Professional Documents
Culture Documents
Hassan TRB For Planning
Hassan TRB For Planning
Guidelines:
The checklist below is not an exhaustive description of jobs carried out in the work area. In case of any activity not listed in this document, please describe the same for proper records.
Date Signature
Station Emergency Procedures.
Fire main rings and its components. Safety Rules: Potential Hazards; Required PPE; Precautions.
Operations: Required Skill Level; Job Steps, Sequence and Duration; Crew
RFO tank fire detection system & logics. Composition, List of Applicable QA / QC.
Observation: Visual Witnessing of operation, Clarification / Discussion with Supervisor /
Boiler foam system.
Seniors.
Fire tenders & equipment/portable fire pumps.
Fire Tenders.
Tools, Plant &
Equipment
Sprinklers.
`
Understanding Safety Rules Operations Observation Date Signature
Others
Area Section
Fire and Rescue Training Notes - Key Learnings Fire Station
To be flled by Trainee
To be flle
Manager Review
Signatures
Date
8/17/2016
Guidelines:
The checklist below is not an exhaustive description of jobs carried out in the work area. In case of any activity not listed in this document, please describe the same for proper records.
Date Signature
Integrated Organization Structure (IOS). 17-Oct-16 Hassan Ahmed
Legend:
Incident Investigation. 18-Oct-16 Hassan Ahmed Understanding: Working Principle of Machine; Knowledge about Tools, Jigs and
Risk Assessment incuding Hazard Identification. 19-Oct-16 Hassan Ahmed fixtures, Applicable Software Packages.
Self Study
`
Understanding Safety Rules Operations Observation Date Signature
Others
Area Section
QSE Training Notes - Key Learnings Safety Walk
To be flled by Trainee
To be flled
Manager Review
Signatures
Date
Tr
Guidelines:
The checklist below is not an exhaustive description of jobs carried out in th
COSHH.
RFO Analysis.
Water Content
Lab Analyzers.
Equipment
PPEs.
Signatures
Date
Training Record Book
Chemistry & Environment
escription of jobs carried out in the work area. In case of any activity not listed in this document, ple
Date Signature
Legend:
Understanding: Working Principle
fixtures, Applicable Software Packa
Safety Rules: Potential Hazards; R
Operations: Required Skill Level;
Composition, List of Applicable QA
Observation: Visual Witnessing o
Seniors.
Understanding Safety Rules Operations
Trainee Supervisor
8/17/2016
Book
ment
Duration: 1 Week
listed in this document, please describe the same for proper records.
Guidelines:
The checklist below is not an exhaustive description of jobs carried out in the work area. In case of any activity not listed in this document, please describe the same for proper records.
Date Signature
Vendor Selection Procedure.
RFQ Issuance.
Field / Major Activities
Introduction to Stores.
RFQ.
Comparative Statement.
Tools
Purchase Order.
Letter of Credit.
Invoice / Bill.
Cheque.
`
Understanding Safety Rules Operations Observation Date Signature
Others
Area Section
Commercial Training Notes - Key Learnings Purchasing
To be flled by Trainee
To be flled by
Manager Review
Signatures
Date
8/17/2016
Guidelines:
The checklist below is not an exhaustive description of jobs carried out in the work area. In case of any activity not listed in this document, please describe the same for proper records.
Date Signature
Heat Rate Calculations.
Infrared Thermography.
Fuel Management.
Plant Operatins, Reliability and Availablity data Capturing,
Monitoring Analysis and Archival.
IR Thermal Camera.
Ullage Tape.
`
Understanding Safety Rules Operations Observation Date Signature
Others
Area Section
Technical & Commercial Training Notes - Key Learnings Vibration Analysis
To be flled by Trainee
To be flled by
Manager Review
Signatures
Date
Train
Guidelines:
The checklist below is not an exhaustive description of jobs carried out in the work are
Preventive Maintenance.
Corrective Maintenance.
The Origin.
Introduction to Maximo.
KKS Coding
Outages.
Calendar.
Duration.
Outage Reports
Resource estimation
Cost Estimation
Work Types
Workfow
Priorities
Labour Groups
Area
Planning
To be flled by Trainee
Scheduling:
Daily and weekly plan for maintenance are schedule from Sunda
equipment.
IN this scheduling the working hours is one of the important thing
technician on stagger provided that they have 2 extra hours for p
Each weekly plan is scheduled in previous week and allocated th
Reports:
There various type of reports available in Maximo which depend
Type of reports for maintenance planning are:
1- Daily work program.
2- Defect in last 24 hours.
3- Service document requirement
4- Defect awaiting for spares
KKS Coding:
The identification system for Power Stations "KKS" serves to iden
according to task, type and location. It is to be used by all engine
KKS is actually a modified version of AKS system, a working party
names like BBC, Siemens, KWU, Inspection agencies etc. The res
BREAKDOWN OF CODE:
The KKS code is generally divided into three parts. The first part
for unit 1, 2, 3 & 4 respectively, number 5 for common componen
part consists of 3 letters and 2 numbers which indicate the syste
level.
Planning Coordination Meeting:
The planning Coordination meeting shall be held each day at 11
engineer, maintenance supervisor form each department, service
to review the ongoing work and confirm the work program. Appli
The KKS code is generally divided into three parts. The first part
for unit 1, 2, 3 & 4 respectively, number 5 for common componen
part consists of 3 letters and 2 numbers which indicate the syste
level.
Planning Coordination Meeting:
The planning Coordination meeting shall be held each day at 11
engineer, maintenance supervisor form each department, service
to review the ongoing work and confirm the work program. Appli
shift engineer shall make the decision for the adequacy of inform
operational changeovers and plant release to enable the plant to
Minutes of Meeting: they are the records of the meeting and desc
consists of list of attendees and the important decisions and disc
meeting chaired by outage planning engineer. The minutes of tha
meeting that were needed to be taken.
Outage Planning:
Outage is an extensive activity which is performed each year. In
the planning starts from year ahead. This step is completed in th
scope and duration of the outage that is planned initially is sent t
approval to the higher management. After this stage, procureme
to avoid any delay in the work. These all tasks are completed bef
planning engineer with supervisors and engineers because they
add value and help to identify the things left out initially. After th
written. After the final plan is drafted, it is circulated 2 weeks bef
get there preparations done. Preparedness matrix is a tool that is
outage is started, a weekly with procurement is started by the ou
department and to plan accordingly. Once the outage starts, the
consist of work done, challenges that are occurring during the ou
has a very key role in outage. They have to make sure that no un
the contractual employees that work during the outage, before th
by the contractual employees and mark these tools with a specifi
maintains a log book and notes all the unsafe observations. Thes
Manager Review
notifies the outage planning engineer with those issues that are m
improvement. Outage planning engineer also chairs daily and we
outage meeting, engineers and section heads are present. Major
important part is the documentation. All the issues and best prac
successful.
1. Activity: Any job which has a very small scope which is not said
job is as same as corrective maintenance.
2. Corrective Maintenance: A result of problems found during the
requirement to carryout work required by the originator e.g. mod
3. Project: Any special job that is unique and has an ending point
with regard to the improvement at the plant. Likewise, projects a
4. Preventative Maintenance: After the installation of the some sp
is maintained for the maintenance activity of the equipment in m
which is triggered on the allocated time as waiting for schedule o
Signatures
Date
Training Record Book
Planning
ion of jobs carried out in the work area. In case of any activity not listed in this document, please de
Date Signature
29-Sep-16 Hassan Ahmed
tation & control is further divided into different teams which includes:
electrical. Various sub groups are defined within
e
ers
nance (Supervisors, Technician)
hop
ng Mechanical. Various sub groups are defined within
ine
kshop
er
am that is not involved in the outage and 0 stands for team that is involve
bine (Normal)
bine (Outage)
hop
ng Mechanical. Various sub groups are defined within
ine
kshop
er
am that is not involved in the outage and 0 stands for team that is involve
bine (Normal)
bine (Outage)
eering Instrumentation. Various sub groups are defined within
Outage
Engineering
Supervisors
Electronic shop
Communication
Analyzers
er divided into:
ce request
he priority and availability of plant
nning coordination meeting
ing and feedback system and manual procedure when CMMS (Maximo) is u
t adjustments HPSL/HUB/ENG/006 is used When any temporary change is m
anges this procedure gives guidance of how to record, the people who can a
s
nance hazards
derived hazards
ves
ethod
etails
ours)
movement
rking party are competent and conversant
g: Provide relevant training.
rements i.e.:
of the activity with concern personal during SD preparation, May ask in writ
assessment to ensure the dangers existence and communicate precautions
e slackness of pin drive is not less than 0.38 mm or otherwise replaced and
SL/HUB/ENG/P/008 i
firmation and visual inspection equipment for which the service request is r
utions are evaluated. Further any additional services or jobs is also conside
eet the acceptable standard then the planning engineer change the status o
ngineer of the respective working group convert the Service Request into w
firmation and visual inspection equipment for which the service request is r
utions are evaluated. Further any additional services or jobs is also conside
eet the acceptable standard then the planning engineer change the status o
ngineer of the respective working group convert the Service Request into w
of work, description, work priority, work instruction, Special tools, required
le in Maximo which depend on what are the some of the important require
ning are:
Stations "KKS" serves to identify plants, sections of plants and item of equip
It is to be used by all engineering disciplines for planning, licensing, constr
AKS system, a working party was set up in 1970 to find a solution for class
ection agencies etc. The result of this joint effort is power system designati
o three parts. The first part consist of a 1-digit number which indicates the
ber 5 for common components of unit 1 & 2 and number 6 for common com
ers which indicate the system level. The third part consists of 2 letters and
hall be held each day at 11 AM in the planning office chaired by the planni
rm each department, service and allied department such as ECP and fire &
firm the work program. Applicable safety documents and details such as sta
o three parts. The first part consist of a 1-digit number which indicates the
ber 5 for common components of unit 1 & 2 and number 6 for common com
ers which indicate the system level. The third part consists of 2 letters and
hall be held each day at 11 AM in the planning office chaired by the planni
rm each department, service and allied department such as ECP and fire &
firm the work program. Applicable safety documents and details such as sta
n for the adequacy of information to enable the safety documents to be pre
elease to enable the plant to be available for the maintenance.
ords of the meeting and describing the key decision and events that occur
mportant decisions and discussions done during that meeting. The meeting
engineer. The minutes of that meeting consisted of list of attendees and im
en.
h is performed each year. In order to deal with the issues that may arrive du
This step is completed in the months of January and February in which the
at is planned initially is sent to WAPDA (NTDC) for approval through Product
After this stage, procurement is generally started so that the spares and th
e all tasks are completed before half year. After this, scope is then finalized
nd engineers because they actually know the ground reality. Before the firs
ings left out initially. After the first draft, some changes are made through t
, it is circulated 2 weeks before starting the outage in order to provide con
dness matrix is a tool that is generally used to help the employees with thi
urement is started by the outage planning engineer in order to get though
Once the outage starts, the planning engineer then has to draft a daily and
t are occurring during the outage and the time variance etc. A HSE report i
have to make sure that no unsafe event occurs during the outage. For this r
during the outage, before they start working. In addition, HSE teams also
ark these tools with a specific color strip that is unique for an outage. Durin
he unsafe observations. These unsafe observations are then classified as re
r with those issues that are most important. The recordable observations a
neer also chairs daily and weekly outage meeting. In daily outage meeting,
on heads are present. Major issues are discussed and information is shared
. All the issues and best practices are documented. These learnings are the
small scope which is not said to be project. For example changing light bul
ance.
f problems found during the operations or inspection is considered to be co
ed by the originator e.g. modifications, Plant improvements, installation or s
que and has an ending point and is generally intended for the improvemen
he plant. Likewise, projects also have the same flow as that for corrective m
he installation of the some specific equipment during a project of plant mod
ctivity of the equipment in maximo. This plan is prepared by planning secti
me as waiting for schedule on maximo and converted to work order by plan
`
Trainee Supervisor
9/30/2016
ook
Duration: 1 Week
Section
earnings Planning
activities the planning department is distributed into:
which includes:
Guidelines:
The checklist below is not an exhaustive description of jobs carried out in the work area. In case of any activity not listed in this document, please describe the same for proper records.
Date Signature
HVAC system- Function and Main components. 1-Nov-16 Hassan Ahmed
2-Sep-16 Hassan Ahmed Safety Rules: Potential Hazards; Required PPE; Precautions.
handling equipment.
Operations: Required Skill Level; Job Steps, Sequence and Duration; Crew
Dredger function and main components. 2-Sep-16 Hassan Ahmed
Composition, List of Applicable QA / QC.
Observation: Visual Witnessing of operation, Clarification / Discussion with Supervisor /
Hydraulic system- Function and main components. 3-Sep-16 Hassan Ahmed
Seniors.
Symbols of hydraulic system. 3-Sep-16 Hassan Ahmed
Site visit & resource estimation for scaffolding. 31-Oct-16 Hassan Ahmed
Crane movement. 2-Nov-16 Hassan Ahmed
Lifting work by crane. 2-Nov-16 Hassan Ahmed
Material movement by Forklifter, Merlo and other
2-Nov-16 Hassan Ahmed
means.
Repair/maintenance work at Heavy equipment
2-Nov-16 Hassan Ahmed
maintenance workshop.
Repair/maintenance work for HVAC system. 1-Nov-16 Hassan Ahmed
Civil Work Inspection. 3-Nov-16 Hassan Ahmed
Dredging work progress monitoring. 2-Nov-16 Hassan Ahmed
Contractor Supervision and Coordination. 4-Nov-16 Hassan Ahmed
Understanding Safety Rules Operations Observation Date Signature
Tools
`
Understanding Safety Rules Operations Observation Date Signature
Others
Area Sections
Services Training Notes - Key Learnings ESS,ESW,ESB,ESH
To be flled by Trainee
To be flled by Tra
Manager Review
Signatures
Date
Traini
Engineer
Guidelines:
The checklist below is not an exhaustive description of jobs carried out in the work area
Blast Pot
Airless Spray
Tools
Conventional Spray
Brush And Roller
Dewpoint Meter
C
DFT Gauge
PH Tester
Profile Gauge
QA / QC
Salt tester
Surface Contaminant Kit
Spark Test
Dc Pull adhesion test
Paint Inspection guage
Preventive Maintainance
Workfow
Blasting Standards
Others
Coating Application
Safty Data Sheet and Msds
Pre Cleaning
Manager Review
Signatures
Date
Training Record Book
Engineering Corrosion Protection
ption of jobs carried out in the work area. In case of any activity not listed in this document, please des
Trainee Supervisor
9/23/2016
ook
ction
Duration: 1 week
Working Principle of Machine; Knowledge about Tools, Jigs and fixtures, Applicable Software
21-Sep-16
21-Sep-16
22-Sep-16
23-Sep-16
23-Sep-16
22-Sep-16
22-Sep-16
23-Sep-16