Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

A Brief History of the

Sarulla Geothermal Field


Development
by Novi Ganefianto1, Paul von Hirtz2, Elisabeth Easley1
1
PT. Thermochem Indonesia; 2 Thermochem, Inc.

The Sarulla Geothermal Field is located in the Early Exploration


Tapanuli Utara District, North Sumatra province, The first systematic exploration studies of the
Indonesia (see Figure 1). The Sarulla Operation Sarulla geothermal field were conducted during
Limited (SOL), a consortium of Medco-Itochu- the second half of the 1980s by PERTAMINA.
Kyushu-Ormat, has been granted the rights to The company was appointed by the Indonesian
utilize the Sarulla geothermal resource for power Government by Presidential Decree 22 of 1981, to
generation under the framework of a Joint Operating have the right to conduct surveys, exploration, and
Contract (JOC) with PERTAMINA. Construction exploitation of geothermal energy in Indonesia.
and development wells drilling for the 330 MW PERTAMINA geothermal group began their
geothermal power development are currently activities in 1987 with the reconnaissance and
underway, scheduled to be fully completed in 2019. exploration of prospects in Sumatra, and recognized
The authors work for the well testing contractor, the broad Sarulla area as one of the several attractive
PT. Thermochem Indonesia and Thermochem, Inc. prospects for geothermal development.
(USA). A subsidiary of Unocal, together with
The development PERTAMINA, undertook follow-up geochemical
of this large resource surveys in Sarulla in 1989-1990. The exploration
has been a long program identified several high-temperature
and interesting prospects in the greater Sarulla area, in a tectonic
story, from the graben associated with strands of the Great
early exploration Sumatra Fault
by PERTAMINA, Zone. Further
resource discovery geoscientific
by Unocal, and the investigation
commercial and identified four
financing closure by geothermal
SOL. The journey prospects
to the current in Sarulla,
field development including (from
program provides north to south)
a unique learning Namora I Langit,
Figure 1. Location of the Sarulla Contract experience worth Silangkitang,
Area. COURTESY OF UNOCAL
capturing. This Donotasik and
paper outlines a brief history of the Sarulla Sibualbuali (see
geothermal field development highlighting Figure 2). The area
regulatory, legal, technical, and commercial was later referred
challenges the geothermal developers have faced to as the Sarulla
over almost three decades. Contract Area. Figure 2. Four geothermal prospects within the
Sarulla Contract Area. COURTESY OF UNOCAL

24 GRC Bulletin l www.geothermal.org


Resource Discovery The four wells drilled in the Namora-I-Langit
More extensive exploration of the Sarulla field were all highly productive, encountering
prospect begun in early 1990s, immediately after a large, high permeability geothermal system.
the government issued Decree 45/1991, which The wells all produced fluids with temperatures
provided more flexibility to PERTAMINA, along in excess of 260C, with a maximum measured
with the contractor, to develop geothermal energy in temperature of 276C. Three of the wells produced
Indonesia and then sell it either in the form of steam neutral Na-Cl brine, but the fourth produced a
or electricity to the State Electric Company, PLN. low-pH Na-Cl-SO4 fluid. The permeability of the
During this period, Unocal, after having established Namora-I-Langit system appears to be widely
an operating geothermal field in Salak, negotiated a distributed and is not directly controlled by the
JOC and Energy Sales Contract (ESC) for Sarulla with Great Sumatra Fault.
PERTAMINA and with PLN, respectively. Two out of five wells drilled in the Silangkitang
In February of 1993 Unocal, PERTAMINA field encountered a strong upflow zone with fluid
and PLN signed a JOC and ESC, enabling Unocal temperatures in excess of 310C. A large-diameter
to explore and develop geothermal energy in the well drilled in this zone is capable of producing
Sarulla Contract Area. The JOC gave Unocal the fluid sufficient for 50 MW equivalent of generation,
right to explore for, and produce geothermal power and has a maximum flowing wellhead pressure of
from, the Sarulla contract area as a contractor to more than 60 bar. Unlike at Namora I Langit, the
PERTAMINA while the ESC states the terms under permeability of the Silangkitang system appears to
which the geothermal power is to be purchased by be strongly controlled by the Great Sumatra Fault.
PLN. The contract area is approximately 15 by 63 Four wells drilled in the Eastern Sibualbuali
km in dimension elongated in a NW-SE direction, geothermal field were all productive, finding
located within the Sumatra volcanic arc and along a geothermal system whose temperature and
the active Great Sumatra Fault System (GSF), permeability structure is strongly controlled by the
covering four prospect areas. Great Sumatra Fault. The maximum temperature
Significant exploration of the Sarulla block measured in the Eastern Sibualbuali wells is 267C,
began shortly after the signing of the contract, but production zone temperatures are in the 218-
involving extensive field geologic and geophysics 248C range. Volumetric and reservoir modelling
surveys in 1993 and 1994. The geologic mapping evaluation of the drilled portion of the Eastern
consisted of 8 months of fieldwork and analysis of Sibualbuali geothermal system suggests reserves of
280 geochemistry samples, as well as geophysics sufficient energy to generate 20 MW of electricity for
data from 720 gravity stations, 500 Time-domain 30 years.
electromagnetic (TDEM) stations, and 240 Significant additional potential remains in
Magnetotelluric (MT) stations. the Sarulla block in the undrilled portions of the
Following these exploration surveys, Unocal Sibualbuali and Namora-I-Langit fields as well as in
drilled a total of 13 deep exploration wells in the undrilled Donotasik prospect.
three of the prospects in Sarulla between 1994 and
1998 (Figure 2), discovering a total of 330 MW of
commercial geothermal resources:

210 MW proven resource in the Namora-I-


Langit field. Four (4) exploration wells have
been drilled in this prospect.
100 MW proven resource in the Silangkitang
field. Five (5) exploration wells have been
drilled in this prospect.
20 MW proven resource in the Eastern
Sibualbuali field. Four (4) exploration wells
were drilled in this area.
Figure 3. Exploration drilling activities in Sarulla between 1994 and 1998.
COURTESY OF UNOCAL

March/April 2015 25
Commercial Renegotiations (SMBC), Socit Gnrale (SG), National Australian
After exploration confirmed a resource of Bank (NAB), Bank of Tokyo Mitsubishi UFJ (BTMU),
330 MW, planning for the construction was Mizuho and ING. JBIC also provides political risk
underway in 1998, when the government, through guaranty for the portion of the loan provided by
Presidential Decree 05/1998, postponed the Sarulla commercial lenders, under an EPRG policy (Figure
project following the Asian financial crisis that 4).
hit Indonesia. Nevertheless, during this difficult
period, Unocal continued to complete the resource
feasibility study, and submitted a Notification of
Reserve Confirmation to PERTAMINA in 2000.
In 2002, the government issued Presidential
Decree 15/2002 effectively rescinding the
postponement of the project. After re-negotiation
with PERTAMINA and PLN, Unocal finally agreed
to pull out from the Sarulla project in the third
quarter of 2003, and sold its interests and rights to
develop to PLN for $60 million.
In 2004, after a law to promote private sector
participation in the geothermal sector was signed,
PLN opened an Independent Power Producers
(IPP) bidding process for the Sarulla development
rights, and in 2006 the Medco-Ormat-Itochu Figure 4. Sarulla Project Structure SOURCE: PFI ASIAN BEST
PRACTICE REPORT
Consortium won the tender to develop the project.
In 2007 Kyushu Electric Power Co Inc. joined the Going Forward New Era of Geothermal Energy
consortium. Converter Technology in Indonesia
An Indonesian special purpose company, Sarulla The Sarulla Operations Limited (SOL) has
Operation Limited (SOL), was then established by formally given notice of its intention to develop a
the consortium members, acting as the operating geothermal power plant of approximately 330 MW
company for steam resource development, and capacity in the Sarulla Contract Area. Following
construction and operation of plant facilities the financing closure, the project construction
under the framework of a Joint Operating Contract and development well drilling are currently
(JOC) with the concession holder, PERTAMINA underway at Sarulla. The project will develop two
Geothermal Energy (PGE), a subsidiary of PT geothermal resources, Namora-I-Langit (NIL) and
PERTAMINA. Silangkitang (SIL), for a total of 330 MW generation.
After a long process of renegotiations, in April PT. Halliburton Logging Indonesia is the drilling
2013 SOL signed a Joint Operating Contract (JOC) contractor and Integrated Process Management
with PT PERTAMINA Geothermal Energy (PGE), (IPM) contractor to SOL. PT. Thermochem Indonesia
which grants SOL the rights to use the geothermal is the well testing subcontractor to Halliburton for
field. An Energy Sales Contract (ESC) for the 330 MW all well testing services, reservoir engineering and
Sarulla geothermal power project was signed in the geochemical consulting, and well test equipment
same month with PT PLN, which will off-take the supply (LECM, piping, PTS tools, cap tubing,
energy produced by the geothermal power plant for instrumentation).
30 years. Due to the large size of development, the project
On March 28, 2014, the Consortium signed the will be constructed in three phases of 110 MW
financing agreements with a syndicate comprised each, starting with the 110 MW Silangkitang Plant
of the Japanese Bank for International Cooperation development, scheduled to be completed by the end
(JBIC) and the Asian Development Bank (ADB), of 2016. The subsequent NIL I and NIL II Plant at
acting as Lead Structuring Banks (ADB acting both the Namora-I-Langit field are scheduled to follow
in its own capacity, as well as an implementing approximately 12 and 18 months after, respectively.
agency for the Clean Technology Fund and for Following a comprehensive evaluation of
the Canadian Climate Fund), plus six commercial the Silangkitang and Namora-I-Langit resource
lenders: Sumitomo Mitsui Banking Corporation thermodynamics and fluid characteristics, the plant

26 GRC Bulletin l www.geothermal.org


will use Ormat's Integrated Geothermal Combined scaling. Thermochem Inc. has performed chemical
Cycle Power Plant (IGCC) technology which is more process design services for Ormat on the plants and
efficient than conventional steam power plants is conducting pilot testing for SOL to validate this
(see Figure 5). These will be the first plants of this process during the well testing phase.
type in Indonesia, although the technology is well The power from Silangkitang will be transmitted
established at other high-enthalpy geothermal fields to a substation at Namora-I via a 20km long, 150kV
worldwide. transmission line. This will be the interface point
The IGCC consists of a back pressure steam where PLN will construct a new transmission line to
turbine and Ormat Energy Converters (OEC transmit power to the national grid.
Vaporizers) heated by the low pressure steam
exiting the topping steam turbine (combined cycle). Game changer for geothermal development
The steam exits the turbine and enters the OEC in Indonesia
vaporizer at just above atmospheric pressure. The The Sarulla Geothermal Power Project will be the
brine OEC units utilize the brine as it leaves the largest geothermal construction project in Indonesia,
separation station (conventional brine binary units). double the previous Salak 165 MW expansion
This project constructed more than 15 years ago. From
technology a regulation stand point, the project is unique in
allows nearly the way that its underlying contract is under the
100% injection of old generation geothermal legislation framework,
the geothermal but it is the first geothermal project in Indonesia to
fluid back into benefit from Indonesian Government support in the
the reservoir, form of a Business Viability Guarantee Letter under
maintaining the regulation 139, which was previously not available.
sustainability of This new form of government support is crucial for
the geothermal any limited recourse financing project going forward
resource thus in Indonesia.
increasing The Sarulla Project is the first Greenfield
power. A geothermal power project in Indonesia in a long
portion of the time to have closed with limited-recourse project
noncondensable financing since the Unit 1 Wayang Windu Project
gas (NCG) will in 1997. The Sarulla Project took an alternative
Figure 5. Schematic diagram of the Geothermal
combined cycle schematic diagram SOURCE: also be injected approach by financing all three separate power
ORMAT TECHNOLOGIES INC. with the brine generating units as an integrated whole, different
and condensate. from many other geothermal projects that are
The steam in the IGCC is condensed at typically financed on a unit-by-unit basis due to
a pressure slightly higher than atmospheric the need to prove up the projects reserves. The
pressure, allowing the NCG to be removed from integrated nature
the condenser (OEC) without an expensive, of the project
power consuming vacuum pumping system or financing for the
steam consuming ejectors. Another significant Sarulla project
advantage of the back-pressure is that the NCG meant that the
does not contain oxygen which is always present bankability
in conventional vacuum-condensing plants, which depended
suffer from air in-leakage. on a detailed
The IGCC technology utilizes separated brine, reserve analysis
producing more power from the same amount of and thorough
fluid extracted from the reservoir than conventional due diligence
flash plants. The cooled brine is mixed with the reports provided
condensed steam and a portion of the NCG, by lenders
providing pH-modification that is inherent to the independent
process, without the need for costly sulphuric or consultants. n Figure 6. The first new well tested at Namora-
I-Langit, shown flowing through Thermochem
hydrochloric acid to reduce the potential for silica LECM well test facility in February, 2015.

March/April 2015 27

You might also like