Preparation Work

Setting Out
Inspection:
- Center Point
- Verticality of Casing
Installation of
- Top Level of Casing
Temporary Casing

Inspection:
- Slurry Property
Drilling Works - Depth of Pile
- Drilling Bucket

Koden Test Inspection:


- Verticality of Hole
- Pile Diameter
Airlifting- First
Cleaning
Inspection:
- Sonic and Core Tube
Installation of Rebar Cage - Rebar Cage
(Including Sonic and Core - Depth of bored hole
Tubes, if required) using rebar cage

Installation of Tremie Inspection:


Pipe - Depth of Bored Pile

Airlifting- Final
Cleaning Inspection:
- Slump of Concrete
- Air Content
- Temperature
Casting Concrete
- Arrival Time of Concrete
- Top Level of Concrete

Removal of Temporary
Casing

Soil Backfilling Test:


- Compressive Strength of
Concrete
- PIT
Pile Testing
- Sonic Test
- PDA
- Coring (If Required)