 331 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.64 nos Mate 320.00 day 204.80
1.00 nos Mason 420.00 day 420.00
15.00 nos Mazdoor 320.00 day 4800.00
0% MCA on Labour charges 5424.80 Cum 0.00
Total 5424.80
(B) Material
13.50 cum Cost of 40mm SS-5 HBG M/C metal 1426.35 cum 19255.73
6.75 cum Sand at site 1227.61 cum 8286.37
3.45 MT Cement at site 5920.00 MT 20424.00
Total 47966.10
Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 456.20 hr 2737.20
6.00 hr Generator set 30 KVA 816.80 hr 4900.80
2.00 hr Water tanker 6 KL capacity 630.00 hr 1260.00
Total 8898.00
(E) Total of (A) + (B)+( C)+(D) 62288.90
(F) Add Contractors Profit at 13.615% on (E) 8480.63
Cost per 15 cum (E)+(F) 70769.53
Rate for 1 cum 4717.97
Rate to be adopted 4718.00
1 Cum
Note: Vibrator is a part of minor T&P which is already included in over head
charges of the contractor
Page 27
Quantity Description of Item Rate per Amount
3 Vibrated cement concrete M 20 Grade Concrete using 40mm , 20mm and 13.615mm size HBG crushed stone
aggregate (Coarse aggregate conforming to table 13.61500-1 and fine aggregate conforming to table 13.61500-2)
including cost and conveyance of all materials to site and all labour charges for machine mixing,laying in position,
Compacting , Vibrating and curing including all other incidental and all other operational charges of T&P required
etc., complete as per MoRT&H Specification 1500,1700, 213.6150 (4th Revision) VCC M-20 for for Footing of
Abutments, Piers, Rigid approns, Cut off walls, Wing walls.
Unit = cum Page 335 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate 320.00 day 275.20
1.50 nos Mason 420.00 day 630.00
20.00 nos Mazdoor 320.00 day 6400.00
0% MCA on Labour charges 7305.20 Cum 0.00
Total 7305.20
(B) Material
5.40 cum Cost of 40mm SS-5 HBG M/C metal 1426.35 cum 7702.29
5.40 cum Cost of 20mm SS-5 HBG M/C metal 1946.35 cum 10510.29
2.70 cum Cost of 10mm SS-5 HBG M/C metal 1444.97 cum 3901.42
6.75 cum Sand at site 1227.61 cum 8286.37
5.16 MT Cement at site 5920.00 MT 30547.20
Total 60947.57
Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 456.20 hr 2737.20
6.00 hr Generator set 30 KVA 816.80 hr 4900.80
Total 7638.00
75890.77
(D) Form work
4.00 % Form work @ 4% on (A)+(B)+( C) 75890.77 Cum 3035.63
(F) Total of (A) + (B)+( C)+(D)+(E) 78926.40
(G) Add Contractors Profit at 13.615% on (F) 10745.83
Cost per 15 cum (F)+(G) 89672.23
Rate for 1 cum 5978.15
Rate to be adopted 5978.00
1 Cum
4 Vibrated cement concrete M 20 Grade Concrete using 40mm , 20mm and 13.615mm size HBG crushed stone
aggregate (Coarse aggregate conforming to table 13.61500-1 and fine aggregate conforming to table 13.61500-2)
including cost and conveyance of all materials to site and all labour charges for machine mixing, laying in
position,Compacting, Vibrating and curing including all other incidental and all other operational charges of T&P
required etc., complete as per MoRT&H Specification 1500,1700, 2200 (4th Revision) for Sub structure .VCC M-
20 for Sub structure of Abutments, Piers and Wing walls.
Unit = cum Page 335,455 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate 320.00 day 275.20
1.50 nos Mason 420.00 day 630.00
20.00 nos Mazdoor 320.00 day 6400.00
0% MCA on Labour charges 7305.20 Cum 0.00
Total 7305.20
(B) Material
5.40 cum Cost of 40mm SS-5 HBG M/C metal 1426.35 cum 7702.29
5.40 cum Cost of 20mm SS-5 HBG M/C metal 1946.35 cum 10510.29
2.70 cum Cost of 10mm SS-5 HBG M/C metal 1516.35 cum 4094.15
6.75 cum Sand at site 1227.61 cum 8286.37
5.16 MT Cement at site 5920.00 MT 30547.20
Total 61140.30
Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 456.20 hr 2737.20
6.00 hr Generator set 30 KVA 816.80 hr 4900.80
7638.00
Page 28
Quantity Description of Item Rate per Amount
(D) Form work 76083.50
10.00 % Form work @ 10% on (A)+(B)+( C) 76083.50 Cum 7608.35
(F) Total of (A) + (B)+( C)+(D)+(E) 83691.85
(G) Add Contractors Profit at 13.615% on (F) 11394.65
Cost per 15 cum (F)+(G) 95086.50
Rate for 1 cum 6339.10
Rate to be adopted 6339.00
1 Cum
5 V.R.C.C. M20 grade concrete using 20mm and 13.615mm size SS5 HBG crushed stone aggregate including cost
and conveyance of all materials to site, labour charges for machine mixing, laying, compacting, curing
etc,including all other incidental and operational charges,T&P charges etc, complete but excluding cost of steel
and its fabrication charges, as per MoRT&H Specifications 1500,1700,213.6150(4th Revision) for bed blocks &
backing walls
Unit = cum Page 472,457 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate 320.00 day 275.20
1.50 nos Mason 420.00 day 630.00
20.00 nos Mazdoor 320.00 day 6400.00
0% MCA on Labour charges 7305.20 Cum 0.00
Total 7305.20
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 1946.35 cum 15765.44
5.40 cum Cost of 10mm SS-5 HBG M/C metal 1516.35 8188.29
6.75 cum Sand at site 1227.61 cum 8286.37
5.16 MT Cement at site 5920.00 MT 30547.20
Total 62787.30
Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 456.20 hr 2737.20
6.00 hr Generator set 30 KVA 816.80 hr 4900.80
Total 7638.00
Total A+B+C for 15 cum 77730.50
a) Height from 5m to 10m
Basic rate for 15 cum of concrete 77730.50
1.60 % Add on cost of concrete to cater extra lift 77730.50 Rs 1243.69
11.50 % Add for Form work on cost of concrete 77730.50 Rs 8939.01
Total Rs 87913.20
87913.20
13.615 % Add for Contractors profit 11969.38
Rate Per 15 Cum 99882.58
Rate Per 1 Cum 6658.84
Rate to be adopted 6659.00
1Cum
b) Height upto 5m
Basic rate for 15 cum of concrete 77730.50
13.62 % Add from work on cost of concrete 77730.50 Rs 10583.01
Total Rs 88313.51
13.615 % Add for Contractors profit 12023.88
Rate Per 15 Cum 100337.39
Rate Per 1 Cum 6689.16
Rate to be adopted 6689.00
1Cum
Page 29
Quantity Description of Item Rate per Amount
6 V.R.C.C concrete M - 20 grade for Super Structure with 20 mm(SS5)HBG M/C graded metal with a cube
strength of 25 N / mm2 at 28 days work test on 150 X 150 X 150 mm cubes and cost and and conveyance of
all materials, vibrating centering machine mixing, curing hire and operational charges of all T& P but excluding
cost and its fabrication charges of steel etc complete as per M.O.T DRG No SD/166 excluding cost of steel and
fabrication charges for VRCC M-30 Super structure of deck slabs
Unit = cum Page 472 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.90 nos Mate 320.00 day 288.00
1.50 nos Mason 420.00 day 630.00
21.00 nos Mazdoor 320.00 day 6720.00
0% MCA on Labour charges 7638.00 Cum 0.00
Total 7638.00
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 1946.35 cum 15765.44
5.40 cum Cost of 10mm SS-5 HBG M/C metal 1516.35 8188.29
6.75 cum Sand at site 1227.61 cum 8286.37
5.16 MT Cement at site 5920.00 MT 30547.20
Total 62787.30
Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 456.20 hr 2737.20
6.00 hr Generator set 35 KVA 816.80 hr 4900.80
Total 7638.00
Total 78063.30
a) For form work add the following (Height 0 - 5 m)
for Deck slab slab Super structure
78063.30
20.00 % Height upto 5m - 20 percent 78063.30 15612.66
93675.96
93675.96
13.615 % Add Contractor's Profit 93675.96 12753.98
Rate per 15 cum 106429.94
Rate per cum 7095.33
Or Say 7095.00
1Cum
b) For form work add the following (Height 5 - 10 m)
for Deck slab Super structure 25
of Basic rate of concrete 78063.30
25.00 % Height above 5m to 10m - 25 percent 78063.30 19515.83
97579.13
97579.13
13.615 % Add Contractor's Profit 97579.13 13285.40
Rate per 15 cum 110864.53
Rate per cum 7390.97
Or Say 7391.00
1Cum
e) For form work and staging add the following
for foot Paths & kerbs
of Basic rate of concrete (M 20) 78063.30
2.00 % Form work - 2 percent 78063.30 1561.27
79624.57
79624.57
13.615 % Add Contractor's Profit 79624.57 10840.89
Rate per 15 cum 90465.46
Rate per cum 6031.03
Or Say 6031.00
1Cum
Page 30
Quantity Description of Item Rate per Amount
7 Construction of RCC railing of M20 grade using in-situ with 12 mm nominal size aggregate, true to line and
grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical posts not
to exceed 1870mm, leaving adequate space between vertical posts for expansion, complete as per approved
drawings and technical specifications asper MoRT&H Spcn. No 2703, 1500, 1600, 1700 as per MORT&H DWG
NO:SD/202
Unit = 1 RM
Hand rails with foot paths
Takingoutput =6.542M 6.542 Rm
M20 grade VRCC
no. of end vertical Posts
2*0.275*0.25*1.1 0.1513 cum
no. of internal vertical posts Posts
3*0.275*0.25*1.1 0.2269 cum
Hand rails in 3 tiers (6.542-(2*0.25+3*0.25)) 5.292 Rm
Qty of RCC (5.292x3x0.175x0.17) 0.4723 cum
Total Concrete for 6.542 Rm = 0.8504 cum
VRCC M 20 Grade taking output = 15.00 cum
(A) Labour
0.90 nos Mate 320.00 day 288.00
1.50 nos Mason 420.00 day 630.00
21.00 nos Mazdoor 320.00 day 6720.00
0% MCA on Labour charges 7638.00 Cum 0.00
Total 7638.00
(B) Material
8.10 cum Cost of 12mm SS-5 HBG M/C metal 1678.85 cum 13598.69
5.40 cum Cost of 10mm SS-5 HBG M/C metal 1516.35 cum 8188.29
6.75 cum Sand at site 1227.61 cum 8286.37
6.10 MT Cement at site 5920.00 MT 36112.00
Total 66185.35
(c) Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 456.20 hr 2737.20
6.00 hr Generator set 30 KVA 816.80 hr 4900.80
Total 7638.00
Cost per 15 cum (A)+(B)+(C) 81461.35
Rate for 1 cum 5430.76
Tacking out put (6.542 m Span)
Material
0.8504 cum VRCC M 20Grade 5430.76 cum 4618.51
(D) Form work
5.00 % Add from work for casting in casting yard 4618.51 Cum 230.93
5.00 % Add handling and fixing of pannels 4849.44 Cum 242.47
(F) Total of (A) + (B)+( C)+(D) 5091.91
(G) Add Contractors Profit at 13.615% on (E) 693.26
Cost per 6.542RM (F)+(G) 5785.18
Rate for 1 RM 884.31
Rate to be adopted Rs 884.00
1 Rm
Page 31
Quantity Description of Item Rate per Amount
8 Plain cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone aggregate
(Coarse aggregate conforming to table 13.61500-1 and fine aggregate conforming to table 13.61500-2) including
cost and conveyance of all materials to site and all labour charges for machine mixing,laying in position,
Compacting , Vibrating and curing including all other incidental and all other operational charges of T&P required
etc., complete as per MoRT&H Specification 1500,1700, 213.6150 & 2700 (4th Revision) for Levelling course
below approach slab.
Unit = cum Page 335 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate 320.00 day 275.20
1.50 nos Mason 420.00 day 630.00
20.00 nos Mazdoor 320.00 day 6400.00
0% MCA on Labour charges 7305.20 Cum 0.00
Total 7305.20
(B) Material
8.10 cum Cost of 40mm SS-5 HBG M/C metal 1426.35 cum 11553.44
4.05 cum Cost of 20mm SS-5 HBG M/C metal 1946.35 cum 7882.72
1.35 cum Cost of 10mm SS-5 HBG M/C metal 1516.35 cum 2047.07
6.75 cum Sand at site 1227.61 cum 8286.37
4.13 MT Cement at site 5920.00 MT 24449.60
Total 54219.20
Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 456.20 hr 2737.20
6.00 hr Generator set 30 KVA 816.80 hr 4900.80
Total 7638.00
(E) Total of (A) + (B)+( C)+(D) 69162.40
(F) Add Contractors Profit at 13.615% on (E) 9416.46
Cost per 15 cum (E)+(F) 78578.86
Rate for 1 cum 5238.59
Rate to be adopted 5239.00
1Cum
9 V.R.C.C. M20 grade concrete using 20mm and 10mm size SS5 HBG crushed stone aggregate including cost and
conveyance of all materials to site, labour charges for machine mixing,laying,compacting,curing etc,including all
other incidental and operational charges,T&P chargesetc, complete but excluding cost of steel and its fabrication
charges, as per MoRT&H Specifications 1500,1700,2704(4th Revision) . For Approach Slab as per DWG
NO:SD/157&158.
Unit = cum Page 340,501 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate 320.00 day 275.20
1.50 nos Mason 420.00 day 630.00
20.00 nos Mazdoor 320.00 day 6400.00
0% MCA on Labour charges 7305.20 Cum 0.00
Total 7305.20
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 1946.35 cum 15765.44
5.40 cum Cost of 10mm SS-5 HBG M/C metal 1516.35 cum 8188.29
6.75 cum Sand at site 1227.61 cum 8286.37
5.16 MT Cement at site 5920.00 MT 30547.20
Total 62787.30
Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 456.20 hr 2737.20
6.00 hr Generator set 35 KVA 816.80 hr 4900.80
Total 7638.00
(D) Form work
2.00 % Form work @ 2% on (A)+(B)+( C) 77730.50 Cum 1554.61
(F) Total of (A) + (B)+( C)+(D)+(E) 79285.11
Page 32
Quantity Description of Item Rate per Amount
(G) Add Contractors Profit at 13.615% on (F) 10794.67
Cost per 15 cum (F)+(G) 90079.78
Rate for 1 cum M 30 Concrete 6005.32
Rate to be adopted 6005.00
1 Cum
10 V.R.C.C. M20 grade concrete using 20mm and 10mm size SS5 HBG crushed stone aggregate including cost and
conveyance of all materials to site, labour charges for machine mixing,laying,compacting,curing etc,including all
other incidental and operational charges,T&P chargesetc, complete but excluding cost of steel and its fabrication
charges, as per MoRT&H Specifications 1500,1700,2702 For Wearing coat .as per DWG NO:SD/151
Unit = cum Page 477,492 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.90 nos Mate 320.00 day 288.00
1.50 nos Mason 420.00 day 630.00
21.00 nos Mazdoor 320.00 day 6720.00
0% MCA on Labour charges 7638.00 Cum 0.00
Total 7638.00
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 1946.35 cum 15765.44
5.40 cum Cost of 10mm SS-5 HBG M/C metal 1516.35 cum 8188.29
6.75 cum Sand at site 1227.61 cum 8286.37
5.16 MT Cement at site 5920.00 MT 30547.20
Total 62787.30
Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 456.20 hr 2737.20
6.00 hr Generator set 30 KVA 816.80 hr 4900.80
7638.00
(A+B+C) =Rate per 15 cum 78063.30
Basic Rate per cum 5204.22
0.15 nos Labour for cleaning deck slab concrete 320.00 day 48.00
0% MCA on Labour charges 48.00 Cum 0.00
Rate per cum 5252.22
(E) Total of (A) + (B)+( C)+(D) 5252.22
(F) Add Contractors Profit at 13.615% on (E) 715.09
Cost per 15 cum (E)+(F) 5967.31
Rate to be adopted 5967.00
1 Cum
11 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters including cost and
conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting, bending,
binding rods, tying grills, placing them in position etc., complete including cost and conveyance of binding wire
and all handling charges and operational charges etc., and including over lapping welding if required etc.,
complete for all R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4th revision) and as per I.S.1786 of 1985
for Super structure of R.C.C items.
Unit = MT Page 489,490 of MoRT&H SDB
Taking output = 1 MT
(A) Labour
0.44 nos Mate 320.00 day 140.80
3.00 nos Black smith 420.00 day 1260.00
8.00 nos Mazdoor 320.00 day 2560.00
0% MCA on Labour charges 3960.80 Cum 0.00
Total 3960.80
(B) Material
1.05 MT HYSD bars including overlaps 42000.00 MT 44100.00
8.00 Kg Binding wire 70000.00 MT 560.00
Total 44660.00
(E) Add Contractors Profit at 13.615% on (D) 6080.46
Rate for 1 MT (D)+(E) 50740.46
Rate to be adopted 50740.00
1 MT
Page 33
Quantity Description of Item Rate per Amount
12 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters including cost and
conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting, bending,
binding rods, tying grills, placing them in position etc., complete including cost and conveyance of binding wire
and all handling charges and operational charges etc., and including over lapping welding if required etc.,
complete for all R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4th revision) and as per I.S.1786 of 1985
for Sub structure of R.C.C items.
Unit = MT Page 459,460 of MoRT&H SDB
Taking output = 1 MT
(A) Labour
0.34 nos Mate 320.00 day 108.80
2.00 nos Black smith 420.00 day 840.00
6.50 nos Mazdoor 320.00 day 2080.00
0% MCA on Labour charges 3028.80 Cum 0.00
Total 3028.80
(B) Material
1.05 MT HYSD bars including overlaps 42000.00 MT 44100.00
6.00 Kg Binding wire 70000.00 MT 420.00
Total 44520.00
(E) Add Contractors Profit at 13.615% on (D) 6061.40
Rate for 1 MT (D)+(E) 50581.40
Rate to be adopted 50581.00
1 MT
13 Providing HYSD bars (Fe-415) of different diameters, wrought and put up bars of all diameters including cost and
conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting, bending,
binding rods, tying grills, placing them in position etc., complete including cost and conveyance of binding wire
and all handling charges and operational charges etc., and including over lapping welding if required etc.,
complete for all R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4th revision) and as per I.S.1786 of 1985
for foundations of R.C.C items.
Unit = MT Page 448 of MoRT&H SDB
Taking output = 1 MT
(A) Labour
0.40 nos Mate 320.00 day 128.00
2.00 nos Black smith 420.00 day 840.00
6.00 nos Mazdoor 320.00 day 1920.00
0% MCA on Labour charges 2888.00 Cum 0.00
Total 2888.00
(B) Material
1.05 MT HYSD bars including overlaps 44000.00 MT 46200.00
6.00 Kg Binding wire 70000.00 MT 420.00
Total 46620.00
(E) Add Contractors Profit at 13.615% on (D) 6347.31
Rate for 1 MT (D)+(E) 52967.31
Rate to be adopted 52967.00
1 MT
14 Back filling behind Abutments with gravel including cost and conveyance of all materials to site etc., complete as
per Clause 713.615.1.4 of IRC : 78and as per MoRT&H Specification No. 2200 (4th Revision) and as per
Drawing and technical specifications for finished item of work
Unit = cum Page 462 of MoRT&H SDB
Taking output = 13.615 cum
(A) Labour
0.28 nos Mate 320.00 day 89.60
7.00 nos Mazdoor 320.00 day 2240.00
0% MCA on Labour charges 2329.60 Cum 0.00
Total 2329.60
(B) Material
12.00 cum Cost of Granular material 274.02 cum 3288.24
Total 3288.24
Page 34
Quantity Description of Item Rate per Amount
Machinery
2.50 hr Plate compactor/Power rammer/road roller 58.00 hr 145.00
0.05 hr Water tanker 6 KL capacity 630.00 hr 31.50
Total 176.50
(E) Total of (A) + (B)+( C)+(D) 5794.34
(F) Add Contractors Profit at 13.615% on (E) 788.90
Cost per 13.615 cum (E)+(F) 6583.24
Rate for 1 cum 483.53
Rate to be adopted 484.00
1 Cum
15 Providing and laying of filter media with Granular materials / stone crushed aggregates satisfying the
requirements laid down in clause 2504.2.2 of MoRT&H specifications to a thickness of not less than 600mm with
smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind the
abutment, wing wall and return wall to the full height compacted to a firm condition including cost and conveyance
of all metal and all labour charges as directed by the departmental officers as per drawing and Technical
specifications as per clause 713.615.1.1 of IRC:78 and Clause 2200 of MoRT&H (4th Revision) for finished item
of work.
Unit = cum Page 463 of MoRT&H SDB
Taking output = 13.615 cum
(A) Labour
0.32 nos Mate 320.00 day 102.40
7.00 nos Mazdoor for filling watering, ramming etc 320.00 day 2240.00
1.00 nos Mazdoor skilled 375.00 day 375.00
0% MCA on Labour charges 2717.40 Cum 0.00
Total 2717.40
(B) Material
Filter media of stone aggregate conforming
to clause 2504.2.2 of MoRT&H
6.00 cum Cost of 150mm size IRC soling stone (HBG) 746.35 cum 4478.10
6.00 cum Cost of 40mm size IRC HBG metal 1426.35 cum 8558.10
Total 13036.20
Machinery
0.06 hr Water tanker 6 KL capacity 630.00 hr 37.80
Total 37.80
(E) Total of (A) + (B)+( C)+(D) 15791.40
(F) Add Contractors Profit at 13.615% on (E) 2150.00
Cost per 10 cum (E)+(F) 17941.40
Rate for 1 cum 1794.14
Rate to be adopted 1794.00
1 Cum
16 Providing Grouted Revetment with rough stone (HBG) of not less than 300 mm size grouted with 0.20 cum of CC
(1:4:8) including cost and conveyance of materials to site and including labour charges for packing the stones for
revetment etc., complete for finished item of work as per MoRT&H specification 2504 ( 4th revision ) and as
directed by the Engineer-in-Charge for quadrential revetment.
Cost of CC(1:4:8) Page 331,522 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.64 nos Mate 320.00 day 204.80
1.00 nos Mason 420.00 day 420.00
15.00 nos Mazdoor 320.00 day 4800.00
0% MCA on Labour charges 5424.80 Cum 0.00
Total 5424.80
(B) Material
13.50 cum Cost of 40mm SS-5 HBG M/C metal 1426.35 cum 19255.73
6.75 cum Sand at site 1227.61 cum 8286.37
2.43 MT Cement at site 5920.00 MT 14385.60
Total 41927.70
Page 35
Quantity Description of Item Rate per Amount
(c) Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 456.20 hr 2737.20
6.00 hr Generator set 30 KVA 816.80 hr 4900.80
2.00 hr Water tanker 630.00 hr 1260.00
8898.00
Cost per 15 cum 56250.50
Rate for 1 cum 3750.03
17 Providing rough stone revetment other than granite 300 mm size rough stone varity including cost and
conveyance of materials to site and including labour charges for packing the stones for revetment etc., complete
for finished item of work as per MoRT&H specification 2504 ( 4th revision ) and as directed by the Engineer-in-
Charge.
(A) Labour Page 522 of MoRT&H SDB
0.04 nos Mate 320.00 day 12.80
0.35 nos Mason 420.00 day 147.00
0.75 nos Mazdoor for laying stones, filling quarry spalls 320.00 day 240.00
0% MCA on Labour charges 399.80 Cum 0.00
Total 399.80
(B) Material
1.00 cum Cost of Rough stone 300mm thick 812.35 cum 812.35
0.20 cum Cost of stone spalls 684.35 cum 136.87
Total 949.22
(D) Total of (A) + (B)+( C) 1349.02
(E) Add Contractors Profit at 13.615% on (D) 183.67
1532.69
Cost per 1 cum 1532.69
Rate to be adopted 1533.00
1 Cum
18 Providing and laying filter material with Gravel underneath pitching in slopes including cost and conveyance of
materials to site including labour charges etc., complete for finished item of work as per MoRT&H Specification
Page 36
Quantity Description of Item Rate per Amount
Cost per 1 cum 874.63
Rate to be adopted 875.00
1 Cum
19 Providing weep holes in Brick masonry/Plain/Reinforced concrete Abutment/wing wall/Return wall with
13.6150mm dia meter A/C pipe extending through the full width of the structure with slope of about 1 V : 20H
towards drawing face Complete as per drawing and technical specification, complete for finished item of work for
weep holes as per MORTH specification No 2706 & 2200 (4th Revision)
Unit = nos
Taking output = 30 RM
Output = 1 Cum, Material for 1:3 Cement Mortor
(A) Labour
0.04 nos Mate 320.00 day 12.80
0.90 nos Mazdoor 420.00 day 378.00
0% MCA on Labour charges 390.80 Cum 0.00
Total 390.80
(B) Material
0.51 MT Cost of Cement 5920.00 MT 3019.20
1.05 Cum Cost of Sand 1227.61 cum 1288.99
Total 4308.19
Cost per 1 Cum CM (1:3) 4698.99
(A) Labour
0.03 nos Mate 320.00 day 9.60
0.50 nos Mason 420.00 day 210.00
0.25 Mazdoor 320.00 day 80.00
0% MCA on Labour charges 299.60 Cum 0.00
Total 299.60
(B) Material
31.5 RM Cost of 100mm dia AC pipe 268.00 RM 8442.00
including 5% wastage (average length= 1m)
10.00 Nos Collors for AC pipe (average) taking 10 of pipe 26.80 Each 268.00
30.00 Nos MS clamps 13.00 Each 390.00
0.05 cum Cement mortor (1:3) 4698.99 Cum 234.95
Total 9334.95
(D) Total of (A) + (B)+( C) 9634.55
(E) Add Contractors Profit at 13.615% on (D) 1311.74
Cost Per 30 RM (D)+(E) 10946.29
Cost per 1RM 364.88
Rate to be adopted 365.00
1 RM
Page 37
Quantity Description of Item Rate per Amount
20 Supplying and fixing CI drianage spoutes complete as per MORTH specification no. 2705
Unit = 1 Nos
Taking output = 1Nos
(a) Material
Corrosion resistant structural steel including 5 percent
4 kg 61.00 kg 244.00
wastage
2.00 meter G.I Pipe 100mm dia 161.00 meter 322.00
6.00 each GI Bolt 10mm dia 11.00 each 66.00
2.00 each Galvanized MS Flat clamp 195.00 each 390.00
Total 1022.00
21 Providing and laying Flexble aprons on river bed for protection against scour with 450 mm to 600 mm jeddy stone
boulders weighing not less than 40 Kg each complete as per drawing and MoRT&H SpecificationNo.2503.
Unit = cum
Taking output = 1 cum
(A) Labour
0.04 nos Mate 320.00 day 12.80
0.35 nos Mazdoor for filling watering, ramming etc 320.00 day 112.00
0.75 nos Mazdoor skilled 375.00 day 281.25
0% MCA on Labour charges 406.05 Cum 0.00
Total 406.05
(B) Material
1.00 cum Stone (jeddy stone) 569.77 cum 569.77
0.20 cum Stone spalls 684.35 cum 136.87
Total 706.64
Total of (A) + (B) 1112.69
1.00 % of cost of material and labour for trimming and preparation of bed 1112.69 11.13
(D) Total of (A) + (B)+( C)+(D) 1529.87
(F) Add Contractors Profit at 13.615% on (E) 208.29
Cost per 1 cum (E)+(F) 1738.16
Rate for 1 cum 1738.16
Rate to be adopted 1738.00
1 Cum
Page 38
Quantity Description of Item Rate per Amount
22 Vibrated cement Reinforced concrete M 20 Grade Concrete in Foundations using 20mm and 13.615mm size
HBG crushed stone aggregate (Coarse aggregate conforming to table 13.61500-1 and fine aggregate conforming
to table 13.61500-2) including cost and conveyance of all materials to site and all labour charges for machine
mixing,laying in position, Compacting , Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 213.6150 (4th Revision) for
Raft foundation. .
Unit = cum Page 335 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate 320.00 day 275.20
1.50 nos Mason 420.00 day 630.00
20.00 nos Mazdoor 320.00 day 6400.00
0% MCA on Labour charges 7305.20 Cum 0.00
Total 7305.20
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 1946.35 cum 15765.44
5.40 cum Cost of 13.615mm SS-5 HBG M/C metal 1516.35 cum 8188.29
6.75 cum Sand at site 1227.61 cum 8286.37
5.16 MT Cement at site 5920.00 MT 30547.20
Total 62787.30
Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 456.20 hr 2737.20
6.00 hr Generator set 30 KVA 816.80 hr 4900.80
Total 7638.00
77730.50
(D) Form work
3.50 % Form work @ 3.5% on (A)+(B)+( C) 77730.50 Cum 2720.57
(F) Total of (A) + (B)+( C)+(D)+(E) 80451.07
(G) Add Contractors Profit at 13.615% on (F) 10953.41
Cost per 15 cum (F)+(G) 91404.48
Rate for 1 cum 6093.63
Rate to be adopted 6094.00
1Cum
23 Sand filling in foundations including cost and conveyence of all materials to site and watering, tamping etc.,
complete for finshed item of work as per MoRT&H specification 304 (4th Revision) and as directed by the
Engineer - in - Charge.
Page 39
Quantity Description of Item Rate per Amount
24 Providing 160mm PVC conduct for services in the foot paths as per the DWG No:SD/13.6153
(A) Material
As per the SSR for the year 2015-16 item no. Vide
1 RM P.No for 160mm dia and 3.0M length PVC-Double 1153.00 Rm 384.33
socket Each (Code BMW-G.32 P. No. 13.6153)
(B) Labour
Labour charges for laying, fixing and
commissioningthe PVC pipes including couplers/
bends/ tees etc any diameter including fixing
1 RM 70.00 Rm 23.33
necessary fittings like bends, plugs, couplers,
junctions, tees, etc with solvent jointing as per
standard practice (Code BMW-G.152 P. No. 13.6156)
0% MCA on Labour charges 23.33 Rm 0.00
407.67
Rate to be adopted 408.00
1 Rm
Page 40
Name of CONSTRUCTION OF HIGH LEVEL BRIDGE ON PETACALAVA MINOR DRAIN @ 3.50
Work :- KM OPPOSITE SRMT STREET IN RAMANAYYAPRTA OF KAKINADA
1 Bridge proper (1 vents of 6.00 m eff span with out footpaths) ,19,54,794
2 Forming approaches to Bridge 2,62,512
L.S Provisions
3 Provision for VAT @ 5% in bridge proper portion ,94,240
4 Provision for VAT @ 5% in Approches portion 13,126
Rs. ,25,00,000
Name of work:- CONSTRUCTION OF HIGH LEVEL BRIDGE ON PETACALAVA MINOR
DRAIN @ 3.50KM NEAR
A) DETAILED CUM ABSTRACT ESTIMATE FOR BRIDGE.
Dept
S.No. Description of Item No. Length Breadth h Quantity Rate Per Amount
1 2 3 4 5 6 8 9 10
1 Earthwork in excavation of foundation of structures as per drawing and
technical specification including setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing sides of
bottom, back filling the excavation earth to the extent required etc.,
complete for finished item of work as per MoRT&H specification 304
a excluding dewatering 0-3.0M DEPTH above sill level.
RAFT 1 x 1 10.00 5.10 1.75 89.25
Wing walls 2 x 2 3.50 2.35 1.60 52.64
225.89
226.00 27.40 1.00 6,192
cum cum
b Excluding dewatering 0-3.0M DEPTH Below sill level.
RAFT 1 x 1 10.00 5.10 1.75 89.25
89.25
90.00 27.40 1.00 2,466
cum cum
Page 42
Page 43
5 Providing PCC (1:3:6) nominal mix in foundation with crushed stone
aggregate 40 mm nominal size mechanically mixed , placed in foundation
and compacted by vibration including curing etc., including all other
incidental and operational charges of all T&P etc., complete for finished
item of work as per MoRT&H specification 2100
Under Raft 1 x 1 10.00 5.10 0.30 15.30
Wing walls 2 X 2 3.50 2.35 0.30 9.87
25.17 4718.00 118,753
cum 1cum
9 V.R.C.C. M20 grade concrete using 20mm and 10mm size SS5 HBG crushed
stone aggregate including cost and conveyance of all materials to site,
labour charges for machine mixing, laying, compacting, curing
etc,including all other incidental and operational charges,T&P charges etc,
complete but excluding cost of steel and its fabrication charges, as per
MoRT&H Specifications 1500,1700,2100(4th Revision) for bed blocks &
backing walls
upto 5.0m to 10.00m height 0
Bed blocks over abutments: 1x 2 4.65 1.00 0.30 2.79
Backingwallsover abutment: 2x 1 4.65 0.50 0.62 2.86
5.65 6659.00 37,624
Page 44
cum 1cum
Page 45
10 V.R.C.C concrete M - 20 grade for Super Structure with 20 mm(SS5)HBG
M/C graded metal with a cube strength of 25 N / mm2 at 28 days
work test on 150 X 150 X 150 mm cubes and cost and and conveyance of
all materials, vibrating centering machine mixing, curing hire and
operational charges of all T& P but excluding cost and its fabrication
charges of steel etc complete as per M.O.T DRG No SD/166 excluding cost
of steel and fabrication charges for VRCC M-30 Super structure of deck
slabs
upto 5.0m to 10.00m height
a) For deck slabs: 1 x 1 7.00 4.65 ### 16.76
say 16.76 7391.00 123,898
cum 1cum
b) Kerbs
Kerbs 1x 2 7.00 0.525 ### 3.3075
3.3075 6031.00 19,948
cum 1cum
12 V.R.C.C. M20 grade concrete using 20mm and 10mm size SS5 HBG crushed
stone aggregate including cost and conveyance of all materials to site,
labour charges for machine mixing,laying,compacting,curing etc,including
all other incidental and operational charges,T&P chargesetc, complete but
excluding cost of steel and its fabrication charges, as per MoRT&H
Specifications 1500,1700,2704 For Approach Slab as per DWG
NO:SD/157&158.
For approach slab 2 x 1 4.65 3.20 ### 8.93
8.93 6005.00 53,613
cum 1cum
13 V.R.C.C M20 grade concrete using 20mm and 10mm size SS5 HBG crushed
stone aggregate including cost and conveyance of all materials to
site,labour charges for machine mixing, laying, compacting,querying
etc,including all other incidental operational charges,T&P charges etc
complete but excluding the cost of steel and its fabrication charges as per
MORT&H specifications 1500,1700,2704 for wearing course over deck
slab as per drawing no.SD/151.
Over deck slabs 1x 1 7.00 4.25 ### 2.98
Over approach slabs 2x 1 4.25 3.20 ### 2.72
5.70 5967.00 33,983
cum 1cum
14 Construction of R.C.C railing of M20grade using in-situ with 12mm
nominbal size aggregate,true to line and grade,tolerance of vertical R.C.C
post not to exceed 1 in 500,center to centre spacing between vertical
posts not to exceed 1870mm,leaving adequate space between vertical
posts for expansion,complete as per approved drawings and technical
specifications as per MORT&H specification no.2703,1500,1600,1700 as
per MORT&H drawing No.SD/202.
Over deck slabs 1 x 2 7.00 14.00
14.00
say 14.00 884.00 12,376
R.M. 1RM
Page 46
15 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up
bars of all diameters including cost and conveyance of steel to site and all
labour charges for fabrication of reinforcement including cutting, bending,
binding rods, tying grills, placing them in position etc., complete including
cost and conveyance of binding wire and all handling charges and
operational charges etc., and including over lapping welding if required
etc., complete for all R.C.C items for finished item of work as per standard
drawings, as per the directions of the Engineer-in-Charge and as per
MoRT&H specification 1600 &2200 (4th revision) and as per I.S.1786 of
1985 for Super structure of R.C.C items. or
say 2.50 ### 126,850
M.T 1MT
Page 47
cum 1cum
Page 48
20 Providing weep holes in Brick masonry/Plain/Reinforced concrete
Abutment/wing wall/Return wall with 100mm dia meter A/C pipe extending
through the full width of the structure with slope of about 1 V : 20H
towards drawing face Complete as per drawing and technical specification,
complete for finished item of work for weep holes as per MORTH
specification No 2706 & 2200
For abutments 2 x 12 1.25 30.00
2x3 30.00 365.00 10,950
R.M. 1RM
23 Provision for painting to railing and unforeseen items and rounding off
Total ###
Page 49
Page 50
CONSTRUCTION OF HIGH LEVEL BRIDGE ON PETACALAVA MINOR DRAIN @ 3.50 KM
Name of work:- ###
OPPOSITE SRMT STREET IN RAMANAYYAPRTA OF KAKINADA
Approaches
B) DETAILED CUM ABSTRACT ESTIMATE FOR APPROACHES Dept
S.No. Description of Item No. Length Breadth h Quantity Rate Amount
1 2 3 4 5 6 8 9
1 Forming embankment with borrowed useful earth from outside road boundary by mechanical
means with all leads and lifts including pre-watering of soil at borrow area, removal of top
soil, excavation of soils at borrowed area, conveyance of soil, depositing the soils on the
embankment, spreading soils, breaking clods, sectioning and consolidation with 8 to 10
Tonnes Power Road Roller @ FMC including all hire and operational charges of T&P and
seigniorage charges, complete for finished item of work as per APSS Specification 301 and
303 and as directed by the Engineer-in-Charge (Payment will be made based on level for
finished item of work).
1 20.00 8.00 3.00 480.00
1 20.00 8.00 0.60 96.00
576.00
Approaches both sides say 576.00 294.00 169,344
cum 1cum
2 Construction of Granular sub-base by providing HBD material confirming
to Grading - III of MoRT&H Table 400-2 including cost, seigniorage charges
and conveyance of all materials to work site and spreading in uniform
layers with motor grader or by approved means, on prepared surface
mixing by mix in place method with Rotavator / approved means at OMC
and compacting with vibratory roller to achieve the desired density etc.,
complete for finished item of work as per MoRT&H Specification 401 (4th
revision) and as directed by the Engineer-in-charge.
1 20.00 4.00 0.20 16.00
1 20.00 4.00 0.20 16.00
32.00
say 32.00 2037.00 65,184
cum 1cum
3 Providing, Laying, Spreading and compacting graded HBG crushed stone
aggregate to Wet Mix macadem specification including cost,seignorage of
all materials and including premixing the material with water at OMC in
Mechanical mix plant carriage of mixed material by tipper to site , laying in
uniform layers with paver in base courses on well prepared surface and
compacting with Vibratory roller to acheive the desired density etc., as
directed by the Engineer-in-Charge and as per MoRT&H specification.406
(4th revision) for finished item of work. (Payment based on levels for
finished item of work)
1 20.00 3.75 0.15 0.00
1 20.00 3.75 0.15 11.25
11.25
12.00 2332.00 27,984
cum 1cum
Page 51
CONSTRUCTION OF HIGH LEVEL BRIDGE ON
Name of work:- PETACALAVA MINOR DRAIN @ 3.50 KM OPPOSITE
SRMT STREET IN RAMANAYYAPRTA OF KAKINADA
C) DETAILED CUM ABSTRACT ESTIMATE FOR PROVIDING RETAINING
WALL ON U/S & D/S OF BRIDGE .
Sl.
Description of Item No Length Breadth Depth Quantity
No. Rate Amount
1 2 3 4 5 6 7 8 10
1 Earthwork in excavation of foundation of structures as per drawing
and technical specification including setting out, construction of
shoring and bracing, removal of stumps and other deleterious matter,
dressing sides of bottom, back filling the excavation earth to the
extent required etc., complete for finished item of work as per
MoRT&H specification 304
924.00
say 924.00 27.40 25,318
Cum 1 cum
365.40
say 366.00 5993.00 21,93,438
Cum 1 cum
Sl.
Description of Item No Length Breadth Depth Quantity
No. Rate Amount
6 Vibrated cement concrete M 20 Grade Concrete using 40mm , 20mm
and 10mm size HBG crushed stone aggregate (Coarse aggregate
conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost and conveyance of all materials to site and all
labour charges for machine mixing, laying in position,Compacting,
Vibrating and curing including all other incidental and all other
operational charges of T&P required etc., complete as per MoRT&H
Specification 1500,1700, 2200 for VCC M-20 for Sub structure of
Retaining wall
1.70+0.45
For Retaing wall Kongodu side U/S 1x1 50.00 2.00 107.50
2
1.70+0.45
D/S 1x1 50.00 2.00 107.50
2
1.70+0.45
For Retaining Wall Gorripudi side U/S 1x1 20.00 3.00 64.50
2
1.70+0.45
D/S 1x1 20.00 3.00 64.50
2
344.00
say 344.00 6339.00 21,80,616
Cum 1 cum
100m length wall Kongodu side 1x98 0.95 --- --- 93.10
--- do --- 1x98 0.75 --- --- 73.50
--- do --- 1x98 0.55 --- --- 53.90
40M length wall Gorripudi side 1x38 1.00 --- --- 38.00
--- do --- 1x38 0.80 --- --- 30.40
--- do --- 1x38 0.60 --- --- 22.80
--- do --- 1x38 0.50 --- --- 19.00
330.70
say 331.00 233.00 77,123
RM 1 Rm
1590.00
say 1590.00 658.00 10,46,220
Cum 1 cum
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
BRIDGE DETAILED CUM ABSTRACT ESTIMATE
Name of work:- RECONSTRUCTION OF HIGH LEVEL BRIDGE ON EAST YELERU DRAIN AT KM.22/8
OF PYNA-KAKINADA ROAD IN EAST GODAVARI DISTRICT
S.No. Description of Item No. Length Breadth Depth Quantity Rate Amount
1 2 3 4 5 6 7 8 9
1 Earth work excavation in all soils upto SDR including removal of existing soil backfill
and depositing of surplus materialon bank at suitable places as directed by the
departmental officers including all leads and lifts,shoring,strutting etc,complete as
per APSS Specification No.308 and as directed by the Engineer-in-Charge for
foundations
Page 57
2 crushed stone
Plain cement concrete (1:3:6) nominal mix in foundation with
aggregate 40 mm nominal size mechanically mixed, placed in foundation
and compacted by vibration including curing complete as per MoRT&H
Specification 2100 (4th Revision) for Levelling course below raft and
wing walls
Page 58
4 Vibrated Reinforced Cement concrete M 20 Grade Concrete using 20mm and
10mm size HBG crushed stone aggregate (Coarse aggregate conforming to table
1000-1 and fine aggregate conforming to table 1000-2) including cost,seignorage
and conveyance of all materials to site and all labour charges for machine
mixing,laying in position, Compacting , Vibrating and curing including all other
incidental and all other operational charges of T&P required etc., complete as per
MoRT&H Specification 1500,1700, 2100 (4th Revision) for Raft.
347.12
say 348.00 #REF! #REF!
cum 1cum
5 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm
size HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1
and fine aggregate conforming to table 1000-2) including cost,seignorage and
conveyance of all materials to site and all labour charges for machine mixing,
laying in position,Compacting, Vibrating and curing including all other incidental and
all other operational charges of T&P required etc., complete as per MoRT&H
Specification 1500,1700, 2200 (4th Revision) for Sub structure of abutments,
piers and wing walls. .
Backingwallsover
2 x 1 11.05 0.30 0.470 3.12
abutment:
Page 59
cum 1cum
Page 60
7 Furnishing and placing reinforced cement concrete VRCC M 20 grade as per
approved drawings and technical specifications as per MoRT&H specification
1500,1600,1700 (4th revision ) and as per M.O.T DRG No BD/5-74 & 6-74A
excluding cost of steel and fabrication charges for VRCC M-20 Super structure of
deck slabs
upto 5.0m to 10.00m height
For deck slabs: As per
Standard Drg. BD/5-74 & 5 x 1 36.85 M3 per Span 184.25
6-74A say 185.00 #REF! #REF!
cum 1cum
Kerbs and foot path slabs in wing wall portion (4*5 = 20.00m)
8.44
9.00 #REF! #REF!
cum 1cum
8 Plain cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size
HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and
fine aggregate conforming to table 1000-2) including cost,seignorage and
conveyance of all materials to site and all labour charges for machine mixing,laying
in position, Compacting , Vibrating and curing including all other incidental and all
other operational charges of T&P required etc., complete as per MoRT&H
Specification 1500,1700, 2100 (4th Revision) for Levelling course below approach
slab
9.00
9.00 #REF! #REF!
cum 1cum
9 V.R.C.C. M30 grade concrete using 20mm and 10mm size SS5 HBG crushed stone
aggregate including cost and conveyance of all materials to site, seigniorage
charges,labour charges for machine mixing,laying,compacting,curing etc,including
all other incidental and operational charges,T&P chargesetc, complete but
excluding cost of steel and its fabrication charges, as per MoRT&H Specifications
1500,1700,2704(4th Revision) . For Approach Slab as per CE Drg. No. 4/71.
19.35
20.00 #REF! #REF!
cum 1cum
Page 61
Page 62
10 V.R.C.C. M30 grade concrete using 20mm and 10mm size SS5 HBG crushed
stone aggregate including cost and conveyance of all materials to site, seigniorage
charges,labour charges for machine mixing,laying,compacting,curing etc,including
all other incidental and operational charges,T&P chargesetc, complete but
excluding cost of steel and its fabrication charges, as per MoRT&H Specifications
1500,1700,2702(4th Revision). For Wearing coat .as per Drg No. BD/1-69A.
23.79
24.00 #REF! #REF!
cum 1cum
11 Construction of RCC railing of M20 grade using in-situ with 12 mm nominal size
aggregate, true to line and grade, tolerance of vertical RCC post not to exceed 1 in
500, centre to centre spacing between vertical posts not to exceed 2000mm,
leaving adequate space between vertical posts for expansion, complete as per
approved drawings and technical specifications asper MoRT&H Spcn. No 2703,
1500, 1600, 1700 as per CE Drg No. 4/71
88.60
say 89.00 #REF! #REF!
R.M. 1RM
12 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of
all diameters including cost and conveyance of steel to site and all labour charges
for fabrication of reinforcement including cutting, bending, binding rods, tying grills,
placing them in position etc., complete including cost and conveyance of binding
wire and all handling charges and operational charges etc., and including over
lapping welding if required etc., complete for all R.C.C items for finished item of
work as per standard drawings, as per the directions of the Engineer-in-Charge and
as per MoRT&H specification 1600 &2200 (4th revision) and as per I.S.1786 of
1985 for Super structure of R.C.C items.
17093.24
17.10
or say 17.10 #REF! #REF!
M.T 1MT
Page 63
Page 64
13 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of
all diameters including cost and conveyance of steel to site and all labour charges
for fabrication of reinforcement including cutting, bending, binding rods, tying grills,
placing them in position etc., complete including cost and conveyance of binding
wire and all handling charges and operational charges etc., and including over
lapping welding if required etc., complete for all R.C.C items for finished item of
work as per standard drawings, as per the directions of the Engineer-in-Charge and
as per MoRT&H specification 1600 &2200 (4th revision) and as per I.S.1786 of
1985 for Sub structure of R.C.C items.
7104.10
kgs
7.11
or say 7.20 #REF! #REF!
M.T 1MT
14 Providing HYSD bars (Fe-415) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for
fabrication of reinforcement including cutting, bending, binding rods, tying grills,
placing them in position etc., complete including cost and conveyance of binding
wire and all handling charges and operational charges etc., and including over
lapping welding if required etc., complete for all R.C.C items for finished item of
work as per standard drawings, as per the directions of the Engineer-in-Charge and
as per MoRT&H specification 1600 &2200 (4th revision) and as per I.S.1786 of
1985 for foundations of R.C.C items.
20055.80
kgs
20.06
or say 20.10 #REF! #REF!
M.T 1MT
Page 65
Page 66
15 Back filling behind Abutments with gravel including cost ,conveyance and
seigniorage of all materials to site etc., complete as per Clause 710.1.4 of IRC :
78and as per MoRT&H Specification No. 2200 (4th Revision) and as per Drawing
and technical specifications for finished item of work
17 Providing and laying filter material with gravel underneath pitching in slopes
including cost and conveyance of materials to site including labour charges etc,
complete for finished item of work as per MoRTH Specification No.2504(4th
Revision)and as directed by the Engineer-in-Charge. For pitching of slopes.
Quadrants 4 x 1 9.990 0.15 5.99
(x3x 2x3
)/4 5.99
6.00 #REF! #REF!
or say cum 1cum
18 Providing Grouted Revetment with rough stone other than granite of not less than
300 mm size grouted with 0.20 cum of CC (1:4:8) including cost, seigniorage
charges and conveyance of materials to site and including labour charges for
packing the stones for revetment etc., complete for finished item of work as per
MoRT&H specification 2504 ( 4th revision ) and as directed by the Engineer-in-
Charge for quadrential revetment.
19
Providing rough stone revelment other than granite 300 mm thick using 300 mm
ize rough stonne varity including cost ,seigniorage and conveyance of all materials
to site , labour cgarges etc , complete as per MOST specification no. 2504
Toe walls 4 5.181 0.6 0.6 7.46
7.46
or say 8.00 #REF! #REF!
cum 1cum
Page 67
Page 68
20 Providing and laying boulders apron on river bed for protecting against scour with
jeddy stine of 450mm stone boulders weighing not less than 40 kg each complete
as per MOST specification no. 2504
21 Providing 100 mm dia AC pipes for weep holes at 1.00 M C/C in both horizontal
and vertical directions so that the weep holes in each horizontal dirction is
staggered from the weep holes lying above and below lines as shown in drawing for
abutments, wing walls, including cost and conveyance of the AC pipes and labour
charges for cutting to required lenghts,placing the pipe with a slope of 1:20 towards
steam side face etc, complete for finished item of work for weep holes, as per
MoRTH Specification No.2706(4th Revision)and as directed by the Engineer-in-
Charge.
5 x 2 10
say 10 #REF! #REF!
Nos 1No.
#REF!
23 Provision towards VAT 5% on Rs #REF!
27 Provision for painting to railing and unforeseen items and rounding off 356024
(RUPEES ONE HUNDRED AND TWENTY LAKHS
#REF!
ONLY)
Page 69
Page 70
APPROACHES DETAILED CUM ABSTRACT ESTIMATE
1 Forming embankment with borrowed useful earth from outside road boundary by
mechanical means with all leads and lifts including pre-watering of soil at borrow
area, removal of top soil, excavation of soils at borrowed area, conveyance of soil,
depositing the soils on the embankment, spreading soils, breaking clods, sectioning
and consolidation with 8 to 10 Tonnes Power Road Roller @ FMC including all hire
and operational charges of T&P and seigniorage charges, complete for finished
item of work as per APSS Specification 301 and 303 and as directed by the
Engineer-in-Charge (Payment will be made based on level for finished item of
work).
Kakinada side
level portion 1 11 14.8 2.42 393.98
Gradient portion 1 60 11.92 0.96 686.59
Pyna side
level portion 1 10 12 1.01 121.20
Deduct crust 1 186.30+147.83+14.175) = -348.305
853.46
Approaches both sides say 854.00 #REF! #REF!
cum 1cum
2 Construction of Granular sub-base by providing HBD material confirming to
Grading - III of MoRT&H Table 400-2 including cost, seigniorage charges and
conveyance of all materials to work site and spreading in uniform layers with motor
grader or by approved means, on prepared surface mixing by mix in place method
with Rotavator / approved means at OMC and compacting with vibratory roller to
achieve the desired density etc., complete for finished item of work as per MoRT&H
Specification 401 (4th revision) and as directed by the Engineer-in-charge.
Page 71
4 Providing and applying tack coat with bitumen emulsion (medium setting) using
pressure distributor at the rate of 0.20 kgs per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom for finished item of
work as per MoRT&H Specification 503 (4th revision) and as directed by the
Engineer-in-Charge.
5 Providing and applying Prime coat with bitumen Emulsion (Medium settting) (Bulk)
using Emulsion pressure distributor at the rate of 0.60 kgs per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom for finished item of
work as per MoRT&H Specification 503 (4th revision) and as directed by the
Engineer-in-Charge.
Page 72
NAME OF WORK
#REF!
COMPARATIVE STATEMENT
a) Excluding Dewatering 647.00 23.90 15,464 #REF! #REF! #REF! #REF! #REF!
Cum / 1 Cum. Cum / 1 Cum.
b) Including Dewatering 1,163.00 #REF! #REF! 0.00 #REF! #REF! #REF! #REF!
Cum / 1 Cum. Cum / 1 Cum.
2 Hire and poerational charges of Vaccume Dewatering system including power generator of not
less than 35 KVA Capacity,driving about 28 numbers of filter points allround the pit at 1.00M
regular intervals in to the ground,connecting the filter points to the PVC pipe and then to the
suction motor, including lanour charges for driving the points,delivering the discharge water to
the nearest outlet,etc., complete as directed by the Engineer-in-Charge.
7 Vibrated Reinforced Cement concrete M 20 Grade Concrete using 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost,seignorage and conveyance of all materials to site
and all labour charges for machine mixing,laying in position, Compacting , Vibrating and curing
including all other incidental and all other operational charges of T&P required etc., complete as
per MoRT&H Specification 1500,1700, 2100 (4th Revision) for Raft.
10 Furnishing and placing reinforced cement concrete VRCC M 20 grade as per approved
drawings and technical specifications as per MoRT&H specification 1500,1600,1700 (4th
revision ) and as per M.O.T DRG No BD/5-74 & 6-74A excluding cost of steel and fabrication
charges for VRCC M-20 Super structure of deck slabs
a) Deck slab 185.00 5,929.00 10,96,865 16.76 7,391.00 1,23,898 --- 972,967
Cum / 1 Cum. Cum / 1 Cum.
12 V.R.C.C. M30 grade concrete using 20mm and 10mm size SS5 HBG crushed stone aggregate
including cost and conveyance of all materials to site, seigniorage charges,labour charges for
machine mixing,laying,compacting,curing etc,including all other incidental and operational
charges,T&P chargesetc, complete but excluding cost of steel and its fabrication charges, as per
MoRT&H Specifications 1500,1700,2704(4th Revision) . For Approach Slab as per CE Drg. No.
4/71.
13 V.R.C.C. M30 grade concrete using 20mm and 10mm size SS5 HBG crushed stone aggregate
including cost and conveyance of all materials to site, seigniorage charges,labour charges for
machine mixing,laying,compacting,curing etc,including all other incidental and operational
charges,T&P chargesetc, complete but excluding cost of steel and its fabrication charges, as per
MoRT&H Specifications 1500,1700,2702(4th Revision). For Wearing coat .as per Drg No. BD/1-
69A.
15 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters
including cost and conveyance of steel to site and all labour charges for fabrication of
reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc.,
complete including cost and conveyance of binding wire and all handling charges and
operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4th revision) and as per
I.S.1786 of 1985 for Super structure of R.C.C items.
16 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters
including cost and conveyance of steel to site and all labour charges for fabrication of
reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc.,
complete including cost and conveyance of binding wire and all handling charges and
operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4th revision) and as per
I.S.1786 of 1985 for Sub structure of R.C.C items.
18 Back filling behind Abutments with gravel including cost ,conveyance and seigniorage of all
materials to site etc., complete as per Clause 710.1.4 of IRC : 78and as per MoRT&H
Specification No. 2200 (4th Revision) and as per Drawing and technical specifications for
finished item of work
19 Providing and laying filter media with stone crushed aggregate satisfying the requirements laid
down in Clause 2504.2.2 of MORTH specifications to a thickness of not less than 600 mm with
smaller size towards the soil and bigger size towards the wall and provided over the entire
surface behind abutment and wing wall, to the full height , compacted to a firm condition
complete as per drawing and technical specification No.710.1.1 of IRC 78 and
2200(Sl.No.13.10)
22 Providing rough stone revelment other than granite 300 mm thick using 300 mm ize rough
stonne varity including cost ,seigniorage and conveyance of all materials to site , labour cgarges
etc , complete as per MOST specification no. 2504
25 Supplying and fixing of CI drainage spouts complete as per MoRT&H Specification No.2705 and
as per drawing BD / 1-69A.
Asst. Executive Engineer (R&B), Dy. Executive Engineer (R&B), Executive Engineer (R&B), Superintending Engineer (R&B),
(R&B) East Section : Kakinada (R&B) East Sub-divn., Kakinada. (R&B) Division : Kakinada (R&B) Circle : Kakinada
Sl. As per Original Estimate As per Revised estimate
Description More Less Remarks
No. Quantity Rate / per Amount Quantity Rate / per Amount
1 2 3 4 5 6 7 8 9 10 11
Sl. As per Original Estimate As per Revised estimate
Description More Less Remarks
No. Quantity Rate / per Amount Quantity Rate / per Amount
1 2 3 4 5 6 7 8 9 10 11
NAME OF WORK
#REF!
COMPARATIVE STATEMENT
APPROACHES
1 Forming embankment with borrowed useful earth from outside road boundary by mechanical
means with all leads and lifts including pre-watering of soil at borrow area, removal of top soil,
excavation of soils at borrowed area, conveyance of soil, depositing the soils on the
embankment, spreading soils, breaking clods, sectioning and consolidation with 8 to 10 Tonnes
Power Road Roller @ FMC including all hire and operational charges of T&P and seigniorage
charges, complete for finished item of work as per APSS Specification 301 and 303 and as
directed by the Engineer-in-Charge (Payment will be made based on level for finished item of
work).
8 Unforeseen items and rounding off L.S. 1,99,546 L.S. #REF! #REF! #REF!
NAME OF WORK
#REF!
COMPARATIVE STATEMENT
1 Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as
per drawing and technical specification including setting out, construction of shoring and bracing,
removal of stumps and other deleterious matter, dressing sides of bottom, back filling the
excavation earth to the extent required etc., complete including seignioarge charges for
finished item of work as per MoRT&H specification 304(4th Revision) and as directed by the The Retaining wall
Engineer-in-Charge are not made in
the sanctioned
estimate and the
--- --- --- 924.00 27.40 25,318 25,318 --- proposals for
Cum / 1 Cum. deviations
2 Hire and poerational charges of Vaccume Dewatering system including power generator of not
less than 35 KVA Capacity,driving about 28 numbers of filter points allround the pit at 1.00M
regular intervals in to the ground,connecting the filter points to the PVC pipe and then to the
suction motor, including lanour charges for driving the points,delivering the discharge water to
the nearest outlet,etc., complete as directed by the Engineer-in-Charge.
--- --- --- 20.00 42,500.00 850,000 850,000 --- ---- do ----
Days / 1 Days.
3 Sand filling in foundations including cost, seignoirage and conveyence of all materials to site and
watering, tamping etc., complete for finshed item of work as per MoRT&H specification 304 (4th
Revision) and as directed by the Engineer - in - Charge.
--- --- --- 63.00 792.00 49,896 49,896 --- ---- do ----
Cum / 1 Cum.
Sl. As per Original Estimate As per Revised estimate
Description More Less Remarks
No. Quantity Rate / per Amount Quantity Rate / per Amount
1 2 3 4 5 6 7 8 9 10 11
4 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing,
laying, Vibrating, curing etc., including all other incidental and operational charges of all T&P
etc., complete for finished item of work as per MoRT&H specification 1500,1700, 2100 (4th
Revision) and as directed by the Engineer-in-Charge for base coarse below Raft.
--- --- --- 63.00 4,718.00 297,234 297,234 --- ---- do ----
Cum / 1 Cum.
5 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost,seignorage and conveyance of all materials to site
and all labour charges for machine mixing,laying in position, Compacting , Vibrating and curing
including all other incidental and all other operational charges of T&P required etc., complete as
---- do ----
per MoRT&H Specification 1500,1700, 2100 (4th Revision) for Raft and footings.
6 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate The Retaining wall
conforming to table 1000-2) including cost,seignorage and conveyance of all materials to site are not made in
and all labour charges for machine mixing,laying in position, Compacting , Vibrating and curing the sanctioned
including all other incidental and all other operational charges of T&P required etc., complete as estimate and the
per MoRT&H Specification 1500,1700, 2100 (4th Revision) for sub structure proposals for
deviations
--- --- --- 344.00 6,339.00 21,80,616 21,80,616 ---
Cum / 1 Cum.
Sl. As per Original Estimate As per Revised estimate
Description More Less Remarks
No. Quantity Rate / per Amount Quantity Rate / per Amount
1 2 3 4 5 6 7 8 9 10 11
7 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters
including cost and conveyance of steel to site and all labour charges for fabrication of
reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc.,
complete including cost and conveyance of binding wire and all handling charges and
operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4th revision) and as per
I.S.1786 of 1985 for Sub structure of R.C.C items.
--- --- --- 3.40 53,795.00 182,903 182,903 --- ---- do ----
Rm / 1 MT
8 Providing and laying of filter media using 50% of 150 mm IRC soling stone and 50 % of 40 mm
HBG metal satisfying the requirements laid down in clause 2504.2.2 of MoRT&H specifications
to athickness of not less than 600mm with smaller size towards the soil and bigger size towards
the wall and provided over the entire surface behind the abutment, wing wall and return wall to
the full height compacted to a firm condition including cost and conveyance of all metal
seignorage charges ,and all labour charges as directed by the departmental officers as per
drawing and Technical specifications as per clause 710.1.1 of IRC:78 and Clause 2200 of
MoRT&H (4th Revision) for finished item of work.
--- --- --- 234.00 1,788.00 418,392 4,18,392 --- ---- do ----
Cum / 1 Cum.
9 Providing 100 mm dia AC pipes for weep holes at 1.00 M C/C in both horizontal and vertical
directions so that the weep holes in each horizontal dirction is staggered from the weep holes
lying above and below lines as shown in drawing for abutments, wing walls, including cost and
conveyance of the AC pipes and labour charges for cutting to required lenghts,placing the pipe
with a slope of 1:20 towards steam side face etc, complete for finished item of work for weep
holes, as per MoRTH Specification No.2706(4th Revision)and as directed by the Engineer-in-
Charge.
--- --- --- 331.00 233.00 77,123 ,77,123 --- ---- do ----
Rm / 1 RM
Sl. As per Original Estimate As per Revised estimate
Description More Less Remarks
No. Quantity Rate / per Amount Quantity Rate / per Amount
1 2 3 4 5 6 7 8 9 10 11
10 Back filling behind Abutments with gravel including cost ,conveyance and seigniorage of all
materials to site etc., complete as per Clause 710.1.4 of IRC : 78and as per MoRT&H
The Retaining wall
Specification No. 2200 (4th Revision) and as per Drawing and technical specifications for
are not made in
finished item of work
the sanctioned
estimate and the
--- --- --- 1,590.00 658.00 10,46,220 10,46,220 --- proposals for
Cum / 1 Cum. deviations
0 73,21,140 73,21,140 0
0 73,78,771 73,78,771 0
-
4 Providing Casuarinas Balli Props - 4" to 5" dia - 20'-0" Height verticla posts and 3" to 4" dia - 12'-
0" Height Horizantal posts including cost and conveyance of Casurina posts and lobour charges
and fixing the Casurina posts including all labour charges such as cutting the Casurina posts to
the required size and shape and bottom of the Casurina post and earth work excavation for
providing holes for fixing Casurina post in position including cost of nails and ropes for fixing,
etc.,for all operations such as loading, unloading and stacking at site of work for verification,
etc., complete.
--- --- --- #REF! #REF! #REF! #REF! #REF! ---- do ----
Rm / 1 RM
5 Laying Sand Bags in the stipulated places including cost of empty cement bag, sand, thread,
stiching charges and labour charges with 10% overhead charges and contractors profits.
--- --- --- #REF! #REF! #REF! #REF! #REF! ---- do ----
Nos / 1 No
Sl. As per Original Estimate As per Revised estimate
Description More Less Remarks
No. Quantity Rate / per Amount Quantity Rate / per Amount
1 2 3 4 5 6 7 8 9 10 11
6 S & F double layer of bamboo matting tarred on both sides including cost and conveyance
and lobour charges for all operations such as unloading and stacking at site of work for
verification, etc., complete.
--- --- --- #REF! #REF! #REF! #REF! #REF! ---- do ----
Sqm / 1 Sqm.
NAME OF WORK
#REF!
COMPARATIVE STATEMENT OF GENERAL ABSTRACT
A Hire and operational charges of Vaccume Dewatering system including power generator of not less than 35
KVA Capacity, driving about 66 number of filter points allround the pit of the size 32.24 x 9.83M x
1.00M at regular intervals in to the ground, connecting the filter points to the PVC Pipe and then to the
suction motor, including labour charges for driving the points, delivering the discharge water to the nearest
outlet, etc., complete as directed by the Engineer-in-Charge.
After removing earth upto prent water water table level, about 66 numbers of filter points are to be
Day - 1, 2 driven into the ground to a depth of 4.00 mts. and same are connected to suction motor by 0.2 m dia
& 3: PVC pipe and run for 24 Hours to control profused water oozing from the silty sand layers under neath.
Day - 4: Balance earth work excavation with machinery, levelling the ground and laying P.C.C. (1:3:6) levelling
course.
After setting of levelling course for 12*2 Hours reinforcement has to be placed and tied as per
Day - 5 & 6 approved designs and errection of side shutters all round the fotting.
Laying of M-15 Grade footing concrete, errection of shutters for bottem beam and concreting and
Day - 7 & 8 removal of side shutters and filter points.
8 / days
Approved rate 316.92 sqm per 1 day for 1 day each = 127500.00 = 15937.50
8.00 1 / day
B Hire and operational charges of Vaccume Dewatering system including power generator of not less than 35
KVA Capacity, driving about 90 numbers of filter points allround the pit of the size 35.42 x 12.25M x
1.00M at regular intervals in to the ground, connecting the filter points to the PVC Pipe and then to the
suction motor, including labour charges for driving the points, delivering the discharge water to the nearest
outlet, etc., complete as directed by the Engineer-in-Charge.
As per approved rate 316.92 sqm for 1 day each = 127500.00 = 15937.50
8.00 1 / day
433.90 sqm per 1 day ? for 1 day each = 15937.50 x 433.90 = 21820.27
316.92 1 / day
6) Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters
for Sub structure of retaining wall.
7) Back filling behind retaining wall with gravel including cost ,conveyance and seigniorage of all
materials to site etc.,as per Drawing and technical specifications.
8) Providing and laying filter media with stone crushed aggregate behind retaining wall to the full
height.
9) Providing 100 mm dia AC pipes for weep holes at 1.00 M C/C in both horizontal and vertical
directions as directed by the Engineer-in-Charge.
L.S. Provisions
1) Provision towards VAT 5%
2) Provision for soil investigation and soil testing
3) Provision for variation in foundation levels
4) Provision for mastic pads and expansion joints
5) Provision for seignorages
6) Provision for Price escalation.
7) Provision for unforseen items and rounding off.
The estimate is prepared with 2015-16 commom SSR for all Engineering Department and
datas as per MoRT&H standard data book duly adopting over head charges @ 5% and contractors profit
at 10% as per G.O.Ms No 141, T(R&B) Dept, dated 27.07.2 The data communicated by the Engineer-in-
Chief (R&B) Admn& Roads, vide circular No: Data/EE / TA 2/ 2006, Dated:2-9-2006, which are
based on Standard data book for analysis of rates (first revision, 2003) published by MORTH, are
adopted. The Over head charges are adopted based on the Memo:No:602/F.8(1)/2006-5, Dated:17-5-
at 10% as per G.O.Ms No 141, T(R&B) Dept, dated 27.07.2 The data communicated by the Engineer-in-
Chief (R&B) Admn& Roads, vide circular No: Data/EE / TA 2/ 2006, Dated:2-9-2006, which are
based on Standard data book for analysis of rates (first revision, 2003) published by MORTH, are
adopted. The Over head charges are adopted based on the Memo:No:602/F.8(1)/2006-5, Dated:17-5-
2007 and VAT of 5.0 % is adopted as per TR&B( RI) dept Memo No 14420/RI(2)/08-2 dated
17/12/2008. Quatations are enclosed for the items to which rates /standard data is not available.