Flow Chart of Bored Pile Work
Flow Chart of Bored Pile Work
Flow Chart of Bored Pile Work
Setting Out
Inspection:
- Center Point
- Verticality of Casing
Installation of
- Top Level of Casing
Temporary Casing
Inspection:
- Slurry Property
Drilling Works - Depth of Pile
- Drilling Bucket
Airlifting- Final
Cleaning Inspection:
- Slump of Concrete
- Air Content
- Temperature
Casting Concrete
- Arrival Time of Concrete
- Top Level of Concrete
Removal of Temporary
Casing